A partition wall removal device and construction method in foundation pit
By installing a main frame and wire saw cutting components on the partition wall in the foundation pit, combined with hoisting pulleys and hydraulic cylinders, semi-automatic demolition of the partition wall in the foundation pit was achieved, solving the problems of low construction efficiency and poor safety, and improving construction speed and stability.
Patent Information
- Application Number
- CN202411266292.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-11
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-09-11
AI Technical Summary
Existing methods for demolishing partition walls in foundation pits are prone to collisions with surrounding underground structures when operating in confined spaces, resulting in low construction efficiency and poor safety.
The system employs components such as a main frame, wire saw cutting assembly, lifting pulleys, and double piston rod hydraulic cylinders. It cuts the central partition wall with a wire saw and uses the lifting pulleys and multiple lifting lugs for stable hoisting, achieving semi-automated continuous operation.
It improves construction speed and stability, reduces the impact on surrounding building structures, and lowers the risk of swaying during construction.
Smart Images

Figure CN118774137B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of foundation pit wall removal, and in particular relates to a partition wall removal device and a construction method in a foundation pit. Background Art
[0002] Due to considerations such as the protection of the surrounding geotechnical environment and the control of foundation pit safety risks, more and more foundation pits are constructed using partition walls. After the underground structure is basically completed, the partition wall is removed to connect the entire basement. There are two main forms of demolition of the partition wall: chiseling and static cutting. In order to adapt to the development of green and low-carbon construction, static cutting and hoisting removal are becoming more and more widely used. After the static cutting is completed, the partition wall blocks are vertically hoisted out along the middle cavity of the underground structures on both sides. The hoisting space is limited, and the completed underground structures on both sides need to be protected. Currently, it mainly relies on manual adjustment of the length of the wire rope to adjust the hoisting flatness to avoid the blocks colliding with the underground structures on both sides. The efficiency is low and the safety risk is high. To solve this technical problem, special clamps and cranes and other tools are usually used to cooperate with each other. The wall to be demolished is cut and fixed with the clamp. , and finally transported to other places by crane. For example, a Chinese patent discloses a brick-concrete encapsulation and removal mechanism and a removal method (patent publication number: CN113279606A). The brick wall is inserted between the first steel frame and the second steel frame, and a latch is installed. The bottom of the first steel frame and the bottom of the second steel frame are provided with a hook assembly for bearing. The brick-concrete wall encapsulation and removal mechanism is lifted by a crane, and the brick wall is lifted to the corresponding position, so that the wall can be quickly removed, forming a streamlined operation, which greatly reduces the burden on construction personnel and speeds up the efficiency of wall removal.
[0003] Although the above technical scheme can realize the semi-automatic demolition of the wall, in the actual construction process, due to the limited space in the foundation pit, the partition wall in the foundation pit is usually connected to other underground structures. For the construction workers, wall cutting and hoisting and other construction steps need to be carried out in a limited space, and damage to the surrounding underground structures must be avoided at all times during the operation. Therefore, the existing construction method cannot well meet the problem of protecting adjacent underground structures when demolishing the partition wall in the foundation pit. Summary of the invention
[0004] In view of this, the purpose of the present invention is to provide a partition wall removal device and construction method in a foundation pit, which is used to solve the problem that when the partition wall in the foundation pit is currently removed, the cutting and hoisting process will collide with the surrounding underground structure, resulting in low construction efficiency and safety.
[0005] In order to achieve the above object, the present invention provides the following technical solutions:
[0006] A partition wall removal device for a foundation pit, comprising a main frame arranged on the upper surface of a partition wall to be removed, the main frame being arranged parallel to the middle partition wall along its length direction and above it, and a rope saw cutting assembly for cutting the middle partition wall is arranged on the upper surface of the main frame; the rope saw cutting assembly is arranged at a position close to one end of the main frame, the rope saw cutting assembly comprises a rope saw for friction cutting the middle partition wall and a driving assembly for driving the rope saw to move, and the rope saw passes through the middle partition wall and is arranged at intervals on both sides of the middle partition wall, and cuts the middle partition wall vertically from bottom to top under the drive of the driving assembly; the main frame The lower surface of the frame is provided with four outer supporting legs for positioning, and the four outer supporting legs correspond to each other in pairs and abut against the two side surfaces of the middle partition wall at the same time. The corresponding two side surfaces of the main frame are provided with lifting pulleys, and there are four lifting pulleys, which are arranged on the two side surfaces of the main frame in pairs. Each group of corresponding two lifting pulleys is commonly connected to a main cable passing through the middle partition wall, and the main cable passes through the inside of the middle partition wall along the width direction of the main frame. The upper surface of the main frame is provided with four lifting ears, and the four lifting ears correspond to each other in pairs and are symmetrically arranged about the main frame.
[0007] Furthermore, the two corresponding outer legs are commonly connected to a double-piston-rod hydraulic cylinder, each of the double-piston-rod hydraulic cylinders is arranged on the lower surface of the main frame, and the double-piston-rod hydraulic cylinders are arranged along the width direction of the main frame, and the telescopic end of each double-piston-rod hydraulic cylinder is fixedly connected to the corresponding outer leg and is used to clamp the middle partition wall.
[0008] Furthermore, two rollers are spaced apart on the lower surface of the main frame, each of the rollers is arranged along the width direction of the main frame, and the two rollers are symmetrically arranged about the main frame, each of the rollers is rotatably connected to the main frame, and when the two rollers are in contact with the upper surface of the middle partition wall at the same time, there is a distance between the surface of the double-piston-rod hydraulic cylinder and the middle partition wall.
[0009] Furthermore, the rope saw cutting assembly also includes a slider that moves along the length direction of the main shell and a turntable rotatably arranged on the upper surface of the slider, and an elastic limiter is arranged between the turntable and the slider, the driving assembly is fixedly arranged on the upper surface of the turntable, the lower surface of the turntable is connected with a gear disk that protrudes downward, and the diameter of the gear disk is greater than the width of the slider, the upper surface of the main frame is rotatably connected with a screw rod along its length direction, one end of the screw rod is connected with a first driving motor that drives it to rotate, the first driving motor is fixed to the surface of the main frame, the slider is penetrated through the surface of the screw rod, and the slider is threadedly connected to the screw rod and moves along the length direction of the main frame under the rotation of the screw rod, the upper surface of the main frame is also fixedly connected with a rack that cooperates with the gear disk, the rack is along the length direction of the main frame, and when the slider drives the turntable to pass through the rack, the rack drives the gear disk to break through the restriction of the elastic limiter and rotate exactly 180°, and the rotated turntable just engages with the elastic limiter.
[0010] Furthermore, the main frame includes a first main shell, two end shells spaced apart at both ends of the main shell, and a plurality of adjustable shells arranged between the main shell and the end shell. Adjacent adjustable shells, the adjustable shell and the end shell, and the main shell and the adjustable shell are all detachably connected by bolts and nuts. The screw rod is composed of a plurality of screw rod segments, each of which is rotatably set on the corresponding main shell, end shell and adjustable shell surfaces. Any two adjacent screw rod segments are detachably connected by means of shaft hole matching and can transmit power at the same time.
[0011] Furthermore, both side surfaces of the two end shells are provided with lifting ears, and the two lifting ears on the same end shell are commonly connected to an auxiliary cable, each auxiliary cable is connected to the lifting ear after passing through the width direction of the middle partition wall, and the width between the two auxiliary cables is greater than the width between the main cables.
[0012] Furthermore, the invention also includes a method for removing partition walls in a foundation pit applied to the equipment, which is characterized by comprising the following steps:
[0013] S1, evenly partition the partition wall in the foundation pit, mark out cutting lines and form multiple cutting and lifting areas, open two first lifting holes for main cable lifting and two second lifting holes for auxiliary cable lifting in each area to be cut, and at the same time, open cutting holes for rope saws to pass through at the four corners of each cutting area;
[0014] S2, transport the pit partition wall removal equipment to the corresponding upper surface of the middle partition wall by lifting equipment, move the pit partition wall removal equipment to the corresponding position by rollers, then start two double-piston rod hydraulic cylinders and drive the outer legs to clamp the middle partition wall, and fix the main frame on the surface of the middle partition wall;
[0015] S3, adjusting the position of the wire saw cutting assembly through the cooperation of the first driving motor and the lead screw, passing one end of the wire saw through the pre-opened cutting hole, and then fine-adjusting the position of the wire saw cutting assembly to ensure that the wire saw is aligned with the boundary line of adjacent cutting areas in the vertical plane, and starting cutting after the position is adjusted; when the lead screw drives the wire saw cutting assembly to move along the length direction of the main frame, the angle of the driving assembly can be adjusted through the cooperation of the rack and the toothed disc, so that the surfaces on both sides of the middle partition wall can be cut quickly and conveniently;
[0016] S4, while cutting the middle partition wall, pass the main cable and the auxiliary cable through the corresponding lifting holes and connect them with the corresponding lifting ears and lifting pulleys;
[0017] S5, after both sides of the middle partition wall are cut, the lifting device applies a certain vertical upward pulling force to the main frame, and then the construction personnel cut the bottom end of the middle partition wall in the divided cutting area. After the cutting is completed, the middle partition wall in this cutting area is separated, and then slowly lifted to other places by the lifting device, completing the cutting and lifting work of part of the middle partition wall;
[0018] S6, repeating the above contents, can realize semi-automatic continuous middle partition wall cutting operation, wherein, by adding or removing a certain number of adjustable shells, the length of the main frame can be adjusted, thereby realizing construction operations on cutting areas of different sizes.
[0019] The beneficial effects of the present invention are:
[0020] 1. The present invention can stabilize the main frame on the surface of the middle partition wall to be demolished by arranging components such as a lifting pulley, a rope saw cutting assembly, outer legs and a double-piston rod hydraulic cylinder on the surface of the main frame, and can quickly cut the middle partition wall in a limited space through the rope saw cutting assembly, which improves the construction speed and optimizes the occupied space of the construction, further reducing the impact on the surrounding building structures. When lifting the demolished middle partition wall, the middle partition wall can be stably lifted by the cooperation of the lifting pulley, a plurality of lifting ears and auxiliary cables, effectively reducing the shaking of the middle partition wall during the lifting process, improving the stability during the construction process, and further reducing the impact on the surrounding building structures.
[0021] Other advantages, objectives and features of the present invention will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art may be taught from the practice of the present invention. The objectives and other advantages of the present invention may be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to make the purpose, technical solution and beneficial effects of the present invention clearer, the present invention provides the following drawings for illustration:
[0023] Figure 1 It is a schematic diagram of the structure and working of the partition wall removal equipment in the foundation pit of the present invention;
[0024] Figure 2 It is a side view of the structure of the partition wall removal equipment in the foundation pit of the present invention;
[0025] Figure 3 for Figure 1 The enlarged schematic diagram at A in the middle;
[0026] Figure 4 It is a schematic diagram of the main frame structure of the present invention;
[0027] Figure 5It is a schematic diagram of the connection between the main housing and the adjustable housing of the present invention;
[0028] Figure 6 This is a schematic diagram of the structure of the wire saw cutting assembly of the present invention;
[0029] Figure 7 for Figure 6 Sectional view at the middle BB;
[0030] Figure 8 It is a schematic diagram of the rotation of the wire saw cutting assembly of the present invention.
[0031] The following are marked in the accompanying drawings:
[0032] 1 middle partition wall, 2 main frame, 201 main shell, 202 end shell, 203 adjustable shell, 3 rope saw cutting assembly, 301 rope saw, 302 slider, 303 turntable, 304 gear plate, 4 outer support leg, 5 lifting pulley, 6 main cable, 7 lifting ear, 8 double piston rod hydraulic cylinder, 9 roller, 10 rack, 11 screw rod, 12 auxiliary cable, 13 first lifting hole, 14 second lifting hole, 15 cutting hole, 16 block, 17 limit hole, 18 support block, 19 guide wheel, 20 driving wheel, 21 first driving motor, 22 second driving motor. DETAILED DESCRIPTION
[0033] like Figures 1 to 8 As shown,
[0034] A partition wall demolition device for a foundation pit comprises a main frame 2 arranged on the upper surface of a partition wall 1 to be demolished, the main frame 2 being arranged parallel to and above the partition wall 1 along the length direction of the partition wall 1, and a rope saw cutting assembly 3 for cutting the partition wall 1 is arranged on the upper surface of the main frame 2; the rope saw cutting assembly 3 is arranged at a position close to one end of the main frame 2, the rope saw cutting assembly 3 comprises a rope saw 301 for frictionally cutting the partition wall 1 and a driving assembly for driving the rope saw 301 to move, and the rope saw 301 passes through the partition wall 1 and is arranged at intervals on both sides of the partition wall 1, and is driven by the driving assembly to vertically cut the partition wall 1 from bottom to top, the driving assembly comprises a second driving motor 22, a support block 18 and a guide wheel 19 rotatably arranged on the support block 18, the output end of the second driving motor 22 is connected to a driving wheel 20 and drives the rope saw 301 to move, and the rope saw 301 moves between the two sides Under the action of the guide wheel 19, there is a gap between the surface of the middle partition wall 1 and the main frame 2; the lower surface of the main frame 2 is provided with four outer supporting legs 4 for positioning, and the lower end of each outer supporting leg 4 protrudes downward from the main frame 2, and the four outer supporting legs 4 correspond to each other and abut against the two side surfaces of the middle partition wall 1 at the same time, and the corresponding two side surfaces of the main frame 2 are provided with lifting pulleys 5, and there are four lifting pulleys 5, which are arranged on the two side surfaces of the main frame 2 in pairs, and each group of corresponding two lifting pulleys 5 is commonly connected to a main cable 6 passing through the middle partition wall 1, and the main cable 6 passes through the inside of the middle partition wall 1 along the width direction of the main frame 2, and the upper surface of the main frame 2 is provided with four lifting ears 7, and the four lifting ears 7 correspond to each other and are symmetrically arranged about the main frame 2, wherein two lifting pulleys 5 are arranged near the center of the main frame 2.
[0035] Combination Figure 1As shown, the main frame 2 is connected to the slings through four lifting ears 7, and the free ends of the four slings are connected to the lifting rings together. The lifting equipment can connect the lifting rings to lift the main frame 2 to the upper surface of the middle partition wall 1, and the four outer legs 4 can first abut against the surface of the middle partition wall 1 and limit the position in the vertical direction, and can adjust the position of the main frame 2 on the middle partition wall 1 to ensure that the main frame 2 is placed parallel to the upper surface of the middle partition wall 1 along the length direction of the middle partition wall 1. At the same time, it can also effectively prevent the main frame 2 from tipping over when cutting the middle partition wall 1, affecting the surrounding underground structure; when the main frame 2 is placed, the rope saw 301 is passed through the cutting hole 15 pre-opened on the middle partition wall 1 and the driving assembly is started, and the second driving motor 22 drives the rope saw 301 to vertically cut the middle partition wall 1 from bottom to top (of course, the relevant equipment for driving the rope saw 301 to move upward is omitted in the text. Since it is a prior art, it will not be described in detail). Since the middle partition wall 1 is usually It is connected to other underground buildings. Therefore, after the cutting of one side surface of the middle partition wall 1 in the first cutting area is completed, it is necessary to hoist and adjust the position of the main frame 2 through a hoisting device so that the rope saw 301 cuts the other side surface of the middle partition wall 1 (the cutting of the subsequent part of the middle partition wall 1 only needs to cut one side surface). When the cutting of both sides is completed at the same time, the two main cables 6 are respectively passed through the pre-opened first hoisting holes 13 and connected to the corresponding hoisting pulleys 5. The main frame 2 is fixedly connected to the cut middle partition wall 1 through the hoisting pulleys 5. Then the hoisting device applies a certain vertical upward pulling force to the main frame 2. The construction personnel cut the bottom end of the middle partition wall 1 in the divided cutting area to complete the cutting and hoisting work of the secondary part of the middle partition wall 1. Through the cooperation of the outer support legs 4, the main cables 6 and the hoisting pulleys 5, the stability of the hoisting of the middle partition wall 1 can be improved, and the shaking during the hoisting process can be effectively reduced.
[0036] In this embodiment, the two corresponding outer legs 4 are commonly connected to a double-piston-rod hydraulic cylinder 8, each of which is arranged on the lower surface of the main frame 2, and the double-piston-rod hydraulic cylinder 8 is arranged along the width direction of the main frame 2, the telescopic end of each double-piston-rod hydraulic cylinder 8 is fixedly connected to the corresponding outer leg 4 and is used to clamp the middle partition wall 1, and each double-piston-rod hydraulic cylinder 8 is fixed to the surface of the main frame 2 by tension screws and bolts; two rollers 9 are arranged at intervals on the lower surface of the main frame 2, each of which is arranged along the width direction of the main frame 2, and the two rollers 9 are symmetrically arranged about the main frame 2, each of which is rotatably connected to the main frame 2, and when the two rollers 9 are in contact with the upper surface of the middle partition wall 1 at the same time, there is a distance between the surface of the double-piston-rod hydraulic cylinder 8 and the middle partition wall 1, and each roller 9 is fixed to the surface of the main frame 2 by the cooperation of tension screws and nuts, and each roller 9 is arranged on one side close to the adjacent double-piston-rod hydraulic cylinder 8.
[0037] As shown in the figure, when the main frame 2 is lifted to the upper surface of the middle partition wall 1, the two double-piston-rod hydraulic cylinders 8 are controlled to drive the corresponding outer legs 4 to clamp the middle partition wall 1, so that the main frame 2 can be stabilized on the surface of the middle partition wall 1, thereby improving the stability of the subsequent rope saw cutting assembly 3 during operation; and the setting of the rollers 9 can separate the main frame 2 from the middle partition wall 1 by a certain distance, thereby preventing the double-piston-rod hydraulic cylinder 8 from being squeezed and damaged. At the same time, the main frame 2 can be moved on the upper surface of the middle partition wall 1 through the two rollers 9, and the position of the main frame 2 can be adjusted, so that the rope saw cutting assembly 3 can reach the specified position and perform cutting, thereby improving the efficiency during operation.
[0038] In the present embodiment, the rope saw cutting assembly 3 further comprises a slider 302 which moves along the length direction of the main housing 201 and a turntable 303 which is rotatably arranged on the upper surface of the slider 302, and an elastic limiter is arranged between the turntable 303 and the slider 302, and the elastic limiter can adopt the cooperation of a spring and a block 16, the block 16 is elastically penetrated on the surface of the slider 302 along the vertical direction, and the surface of the turntable 303 is provided with two limiter holes 17 which cooperate with the block 16, and the upper end surface of the block 16 is arranged at a chamfered angle, and the driving assembly is fixedly arranged on the upper surface of the turntable 303, and the lower surface of the turntable 303 is fixedly connected with a downwardly protruding toothed disc 304 by bolts, and the diameter of the toothed disc 304 is larger than the width of the slider 302, and a part of the surface of the toothed disc 304 is located outside the slider 302, and the upper surface of the main frame 2 is rotatably connected with a screw rod along its length direction. 11, one end of the screw rod 11 is connected to a first driving motor 21 that drives it to rotate, the first driving motor 21 is fixed to the surface of the main frame 2, the slider 302 is penetrated through the surface of the screw rod 11, and the slider 302 is threadedly connected to the screw rod 11, and moves along the length direction of the main frame 2 under the rotation of the screw rod 11, and the upper surface of the main frame 2 is also fixedly connected with a rack 10 that matches with the toothed disc 304, wherein the length of the rack 10 is a special length that can make the toothed disc 304 passing through rotate exactly 180°, the rack 10 is along the length direction of the main frame 2, and when the slider 302 drives the rotating disk 303 to pass through the rack 10, the rack 10 drives the toothed disc 304 to break through the restrictions of the block 16 and the limiting hole 17 and rotate exactly 180°, and the rotating disk 303 is just fixed after rotation, and at this time the block 16 matches with another limiting hole 17;
[0039] The two guide wheels 19 are symmetrically arranged about the vertical axis of the driving wheel 20 , and the distance between the two guide wheels 19 is greater than the width of the middle partition wall 1 , so as to prevent the wire saw 301 from cutting at too short a distance and damaging the main frame 2 .
[0040] Combination Figure 1As shown, when the cutting of the middle partition wall 1 begins, the middle partition wall 1 needs to be divided into cutting areas, and when the cutting area of the first middle partition wall 1 is cut, the surfaces of both sides of this area need to be cut (because the middle partition wall 1 is usually connected to the underground building of the foundation pit), and the first driving motor 21 is controlled to drive the screw rod 11 to rotate, and the screw rod 11 drives the slider 302 to move along the length direction of the main frame 2 through the thread, so as to control and adjust the position of the rope saw cutting assembly 3, and then control the cutting position, and the screw rod 11 and the slider 302 also have a certain self-locking effect through the threaded cooperation, which can ensure the stability of the rope saw cutting assembly 3 during operation; because the rope saw cutting assembly 3 needs to cut both sides of the cutting area of the middle partition wall 1, in order to facilitate the turning of the rope saw cutting assembly 3, a rack 10 is provided on the surface of the main frame 2, and when the screw rod 11 drives the rope saw cutting assembly 3 to pass through the rack 10, the toothed disc 304 begins to mesh with one end of the rack 10, and because the rack 10 is fixed, the rack 10 will drive the toothed disc 304 to rotate exactly 180° (combined with Figure 8 As shown), the working end of the wire saw cutting assembly 3 can correspond to the cutting area of the middle partition wall 1 on the other side, which is convenient for adjusting the wire saw cutting assembly 3 when the space in the foundation pit is limited, facilitating construction and effectively improving the construction speed;
[0041] Among them, the elastic limiter is mainly used to prevent the rope saw cutting assembly 3 from rotating during operation. Only when the turntable 303 and the rack 10 are engaged with each other, the rack 10 drives the turntable 303 to rotate. At this time, the force of rotation will cause the block 16 to disengage from the limit hole 17, causing the turntable 303 to rotate. When the turntable 303 rotates 180°, the elastic limiter will cooperate with another limit hole 17 and fix the turntable 303 to prevent it from rotating, thereby effectively improving the stability of the rope saw cutting assembly 3 during operation.
[0042] In this embodiment, the main frame 2 includes a first main shell 201, two end shells 202 spaced apart at both ends of the main shell 201, and a plurality of adjustable shells 203 arranged between the main shell 201 and the end shell 202. Adjacent adjustable shells 203, between the adjustable shell 203 and the end shell 202, and between the main shell 201 and the adjustable shell 203 are all detachably connected by tension bolts and nuts. The screw rod 11 is composed of a plurality of screw rod 11 segments, and each screw rod 11 segment is rotatably set on the corresponding surfaces of the main shell 201, the end shell 202 and the adjustable shell 203. Any two adjacent screw rod 11 segments are detachably connected by means of shaft hole matching and transmit power at the same time.
[0043] Combination Figure 5As shown, since the sizes of the middle partition walls 1 in the foundation pit are different, the sizes during cutting also need to be re-planned. When the cutting size needs to be adjusted, the overall length of the main frame 2 can be changed by adding or removing one or more adjustable shells 203, so that the partition wall 1 removal equipment in the foundation pit can adapt to the removal of middle partition walls 1 of different sizes without affecting its overall function, effectively increasing the construction scope and ensuring the construction quality.
[0044] In this embodiment, both side surfaces of the two end shells 202 are welded and fixed with lifting ears 7, and the two lifting ears 7 on the same end shell 202 are commonly connected to an auxiliary cable 12, each of the auxiliary cables 12 is connected to the lifting ears 7 after passing through the middle partition wall 1 in the width direction, and the width between the two auxiliary cables 12 is greater than the width between the main cables 6.
[0045] As shown in the figure, two auxiliary cables 12 and the cable together fix the cut middle partition wall 1, which can further improve the stability during lifting and prevent the middle partition wall 1 from tipping over and falling during lifting, affecting the surrounding foundation pit structure.
[0046] In this embodiment, a method for removing partition walls in a foundation pit applied to the equipment is also included, which is characterized by comprising the following steps:
[0047] S1, evenly partition the partition wall 1 in the foundation pit, draw cutting lines and form multiple cutting and lifting areas, open two first lifting holes 13 for the main cable 6 to be lifted and rotated and two second lifting holes 14 for the auxiliary cable 12 to be lifted in each area to be cut, and at the same time, open cutting holes 15 for the rope saw 301 to pass through at the four corners of each cutting area; according to the divided cutting areas, disassemble and assemble the adjustable shell 203 and adjust the total length of the main frame 2. For specific division of areas, please refer to Figure 1 As shown, of course, the divided cutting area is determined according to the specific size of the middle partition wall 1, and the total length of the main frame 2 can be adjusted according to the size of the divided middle partition wall 1, so as to facilitate the cutting by the rope saw cutting assembly 3;
[0048] S2, transport the pit partition wall 1 removal equipment to the corresponding upper surface of the partition wall 1 through the lifting equipment, move the pit partition wall 1 removal equipment to the corresponding position through the roller 9, then start the two double piston rod hydraulic cylinders 8 and drive the outer legs 4 to clamp the partition wall 1, and fix the main frame 2 on the surface of the partition wall 1 to facilitate stability during subsequent construction;
[0049] S3, the position of the wire saw cutting assembly 3 is adjusted by the cooperation of the first driving motor 21 and the screw rod 11, one end of the wire saw 301 is passed through the pre-opened cutting hole 15, and then the position of the wire saw cutting assembly 3 is finely adjusted to ensure that the wire saw 301 is aligned with the boundary line of the adjacent cutting areas in the vertical plane, and the cutting is started after the position is adjusted; when the screw rod 11 drives the wire saw cutting assembly 3 to move along the length direction of the main frame 2, the angle of the driving assembly can be adjusted by the cooperation of the rack 10 and the toothed disc 304, so that the surfaces on both sides of the middle partition wall 1 can be cut quickly and conveniently;
[0050] S4, while cutting the middle partition wall 1, the main cable 6 and the auxiliary cable 12 are passed through the corresponding lifting holes and connected to the corresponding lifting ears 7 and the lifting pulley 5, and the lifting pulley 5 and the main cable 6 cooperate to apply a vertical upward pulling force to the main frame 2, so as to fasten the main frame 2 and the middle partition wall 1 in the cutting area;
[0051] S5, after both sides of the middle partition wall 1 are cut, the lifting device applies a certain vertical upward pulling force to the main frame 2, and then the construction personnel cut the bottom end of the middle partition wall 1 in the divided cutting area. The cutting method can be an electric saw or drilling method. After the cutting is completed, the middle partition wall 1 in this cutting area is separated. Since the main frame 2 is fastened to the cutting area and the main frame is connected to the lifting device through 4 equal-length slings, the shaking during the lifting process can be effectively reduced, which effectively improves the stability of the construction. It is slowly lifted to other places by the lifting device to complete the cutting and lifting work of part of the middle partition wall 1;
[0052] S6, repeating the above contents, can realize semi-automatic continuous cutting operation of the middle partition wall 1, wherein, by adding or removing a certain number of adjustable shells 203, the length of the main frame 2 can be adjusted, thereby realizing construction operations on cutting areas of different sizes.
[0053] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present invention.
Claims
1. A device for removing partition walls in a foundation pit, comprising a main frame (2) arranged on the upper surface of a partition wall (1) to be removed, characterized in that: The main frame (2) is arranged parallel to and above the middle partition wall (1) along its length direction, and a rope saw cutting assembly (3) for cutting the middle partition wall (1) is provided on the upper surface of the main frame (2); the rope saw cutting assembly (3) is arranged at a position close to one end of the main frame (2), and the rope saw cutting assembly (3) comprises a rope saw (301) for friction cutting the middle partition wall (1) and a driving assembly for driving the rope saw (301) to move, and the rope saw (301) passes through the middle partition wall (1) and is arranged at intervals on both sides of the middle partition wall (1), and is driven by the driving assembly to vertically cut the middle partition wall (1) from bottom to top; the lower surface of the main frame (2) is provided with four positioning members Outer supporting legs (4), four outer supporting legs (4) correspond to each other in pairs and abut against the two side surfaces of the middle partition wall (1) at the same time, the corresponding two side surfaces of the main frame (2) are provided with lifting pulleys (5), and there are four lifting pulleys (5), which are arranged in pairs on the two side surfaces of the main frame (2), each group of corresponding two lifting pulleys (5) are commonly connected to a main cable (6) passing through the middle partition wall (1), and the main cable (6) passes through the inside of the middle partition wall (1) along the width direction of the main frame (2), and the upper surface of the main frame (2) is provided with four lifting ears (7), and the four lifting ears (7) correspond to each other in pairs and are symmetrically arranged with respect to the main frame (2).
2. The partition wall removal equipment in a foundation pit according to claim 1 is characterized in that: The two corresponding outer supporting legs (4) are both connected to a double-piston-rod hydraulic cylinder (8), each of which is arranged on the lower surface of the main frame (2), and the double-piston-rod hydraulic cylinder (8) is arranged along the width direction of the main frame (2), and the telescopic end of each double-piston-rod hydraulic cylinder (8) is fixedly connected to the corresponding outer supporting leg (4) and is used to clamp the middle partition wall (1).
3. The partition wall removal equipment in a foundation pit according to claim 2 is characterized in that: Two rollers (9) are arranged at intervals on the lower surface of the main frame (2), each of the rollers (9) is arranged along the width direction of the main frame (2), and the two rollers (9) are symmetrically arranged with respect to the main frame (2), each of the rollers (9) is rotatably connected to the main frame (2), and when the two rollers (9) are in contact with the upper surface of the middle partition wall (1) at the same time, a distance is separated between the surface of the double-piston-rod hydraulic cylinder (8) and the middle partition wall (1).
4. The partition wall removal equipment in a foundation pit according to claim 3 is characterized in that: The rope saw cutting assembly (3) further comprises a slider (302) that moves along the length direction of the main housing (201) and a turntable (303) that is rotatably arranged on the upper surface of the slider (302), and an elastic stopper is arranged between the turntable (303) and the slider (302); the driving assembly is fixedly arranged on the upper surface of the turntable (303); the lower surface of the turntable (303) is connected to a toothed disc (304) that protrudes downward, and the diameter of the toothed disc (304) is greater than the width of the slider (302); the upper surface of the main frame (2) is rotatably connected to a lead screw (11) along its length direction; one end of the lead screw (11) is connected to a first driving motor (21) that drives the lead screw (11) to rotate; and the first driving motor (21) is connected to the first driving motor (21) that drives the lead screw (11) to rotate. The motor (21) is fixed on the surface of the main frame (2), the slider (302) is inserted into the surface of the screw rod (11), and the slider (302) is threadedly connected to the screw rod (11), and moves along the length direction of the main frame (2) under the rotation of the screw rod (11). The upper surface of the main frame (2) is also fixedly connected with a rack (10) matched with the toothed disc (304), and the rack (10) is along the length direction of the main frame (2). When the slider (302) drives the rotating disk (303) to pass through the rack (10), the rack (10) drives the toothed disc (304) to break through the restriction of the elastic limiting member and rotate exactly 180 degrees, and the rotating disk (303) after rotation is exactly engaged with the elastic limiting member.
5. The partition wall removal equipment in a foundation pit according to claim 4 is characterized in that: The main body frame (2) comprises a first main housing (201), two end housings (202) spaced apart at both ends of the main housing (201), and a plurality of adjustable housings (203) arranged between the main housing (201) and the end housings (202); adjacent adjustable housings (203), between the adjustable housing (203) and the end housings (202), and between the main housing (201) and the adjustable housing (203) are all detachably connected via bolts and nuts; the screw rod (11) is composed of a plurality of screw rod (11) segments; each screw rod (11) segment is rotatably arranged on the surface of the corresponding main housing (201), the end housing (202), and the adjustable housing (203); any two adjacent screw rod (11) segments are detachably connected via shaft hole matching and transmit power at the same time.
6. The partition wall removal equipment in a foundation pit according to claim 5, characterized in that: Lifting ears (7) are provided on both side surfaces of the two end shells (202), and the two lifting ears (7) on the same end shell (202) are commonly connected to an auxiliary cable (12), each of the auxiliary cables (12) passes through the middle partition wall (1) in the width direction and is connected to the lifting ear (7), and the width between the two auxiliary cables (12) is greater than the width between the main cables (6).
7. A construction method for removing partition walls in a foundation pit, characterized in that: In the partition wall removal equipment in the foundation pit as described in claim 6, the implementation steps are as follows: S1, evenly partitioning the partition wall (1) in the foundation pit, marking cutting lines and forming a plurality of cutting and lifting areas, opening two first lifting holes (13) for the main cable (6) to be lifted and rotating and two second lifting holes (14) for the auxiliary cable (12) to be lifted in each area to be cut, and at the same time, opening cutting holes (15) for the rope saw (301) to pass through at the four corners of each cutting area; S2, transporting the foundation pit partition wall (1) removal equipment to the corresponding upper surface of the partition wall (1) by means of a lifting device, moving the foundation pit partition wall (1) removal equipment to the corresponding position by means of rollers (9), then starting two double-piston rod hydraulic cylinders (8) and driving the outer legs (4) to clamp the partition wall (1), and fixing the main frame (2) on the surface of the partition wall (1); S3, adjusting the position of the rope saw cutting assembly (3) by the cooperation of the first driving motor (21) and the screw rod (11), passing one end of the rope saw (301) through the pre-opened cutting hole (15), and then fine-adjusting the position of the rope saw cutting assembly (3) to ensure that the rope saw (301) is aligned with the boundary line of adjacent cutting areas in the vertical plane, and starting cutting after the position is adjusted; when the screw rod (11) drives the rope saw cutting assembly (3) to move along the length direction of the main frame (2), the angle of the driving assembly can be adjusted by the cooperation of the rack (10) and the toothed disc (304), so that the surfaces on both sides of the middle partition wall (1) can be cut quickly and conveniently; S4, while cutting the middle partition wall (1), pass the main cable (6) and the auxiliary cable (12) through the corresponding lifting holes and connect them to the corresponding lifting ears (7) and the lifting pulley (5); S5, after both sides of the middle partition wall (1) are cut, the lifting device applies a certain vertical upward pulling force to the main frame (2), and then the construction personnel cut the bottom end of the middle partition wall (1) in the divided cutting area. After the cutting is completed, the middle partition wall (1) in this cutting area is separated, and then slowly lifted to other places by the lifting device, completing the cutting and lifting work of part of the middle partition wall (1); S6, repeating the above contents, can realize semi-automatic continuous cutting operation of the middle partition wall (1), wherein, by adding or removing a certain number of adjustable shells (203), the length of the main frame (2) can be adjusted, thereby realizing construction operations on cutting areas of different sizes.