Anti-skid treatment method for river-side roadbed in soft soil area

By using the cement soil core wall method in the construction of the Linhe side roadbed in soft soil area, combined with the lattice layout of cement mixing piles and prefabricated pipe piles, an anti-slip wall is formed, which solves the problem of roadbed slippage and improves structural stability and construction efficiency meet the needs of river and surging embankment foundations and reduce the project cost.

CN118895693APending Publication Date: 2024-11-05珠海城建市政建设有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411210584.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

During the construction of the roadbed on the riverside side of the soft soil area, due to factors such as thick silt layer, high moisture content and thin overlying fill, conventional soft foundation treatment methods are prone to instability and slippage of the roadbed, resulting in construction quality accidents and economic losses.

Method used

The cement soil core wall method is adopted. By setting cement mixing piles and prefabricated pipe piles in the soft soil area, a lattice cement soil core wall is formed, and the C30 concrete crown beam and slab are connected on the basis of it to enhance resistance. Shear strength, combined with cofferdam construction and subgrade leveling treatment, ensure the stability of the subgrade.

Benefits of technology

Effectively prevent roadbed slippage, improve the shear strength and structural stability of cement-core walls, reduce the project cost, and meet the needs of river and surfing embankment foundations, and realize the stability and economical construction of the road.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118895693A_ABST
    Figure CN118895693A_ABST
Patent Text Reader

Abstract

The invention discloses a soft soil area river side roadbed anti-sliding treatment method which comprises the steps that S1, cofferdam construction is conducted, S2, filling and leveling are conducted, S3, mixing pile construction is conducted, specifically, cement mixing pile construction is conducted in sequence from the outer side close to a river branch to the inner side close to a road, cement mixing pile extension construction is conducted in the longitudinal direction of the road, and cement mixing piles are arranged in a lattice mode; s4, pile sinking construction of the prefabricated pipe piles is conducted, specifically, the prefabricated pipe piles are inserted into the cement mixing piles on the outer side, and reinforcing steel bars are inserted into the cement mixing piles on the inner side; s5, pile foundation detection and crown beam construction; s6, inner side roadbed soft foundation treatment construction is conducted; s7, roadbed slope protection construction is conducted; and S8, the temporary construction cofferdam in the river branch is cleaned, and the river channel is recovered. According to the construction process, the cement soil and the core wall are adopted, the stability of the roadbed is met, meanwhile, the river bank foundation is also used, the construction cost can be saved, and the problem of slippage of the soft soil roadbed is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of soft soil roadbed construction, and in particular to an anti-slip treatment method for a riverside roadbed in a soft soil area. Background Art

[0002] The following are the commonly used methods for soft soil roadbed treatment:

[0003] Composite foundation method: cement soil mixing piles, rotary jet grouting piles, crushed stone piles, CFG piles, prefabricated pipe piles, etc.; drainage consolidation method: preloading, vacuum preloading and vacuum combined preloading; dynamic compaction method; shallow filling method.

[0004] In areas with thick soft soil, such as roadbed construction near rivers, due to the large height difference of the free surface, the generally thick silt layer, the high water content, the saturated and plastic state, and the thin overlying fill layer, etc., the roadbed is prone to instability and slippage when the above-mentioned conventional soft foundation treatment method is used for roadbed construction, resulting in large property losses and serious construction quality accidents. In view of this, the inventors propose an anti-skid treatment design scheme and method to solve the problem of roadbed slippage under such circumstances. Summary of the invention

[0005] The purpose of the present invention is to provide an anti-slip treatment method for the riverside roadbed in a soft soil area. By adopting a cement soil core wall, the roadbed stability is met while serving as the river bank foundation, and the project cost can be saved, thereby solving the slip problem of the soft soil roadbed.

[0006] To achieve the above object, the technical solution adopted by the present invention is:

[0007] The present invention provides a method for anti-sliding treatment of river-side roadbed in a soft soil area, comprising the following steps:

[0008] S1. Cofferdam construction: A wide temporary cofferdam is set outside the wall of the river road, and the cofferdam is higher than the normal water level;

[0009] S2. Filling and leveling: Filling and leveling in the target construction area;

[0010] S3, cement mixing pile construction: cement mixing pile construction is carried out in sequence from the outer side of the river to the inner side of the road, and then cement mixing pile extension construction is carried out along the longitudinal direction of the road. The cement mixing piles are arranged in a lattice structure;

[0011] S4. Prefabricated pipe pile sinking construction: insert prefabricated pipe piles into the outer cement mixing piles, and insert steel bars into the inner cement mixing piles;

[0012] S5. Pile foundation inspection and cap beam construction: After the cement mixing piles reach the age, the pile foundation inspection is carried out. After the requirements are met, reverse excavation is carried out to carry out C30 thin-walled concrete cap beam construction. The concrete cap beam connects the adjacent pipe piles into a whole, and C30 concrete slabs are constructed. The concrete slab connects the pipe piles with the inner cement mixing piles to form a cement soil core wall;

[0013] S6. Carry out the construction of inner roadbed soft foundation treatment;

[0014] S7. Carry out roadbed slope protection construction;

[0015] S8. Clear the temporary construction cofferdams in the river and restore the river channel.

[0016] Furthermore, the cofferdam construction in step S1 specifically includes: setting up a 2m wide temporary construction cofferdam on the river side, and pumping water in the cofferdam area to make the cofferdam at least 50cm higher than the normal water level.

[0017] Furthermore, the spacing between the cement mixing piles in the lattice arrangement is 60 cm, the lattice size is 1.8 m×1.8 m, and it is composed of 2 groups of lattices.

[0018] Furthermore, the cement mixing pile has the following construction requirements:

[0019] S31. The diameter of cement mixing pile is 800mm. Single-shaft deep mixer is used for cement mixing pile. The pile body of cement mixing pile adopts 42.5 grade ordinary Portland cement, cement content is 180kg / m, water-cement ratio is 0.5-0.6. Before the construction of cement mixing pile, the original soil shall be taken for indoor test, and the mixing ratio of cement and admixture shall be determined according to the mix ratio report.

[0020] S32. During the construction of cement mixing piles, the grouting time and the mortar stopping time shall be controlled, and the grouting shall not be interrupted to ensure the pile length. Drilling and lifting work shall not be carried out before the grouting. The construction of cement mixing piles adopts the four-mixing and four-spraying process, the lifting speed of the mixing shaft is <0.8 / min, the verticality of the mixing pile reaches 99%, the pile plane deviation is not more than 50mm, and the pile diameter deviation is not more than ±10mm;

[0021] S33. Cement mixing piles should be excavated and inspected within one week after construction or the quality of the piles should be checked by drilling and coring. If they do not meet the design requirements, the construction process should be adjusted. Before excavating the earth, the piles should be drilled and cored. The compressive strength of cement mixing piles should be ≥1.0MPa after 28 days.

[0022] S34. The construction interval between adjacent cement mixing piles shall not exceed 24 hours. If it exceeds the time limit, the construction of adjacent cement mixing piles shall be slowed down. If the overlap is impossible or the overlap is poor due to too long a time limit, measures shall be taken to make additional cement mixing piles or rotary jet piles at the overlap.

[0023] Furthermore, the prefabricated pipe pile sinking construction specifically includes: driving PRC500Ⅱ(125) prefabricated pipe piles on the outside of the wall, with a pipe pile spacing of 1.2m, inserting 6m long C16 steel bars into the cement mixing piles on the inside of the wall, connecting adjacent pipe piles into a whole with a 700×500 C30 concrete crown beam, and connecting the prefabricated pipe piles and the cement mixing piles on their inside with a 150mm thick C30 concrete slab.

[0024] Furthermore, the prefabricated pipe pile sinking has the following construction requirements:

[0025] S41. Within 12 hours after the completion of cement mixing pile construction, the prefabricated pipe piles shall be sunk by a vibrating hammer pile driver;

[0026] S42. If the underlying geological layer is a hard soil layer, a pilot hole should be made before the cement mixing pile construction;

[0027] S43. When the first section of pile is inserted, check the verticality deviation of the pile position and pile body. The verticality deviation after correction should be ±0.5%, and the pile plane deviation should not exceed 50mm;

[0028] S44. The pile foundation is constructed by welding. The pipe pile is extended by welding the pile end plate along the circumferential groove. A guide hoop is provided at the head of the lower pile. The deviation between the upper and lower pile sections should not be greater than 2mm. Before welding, confirm whether the pipe pile joint is qualified.

[0029] Furthermore, the pile foundation detection includes:

[0030] S51. Cement mixing pile inspection: The integrity of the pile body shall be inspected by core extraction method, and the number of inspections shall not be less than 1% of the total number and shall not be less than 3 locations;

[0031] S52. Inspection of prefabricated pipe piles: Use low-strain method to inspect the integrity of the pipe pile body. The number of integrity inspections should not be less than 20% of the total number of piles.

[0032] S53. Composite foundation bearing capacity test: The characteristic value of composite foundation bearing capacity shall not be less than 120 kPa. The number of tests shall not be less than 0.5% of the total number and shall not be less than 3 locations.

[0033] After adopting the above scheme, the present invention has the following beneficial effects:

[0034] 1. The existing single cement soil mixing pile has low shear strength and is difficult to achieve anti-slip effect. The present invention adopts a lattice-shaped cement soil core wall and inserts PRC500Ⅱ(125) prefabricated pipe piles (prestressed pipe piles) into the cement mixing piles on the outer side of the cement soil core wall to improve the shear strength of the cement soil. The pile tops are connected by thin-walled reinforced concrete crown beams (C30 concrete crown beams) to form a whole. After the construction of the cement soil core wall is completed, the strength will increase accordingly with the increase of age. Therefore, this method has a stable structure and good mechanical properties.

[0035] Second, the cement soil core wall includes cement mixing piles and prefabricated pipe piles. Single piles are common construction processes with mature construction processes and guaranteed quality. The construction process of the present invention improves the cement soil wall structure, thereby not only improving the wall strength on the basis of the existing process, but also ensuring the construction efficiency and quality;

[0036] 3. The cement soil core wall is implemented on the river side, which not only plays an anti-slip protection role for the road, but also serves as the foundation of the river bank, serving two purposes;

[0037] Fourth, under the premise of meeting stability, the cost of the present invention is relatively low. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is a process diagram of the anti-sliding treatment method of the riverside roadbed in soft soil areas;

[0039] Figure 2 It is the plan layout of the cement soil core wall;

[0040] Figure 3 This is the elevation layout drawing of the cement soil core wall.

[0041] Description of symbols

[0042] Cement mixing piles 1, prefabricated pipe piles 2, steel bars 3, C30 concrete cap beams 4, C30 concrete slabs 5, actual riverbed line 6, mortar-laid stone footings 7, mortar-laid stone slope protection 8. DETAILED DESCRIPTION

[0043] like Figure 1 As shown, the present invention discloses a method for anti-sliding treatment of riverside roadbed in soft soil area, the steps are as follows:

[0044] S1. Cofferdam construction: Set up a 2m wide temporary construction cofferdam on the river side, pump water in the cofferdam area, and make the cofferdam at least 50cm above the normal water level. The cofferdam construction includes the following specific requirements in the entire roadbed construction:

[0045] S11. Cofferdam construction process: including riverbed dredging, riprap treatment, bagging, stacking, pumping, filling and leveling, cement soil core wall construction, and cofferdam removal;

[0046] S12. Cofferdam materials: Use straw bags, sacks, or woven bags to hold soil for cofferdam construction. Fill the bags to 70% of the capacity and sew the bag mouths shut to prevent soil leakage.

[0047] S13. Stacking requirements: Build the upstream cofferdam first, then build the downstream, and the independent cofferdam should also be closed from upstream to downstream. For the earth bags stacked in the water, iron hooks or iron cages can be welded with steel bars to send the bags into the water. The upper and lower layers and the inner and outer layers should be staggered accordingly, and the stacking should be as dense and neat as possible;

[0048] S13. After the cofferdam is repaired, water is pumped out to check for water leakage in the cofferdam. The pumping speed should be slow at the beginning so that the cofferdam can gradually withstand the water pressure and complete pre-deformation to prevent the cofferdam from collapsing due to excessive pumping.

[0049] S14. When dismantling the cofferdam, start from the downstream, and dismantle it step by step from the top to the bottom of the cofferdam, and from the back water side to the front water side.

[0050] S2. Filling and leveling: Filling and leveling are carried out in the target construction area to provide a construction platform for the construction of cement mixing piles and prefabricated pipe piles;

[0051] S3. Cement mixing pile construction: Cement mixing pile construction is carried out in sequence from the outer side near the river to the inner side near the road, and then the cement mixing pile extension construction is carried out along the longitudinal direction of the road. The cement mixing piles are arranged in a lattice structure; the spacing between the cement mixing piles in the lattice structure is 60 cm, the lattice size is 1.8m×1.8m, and it consists of 2 groups of lattices.

[0052] Furthermore, the cement mixing pile has the following construction requirements:

[0053] S31. The diameter of cement mixing pile is 800mm. Single-shaft deep mixer is used for cement mixing pile. The pile body of cement mixing pile adopts 42.5 grade ordinary Portland cement, cement content is 180kg / m, water-cement ratio is 0.5-0.6. Before the construction of cement mixing pile, the original soil shall be taken for indoor test, and the mixing ratio of cement and admixture shall be determined according to the mix ratio report.

[0054] S32. During the construction of cement mixing piles, the grouting time and the mortar stopping time must be controlled, and the grouting must not be interrupted to ensure the pile length. Drilling and lifting work must not be carried out before the grouting. The construction of cement mixing piles adopts the four-mixing and four-spraying process, the lifting speed of the mixing shaft is <0.8 / min, the verticality of the mixing pile reaches 99%, the pile plane deviation is not more than 50mm, the pile diameter deviation is not more than ±10mm, and the pile top and pile bottom elevations should meet the design requirements;

[0055] S33. Cement mixing piles should be excavated and inspected within one week after construction or the quality of the piles should be checked by drilling and coring. If they do not meet the design requirements, the construction process should be adjusted. Before excavating the earthwork, the piles should be drilled and cored. The compressive strength of cement mixing piles should be ≥1.0MPa after 28 days.

[0056] S34. The construction interval between adjacent cement mixing piles shall not exceed 24 hours. If it exceeds the time limit, the construction of adjacent cement mixing piles shall be slowed down to ensure the quality of the overlap. If the overlap is impossible or poor due to a long time, measures shall be taken to make additional cement mixing piles or rotary jet piles at the overlap to ensure the construction quality of the cement mixing piles.

[0057] S4. Prefabricated pipe pile sinking construction: Figure 2 and 3 As shown, a prefabricated pipe pile 2 (prestressed pipe pile) is inserted into the cement mixing pile 1 on the outer side (on the river side), and a steel bar 3 is inserted into the cement mixing pile on the inner side (on the road side); this step specifically includes: driving PRC500Ⅱ(125) prefabricated pipe piles (with steel pile tips) on the outer side of the wall (on the river side), with a pipe pile spacing of 1.2m, inserting 6m long C16 steel bars into the cement mixing piles on the inner side of the wall (on the road side), connecting adjacent pipe piles into a whole by a 700×500 C30 concrete crown beam 4, and connecting the prefabricated pipe pile and the cement mixing pile on its inner side by a 150mm thick C30 concrete slab 5.

[0058] The prefabricated pipe pile sinking has the following construction requirements:

[0059] S41. Within 12 hours after the completion of cement mixing pile construction, prefabricated pipe piles are sunk by vibrating hammer pile driver. Due to the proximity to the river, the deadweight and construction working surface of the static pressure pile driver are too large to be applicable to this working condition. The vibration of the hammer pile driver during construction is large, and the stability during construction is difficult to guarantee, which also affects the quality of the mixing pile. The machine moves slowly and cannot match the construction period of the mixing pile. Considering that the strength of the pile body is low after the mixing pile construction, the pipe piles of this method are sunk by vibrating hammer pile driver, and the pipe piles are hoisted by crane to reduce the impact of the pipe pile sinking construction on the quality of the cement mixing pile and the stability of the cofferdam. One vibrating hammer pile driver is matched with multiple cement mixing pile drivers to improve construction efficiency.

[0060] S42. If the underlying geological layer is a hard soil layer such as strongly weathered or moderately weathered, a pilot hole should be made before the cement mixing pile construction to meet the needs of pile sinking construction;

[0061] S43. When the first section of pile is inserted, the pile position and pile body verticality deviation should be checked. The verticality deviation after correction should be ±0.5%, and the pile plane deviation should not exceed 50mm;

[0062] S44. The pile foundation is constructed by welding. The extension of the pipe pile is welded along the circumferential groove of the pile end plate. The lower pile head must be equipped with a guide hoop. The deviation of the upper and lower pile sections should not be greater than 2mm. Before welding, confirm whether the pipe pile joint is qualified. The upper and lower end plates should be cleaned with a wire brush and kept dry. The groove should be brushed until the metallic luster is exposed, and the oil stains and rust should be cleaned. Before welding, six symmetrical spot weldings are performed on the circumference of the groove. After the upper and lower pile sections are fixed, the guide hoop is removed, and then the welding is performed in layers and symmetrically. Defects such as slag inclusions or pores are not allowed. After manual welding, it must be cooled naturally before continuing to be applied. It is strictly forbidden to use water cooling or to apply immediately after welding.

[0063] S5. Pile foundation inspection and cap beam construction: After the construction of cement mixing piles and prestressed pipe piles, the pile body quality needs to be inspected to determine whether the pile quality can meet the design requirements. Specifically, the pile foundation is inspected after the cement mixing piles reach the age. After the requirements are met, reverse excavation is carried out to construct C30 thin-walled concrete cap beams. The concrete cap beams connect the adjacent pipe piles into a whole, and C30 concrete slabs are constructed. The concrete slabs connect the pipe piles with the inner cement mixing piles to form a cement soil core wall.

[0064] The pile foundation detection includes:

[0065] S51. Cement mixing pile inspection: The integrity of the pile body shall be inspected by core extraction method, and the number of inspections shall not be less than 1% of the total number and shall not be less than 3 locations;

[0066] S52. Inspection of prefabricated pipe piles: Use low-strain method to inspect the integrity of the pipe pile body. The number of integrity inspections should not be less than 20% of the total number of piles.

[0067] S53. Composite foundation bearing capacity test: The characteristic value of composite foundation bearing capacity shall not be less than 120 kPa. The number of tests shall not be less than 0.5% of the total number and shall not be less than 3 locations.

[0068] S6. Carry out the construction of inner roadbed soft foundation treatment;

[0069] S7. Carry out roadbed slope protection construction;

[0070] S8. Clear the temporary construction cofferdams in the river and restore the river channel.

[0071] Anti-slide pile monitoring: Relevant displacement monitoring is required during the construction of anti-slide piles, road filling and road operation to dynamically understand the deformation of the anti-slide piles and provide guidance for subsequent construction.

[0072]

[0073] Table 1: Anti-slide pile monitoring requirements

[0074] When the monitoring values ​​are relatively stable, the monitoring frequency can be reduced to once / 3 days to once / 4 days.

[0075] The monitoring will end 2 years after construction, the monitoring frequency will be once every month half a year after construction, and once every 2 months after 1 year after construction.

[0076] The above description is only an implementation example of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for anti-sliding treatment of riverside roadbed in soft soil area, characterized in that: The following steps are involved: S1. Cofferdam construction: A wide temporary cofferdam is set outside the wall of the river road, and the cofferdam is higher than the normal water level; S2. Filling and leveling: Filling and leveling in the target construction area; S3, cement mixing pile construction: cement mixing pile construction is carried out in sequence from the outer side of the river to the inner side of the road, and then the cement mixing pile extension construction is carried out along the longitudinal direction of the road. The cement mixing piles are arranged in a lattice structure; S4. Prefabricated pipe pile sinking construction: insert prefabricated pipe piles into the outer cement mixing piles, and insert steel bars into the inner cement mixing piles; S5. Pile foundation inspection and cap beam construction: After the cement mixing piles reach the age, the pile foundation inspection is carried out. After the requirements are met, reverse excavation is carried out to carry out C30 thin-walled concrete cap beam construction. The concrete cap beam connects the adjacent pipe piles into a whole, and C30 concrete slabs are constructed. The concrete slab connects the pipe piles with the inner cement mixing piles to form a cement soil core wall; S6. Carry out the soft foundation treatment construction on the inner side of the roadbed; S7. Carry out roadbed slope protection construction; S8. Clear the temporary construction cofferdams in the river and restore the river channel.

2. The method for anti-sliding treatment of riverside roadbed in soft soil area according to claim 1, characterized in that The cofferdam construction described in step S1 specifically includes: setting up a 2m wide temporary construction cofferdam on the river side, and pumping water in the cofferdam area to make the cofferdam at least 50cm higher than the normal water level.

3. The anti-sliding treatment method for riverside roadbed in soft soil area according to claim 1, characterized in that: The spacing between the cement mixing piles in the lattice arrangement is 60 cm, the lattice size is 1.8 m×1.8 m, and it is composed of 2 groups of lattices.

4. The anti-sliding treatment method for riverside roadbed in soft soil area according to claim 1, characterized in that The cement mixing pile has the following construction requirements: S31. The diameter of cement mixing pile is 800mm. Single-shaft deep mixer is used for cement mixing pile. The pile body of cement mixing pile adopts 42.5 grade ordinary Portland cement, cement content is 180kg / m, water-cement ratio is 0.5-0.

6. Before the construction of cement mixing pile, the original soil shall be taken for indoor test, and the mixing ratio of cement and admixture shall be determined according to the mix ratio report. S32. During the construction of cement mixing piles, the grouting time and the mortar stopping time shall be controlled, and the grouting shall not be interrupted to ensure the pile length. Drilling and lifting work shall not be carried out before the grouting. The construction of cement mixing piles adopts the four-mixing and four-spraying process, the lifting speed of the mixing shaft is <0.8 / min, the verticality of the mixing pile reaches 99%, the pile plane deviation is not more than 50mm, and the pile diameter deviation is not more than ±10mm; S33. Cement mixing piles should be excavated and inspected within one week after construction or the quality of the piles should be checked by drilling and coring. If they do not meet the design requirements, the construction process should be adjusted. Before excavating the earth, the piles should be drilled and cored. The compressive strength of cement mixing piles should be ≥1.0MPa after 28 days. S34. The construction interval between adjacent cement mixing piles shall not exceed 24 hours. If it exceeds the time limit, the construction of adjacent cement mixing piles shall be slowed down. If the overlap is impossible or the overlap is poor due to too long a time limit, measures shall be taken to make additional cement mixing piles or rotary jet piles at the overlap.

5. The anti-sliding treatment method for riverside roadbed in soft soil area according to claim 1, characterized in that The prefabricated pipe pile sinking construction specifically includes: driving PRC500Ⅱ(125) prefabricated pipe piles on the outside of the wall, with a pipe pile spacing of 1.2m, inserting 6m long C16 steel bars into the cement mixing piles on the inside of the wall, connecting adjacent pipe piles into a whole with a 700×500 C30 concrete crown beam, and connecting the prefabricated pipe piles and the cement mixing piles on their inside with a 150mm thick C30 concrete slab.

6. The anti-sliding treatment method for riverside roadbed in soft soil area as claimed in claim 1, characterized in that The prefabricated pipe pile sinking has the following construction requirements: S41. Within 12 hours after the completion of cement mixing pile construction, the prefabricated pipe piles shall be sunk by a vibrating hammer pile driver; S42. If the underlying geological layer is a hard soil layer, a pilot hole should be made before the cement mixing pile construction; S43. When the first section of pile is inserted, check the verticality deviation of the pile position and pile body. The verticality deviation after correction should be ±0.5%, and the pile plane deviation should not exceed 50mm; S44. The pile foundation is constructed by welding. The pipe pile is extended by welding the pile end plate along the circumferential groove. A guide hoop is provided at the head of the lower pile. The deviation between the upper and lower pile sections should not be greater than 2mm. Before welding, confirm whether the pipe pile joint is qualified.

7. The method for anti-sliding treatment of riverside roadbed in soft soil area as claimed in claim 1, characterized in that The pile foundation detection includes: S51. Cement mixing pile inspection: The integrity of the pile body shall be inspected by core extraction method, and the number of inspections shall not be less than 1% of the total number and shall not be less than 3 locations; S52. Inspection of prefabricated pipe piles: Use low-strain method to inspect the integrity of the pipe pile body. The number of integrity inspections should not be less than 20% of the total number of piles. S53. Composite foundation bearing capacity test: The characteristic value of composite foundation bearing capacity shall not be less than 120 kPa. The number of tests shall not be less than 0.5% of the total number and shall not be less than 3 locations.