Construction method of large-diameter circular stockyard for raw coal storage and transportation system
By adopting technical means such as prefabricated square pile foundations, reinforced concrete structures and steel pipe pile support, the complexity and high cost problems of large-diameter circular material yard construction projects have been solved, and the stability and efficiency of construction have been improved, ensuring that Safety and quality.
Patent Information
- Application Number
- CN202411042354.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-08
AI Technical Summary
The construction project of large-diameter circular material yards is complex and lacks a perfect, efficient and cost-reducing construction method. It requires comprehensive consideration of multiple factors, including site selection, design, structure, materials, equipment, environmental protection and safety.
Prefabricated square pile foundation, reinforced concrete retaining wall foundation, reinforced concrete raft foundation, reinforced concrete retaining wall and underground corridor, and technical measures such as steel pipe pile support, engineering pile protection, concrete construction joint intercepting airbags and PVC formwork, Achieve the stability and efficiency of construction.
We have successfully overcome weak geological conditions, built underground corridors and raft foundations, and undamaged high piles of projects, achieving cost reduction and efficiency improvement, ensuring the safety and quality of construction.
Smart Images

Figure CN118911508A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of circular stockyard construction, and in particular to a construction method of a large-diameter circular stockyard for a raw coal storage and transportation system. Background Art
[0002] With the continuous development of my country's economy, the development of the petrochemical industry is bound to seize the opportunity of regional integrated development, take the leading petrochemical base as the foundation and core, and accelerate the construction of a number of cross-field, extended chain world-class scale and global leading level industrial clusters. The construction of a large-diameter circular material yard is a complex engineering project involving multiple considerations. It is necessary to comprehensively consider multiple factors such as site selection, design, structure, materials, equipment, environmental protection and safety. In actual operation, there is a lack of perfect, efficient and cost-saving construction methods. Summary of the invention
[0003] In order to solve the above problems, the present invention discloses a method for constructing a large-diameter circular stockyard for a raw coal storage and transportation system.
[0004] The specific plan is as follows: A method for constructing a large-diameter circular stockyard for a raw coal storage and transportation system, characterized in that the large-diameter circular stockyard comprises a prefabricated square pile foundation, a reinforced concrete retaining wall foundation, a reinforced concrete raft foundation, a reinforced concrete retaining wall and an underground corridor; specifically comprising the following steps: S1. Construction of underground corridors, retaining wall foundations and raft foundations; S2, circular material yard retaining wall construction; S3, construction of top ring beam of circular material yard; S4. Construction of dome grid foundation of circular material yard.
[0005] As a further improvement of the present invention, the prefabricated square pile foundation is composed of 1427 500mm×500mm prestressed concrete square piles with a designed pile length of 47m; the outer diameter of the reinforced concrete retaining wall foundation is 109.2m, the inner diameter is 91.6m, the thickness of the retaining wall foundation is 1.8m, and the retaining wall foundation concrete adopts C40P8 (with additives resistant to strong corrosion of sulfates and chlorides, steel bar rust inhibitors and mineral admixtures); the outer diameter of the reinforced concrete raft foundation is 91.6m, the inner diameter is 12m, and the thickness of the raft foundation is 0.5m; the outer diameter of the reinforced concrete retaining wall is 101m, the inner diameter of the wall is 100m, the wall thickness is 0.5m, the height is 17.6m, and a 1m* 1m middle ring beam, 2.7m*1m top ring beam is set on the top of the wall, the inner side of the wall is cantilevered 1m, and the outer side of the wall is cantilevered 1.2m; 36 buttresses are evenly arranged along the outer circumference of the wall; the length of the buttresses ranges from ±0.000m to +7,4m at an elevation, gradually changes from 2.5m to 1m, and the width is 1m. A reinforced concrete spherical grid foundation with a length of 1.25m, a width of 1m and a height of 2m is set on the top of each buttress; the underground corridor consists of two parts, the central tube and the underground corridor, the diameter of the central tube is 12m, the thickness of the raft foundation is 2.5m, the base elevation is -9.25m, the excavation depth is 8.65m, the total length of the underground corridor is 77.04m, and the height of the underground corridor gradually extends upward from the central tube, the thickness of the raft foundation is 1m, the thickness of the retaining wall is 0.7m, and the thickness of the top plate is 0.5m.
[0006] As a further improvement of the present invention, the construction of the circular material yard retaining wall starts after the construction of the retaining wall foundation is completed; since the retaining wall is 16.6 meters high and only 0.5 meters thick. Therefore, during the construction of the retaining wall, a ground-type disc-type scaffolding is set up inside and outside the retaining wall as a working frame for construction; the disc-type scaffolding is set up in modular form and cannot be set up in parallel according to the arc shape of the retaining wall; the outer frame is set up as an independent frame according to the spacing of the buttress columns, and the two adjacent outer frames are tied together with steel pipe fasteners in the middle of the buttress columns; the inner frame is set up as an independent frame every 6 meters, and the tie between the two adjacent frames is adjusted with steel pipe fasteners.
[0007] As a further improvement of the present invention, during the construction of the top ring beam of the circular material yard, the top elevation of the top ring beam is +17.6m; its function is to support the rotating arm of the stacker and reclaimer and the short column of the dome grid; the construction position of the top ring beam is at the top of the retaining wall, the beam is 1 meter high and 2.7 meters wide, and its formwork support construction belongs to an ultra-dangerous large project. In order to save construction costs and speed up construction progress, the requirements for the erection of the high formwork of the top ring beam must be comprehensively considered before the construction of the retaining wall scaffolding. After the construction of the retaining wall is completed, before the construction of the top ring beam, the retaining wall work frame must be changed to the top ring beam high formwork for reinforcement and transformation in accordance with the construction plan that has been approved by the supervisor after expert demonstration.
[0008] As a further improvement of the present invention, in the construction of the underground corridor, the foundation pit of the underground corridor is arranged in a rectangular shape along the east-west direction; the foundation pit is 85.5m long and 18m wide; the circumference is 189.7m, and the area is 1192㎡; the excavation depth of the foundation pit is 7.25m except for the 18m area on the west side of the foundation pit, which is 8.6m deep; among them, 630×14 type 18m steel pipe piles and 500mm diameter and 10m long high-pressure rotary spraying silt squeezing piles are used for support in the central tube of the underground corridor, and 630×14 type 18m steel pipe piles and 500mm diameter and 10m long high-pressure rotary spraying silt squeezing piles are used in the rest of the parts. The support system is designed with three enclosure supports: the first one uses reinforced concrete crown beams with 600×12 steel pipe top supports, the second one uses HW400X400X13X21 double-jointed I-beams with 600×12 steel pipe top supports; the third one uses 1m thick plain concrete with the same strength as the raft foundation; the bottom of the underground corridor foundation pit uses high-pressure jet grouting piles with a diameter of 700mm, a length of 6 meters, and a spacing of 500mm for bite solidification. This support scheme fully considers the characteristics of the geological conditions of under-consolidated silty soil, which not only provides a stable and safe foundation pit support environment for the underground corridor, but also the base high-pressure jet grouting piles firmly consolidate the underground corridor raft foundation engineering piles, which plays a positive role in the protection of engineering high piles during the deep foundation pit support process.
[0009] As a further improvement of the present invention, measures need to be taken to protect the engineering high piles in the adjacent 2.5m wide area between the raft foundation and the retaining wall foundation, the raft foundation and the underground corridor steel pipe pile support, the underground corridor retaining wall and the steel pipe pile support, and the retaining wall foundation and the underground corridor retaining wall, according to the different excavation depths of the engineering high piles, to prevent the piles from being skewed or broken.
[0010] (1) When the excavation depth of the soil on one side of the engineering high pile does not exceed 1.5m, prevent the lateral soil creep from causing the pile to deviate; the parts where such a situation is prone to occur are the joints between the raft foundation and the steel sheet pile support of the retaining wall foundation, the joints between the raft foundation and the steel pipe pile support of the underground corridor, and the joints between the retaining wall foundation and the steel pipe pile support of the underground corridor. The high pile protection measures taken for the above situations are: (a) Before excavation of the foundation pit, the site for high-pile engineering is leveled, and HRB400 steel mesh with a diameter of 8mm@200mm is tied on it, and then 150mm thick C20 concrete is poured; each side of the concrete pouring area exceeds the boundary line of the foundation pit excavation by no less than 5m to ensure that the adjacent engineering piles and the surrounding engineering piles in good condition form a tie-in as a whole to jointly resist the lateral force of the eccentric piles; (b) Before the excavation of the foundation pit, the construction of the raft foundation or retaining wall foundation has begun. In this case, the gravity of the foundation concrete is used to resist the lateral pressure of the soil. The specific method is to use 22mm diameter HRB400 steel bars to complete the sealing sleeve of the adjacent engineering high piles, and then connect the sleeve to 2 additional steel bars pre-buried in the nearby foundation concrete, and then use wooden wedges to wedge the engineering high piles and the sleeves tightly. On this basis, part of the soil around the engineering high piles can also be appropriately excavated to reduce the soil height and reduce the lateral pressure of the soil.
[0011] (2) When the excavation depth of the soil around the engineering high pile exceeds 1.5m, prevent the occurrence of broken piles due to pile deviation; the greater the excavation depth, the greater the possibility of broken piles due to pile deviation; this situation mainly occurs on the engineering high piles inside the supporting structure and between the structural entities, including the engineering piles between the inner side of the steel pipe pile support of the underground corridor and the outer side of the raft foundation of the underground corridor; in this case, the engineering high pile protection measures are taken with the help of the steel pipe pile support stabilization system; (a) Use 22mm diameter HRB400 steel bars to seal the adjacent engineering piles, then weld the hoop to two steel pipe piles, and then use wooden wedges to wedge the engineering piles and the hoop tightly; add a hoop steel bar every 2m, excavate in layers, and add in layers; when the adjacent engineering piles are too close to the steel pipe piles, cast the engineering piles and reinforced concrete cap beams as a whole.
[0012] As a further improvement of the present invention, in the construction of the raft foundation, according to the underground corridor support position and the distribution of the raft post-casting belt, there are ten construction areas from A to G; in order to meet the ground traffic conditions such as the underground corridor construction material transportation station, the raft foundation construction sequence must be carried out around the underground corridor construction; this project considers the comprehensive factors affecting transportation, material stacking, on-site processing and cross-operation construction in adjacent areas, and proposes the construction sequence of each area of the raft foundation as follows: EABGIJDCHF; among them, the concrete construction joint construction airbag used by the civil construction is quoted, and the specific construction method is as follows: (1) Tie the concrete intercepting airbag limiting steel bars to the steel mesh at the location of the temporary concrete construction joint; (2) A supporting steel bar is installed every 500 mm outside the concrete intercepting airbag limiting steel bar; (3) Concrete interception airbags are laid inside the concrete interception airbag limiting steel bars. The number of interception airbags laid should be sufficient to inflate and seal the construction joints; (4) Inflate the interception airbags in the concrete and check the airtightness of the construction joints. If the airtightness is not tight, add more airbags if necessary; (5) After passing the self-inspection, apply for acceptance and pour concrete; (6) During the pouring process, check the air leakage of the interception air bag and replenish compressed air in time to ensure the construction effect of the interception air bag; (7) After the concrete has finally set, release the compressed air in the interception airbag, clean the cement slurry on the surface of the airbag, and keep it for maintenance.
[0013] As a further improvement of the present invention, the circular material yard retaining wall is a reinforced concrete thin-walled silo structure; and the circular material yard retaining wall is a curved structure, which is difficult to construct and requires high tensile strength on the template surface. Although traditional wooden plywood is relatively durable, as the number of turnovers increases, after 2 to 3 curved surface force turnovers, the template is prone to debonding, and scabbing or peeling will appear on the outer surface of the board, resulting in a large amount of manpower required for exterior repairs on the retaining wall surface. In addition, the wooden formwork uses wooden squares or self-made limiting steel bars to control the cross-sectional dimensions, and the method is simple and the management is relatively extensive. PVC formwork is used to solve the problem of template peeling and scabbing; the wall section internal support used in conjunction with it is customized and installed on-site according to the construction drawings, which can more accurately control the wall section size and reduce the waste of concrete volume caused by expanding the formwork and excessively long internal supports. The specific construction method is as follows: (1) Open the tensioning holes at the appropriate positions of the PVC formwork according to the formwork construction plan; (2) Fix the PCV formwork inside the wall; (3) Tie rods through the wall; (4) Put the PVC formwork supporting top support on the tie rod; (5) Install the outer PVC formwork; (6) Strengthen the inner and outer formwork and tie the tie rods to ensure the wall interface dimensions; (7) Adjust the verticality of the wall formwork and pour concrete after acceptance; (8) After the concrete curing is completed, the PCV formwork is removed and the stack is cleaned and ready for use.
[0014] As a further improvement of the present invention, during the construction of the circular material yard top ring beam, the top elevation of the top ring beam is 17.6m; plus the beam height of 1m and the beam width of 2.7m; the structure of the top ring beam itself is not complicated, except that 0.5m of the beam is located on the circular material yard retaining wall, the inner side of the wall is cantilevered by 1m, and the outer side of the wall is cantilevered by 1.2m. This makes the inner and outer cantilevered parts become super-dangerous large engineering structural units, and its high formwork system needs to be constructed after expert demonstration. The top ring beam is located on the upper part of the retaining wall, and the top ring beam structure construction can only be carried out after the retaining wall construction is completed. In order to facilitate the rapid transformation of the retaining wall enclosure frame that was previously used as a top ring beam formwork support frame, and then comprehensively consider factors such as different functional requirements when constructing the disc-type scaffolding body in different structural parts; the load-bearing problem of the vertical poles for the top ring beam has been calculated during the retaining wall construction, and the stability and rigidity of the frame can be considered later. The specific measures are as follows: (1) The two vertical poles of the scaffolding on the inner side of the circular material yard are hung with diagonal bars along the entire length of the frame from top to bottom; (2) Two additional wall ties are installed at 7.8m and 13.8m above the top elevation of the raft slab through wall tie rods with a diameter of 18mm; the spacing between the wall tie rods in each row is about 3m, and they are arranged perpendicular to the original steel pipe wall tie rods; (3) Add horizontal diagonal rods or steel pipe scissors braces; add a horizontal diagonal rod or steel pipe scissors brace along the longitudinal direction of the horizontal rod near each wall connection of the inner frame of the circular material yard; add a horizontal diagonal rod or steel pipe scissors brace at the sweeping rod position; add a horizontal diagonal rod or steel pipe scissors brace near the horizontal rod of the wall connection from the middle ring beam upwards of the outer frame of the circular material yard; add a full-length diagonal rod along the longitudinal direction of the four vertical rods on both sides of the wall between the top two through-wall rods.
[0015] The beneficial effects of the present invention are as follows: through technical measures such as steel pipe pile support and engineering pile protection, the weak geological conditions are successfully overcome, an underground corridor and a raft foundation are built, and no engineering high piles are damaged; through the good application of concrete construction joint interception air bags and PVC formwork new materials and new processes, cost reduction and efficiency improvement are achieved. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a flow chart of the present invention.
[0017] Figure 2 Schematic diagram of retaining wall construction.
[0018] Figure 3 Schematic diagram of the top ring beam construction.
[0019] Figure 4 This is a schematic diagram of the underground corridor construction.
[0020] Figure 5 This is the construction flow chart of the underground corridor support scheme.
[0021] Figure 6 This is a schematic diagram of the high pile protection construction of the project.
[0022] Figure 7 Schematic diagram of preventing pile breakage due to pile deviation when the excavation depth of soil around the engineering high pile exceeds 1.5m. DETAILED DESCRIPTION
[0023] The present invention will be further explained below in conjunction with the accompanying drawings and specific embodiments. It should be understood that the following specific embodiments are only used to illustrate the present invention and are not used to limit the scope of the present invention.
[0024] The geomorphic unit of the large-diameter circular material yard of the raw coal storage and transportation system of a certain project is a marine plain. The site was originally dominated by salt pans. The shallow strata are mainly under-consolidated clay soils accumulated in marine, coastal and continental phases since the Holocene. The most notable feature is the horizontal bedding development of the strata. The groundwater of the site is mainly surface groundwater, and the stable water level is 1.77~2.08m.
[0025] As shown in the figure, the present invention provides a method for constructing a large-diameter circular stockyard for a raw coal storage and transportation system, wherein the large-diameter circular stockyard includes a prefabricated square pile foundation, a reinforced concrete retaining wall foundation, a reinforced concrete raft foundation, a reinforced concrete retaining wall and an underground corridor; specifically, the following steps are included: S1. Construction of underground corridors, retaining wall foundations and raft foundations; S2, circular material yard retaining wall construction; S3, construction of top ring beam of circular material yard; S4. Construction of dome grid foundation of circular material yard.
[0026] In this embodiment, the prefabricated square pile foundation is composed of 1427 500mm×500mm prestressed concrete square piles with a designed pile length of 47m; the outer diameter of the reinforced concrete retaining wall foundation is 109.2m, the inner diameter is 91.6m, the thickness of the retaining wall foundation is 1.8m, and the retaining wall foundation concrete adopts C40P8 (with additives resistant to strong corrosion of sulfates and chlorides, steel bar rust inhibitors and mineral admixtures); the outer diameter of the reinforced concrete raft foundation is 91.6m, the inner diameter is 12m, and the thickness of the raft foundation is 0.5m; the outer diameter of the reinforced concrete retaining wall is 101m, the inner diameter of the wall is 100m, the wall thickness is 0.5m, the height is 17.6m, and a 1m*1m center hole is set at the middle of the outer side of the wall +7.400m Ring beam, a 2.7m*1m top ring beam is set on the top of the wall, the inner side of the wall is cantilevered 1m, and the outer side of the wall is cantilevered 1.2m; 36 buttresses are evenly arranged along the outer circumference of the wall; the length of the buttresses ranges from ±0.000m to +7,4m at an elevation, gradually changes from 2.5m to 1m, and the width is 1m. A reinforced concrete spherical grid foundation with a length of 1.25m, a width of 1m and a height of 2m is set on the top of each buttress; the underground corridor consists of two parts: a central tube and an underground corridor. The diameter of the central tube is 12m, the thickness of the raft foundation is 2.5m, the base elevation is -9.25m, the excavation depth is 8.65m, the total length of the underground corridor is 77.04m, and the height of the underground corridor gradually extends upward from the central tube. The thickness of the raft foundation is 1m, the thickness of the retaining wall is 0.7m, and the thickness of the top plate is 0.5m.
[0027] In this embodiment, the construction of the circular material yard retaining wall begins after the construction of the retaining wall foundation is completed; since the retaining wall is 16.6 meters high and only 0.5 meters thick, ground-type disc-type scaffolding is set up inside and outside the retaining wall as a work frame for construction; the disc-type scaffolding is set up in modular form and cannot be set up in parallel according to the arc shape of the retaining wall; the outer frame is set up as an independent frame according to the spacing of the buttress columns, and the two adjacent outer frames are tied together with steel pipe fasteners in the middle of the buttress columns; the inner frame is set up as an independent frame every 6 meters, and the tie between the two adjacent frames is adjusted with steel pipe fasteners.
[0028] In this embodiment, during the construction of the top ring beam of the circular material yard, the top elevation of the top ring beam is +17.6m; its function is to support the rotating arm of the stacker and reclaimer and the short column of the dome grid; the construction position of the top ring beam is at the top of the retaining wall, the beam is 1 meter high and 2.7 meters wide, and its formwork support construction belongs to an ultra-dangerous and large project. In order to save construction costs and speed up the construction progress, the requirements for the erection of the high formwork of the top ring beam must be comprehensively considered before the construction of the retaining wall scaffolding. After the construction of the retaining wall is completed, before the construction of the top ring beam, the retaining wall work frame must be changed to the top ring beam high formwork for reinforcement and transformation in accordance with the construction plan that has been approved by the supervisor after expert demonstration.
[0029] In this embodiment, during the construction of the underground corridor, the foundation pit of the underground corridor is rectangular and arranged in the east-west direction; the foundation pit is 85.5m long and 18m wide; the circumference is 189.7m, and the area is 1192㎡; except for the excavation depth of 8.6m in the 18m area on the west side of the foundation pit, the rest of the excavation depth is 7.25m; among them, 630×14 type 18m steel pipe piles and 500mm diameter and 10m long high-pressure rotary spraying silt squeezing piles are used for support in the central tube of the underground corridor, and 630×14 type 1 8m steel pipe piles and 600X210 type 18m long Larsen steel plates are used for support; the support system is designed with three enclosure supports; the first one uses reinforced concrete crown beams with 600×12 type steel pipe top supports, the second one uses HW400X400X13X21 type double-piece I-beams with 600×12 type steel pipe top supports; the third one uses 1m thick plain concrete with the same strength as the raft foundation; the bottom of the underground corridor foundation pit uses high-pressure jet grouting piles with a diameter of 700mm, a length of 6 meters, and a spacing of 500mm for bite solidification. This support plan fully considers the characteristics of the geological conditions of under-consolidated silty soil, which not only provides a stable and safe foundation pit support environment for the underground corridor, but also the base high-pressure jet grouting piles firmly consolidate the underground corridor raft foundation engineering piles together, which plays a positive role in the protection of engineering high piles during the deep foundation pit support process.
[0030] In this embodiment, measures need to be taken to protect the engineering high piles in the adjacent 2.5m wide area between the raft foundation and the retaining wall foundation, the raft foundation and the underground corridor steel pipe pile support, the underground corridor retaining wall and the steel pipe pile support, and the retaining wall foundation and the underground corridor retaining wall according to the different excavation depths of the engineering high piles to prevent them from being skewed or broken.
[0031] (1) When the excavation depth of the soil on one side of the engineering high pile does not exceed 1.5m, prevent the lateral soil creep from causing the pile to deviate; the parts where such a situation is prone to occur are the joints between the raft foundation and the steel sheet pile support of the retaining wall foundation, the joints between the raft foundation and the steel pipe pile support of the underground corridor, and the joints between the retaining wall foundation and the steel pipe pile support of the underground corridor. The high pile protection measures taken for the above situations are: (a) Before excavation of the foundation pit, the site for high-pile engineering is leveled, and HRB400 steel mesh with a diameter of 8mm@200mm is tied on it, and then 150mm thick C20 concrete is poured; each side of the concrete pouring area exceeds the boundary line of the foundation pit excavation by no less than 5m to ensure that the adjacent engineering piles and the surrounding engineering piles in good condition form a tie-in as a whole to jointly resist the lateral force of the eccentric piles; (b) Before the excavation of the foundation pit, the construction of the raft foundation or retaining wall foundation has begun. In this case, the gravity of the foundation concrete is used to resist the lateral pressure of the soil. The specific method is to use 22mm diameter HRB400 steel bars to complete the sealing sleeve of the adjacent engineering high piles, and then connect the sleeve to 2 additional steel bars pre-buried in the nearby foundation concrete, and then use wooden wedges to wedge the engineering high piles and the sleeves tightly. On this basis, part of the soil around the engineering high piles can also be appropriately excavated to reduce the soil height and reduce the lateral pressure of the soil.
[0032] (2) When the excavation depth of the soil around the engineering high pile exceeds 1.5m, prevent the occurrence of broken piles due to pile deviation; the greater the excavation depth, the greater the possibility of broken piles due to pile deviation; this situation mainly occurs on the engineering high piles inside the supporting structure and between the structural entities, including the engineering piles between the inner side of the steel pipe pile support of the underground corridor and the outer side of the raft foundation of the underground corridor; in this case, the engineering high pile protection measures are taken with the help of the steel pipe pile support stabilization system; (a) Use 22mm diameter HRB400 steel bars to seal the adjacent engineering piles, then weld the hoop to two steel pipe piles, and then use wooden wedges to wedge the engineering piles and the hoop tightly; add a hoop steel bar every 2m, excavate in layers, and add in layers; when the adjacent engineering piles are too close to the steel pipe piles, cast the engineering piles and reinforced concrete cap beams as a whole.
[0033] In this embodiment, the raft foundation construction is divided into ten construction areas from A to G according to the underground corridor support position and the distribution of the raft post-casting belt; in order to meet the ground traffic conditions such as the underground corridor construction material transportation station, the raft foundation construction sequence must be carried out around the underground corridor construction; this project considers the comprehensive factors affecting transportation, material stacking, on-site processing and cross-operation construction in adjacent areas, and proposes the construction sequence of each area of the raft foundation as follows: EABGIJDCHF; among them, the civil construction uses concrete construction joints to construct airbags, and the specific construction method is as follows: (1) Tie the concrete intercepting airbag limiting steel bars to the steel mesh at the location of the temporary concrete construction joint; (2) A supporting steel bar is installed every 500 mm outside the concrete intercepting airbag limiting steel bar; (3) Concrete interception airbags are laid inside the concrete interception airbag limiting steel bars. The number of interception airbags laid should be sufficient to inflate and seal the construction joints; (4) Inflate the interception airbags in the concrete and check the airtightness of the construction joints. If the airtightness is not tight, add more airbags if necessary; (5) After passing the self-inspection, apply for acceptance and pour concrete; (6) During the pouring process, check the air leakage of the interception air bag and replenish compressed air in time to ensure the construction effect of the interception air bag; (7) After the concrete has finally set, release the compressed air in the interception airbag, clean the cement slurry on the surface of the airbag, and keep it for maintenance.
[0034] In this embodiment, the circular material yard retaining wall is a reinforced concrete thin-walled silo structure; and the circular material yard retaining wall is a curved structure, which is difficult to construct and requires high tensile strength on the surface of the formwork. Although traditional wooden plywood is relatively durable, as the number of turnovers increases, after 2 to 3 curved surface force turnovers, the formwork is prone to debonding, and scabs or peeling will appear on the outer surface of the board, causing the retaining wall to require a lot of manpower for appearance repairs. In addition, the wooden formwork uses wooden squares or homemade limiting steel bars to control the cross-sectional dimensions, which is a simple method and relatively extensive management. PVC formwork is used to solve the problem of formwork peeling and scabbing; the wall section internal support used in conjunction with it is customized and installed on-site according to the construction drawings, which can more accurately control the wall section size and reduce the waste of concrete volume caused by expanding the formwork and excessively long internal supports. The specific construction method is as follows: (1) Open the tensioning holes at the appropriate positions of the PVC formwork according to the formwork construction plan; (2) Fix the PCV formwork inside the wall; (3) Tie rods through the wall; (4) Put the PVC formwork supporting top support on the tie rod; (5) Install the outer PVC formwork; (6) Strengthen the inner and outer formwork and tie the tie rods to ensure the wall interface dimensions; (7) Adjust the verticality of the wall formwork and pour concrete after acceptance; (8) After the concrete curing is completed, the PCV formwork is removed and the stack is cleaned and ready for use.
[0035] In this embodiment, during the construction of the circular material yard top ring beam, the top elevation of the top ring beam is 17.6m; plus the beam height of 1m and the beam width of 2.7m; the structure of the top ring beam itself is not complicated, except that 0.5m of the beam is located on the circular material yard retaining wall, the inner side of the wall is cantilevered by 1m, and the outer side of the wall is cantilevered by 1.2m. This makes the inner and outer cantilevered parts become super-dangerous large engineering structural units, and its high formwork system needs to be constructed after expert demonstration. The top ring beam is located on the upper part of the retaining wall, and the top ring beam structure construction can only be carried out after the retaining wall construction is completed. In order to facilitate the rapid transformation of the retaining wall enclosure frame that was previously used as a top ring beam formwork support frame, and then comprehensively consider the different functional requirements of the disc-type scaffolding body during the construction of different structural parts; the load-bearing problem of the vertical poles for the top ring beam has been calculated during the retaining wall construction, and the stability and rigidity of the frame can be considered later. The specific measures are as follows: (1) The two vertical poles of the scaffolding on the inner side of the circular material yard are hung with diagonal bars along the entire length of the frame from top to bottom; (2) Two additional wall ties are installed at 7.8m and 13.8m above the top elevation of the raft slab through wall tie rods with a diameter of 18mm; the spacing between the wall tie rods in each row is about 3m, and they are arranged perpendicular to the original steel pipe wall tie rods; (3) Add horizontal diagonal rods or steel pipe scissors braces; add a horizontal diagonal rod or steel pipe scissors brace along the longitudinal direction of the horizontal rod near each wall connection of the inner frame of the circular material yard; add a horizontal diagonal rod or steel pipe scissors brace at the sweeping rod position; add a horizontal diagonal rod or steel pipe scissors brace near the horizontal rod of the wall connection from the middle ring beam upwards of the outer frame of the circular material yard; add a full-length diagonal rod along the longitudinal direction of the four vertical rods on both sides of the wall between the top two through-wall rods.
[0036] The technical means disclosed in the scheme of the present invention are not limited to the technical means disclosed in the above-mentioned implementation mode, but also include technical schemes composed of any combination of the above-mentioned technical features. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications are also regarded as the protection scope of the present invention.
Claims
1. A method for constructing a large diameter circular stockyard for a raw coal storage and transportation system, characterized in that: The large diameter circular material yard comprises a prefabricated square pile foundation, a reinforced concrete retaining wall foundation, a reinforced concrete raft foundation, a reinforced concrete retaining wall and an underground corridor; specifically comprises the following steps: S1. Construction of underground corridors, retaining wall foundations and raft foundations; S2, circular material yard retaining wall construction; S3, construction of top ring beam of circular material yard; S4. Construction of dome grid foundation of circular material yard.
2. A method for constructing a large diameter circular stockyard for a raw coal storage and transportation system according to claim 1, characterized in that: The prefabricated square pile foundation is composed of prestressed concrete square piles; the concrete of the reinforced concrete retaining wall foundation adopts C40P8; a middle ring beam is arranged in the middle of the outer side of the reinforced concrete retaining wall, and a top ring beam is arranged on the top of the wall; buttresses are arranged evenly along the outer circumference of the wall; a reinforced concrete spherical grid foundation is arranged on the top of each buttress; the underground corridor is composed of two parts, a central tube and an underground corridor, and the height of the underground corridor gradually extends upward from the central tube.
3. The method for constructing a large diameter circular stockyard for a raw coal storage and transportation system according to claim 1, characterized in that: The construction of the circular material yard retaining wall begins after the construction of the retaining wall foundation is completed. During the construction of the retaining wall, ground-based disc-type scaffolding is erected inside and outside the retaining wall as a working frame for construction; the disc-type scaffolding is erected in modules, and the outer frame is erected as an independent frame according to the spacing between the buttress columns, and the two adjacent outer frames are tied together with steel pipe fasteners in the middle position of the buttress columns; the inner frame is erected as an independent frame, and the connection between the two adjacent frames is adjusted with steel pipe fasteners.
4. The method for constructing a large diameter circular stockyard for a raw coal storage and transportation system according to claim 1, characterized in that: During the construction of the top ring beam of the circular material yard, the function of the top of the top ring beam is to support the rotating arm of the stacker and reclaimer and the short columns of the dome grid; the construction position of the top ring beam is at the top of the retaining wall.
5. The method for constructing a large-diameter circular stockyard for a raw coal storage and transportation system according to claim 1, characterized in that: During the construction of the underground corridor, the foundation pit of the underground corridor is arranged in a rectangular shape along the east-west direction; steel pipe piles and high-pressure rotary grouting piles are used for support in the central tube of the underground corridor, and steel pipe piles and Larsen steel plates are used for support in the remaining parts; the support system is designed with three retaining supports; the first one adopts reinforced concrete crown beams with steel pipe top supports, the second one adopts double-piece I-beams with steel pipe top supports; the third one adopts 1m thick plain concrete with the same strength as the raft foundation; high-pressure rotary grouting piles are used for bite-lock solidification at the bottom of the foundation pit of the underground corridor.
6. The method for constructing a large diameter circular stockyard for a raw coal storage and transportation system according to claim 1, characterized in that: Measures shall be taken to protect the high piles in the adjacent 2.5m width area between the raft foundation and the retaining wall foundation, the raft foundation and the underground corridor steel pipe pile support, the underground corridor retaining wall and the steel pipe pile support, and the retaining wall foundation and the underground corridor retaining wall, according to the different excavation depths of the high piles; prevent the piles from being skewed or broken.
7. A method for constructing a large diameter circular stockyard for a raw coal storage and transportation system according to claim 6, characterized in that: (1) When the excavation depth of the soil on one side of the engineering high pile does not exceed 1.5m, prevent the lateral soil creep from causing the pile to deviate; the parts where such a situation is prone to occur are the joints between the raft foundation and the steel sheet pile support of the retaining wall foundation, the joints between the raft foundation and the steel pipe pile support of the underground corridor, and the joints between the retaining wall foundation and the steel pipe pile support of the underground corridor. The high pile protection measures taken for the above situations are: (a) Before excavation of the foundation pit, the site for high piles shall be leveled, steel mesh shall be tied on it, and then concrete shall be poured; the concrete pouring area shall extend beyond the boundary line of the foundation pit by at least 5m on each side to ensure that the adjacent engineering piles and the surrounding engineering piles in good condition form a tie-in as a whole to jointly resist the lateral force of the eccentric piles; (b) Before the excavation of the foundation pit, the raft foundation or retaining wall foundation has been constructed, and the gravity of the foundation concrete is used to resist the lateral pressure of the soil. The specific method is to use steel bars to complete the sealing sleeve of the adjacent engineering piles, and then connect the sleeve to two additional steel bars pre-buried in the nearby foundation concrete, and then use wooden wedges to wedge the engineering piles and the sleeves tightly. On this basis, part of the soil around the engineering piles can also be appropriately excavated to reduce the height of the soil and reduce the lateral pressure of the soil. (2) When the excavation depth of the soil around the engineering high pile exceeds 1.5m, prevent the occurrence of broken piles due to pile deviation; the greater the excavation depth, the greater the possibility of pile breakage due to pile deviation; it occurs on the engineering high piles inside the support structure and between the structural entities, including the engineering piles between the inner side of the underground corridor steel pipe pile support and the outer side of the underground corridor raft foundation; take engineering high pile protection measures with the help of the steel pipe pile support stabilization system; (a) Use steel bars to seal the high piles of the adjacent project, then weld the hoops to two steel pipe piles, and then use wooden wedges to wedge the high piles and hoops tightly; add hooping steel bars every 2m, excavate in layers, and add in layers; when the high piles of the adjacent project are too close to the steel pipe piles, cast the high piles and reinforced concrete cap beams as a whole.
8. The method for constructing a large diameter circular stockyard for a raw coal storage and transportation system according to claim 1, characterized in that: The raft foundation construction is divided into ten construction areas from A to G; the construction order of each area of the raft foundation is: EABGIJDCHF; among them, the concrete construction joint construction airbag is used by the civil construction, and the specific construction method is as follows: (1) Tie the concrete intercepting airbag limiting steel bars to the steel mesh at the location of the temporary concrete construction joint; (2) A supporting steel bar is installed every 500 mm outside the concrete intercepting airbag limiting steel bar; (3) Arrange concrete interception airbags on the inner side of the concrete interception airbag limiting steel bars; (4) Inflate the interception airbags in the concrete and check the airtightness of the construction joints. If the airtightness is not tight, add more airbags if necessary; (5) After passing the self-inspection, apply for acceptance and pour concrete; (6) During the pouring process, check the air leakage of the interception air bag and replenish compressed air in time to ensure the construction effect of the interception air bag; (7) After the concrete has finally set, release the compressed air in the interception airbag, clean the cement slurry on the surface of the airbag, and keep it for maintenance.
9. The method for constructing a large diameter circular stockyard for a raw coal storage and transportation system according to claim 1, characterized in that: The circular material yard retaining wall is a reinforced concrete thin-wall silo structure; and the circular material yard retaining wall is a curved structure, and a PVC formwork is used to solve the problem of formwork peeling and scabbing; the wall section internal support used in conjunction with it is customized and installed on-site in the factory according to the construction drawings, and the specific construction method is as follows: (1) Open the tensioning holes at the appropriate positions of the PVC formwork according to the formwork construction plan; (2) Fix the PCV formwork inside the wall; (3) Tie rods through the wall; (4) Put the PVC formwork supporting top support on the tie rod; (5) Install the outer PVC formwork; (6) Strengthen the inner and outer formwork and tie the tie rods to ensure the wall interface dimensions; (7) Adjust the verticality of the wall formwork and pour concrete after acceptance; (8) After the concrete curing is completed, the PCV formwork is removed and the stack is cleaned and ready for use.
10. The method for constructing a large-diameter circular stockyard for a raw coal storage and transportation system according to claim 1, characterized in that: In the construction of the top ring beam of the circular material yard, the top ring beam has a top elevation of 17.6m; plus the beam height of 1m and the beam width of 2.7m; the specific measures are as follows: (1) The two vertical poles of the scaffolding on the inner side of the circular material yard are hung with diagonal bars along the entire length of the frame from top to bottom; (2) Two additional wall ties are installed at 7.8m and 13.8m above the top elevation of the raft slab through wall tie rods with a diameter of 18mm; the spacing between the wall tie rods in each row is about 3m, and they are arranged perpendicular to the original steel pipe wall tie rods; (3) Add horizontal diagonal rods or steel pipe scissors braces; add a horizontal diagonal rod or steel pipe scissors brace along the longitudinal direction of the horizontal rod near each wall connection of the inner frame of the circular material yard; add a horizontal diagonal rod or steel pipe scissors brace at the sweeping rod position; add a horizontal diagonal rod or steel pipe scissors brace near the horizontal rod of the wall connection from the middle ring beam upwards of the outer frame of the circular material yard; add a full-length diagonal rod along the longitudinal direction of the four vertical rods on both sides of the wall between the top two through-wall rods.