Ship shafting and main engine pre-embedding method and ship shafting and main engine pre-embedding system

By accurately planning the hoisting and installation time nodes of the ship's shafting and main engine in the dock, the problem of long installation cycles of the ship's shafting and main engine is solved, a more efficient installation process is achieved, and the integrity of the engine room and main engine before undocking is improved. Debugging convenience.

CN118770489APending Publication Date: 2024-10-15SHANGHAI WAIGAOQIAO SHIP BUILDING CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411115164.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The installation cycle of ship shafting and main engine is long and the work efficiency is low, making the entire installation process time-consuming.

Method used

By presetting the hoisting position and time node in the cabin, the hoisting and installation of the ship's shaft system and main engine can be completed in advance in the dock, including preset distance, position determination, precise planning of hoisting and installation time nodes, and the use of multiple cranes Lift and install the ship's shafting and main engine respectively, ensuring that all operations are completed in the dock.

Benefits of technology

It effectively shortens the installation cycle in the dock, improves the integrity of the engine room and the convenience of main engine debugging before undocking, and improves the installation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118770489A_ABST
    Figure CN118770489A_ABST
Patent Text Reader

Abstract

The invention provides a ship shafting and main engine pre-embedding method and a ship shafting and main engine pre-embedding system. The method comprises the following steps: a distance presetting step: presetting a first preset distance from a ship shafting to the bottom of a cabin and a second preset distance from a ship main engine to the bottom of the cabin, and a position determining step: determining a first preset hanging position of the ship shafting and a second preset hanging position of the ship shafting; a hoisting time node determination and hoisting step: hoisting a ship shafting in the dock within a first preset time, and hoisting a ship main engine within a second preset time; and an installation time node determination and installation step: installing the ship shafting at the first preset installation position at the third preset time in the dock, and installing the ship main engine at the second preset installation position at the fourth preset time. Hoisting and mounting are both completed in the dock, the process stage is advanced, the dock period can be effectively shortened, and the cabin integrity before the dock is undocked is improved; and convenience can be created for oil feeding (debugging) of the main engine.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of ship technology, and in particular to a ship shaft system, a main engine pre-embedded method, and a ship shaft system, a main engine pre-embedded system. Background Art

[0002] The ship shaft system and the ship main engine are the core components of the ship; among them, the ship shaft system refers to the ship power device, which transmits the power generated by the ship main engine to the propeller, and at the same time transmits the thrust generated by the propeller to the hull to drive the ship. The ship main engine is used to generate power.

[0003] During the installation process, the main engine of the ship is hoisted before leaving the dock and installed after leaving the dock; the hoisting and installation of the ship's shaft system are both completed in the dock, and the ship's shaft system is installed after half of the ship is floated; this installation method results in a long cycle for the entire installation process and low work efficiency.

[0004] Therefore, there is an urgent need for a ship shaft system, a main engine pre-embedding method and a ship shaft system, a main engine pre-embedding system, so as to solve the technical problems existing in the prior art to a certain extent. Summary of the invention

[0005] The purpose of the present application is to provide a method for pre-embedding a ship shaft system and a main engine and a system for pre-embedding a ship shaft system and a main engine, which can, to a certain extent, solve the technical problems of long installation period and low working efficiency of ship main engines and shaft systems in the prior art.

[0006] The present application provides a method for pre-embedding a ship shaft system and a main engine, comprising the following steps:

[0007] Distance preset step: according to the height of the cabin, the distance from the ship shaft system to the bottom of the cabin is preset as the first preset distance, and the distance from the ship main engine to the bottom of the cabin is preset as the second preset distance;

[0008] Position determination step: determining a first preset hoisting position of the ship shaft system according to the first preset distance, and determining a second preset hoisting position of the ship shaft system according to the second preset distance;

[0009] Determination of the hoisting time node and the hoisting steps: hoisting the ship shaft system at a first preset time in the dock, and hoisting the ship main engine at a second preset time;

[0010] Installation time node determination and installation steps: installing the ship shaft system at the first preset installation position at the third preset time in the dock, and installing the ship main engine at the second preset installation position at the fourth preset time.

[0011] In the above technical solution, further, the first preset distance and the second preset distance are both 2.4 m.

[0012] In the above technical solution, further, the ship shaft system includes a first intermediate shaft, a second intermediate shaft and a stern shaft;

[0013] The first intermediate shaft, the second intermediate shaft and the stern shaft are connected in sequence along a center line of the cabin.

[0014] In the above technical solution, further, the first preset time is before leaving the dock, and the second preset time is after entering the dock.

[0015] In the above technical solution, further, the hoisting time node determination and the hoisting steps specifically include the following steps:

[0016] A first hoisting step: hoisting the first intermediate shaft and the second intermediate shaft into the first preset hoisting position of the cabin by using a first hoisting horse; the first intermediate shaft and the second intermediate shaft are located on both sides of the center line, and the axis of the first intermediate shaft and the axis of the second intermediate shaft are parallel to the center line;

[0017] A second hoisting step: hoisting the stern shaft to the first preset hoisting position by using a second hoisting horse; the stern shaft is located between the first intermediate shaft and the second intermediate shaft and the axis of the stern shaft is parallel to the center line;

[0018] The third lifting step: using the third lifting horse to lift the main engine of the ship to the second preset lifting position.

[0019] In the above technical solution, further, three first hanging horses are provided, and the three first hanging horses are arranged at intervals along the extension direction of the first intermediate shaft and the second intermediate shaft.

[0020] In the above technical solution, further, the number of the second hanging horses is five, and the five second hanging horses are arranged at intervals along the extension direction of the stern shaft.

[0021] In the above technical solution, further, the third preset installation time is before leaving the dock; the fourth preset installation time is before leaving the dock.

[0022] In the above technical solution, further, the installation time node determination and the installation steps specifically include the following steps:

[0023] The first installation step: using the first lifting horse to lift the first intermediate shaft and the second intermediate shaft, and using the second lifting horse to lift the stern shaft, so that the first intermediate shaft, the second intermediate shaft and the stern shaft are connected in sequence and placed at the first preset installation position at the bottom of the cabin;

[0024] The second installation step is to install the ship shaft at the second preset installation position at the bottom of the cabin in the dock by using a third lifting horse at the third preset installation time.

[0025] The present application also provides a ship shafting and main engine pre-embedding system based on the above-mentioned ship shafting and main engine pre-embedding method.

[0026] Compared with the prior art, the beneficial effects of this application are:

[0027] The present application provides a method for pre-embedding a ship shaft system and a main engine, comprising the following steps:

[0028] Distance preset steps: according to the height of the cabin, the distance from the ship's shaft system to the bottom of the cabin is preset as the first preset distance, and the distance from the ship's main engine to the bottom of the cabin is preset as the second preset distance.

[0029] Position determination step: determining a first preset hoisting position of the ship shaft system according to the first preset distance, and determining a second preset hoisting position of the ship shaft system according to the second preset distance;

[0030] Determination of the hoisting time node and the hoisting steps: hoisting the ship shaft system at a first preset time in the dock, and hoisting the ship main engine at a second preset time;

[0031] Installation time node determination and installation steps: installing the ship shaft system at the first preset installation position at the third preset time in the dock, and installing the ship main engine at the second preset installation position at the fourth preset time.

[0032] In summary, the lifting and installation of the present application are all completed in the dock, which advances the process stage, can effectively shorten the dock cycle, and improve the integrity of the engine room before leaving the dock; it can create convenience for the main engine oiling (debugging).

[0033] The present application also provides a ship shafting and main engine pre-embedding system, which is based on the above-mentioned ship shafting and main engine pre-embedding method, and thus has all the beneficial effects of the above-mentioned ship shafting and main engine pre-embedding method, which will not be described in detail here. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the specific implementation methods of the present application or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0035] Figure 1 This is a side view of the ship's shaft system inside the cabin during hoisting;

[0036] Figure 2This is a top view of the ship's shaft system inside the cabin during hoisting;

[0037] Figure 3 This is a top view of the ship's shafting system inside the cabin during installation.

[0038] Figure numerals: 1 - cabin bottom; 2 - first hoisting horse; 3 - second hoisting horse; 5 - ship shaft system; 6 - cabin top; 7 - first intermediate shaft; 8 - second intermediate shaft; 9 - stern shaft. DETAILED DESCRIPTION

[0039] The following specific embodiments are provided to help the reader obtain a comprehensive understanding of the methods, devices and / or systems described herein. However, after understanding the disclosure of the present application, various changes, modifications and equivalents of the methods, devices and / or systems described herein will be apparent. For example, the order of operations described herein is merely an example, and is not limited to the order set forth herein, but in addition to the operations that must occur in a particular order, changes that will be apparent after understanding the disclosure of the present application may be made. In addition, in order to improve clarity and brevity, descriptions of features known in the art may be omitted.

[0040] The features described herein may be implemented in different forms and should not be interpreted as being limited to the examples described herein. Rather, the examples described herein have been provided only to illustrate some of the many possible ways of implementing the methods, devices and / or systems described herein that will be apparent after understanding the disclosure of the present application.

[0041] Throughout the specification, when an element (such as a layer, a region, or a substrate) is described as being “on”, “connected to”, “bound to”, “over”, or “covering” another element, it may be directly “on”, “connected to”, “bound to”, “over”, or “covering” another element, or one or more other elements may be present between them. In contrast, when an element is described as being “directly on”, “directly connected to”, “directly bound to”, “directly over”, or “directly covering” another element, there may be no other elements present between them.

[0042] As used herein, the term "and / or" includes any one of the associated listed items and any combination of any two or more items.

[0043] Although terms such as "first," "second," and "third" may be used herein to describe various members, components, regions, layers, or portions, these members, components, regions, layers, or portions are not limited by these terms. Rather, these terms are only used to distinguish one member, component, region, layer, or portion from another member, component, region, layer, or portion. Therefore, without departing from the teachings of the examples described herein, the first member, component, region, layer, or portion referred to may also be referred to as the second member, component, region, layer, or portion.

[0044] For ease of description, spatial relational terms such as "above", "upper", "below", and "lower" may be used herein to describe the relationship of one element to another element as shown in the accompanying drawings. Such spatial relational terms are intended to include different orientations of the device in use or operation in addition to the orientation depicted in the accompanying drawings. For example, if the device in the accompanying drawings is turned over, an element described as being "above" or "upper" relative to another element will subsequently be "below" or "lower" relative to the other element. Therefore, the term "above" includes both "above" and "below" orientations depending on the spatial orientation of the device. The device may also be positioned in other ways (e.g., rotated 90 degrees or in other orientations), and the spatial relational terms used herein will be interpreted accordingly.

[0045] The terms used herein are only used to describe various examples and are not used to limit the present disclosure. Unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. The terms "include", "comprise" and "have" list the stated features, quantities, operations, components, elements and / or their combinations that exist, but do not exclude the existence or addition of one or more other features, quantities, operations, components, elements and / or their combinations.

[0046] Variations in the shapes shown in the drawings may occur due to manufacturing techniques and / or tolerances. Therefore, the examples described herein are not limited to the specific shapes shown in the drawings but include variations in shapes that occur during manufacturing.

[0047] The features of the examples described herein may be combined in various ways that will be apparent after understanding the disclosure of the present application. In addition, although the examples described herein have various configurations, other configurations are possible as will be apparent after understanding the disclosure of the present application.

[0048] Embodiment 1

[0049] Combination Figure 1-Figure 3 The above-mentioned method for pre-embedding a ship shaft system 5 and a main engine provided by the present application is described in detail.

[0050] In this embodiment, a method for pre-embedding a ship shaft system 5 and a main engine is provided, and the method comprises the following steps:

[0051] Distance preset step 100: according to the height of the cabin, the distance from the ship shaft system 5 to the cabin bottom 1 (opposite to the cabin top 6) is preset as a first preset distance L1, and the distance from the ship main engine to the cabin bottom 1 is preset as a second preset distance;

[0052] Position determination step 200: determining a first preset hoisting position of the ship shaft system 5 according to a first preset distance, and determining a second preset hoisting position of the ship shaft system 5 according to a second preset distance;

[0053] Determine the hoisting time node and hoisting step 300: hoist the ship shaft system 5 at a first preset time in the dock, and hoist the ship main engine at a second preset time;

[0054] Installation time node determination and installation step 400: installing the ship shaft system 5 at the first preset installation position at the third preset time in the dock, and installing the ship main engine at the second preset installation position at the fourth preset time.

[0055] In summary, the lifting and installation of the present application are all completed in the dock, which advances the process stage, can effectively shorten the dock cycle, and improve the integrity of the engine room before leaving the dock; it can create convenience for the main engine oiling (debugging).

[0056] In addition, the present application solves the difficulties in the process of pulling and lighting the ship shaft system 5 after pre-embedding by forming a pre-embedding scheme for the main engine of the ship shaft system 5, thereby avoiding blocking the center line of the shaft system during the pre-embedding process of the shaft system.

[0057] The dock mentioned above refers to: dock-type buildings. Docks refer to dock-type buildings used for ship repair and construction. After filling with water, ships can enter and exit. After draining, ships can be repaired and built on a dry bottom. Docks can be divided into three categories: dry docks, water-filled docks, and floating docks. Dry docks are more commonly used, and the docks generally referred to are dry docks. Docks have evolved from the original "ship pits". On tidal coasts, people use the rise and fall of water levels to lift and lower ships, that is, when the tide is high, the ship is introduced into a "ship pit" surrounded by earth embankments on three sides. When the tide is low, the ship sits on the pre-placed piers, and then the gap is closed with a dam for repair work. When the ship leaves the pit, the dam is removed and the pit is left at high tide.

[0058] In this embodiment, combined Figure 1 The first preset distance and the second preset distance are both 2.4 m, that is, the distance from the ship shaft system 5 to the cabin bottom 1 is 2.4 m.

[0059] In this embodiment, the ship shafting 5 includes a first intermediate shaft 7, a second intermediate shaft 8 and a stern shaft 9; specifically, the first intermediate shaft 7, the second intermediate shaft 8 and the stern shaft 9 are connected in sequence along the center line of the cabin.

[0060] In this embodiment, the first preset time is before leaving the dock, and the second preset time is after entering the dock.

[0061] In this embodiment, the hoisting time node determination and the hoisting steps specifically include the following steps:

[0062] First hoisting step 301: using the first hoisting horse 2 to hoist the first intermediate shaft 7 and the second intermediate shaft 8 into the first preset hoisting position of the cabin respectively; the first intermediate shaft 7 and the second intermediate shaft 8 are located on both sides of the center line, and the axis of the first intermediate shaft 7 and the axis of the second intermediate shaft 8 are parallel to the center line;

[0063] Second hoisting step 302: hoisting the stern shaft 9 at the first preset hoisting position by using the second hoisting horse 3; the stern shaft 9 is located between the first intermediate shaft 7 and the second intermediate shaft 8 and the axis of the stern shaft 9 is parallel to the center line;

[0064] The third lifting step 303: using the third lifting horse to lift the main engine of the ship to the second preset lifting position.

[0065] In this embodiment, further, three first hanging horses 2 are provided, and the three first hanging horses 2 are arranged at intervals along the extending direction of the first intermediate shaft 7 and the second intermediate shaft 8 .

[0066] Furthermore, the distance between the center of the first intermediate shaft 7 and the center line is set to 855 mm, and the distance between the center of the second intermediate shaft 8 and the center line is set to 882 mm.

[0067] It is worth noting that the specific positions of the three lifting horses on the first intermediate shaft 7 are determined according to the actual weight simulation situation, and the specific positions of the three lifting horses on the second intermediate shaft 8 are determined according to the actual weight simulation situation.

[0068] In this embodiment, further, five second hanging horses 3 are provided, and the five second hanging horses 3 are arranged at intervals along the extension direction of the stern shaft 9. It is worth noting that the specific positions of the five second hanging horses 3 on the stern shaft 9 are determined according to the actual weight simulation situation.

[0069] In this embodiment, further, the third preset installation time is before leaving the dock; the fourth preset installation time is before leaving the dock.

[0070] In this embodiment, the installation time node determination and installation steps specifically include the following steps:

[0071] The first installation step 401: use the first lifting horse 2 to lift the first intermediate shaft 7 and the second intermediate shaft 8, and use the second lifting horse 3 to lift the stern shaft 9, so that the first intermediate shaft 7, the second intermediate shaft 8 and the stern shaft 9 are connected in sequence and placed at the first preset installation position of the cabin bottom 1; finally, the stern shaft must be inserted into the stern tube.

[0072] The second installation step 402: using a third hoisting horse to install the ship shaft system 5 at the second preset installation position of the cabin bottom 1 in the dock at the third preset installation time.

[0073] It is worth noting that during the pre-embedding of the shaft system, the equipment needs to be avoided, the relevant interfering pipes and the stern seal air control unit pipe need to be modified, and the outfitting parts and platform railings need to be modified to be detachable and temporarily removed. The following issues also need to be considered: the external conditions for the pre-embedding of the main engine; during the pre-embedding of the shaft system, the interfering pipes and outfitting parts at the bottom and top of the cabin have been removed; the main engine oil return hole and the anchor bolt hole have been drilled; the cabin hanging code has been completely welded.

[0074] Embodiment 2

[0075] In this embodiment, a ship shaft system 5 and main engine pre-embedding system is also provided, which is based on the above-mentioned ship shaft system 5 and main engine pre-embedding method. Therefore, it has all the beneficial effects of the above-mentioned ship shaft system 5 and main engine pre-embedding method, which will not be repeated here.

[0076] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present application.

Claims

1. A method for pre-embedding ship shafting and main engine, characterized in that: The steps include: Distance preset step: according to the height of the cabin, the distance from the ship's shaft system to the cabin bottom is preset as the first preset distance, and the distance from the ship's main engine to the cabin bottom is preset as the second preset distance; Position determination step: determining a first preset hoisting position of the ship shafting according to the first preset distance, and determining a second preset hoisting position of the ship shafting according to the second preset distance; Determination of the hoisting time node and hoisting steps: hoisting the ship shaft system at a first preset time in the dock, and hoisting the ship main engine at a second preset time; Installation time node determination and installation steps: installing the ship shafting at the first preset installation position at the third preset time in the dock, and installing the ship main engine at the second preset installation position at the fourth preset time.

2. The method for pre-embedding ship shafting and main engine according to claim 1, characterized in that: The first preset distance and the second preset distance are both 2.4 m.

3. The method for pre-embedding ship shafting and main engine according to claim 1, characterized in that: The ship shaft system includes a first intermediate shaft, a second intermediate shaft and a stern shaft; The first intermediate shaft, the second intermediate shaft and the stern shaft are connected in sequence along a center line of the cabin.

4. The method for pre-embedding ship shafting and main engine according to claim 3, characterized in that: The first preset time is before leaving the dock, and the second preset time is after entering the dock.

5. The method for pre-embedding ship shafting and main engine according to claim 3, characterized in that: The hoisting time node determination and hoisting steps specifically include the following steps: A first hoisting step comprises hoisting the first intermediate shaft and the second intermediate shaft into the first predetermined hoisting position of the cabin using a first hoisting horse; the first intermediate shaft and the second intermediate shaft are located on either side of the center line, and the axes of the first intermediate shaft and the second intermediate shaft are parallel to the center line; A second hoisting step: hoisting the stern shaft to the first preset hoisting position using a second hoisting horse; the stern shaft is located between the first intermediate shaft and the second intermediate shaft, and the axis of the stern shaft is parallel to the center line; The third hoisting step: using the third hoisting horse to hoist the main engine of the ship to the second preset hoisting position.

6. The method for pre-embedding ship shafting and main engine according to claim 5, characterized in that: Three first hanging horses are provided, and the three first hanging horses are arranged at intervals along the extending direction of the first intermediate shaft and the second intermediate shaft.

7. The method for pre-embedding ship shafting and main engine according to claim 5, characterized in that: There are five second hanging horses, and the five second hanging horses are arranged at intervals along the extending direction of the stern shaft.

8. The method for pre-embedding ship shafting and main engine according to claim 5, characterized in that: The third preset time is before leaving the dock; the fourth preset time is before leaving the dock.

9. The method for pre-embedding ship shafting and main engine according to claim 8, characterized in that: The installation time node determination and installation steps specifically include the following steps: The first installation step comprises: using a first lifting horse to lift the first intermediate shaft and the second intermediate shaft, and using a second lifting horse to lift the stern shaft, so that the first intermediate shaft, the second intermediate shaft, and the stern shaft are sequentially connected and placed at the first preset installation position on the bottom of the cabin; The second installation step is to use a third hoisting horse to install the ship shaft at the second installation preset position on the bottom of the cabin at the third preset time in the dock.

10. A ship shafting and main engine pre-buried system, characterized in that: A method for pre-embedding a ship shafting and main engine according to any one of claims 1 to 9.