Power grid flood investigation method and system for analyzing topographic surface morphology
By analyzing the terrain surface morphology, the power grid flood survey method is used to accurately calculate the disaster situation of power equipment, and the problem of untimely emergency response in the existing technology is solved, and the power supply efficiency of power equipment is improved.
Patent Information
- Application Number
- CN202410030953.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-09
- Publication Date
- 2024-11-08
AI Technical Summary
The prior art is difficult to accurately predict the area and scope of power equipment affected by flood disasters, resulting in untimely emergency response and hindering the restoration of power supply order of power equipment.
The power grid flood survey method is adopted to analyze the terrain surface morphology, and by collecting geographical information data, building a neural network, inputting water level monitoring data, calculating the disaster situation in the power equipment area, outputting the degree of impacted by flood disasters and the terrain surface morphology survey results, and publishing directionally Early warning notice, optimize emergency response.
Accurate calculation and timeliness prediction of the disaster situation of power equipment have been achieved, emergency response efficiency has been improved, emergency command and power supply recovery work have been helped, and power equipment operation time and user power supply time have been improved.
Smart Images

Figure CN118917448A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electric power disaster prevention and reduction, and in particular to a method and system for electric power grid flood survey for analyzing terrain surface morphology. Background Art
[0002] Heavy rains, floods and other natural disasters have a serious impact on power facilities and equipment, causing power grid load reduction, and large-scale power outages that pose a serious impact and threat to national security, social stability, and people's production and life. Natural disasters such as floods and waterlogging will damage power workers, power equipment (facilities), and the ecological environment. In the emergency response after a natural disaster, a series of response actions including emergency command, personnel search and rescue, emergency command and emergency power supply should be taken urgently, and the power equipment (facilities) and related buildings (structures) damaged by the emergency should be repaired and rebuilt to restore normal power supply order.
[0003] Affected by factors such as altitude, terrain and climatic conditions, and faced with increasingly frequent natural disasters such as heavy rainfall-induced floods in small and medium rivers, mountain torrents and geological disasters, the current methods used to prevent the impact of flood disasters on the area of power equipment (facilities) lack foresight and accuracy, which not only restricts effective and accurate emergency response, but also hinders the effective restoration of normal power supply order. Summary of the invention
[0004] In view of the above-mentioned problems, the present invention is proposed.
[0005] Therefore, the technical problem solved by the present invention is: how to accurately predict the area of power equipment affected by flood disasters, accurately respond to emergencies, and effectively restore normal power supply order.
[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a method for power grid flood survey for analyzing terrain surface morphology, comprising:
[0007] Collect geographic information data of the disaster-affected areas;
[0008] Construct a neural network and input the water level monitoring data of the disaster-affected location;
[0009] Calculate the disaster location and flooding degree of the power equipment area, and estimate the damage scope of the power equipment area caused by the disaster;
[0010] Output the survey results of the degree of impact of flood disasters and the terrain surface morphology of the area where the power equipment is located.
[0011] As a preferred solution of the power grid flood survey method for analyzing terrain surface morphology described in the present invention, wherein: the collection of geographical information data of the disaster-stricken area includes, after receiving a flood defense emergency response notification of a rainstorm warning, a typhoon warning, or a flood warning, starting a survey process for power equipment suffering from flood disasters;
[0012] Input the flood defense emergency response notice to determine whether it affects the area where the power equipment and facilities are located; when it affects the area where the power equipment and facilities are located, issue a targeted early warning notice to collect geographic information data of the affected area; this is collected through flood satellite monitoring images, water level monitoring devices, and liquid level sensors.
[0013] As a preferred embodiment of the method for power grid flood investigation for analyzing terrain surface morphology described in the present invention, the disaster-affected location and flooding degree include the estimated area of power equipment affected by the flood disaster, the height of the flooded surface, the flooding time, and the emergency response level for power supply security in the area.
[0014] As a preferred solution of the method for power grid flood survey by analyzing terrain surface morphology of the present invention, wherein: the calculation of the damage range of the power equipment area due to the disaster includes estimating the disaster location, calculating the flooded height and the flooded area;
[0015] Estimating the disaster location includes determining whether the power equipment is within the area of the flood defense emergency response notification. The determination formula is expressed as:
[0016] J(x,y)=|Ax-Ay|+|Bx-By |
[0017] Where J(x,y) represents the distance between the power equipment coordinates and the flood area coordinates; |A x -A y | represents the power equipment coordinate matrix generated according to the power geographic information map of the power grid intelligent system; |B x -B y | represents the coordinate matrix of the flooded area generated according to the established flood risk map; when J(x,y)=0, it is judged that the power equipment is in the flooded area mentioned in the flood defense emergency response notice; the height of the submerged surface of the area where the power equipment is located is calculated The expression is:
[0018]
[0019] Among them, S n It refers to the total area of power equipment affected by flood disaster; dS i Indicates the separate area of electrical equipment affected by flood disasters; E i Indicates the height of the submerged electrical equipment; μi Indicates the weights of different area types, which are set according to the accuracy level of the liquid level sensor;
[0020] The affected area is calculated as follows: the actual area of the power equipment area submerged by the flood S1 comes from the power supply radius area of the medium and low voltage distribution network lines marked on the power geographic information map; the area between the secondary side outgoing line of the distribution transformer and the farthest load point of its power supply, and its structure is radial;
[0021] Based on the area s1 of power equipment submerged by the flood, calculate the area s2 of power user facilities affected by the flood;
[0022]
[0023] Where L represents the collection of medium and low voltage distribution network lines; i Indicates the power supply distance of the radial distribution network line; p i Indicates the area of power user facilities in the region; K i It represents the proportional coefficient between the power supply radius area of the i-th medium and low voltage distribution network line and the area of its related power user facilities.
[0024] As a preferred solution of the power grid flood survey method for analyzing terrain surface morphology described in the present invention, wherein: the power geographic information map includes digital simulation of the regional surface curved surface, and the simulation area is defined as a finite sequence of three-dimensional vectors of the terrain surface morphology of the power supply area D where a distribution transformer is located;
[0025] When not affected by flood disasters, the formula for D is:
[0026] C i =(x i ,y i , z i ), i=1, 2, …, n)
[0027] Among them, C i represents a finite sequence of three-dimensional vectors of the terrain surface morphology not affected by flood disasters, (x i ,y i )∈D represents the plane coordinates, z i Represents a point (x i ,y i ) The corresponding elevation in the power grid intelligent observation system can continuously express the terrain surface morphology into a discrete mathematical form; in order to restore continuity, an ordered set of two-dimensional functions is used to express the relationship between the elevation of the terrain surface morphology and the point position, and the formula is expressed as follows:
[0028] z i =f(x i ,y i ), (x i,y i )∈D
[0029] When affected by flood disaster, D is expressed as:
[0030] C' i =(x i ,y i ,z' i ), (i=1,2,...,n)
[0031] Among them, C' i Represents a finite sequence of three-dimensional vectors of the terrain surface affected by flood disasters, (x i ,y i )∈D represents the plane coordinates, z' i Represents a point (x i ,y i ) is the value obtained by superimposing the water level on the corresponding elevation in the power grid intelligent monitoring system.
[0032] As a preferred solution of the power grid flood survey method for analyzing terrain surface morphology described in the present invention, the neural network includes collecting historical flood data, standardizing the collected flood disaster data; dividing the training set and the test set; extracting key factors affecting the terrain surface morphology as input features;
[0033] A multi-layer perceptron model was constructed as the network structure, which includes an input layer, a hidden layer, and an output layer. The hidden layer uses the ReLU activation function. The output layer is designed as a regression task to predict the flooded height, flooded area, and water flow velocity parameters of the affected area.
[0034] The mean square error is used as the loss function and optimized by gradient descent. The neural network is trained using historical flood data and the hyperparameters are adjusted using the validation set. The performance of the model is evaluated on the test set.
[0035] As a preferred solution of the power grid flood survey method for analyzing terrain surface morphology described in the present invention, the neural network includes collecting historical flood data, standardizing the collected flood disaster data; dividing the training set and the test set; extracting key factors affecting the terrain surface morphology as input features;
[0036] A multi-layer perceptron model was constructed as the network structure, which includes an input layer, a hidden layer, and an output layer. The hidden layer uses the ReLU activation function. The output layer is designed as a regression task to predict the flooded height, flooded area, and water flow velocity parameters of the affected area.
[0037] Use mean square error as the loss function and optimize it by gradient descent. Use historical flood data to train the neural network and use the validation set to adjust the hyperparameters. Evaluate the performance of the model on the test set.
[0038] The survey results include receiving an early warning of a flood defense emergency response notice and initiating a flood disaster survey process for power equipment; using a neural network model to calculate flood flow direction and velocity information based on satellite images, and combining it with a power geographic information map to determine whether the area where the power equipment is located is affected; if the area where the power equipment is located is affected, issuing a warning notice to the affected area; if the area where the power equipment is located is not affected, maintaining monitoring of the flood disaster impact area and continuing to operate the power equipment normally;
[0039] The neural network model determines whether the area where the power equipment is located is within the boundary of the waterlogged area based on the power geographic information map; if it is not within the boundary of the waterlogged area, the disaster warning state is maintained and the power equipment continues to operate normally; if it is within the boundary of the waterlogged area, a disaster alarm is issued, the operation of the power equipment in the disaster-stricken area is stopped, and the power equipment information in the power grid system is input into the neural network to calculate the actual area of the area where the power equipment is located and the area and height of the flooding caused by the flood; based on the actual area of the power equipment affected by the flood, the flooded area and the water level monitoring data of the location of the power equipment and the water level observation data of the adjacent river channel, the surface conditions of the disaster-stricken area are surveyed, and the survey results of the degree of impact of the flood disaster on the area where the power equipment is located, the terrain surface morphology and the prediction of the continuous impact of the disaster on the power equipment area are output;
[0040] As a preferred solution of the power grid flood investigation method for analyzing terrain surface morphology described in the present invention, wherein: the power supply restoration strategy includes solving the flood sensitive load condition index, expressed as;
[0041]
[0042] Among them, FSLI represents the flood sensitive load condition index at any time, T represents the rainfall at the corresponding time, U represents the relative water level at the location of the power equipment at the corresponding time, and V represents the flow velocity of the river near the power equipment at the corresponding time;
[0043] Solve the flood sensitive electricity consumption condition index, expressed as:
[0044]
[0045] Among them, FSPI represents the daily flood-sensitive electricity consumption condition index; represents the average daily rainfall; Indicates the daily average water level at the location of the power equipment. Indicates the daily average flow velocity of the river near the power equipment; T max Indicates the daily maximum water level at the location of the power equipment; T min Indicates the daily minimum water level at the location of the power equipment; provides strategic guidance on power restoration based on the power condition index, and carries out power restoration work in the affected areas.
[0046] A power grid flood survey system for analyzing terrain surface morphology using any of the methods described in the present invention, characterized in that:
[0047] The acquisition module receives rainstorm warnings or typhoon warnings issued by the meteorological station, flood warning notices issued by the hydrological center, and water level monitoring data at the location of power equipment, and inputs relevant information of the power geographic information map;
[0048] A data storage module for storing data processed by the flood disaster investigation system for electric power equipment;
[0049] A comprehensive processing module is used to start the investigation process of power equipment suffering from flood disasters after receiving the flood defense emergency response notification;
[0050] The application module is used to display the flooded area, terrain surface morphology and related data of the area where the power equipment is located output by the processing layer, and transmit the data through the website server.
[0051] A computer device comprises: a memory and a processor; the memory stores a computer program, wherein the processor implements the steps of any one of the methods of the present invention when executing the computer program.
[0052] A computer-readable storage medium stores a computer program, wherein the computer program, when executed by a processor, implements the steps of any one of the methods of the present invention.
[0053] Beneficial effects of the invention: The power grid flood survey method for analyzing terrain surface morphology provided by the invention creatively realizes the function of real-time survey of flood disasters around the clock based on meteorological release, hydrological release, water level monitoring, and water level observation data, overcomes the difficulty of measuring the terrain surface morphology (including flooded area, height, and time) of the area where the power equipment (facilities) is located, and the calculation results of the disaster situation have excellent timeliness and accuracy, which is helpful for the emergency command center to guide emergency response, load transfer, flood prevention and reinforcement, emergency repair and power restoration, material allocation, customer service, grid planning and other tasks, and greatly improves the operating time of power equipment (facilities) and the power supply time to users. BRIEF DESCRIPTION OF THE DRAWINGS
[0054] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. Among them:
[0055] Figure 1 An overall flow chart of a power grid flood survey method for analyzing terrain surface morphology provided by the first embodiment of the present invention;
[0056] Figure 2 A flow chart of a method for flood disaster investigation for power equipment in a method for flood disaster investigation for power grids by analyzing terrain surface morphology provided in a first embodiment of the present invention;
[0057] Figure 3 A schematic diagram of a neural network structure of a power grid flood survey method for analyzing terrain surface morphology provided by the first embodiment of the present invention;
[0058] Figure 4 A schematic diagram of a flood disaster investigation system for a power grid flood investigation method for analyzing terrain surface morphology provided by a first embodiment of the present invention;
[0059] Figure 5 A schematic diagram of a flood disaster investigation system for a power grid flood investigation method for analyzing terrain surface morphology provided by a first embodiment of the present invention. DETAILED DESCRIPTION
[0060] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the drawings of the specification. Obviously, the described embodiments are part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary persons in the art without creative work should fall within the scope of protection of the present invention.
[0061] Example 1
[0062] Reference Figure 1-Figure 5 , which is an embodiment of the present invention, provides a power grid flood investigation method for analyzing terrain surface morphology, comprising:
[0063] S1: Collect geographic information data of the disaster-stricken area.
[0064] Further, such as Figure 2 As shown, after receiving the flood defense emergency response notification, the investigation process of the power equipment (facilities) suffering from the flood disaster is initiated.
[0065] Furthermore, the emergency command center of the power grid company receives the rainstorm warning, typhoon warning issued by the meteorological station, or the flood warning issued by the hydrological center. Among them, the rainstorm warning and typhoon warning come from the website of the meteorological bureau, and the flood warning comes from the website of the hydrological center. After receiving the flood defense emergency response notice, the investigation process of the power equipment (facilities) suffering from flood disasters is initiated.
[0066] Furthermore, a flood defense emergency response notice is input to determine whether the area where the power equipment (facilities) is located is affected. When the area where the power equipment (facilities) is affected, a warning notice is issued in a targeted manner and the next step is entered.
[0067] Furthermore, the flood defense emergency response notification information about the power supply area and the flood risk map in the flood defense emergency response notification are used to determine whether the area where the power equipment (facilities) is located is affected, and the emergency response level of the power grid flood investigation in the area where the power equipment (facilities) is located is included in the issued early warning notice.
[0068] Table 1 Warning (adjustment) notification release level
[0069]
[0070] The power supply area includes the power supply area of the branch of the municipal power supply bureau and the power supply area of the county power supply bureau. The flood risk map refers to a map that reflects the spatial distribution of flood risk factor information. Information is collected to produce the flood risk map.
[0071] Furthermore, the provincial power grid emergency command center receives warnings including rainstorm warnings and typhoon warnings issued by the meteorological station and flood warnings issued by the hydrological center. The warning notification information includes: warning level, warning area and time, and also includes rainfall, wind speed, water level or flow.
[0072] Furthermore, flood warnings are divided into four levels: red, orange, yellow and blue. Red warning means that the water level (flow) reaches or exceeds the highest water level (maximum flow) in history, and the flood element recurrence period reaches or exceeds 50 years; orange warning means that the water level (flow) reaches or exceeds the guaranteed water level (flow), and the flood element recurrence period reaches or exceeds 20 years; yellow warning means that the water level (flow) reaches or exceeds the warning water level (flow), and the flood element recurrence period reaches or exceeds 5 years; blue warning means that the water level (flow) is close to the warning water level (flow), and the flood element recurrence period is close to 5 years.
[0073] Furthermore, the rainstorm warning is divided into four levels: red, orange, yellow and blue. The red warning means that the rainfall will reach more than 100 mm within 3 hours, or has reached more than 100 mm and the rainfall may continue; the orange warning means that the rainfall will reach more than 50 mm within 3 hours, or has reached more than 50 mm and the rainfall may continue; the yellow warning means that the rainfall will reach more than 50 mm within 6 hours, or has reached more than 50 mm and the rainfall may continue; the blue warning means that the rainfall will reach more than 50 mm within 12 hours, or has reached more than 50 mm and the rainfall may continue.
[0074] Furthermore, typhoon warnings are divided into four levels: red, orange, yellow, and blue. Among them, a red warning means that the typhoon may or has been affected within 12 hours, and the average wind speed may reach above level 12, or has reached above level 12 and may continue; an orange warning means that the tropical cyclone may or has been affected within 12 hours, and the average wind speed along the coast or on land may reach above level 10, or the gusts may reach above level 12 and may continue; a yellow warning means that the tropical cyclone may or has been affected within 24 hours, and the average wind speed along the coast or on land may reach above level 8, or the gusts may reach above level 10 and may continue; a blue warning means that the tropical cyclone may or has been affected within 24 hours, and the average wind speed along the coast or on land may reach above level 6, or the gusts may reach above level 8 and may continue. As an optional embodiment, the area where the power equipment (facilities) and power user facilities affected by the flood are located within the boundary range of the waterlogged area refers to the corresponding flood risk map that intuitively reflects the flooded area, such as the characteristic parameters and spatial location information of the wire-mounted features with a flooded depth of more than 0.5 meters, and its equipment (facility) data meets the requirements of reality, timeliness and accuracy.
[0075] Furthermore, whether the power equipment (facilities) affected by the flood is within the boundary of the flooded area refers to whether the coordinate information of the power equipment (facilities) in the power grid intelligent system is within the boundary of the heavy rain, typhoon and flood warning in the early warning notice.
[0076] Furthermore, under the spatial association rule, the area of power user facilities affected by floods is not only affected by the local water level, but also depends on the area where the power equipment (facilities) are submerged by the flood. When a certain power equipment (facility) is submerged by the flood, the power user facilities connected to the power equipment (facility) will also be affected.
[0077] It should be noted that based on the early warning information and flood risk map, it is determined whether the power equipment is in the affected area and a corresponding level of early warning notice is issued. The early warning level is set according to the specific parameters of water level and rainfall to ensure the safety of the power supply area and timely response. This systematic early warning mechanism can improve the efficiency and effectiveness of responding to flood disasters.
[0078] S2: Build a neural network and input the monitoring data of the disaster location.
[0079] Furthermore, a flood defense emergency response notice regarding a rainstorm warning, typhoon warning, or flood warning is input to determine whether it affects the area where the power equipment (facilities) is located. If it affects the area where the power equipment (facilities) is located, a warning notice is issued in a targeted manner and the next step is entered.
[0080] Specifically, a taxi geometry algorithm is used to determine whether the power equipment (facility) is within the area of the flood defense emergency response notification. The formula of the taxi geometry algorithm is:
[0081] J(x,y)=|Ax-Ay|+|Bx-By |
[0082] Where J(x,y) represents the distance between the power equipment coordinates and the flood area coordinates; |Ax-A y | represents the power equipment coordinate matrix generated according to the power geographic information map of the power grid intelligent system; |Bx-B y | represents the coordinate matrix of the flood-prone area generated according to the established flood risk map; when J(x, y) = 0, it is determined that the power equipment is in the flood-prone area mentioned in the flood defense emergency response notice.
[0083] Furthermore, the water level observation data and time of the river channel near the power equipment (facilities) affected by the flood disaster are input; the water level observation data and time of the river channel near the power equipment (facilities) are observed by automatic monitoring equipment.
[0084] Furthermore, the automatic water level monitoring equipment refers to a device that measures the height of the liquid level (including the water level) by transmitting and receiving electromagnetic pulses or high-frequency ultrasonic pulse signals reflected from the water surface.
[0085] Furthermore, the automatic monitoring equipment includes: paper medium analog self-recording water level gauges and digital self-recording water level gauges, and should comply with the access permit requirements of the national hydrological quality inspection department.
[0086] Furthermore, the automatic monitoring equipment and output signal lines should have lightning protection and anti-interference measures and wave suppression measures, with a water level resolution of 1 cm, a water level measurement range of 0 to 40 meters, a water level change rate of not less than 40 cm / minute, and a water level error of less than 3 cm.
[0087] Furthermore, based on the area S1 of the power equipment (facilities) submerged by the directional regional flood, the area S2 of the power user facilities affected by the flood, the water level monitoring data of the location of the power equipment (facilities) and the water level observation data of the nearby river, a neural network is constructed to measure the terrain surface morphology of the affected area, and the survey results of the terrain surface morphology (including the submerged area, height, and time) of the area where the power equipment (facilities) is located are output.
[0088] Furthermore, Figure 3 As shown, the neural network constructed to depict the surface morphology of the disaster-stricken area includes: an input layer, a hidden layer and an output layer. The entire network is a multi-input, multi-output type neural network.
[0089] Furthermore, the input layer node x includes: power geographic information of the power grid intelligence system, power user information of the power grid marketing system, meteorological release data, hydrological release data, water level monitoring data, and water level observation data.
[0090] Furthermore, the hidden layer is used to solve the terrain surface morphology of the area where the power equipment (facilities) and power user facilities are located, as well as the flooded area, height, and time of the area where the power equipment (facilities) are located. The formula is expressed as follows:
[0091]
[0092]
[0093]
[0094] Among them, x 水 Represents the water level information input vector collected by the sensor; x 电 Represents the input vector of the power equipment operation information collected by the sensor; n 水 Indicates the collected water level information data; n 电 represents the collected power equipment operation information data; b represents the bias term of the neural network; h represents the output of the hidden layer; w represents the weight term;
[0095] Furthermore, the output layer outputs the terrain surface morphology (including flooded area, height, and time) of the areas where the power equipment (facilities) and power user facilities are located, as well as the power security emergency response level.
[0096] Furthermore, the survey results of the flooded area and terrain surface morphology of the areas where the power equipment (facilities) and power user facilities are located include: the actual area of the power equipment (facilities) affected by the flood disaster, the flooded area, the height of the flooded surface, the flooding time, and the emergency response level of power supply security in the area.
[0097] It should be noted that by selecting two different water level meters, paper medium analog self-recording water level meter and digital self-recording water level meter, according to site conditions, site locations, cost constraints and application scale, the present invention is made more versatile and practical, and facilitates the promotion and application of patented technology.
[0098] S3: Calculate the disaster-affected location and flooding degree of the power equipment area, and the scope of damage caused by the disaster in the power equipment area.
[0099] Furthermore, the water level monitoring data and time of the location of the power equipment (facilities) affected by the flood disaster are input; the water level observation data and time of the river channel near the power equipment (facilities) affected by the flood disaster are input.
[0100] Furthermore, the power geographic information in the power grid intelligent monitoring system is input to determine whether the area where the power equipment (facilities) for which the warning notice is issued is located is within the boundary of the flooded area, and the actual area S1 of the power equipment (facilities) submerged by the flood is calculated.
[0101] Furthermore, the actual area S1 of the area submerged by flooded power equipment (facilities) comes from the power supply radius area of the medium and low voltage distribution network lines marked on the power geographic information map, specifically the area from the secondary side outgoing line of the distribution transformer to the farthest load point of its power supply, and its structure refers to the radial type.
[0102] Furthermore, the height of the flooded surface in the area where the power equipment is located is calculated. The expression is:
[0103]
[0104] Among them, S n It refers to the total area of power equipment affected by flood disaster; dS i Indicates the separate area of electrical equipment affected by flood disasters; E i Indicates the height of the submerged electrical equipment; μ i Indicates the weights of different area types, which are set according to the accuracy level of the liquid level sensor.
[0105] Furthermore, the disaster-stricken area is calculated including the actual area S1 of the power equipment area submerged by the flood, which comes from the power supply radius area of the medium and low voltage distribution network lines marked on the power geographic information map; the area from the secondary side outgoing line of the distribution transformer to the farthest load point of its power supply, and its structure is radial.
[0106] Furthermore, based on the area s1 of the power equipment submerged by the flood, the area s2 of the power user facilities affected by the flood is calculated;
[0107]
[0108] Where L represents the collection of medium and low voltage distribution network lines; i Indicates the power supply distance of the radial distribution network line; p i Indicates the area of power user facilities in the region; K i It represents the proportional coefficient between the power supply radius area of the i-th medium and low voltage distribution network line and the area of its related power user facilities.
[0109] Furthermore, based on the area S1 of the flooded power equipment (facilities), the flooded area S2, the water level monitoring data of the location of the power equipment (facilities), and the water level observation data of the nearby river, a neural network is constructed to measure the terrain surface morphology of the disaster-stricken area, and the survey results of the terrain surface morphology (including the flooded area, height, and time) of the area where the power equipment (facilities) is located are output.
[0110] Furthermore, through the terrain surface morphology elevation data from the power grid intelligence system based on digital twin power grid technology, the surface curve of the power supply area is digitally simulated and expressed, which can be defined as a finite sequence of three-dimensional vectors of the terrain surface morphology of the power supply area D where a distribution transformer is located.
[0111] Furthermore, through the ArcGIS programmable platform software, the basic data such as topographic maps, contour lines, and elevation points are interpolated and analyzed to generate a digital elevation model of an irregular triangulated network of the area where the power equipment (facilities) are located, and then a raster graphic file of the ground surface is obtained for the analysis and measurement of the flooded area and height.
[0112] Furthermore, when not affected by flood disasters, the expression of D is:
[0113] C i =(x i ,y i , z i ), i=1, 2, …, n)
[0114] In the formula, Ci refers to the finite sequence of three-dimensional vectors of the terrain surface morphology that is not affected by flood disasters, (xi, yi)∈D refers to the plane coordinates, and zi refers to the elevation corresponding to the point (xi, yi) in the power grid intelligent vision system. The terrain surface morphology can be continuously expressed in discrete mathematical forms. In order to restore its continuity, an ordered set of two-dimensional functions can also be used to express the relationship between the elevation of the terrain surface morphology and the point position. The expression is:
[0115] z i =f(x i ,y i ), (x i ,y i )∈D
[0116] Furthermore, when affected by flood disasters, the expression of D is:
[0117] C' i =(x i ,y i ,z' i ), (i=1,2,...,n)
[0118] Where C' i It refers to a finite sequence of three-dimensional vectors of the terrain surface morphology affected by flood disasters, (xi, yi)∈D refers to the plane coordinates, z' i It refers to the value of the corresponding elevation of the point (xi, yi) in the power grid intelligent system after superimposing the water level height. i It is the value of the corresponding elevation of the area in the power grid intelligent monitoring system, superimposed with the water level monitoring height measured by the liquid level sensor or the water level observation height observed by the automatic monitoring equipment.
[0119] Furthermore, the survey results of the flooded area and terrain surface morphology of the area where the power equipment (facilities) are located include: the actual area of the power equipment (facilities) affected by the flood disaster, the flooded area, the height of the flooded surface, the flooding time and the emergency response level of power supply in the area.
[0120] Furthermore, the flood defense emergency response notification information about the power supply area and the flood risk map in the flood defense emergency response notification are used to determine whether the area where the power equipment (facilities) is located is affected. The water level monitoring data of the location of the power equipment (facilities) is obtained by monitoring the liquid level sensor at all times. The water level observation data of the river near the power equipment (facilities) is obtained by observing the automatic monitoring equipment at all times.
[0121] Furthermore, as an optional embodiment, the water level monitoring data and time at the location of the power equipment (facility) are obtained by monitoring the liquid level sensor. The liquid level sensor refers to a sensor that measures the pressure at the location of the pressure-sensitive part of the sensor in the liquid medium to measure the height of the liquid level (including the water level). The liquid level sensor includes: a piezoresistive liquid level sensor, a capacitive liquid level sensor, an inductive liquid level sensor, and a strain resistor liquid level sensor. The output mode of the liquid level sensor is divided into three modes: analog output, digital output, and analog and digital mixed output. Among them, the mode output means that the output signal is a DC current or DC voltage signal; the digital output means that the output signal is a digital signal; the mixed output means that in addition to outputting the analog output signal, a digital signal is modulated on its signal.
[0122] It should be noted that by selecting four different liquid level sensors, namely, piezoresistive liquid level sensor, capacitive liquid level sensor, inductive liquid level sensor and strain resistor liquid level sensor, according to site conditions, cost constraints, water quality type and application scale, the present invention is made more versatile and practical, and facilitates the promotion and application of patented technology.
[0123] S4: Output the survey results of the degree of impact of flood disasters and terrain surface morphology in the area where the power equipment is located, and formulate a strategy for restoring power supply in the disaster-stricken area.
[0124] Furthermore, after the power companies automatically implement emergency plans due to natural disasters such as floods, they will carry out emergency handling and rescue, and post-event recovery and reconstruction according to the power supply emergency response levels I to IV.
[0125] Furthermore, Figure 4 Figure 5 The disaster strategy formulation system shown includes a vertical collection layer, a horizontal collection layer, a data layer, a processing layer, and an application layer.
[0126] Furthermore, the vertical collection layer is used to receive rainstorm warnings or typhoon warnings issued by the meteorological station, flood warning notices issued by the hydrological center, water level monitoring data at the location of power equipment (facilities), and water level observation data of nearby rivers.
[0127] Furthermore, the horizontal collection layer is used to collect power geographic information in the power grid intelligence system and power user-related information in the power grid marketing system.
[0128] Furthermore, a data layer is used to store data processed by the flood disaster investigation system for power equipment (facilities).
[0129] Furthermore, the processing layer is used to start the survey process of the power equipment (facilities) suffering from flood disasters after receiving the flood defense emergency response notification; first, according to the flood defense emergency response notification, it is judged whether the area where the power equipment (facilities) is located is affected. When the area where the power equipment (facilities) is affected, a warning notice is issued in a targeted manner and the next step is entered; secondly, according to the power geographic information map, it is judged that the area where the power equipment (facilities) is located is within the boundary of the waterlogged area, the power user information in the power grid marketing system is input, and the actual area of the area where the power equipment (facilities) affected by the flood disaster is located and the area submerged by the flood is calculated; again, according to the actual area of the power equipment (facilities) affected by the flood disaster, the submerged area and the water level monitoring data of the location of the power equipment (facilities) and the water level observation data of the nearby river, a neural network is constructed to measure the damage range of the power equipment (facilities) area due to the disaster, and the survey results of the flooded area and the terrain surface morphology of the area where the power equipment (facility) μ1 is located are output.
[0130] Furthermore, the display layer is used to display the survey results and related data of the flooded area and terrain surface morphology of the area where the power equipment (facilities) are located output by the processing layer, and provide power grid flood survey application services and publish related data through the website server.
[0131] Solving the Flood Sensitive Load Condition Index (FSLI)
[0132]
[0133] Among them, FSLI represents the flood sensitive load condition index at any time, T represents the rainfall at the corresponding time (mm), U represents the relative water level at the location of the power equipment (facility) at the corresponding time (mm), and V represents the flow velocity of the river near the power equipment (facility) at the corresponding time (m / s).
[0134] Secondly, solve the flood sensitive electricity condition index (FSPI)
[0135]
[0136] Among them, FSPI represents the daily flood sensitive electricity consumption condition index, is the average daily rainfall (mm), Indicates the daily average water level (mm) at the location of the power equipment (facilities). It indicates the daily average flow velocity (m / s) of the river near the power equipment (facilities), T max Indicates the daily maximum water level (mm) at the location of the power equipment (facility), T min Indicates the daily minimum water level (mm) at the location of the power equipment (facilities). Provide strategic guidance for power restoration based on the power condition index and carry out power restoration work in the affected areas.
[0137] Furthermore, based on the historical experience of disasters, the relationship between the FSPI threshold μ and FSPI is used to determine the damage to power facilities and formulate disaster relief strategies; μ includes a low-risk threshold μ0 and a high-risk threshold μ1. When FSPI is higher than the low-risk threshold, floods will inundate the power equipment area, but will not have adverse effects on the power equipment in a short period of time; when FSPI is higher than the high-risk threshold, the power equipment is damaged by the flood and cannot operate normally.
[0138] When FSPI is less than μ0, the operation of power equipment is not affected, and the flood disaster will not affect the power equipment in the next few hours. In this case, a low-risk strategy is implemented to maintain the original power supply strategy, and continue to monitor the water level of nearby rivers and the disaster situation in the power area; when μ0 is less than FSPI is less than μ1, the operation of power equipment is not affected, but the flood disaster may cause harm in the next few hours. In this case, a medium-risk strategy is implemented, the power equipment disaster warning system is activated, and it is prepared to switch to the power equipment that should be used, and the water level sensing sensor of the power equipment is activated to monitor the water level of nearby rivers and the water level information of the power area; when μ1 is less than FSPI, the operation of the power equipment has been affected by the flood. If it cannot operate normally, a high-risk strategy will be implemented, and power supply will be switched to emergency power equipment. According to the importance of the power supply area of the power grid, the principle of giving priority to hospitals, disaster relief centers and infrastructure, priority will be given to ensuring the power supply of key facilities, and preparations will be made for emergency evacuation and repair plans. When a high-risk strategy is implemented and it is detected that FSPI < μ0, the repair plan will be implemented, and the power equipment sensor functions will be re-tested to see if they are normal, and the investigation will be carried out step by step. If all power equipment in an area is tested to be normal, power supply will be restored. If abnormal equipment is found, it will be repaired, and the power area of the abnormal equipment will continue to use the backup line for power supply until all equipment is tested to be normal.
[0139] It should be noted that this method and system creatively realize the function of real-time survey of flood disasters around the clock based on meteorological release, hydrological release, water level monitoring and water level observation data, and overcome the difficulty of measuring the terrain surface morphology (including flooded area, height and time) of the area where the power equipment (facilities) is located. The calculation results of the disaster situation are extremely timely and accurate, which helps the emergency command center to guide emergency response, load transfer, flood prevention and reinforcement, emergency power restoration, material allocation, customer service, grid planning and other tasks, and greatly improves the operating time of power equipment (facilities) and the power supply time to users.
[0140] On the other hand, this embodiment also provides a power grid flood investigation system for analyzing terrain surface morphology, which includes:
[0141] The collection module receives rainstorm warnings or typhoon warnings issued by the meteorological station, flood warning notices issued by the hydrological center, and water level monitoring data at the location of power equipment, and inputs relevant information of the power geographic information map.
[0142] The data storage module stores the data processed by the flood disaster investigation system for electric power equipment.
[0143] The comprehensive processing module is used to initiate the investigation process of power equipment suffering from flood disasters after receiving the flood defense emergency response notification.
[0144] The application module is used to display the flooded area, terrain surface morphology and related data of the area where the power equipment is located output by the processing layer, and transmit the data through the website server.
[0145] If the above functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk and other media that can store program codes.
[0146] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute instructions), or in conjunction with such instruction execution systems, devices or apparatuses. For the purposes of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in conjunction with such instruction execution systems, devices or apparatuses.
[0147] More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk case (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), an optical fiber device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be a paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium, followed by editing, deciphering or, if necessary, processing in another suitable manner, and then stored in a computer memory.
[0148] It should be understood that the various parts of the present invention can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, a plurality of steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0149] Example 2
[0150] The following is an embodiment of the present invention, which provides a method for power grid flood investigation by analyzing terrain surface morphology. In order to verify the beneficial effects of the present invention, scientific demonstration is carried out through economic benefit calculation and simulation experiments.
[0151]
[0152] The method of the present invention is significantly superior to existing technical solutions in terms of reducing power restoration time, increasing power restoration coverage, improving system stability and customer satisfaction, and has significant improvements in survey accuracy, data processing speed, system stability, and cost-effectiveness.
[0153] The present invention calculates the flooded area, height, and time level of the area where the power equipment (facilities) are located under each round of flood disasters, adjusts the flood control standards according to the recurrence period reached in the area, and provides decision-making information for planning, transformation, and reinforcement of flood prevention and control of power equipment (facilities); and provides users with flood control suggestions for power supply systems and their facilities.
[0154] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.
Claims
1. A method for power grid flood investigation by analyzing terrain surface morphology, characterized in that: include: Collecting data and information on power equipment and water level monitoring in the affected areas; Construct a neural network model to measure the disaster-affected area, input monitoring data, and determine the disaster-affected location of power equipment; Calculate the disaster-affected location and flooding degree of the power equipment area, and the scope of damage caused by the disaster in the power equipment area; Output the survey results of the degree of impact of flood disasters and terrain surface morphology in the area where the power equipment is located, and formulate a strategy for restoring power supply in the disaster-stricken area.
2. The method for power grid flood investigation by analyzing terrain surface morphology according to claim 1, characterized in that: The power equipment and water level monitoring data information in the disaster-affected area includes, after receiving the flood defense emergency response notification of the rainstorm warning, typhoon warning, and flood warning, starting the investigation process of the power equipment suffering from the flood disaster; Input the flood defense emergency response notice to determine whether it affects the area where the power equipment and facilities are located; When the area where power equipment and facilities are located is affected, a targeted early warning notice will be issued to collect geographic information data of the affected area; this data is collected through flood satellite monitoring images, water level monitoring devices, and liquid level sensors.
3. The method for power grid flood investigation by analyzing terrain surface morphology according to claim 2, characterized in that: The disaster-affected locations and flooding levels include the estimated area of power equipment affected by the flood, the height of the flooded surface, the flooding time, and the emergency response level for power supply security in the area.
4. The method for power grid flood investigation by analyzing terrain surface morphology according to claim 3, characterized in that: The scope of damage to the power equipment area due to the disaster includes estimating the disaster location, measuring the flooded height and flooded area; Estimating the disaster location includes determining whether the power equipment is within the area of the flood defense emergency response notification. The determination formula is expressed as: Where J(x,y) represents the distance between the power equipment coordinates and the flood area coordinates; |A x -A y | represents the power equipment coordinate matrix generated according to the power geographic information map of the power grid intelligent system; |B x -B y | represents the coordinate matrix of the flooded area generated according to the established flood risk map; when J(x,y)=0, it is judged that the power equipment is in the flooded area mentioned in the flood defense emergency response notice; the height of the submerged surface of the area where the power equipment is located is calculated The expression is: Among them, S n It refers to the total area of power equipment affected by flood disaster; dS i Indicates the separate area of electrical equipment affected by flood disasters; E i Indicates the height of the submerged electrical equipment; μ i Indicates the weights of different area types, which are set according to the accuracy level of the liquid level sensor; The affected area is calculated as follows: the actual area of the power equipment area submerged by the flood S1 comes from the power supply radius area of the medium and low voltage distribution network lines marked on the power geographic information map; the area between the secondary side outgoing line of the distribution transformer and the farthest load point of its power supply, and its structure is radial; Based on the area s1 of power equipment submerged by the flood, calculate the area s2 of power user facilities affected by the flood; Where L represents the set of medium and low voltage distribution network lines; i Indicates the power supply distance of the radial distribution network line; p i Indicates the area of power user facilities in the region; K i It represents the ratio coefficient between the power supply radius area of the i-th medium and low voltage distribution network line and the area of its related power equipment.
5. The method for power grid flood investigation by analyzing terrain surface morphology according to claim 4, characterized in that: The electric power geographic information map includes digital simulation of the regional surface, and defines the simulation area as a finite sequence of three-dimensional vectors of the terrain surface morphology of the power supply area D where a distribution transformer is located; When not affected by flood disasters, the formula for D is: C i =(x i ,y i ,z i ),i=1,2,…,n) Among them, C i represents a finite sequence of three-dimensional vectors of the terrain surface morphology not affected by flood disasters, (x i ,y i )∈D represents the plane coordinates, z i Represents a point (x i ,y i ) The corresponding elevation in the power grid intelligent observation system can continuously express the terrain surface morphology into a discrete mathematical form; in order to restore continuity, an ordered set of two-dimensional functions is used to express the relationship between the elevation of the terrain surface morphology and the point position, and the formula is expressed as follows: z i =f(x i ,y i ),(x i ,y i )∈D When affected by flood disaster, D is expressed as: C′ i =(x i ,y i ,z′ i ),(i=1,2,...,n) Among them, C′ i Represents a finite sequence of three-dimensional vectors of the terrain surface affected by flood disasters, (x i ,y i )∈D represents the plane coordinates, z′ i Represents a point (x i ,y i ) is the value obtained by superimposing the water level on the corresponding elevation in the power grid intelligent monitoring system.
6. The method for power grid flood investigation by analyzing terrain surface morphology according to claim 5, characterized in that: The neural network includes collecting historical flood disaster data, standardizing the collected flood disaster data; dividing the training set and the test set; extracting key factors affecting the terrain surface morphology as input features; A multi-layer perceptron model was constructed as the network structure, which includes an input layer, a hidden layer, and an output layer. The hidden layer uses the ReLU activation function. The output layer is designed as a regression task to predict the flooded height, flooded area, and water flow velocity parameters of the affected area. Use mean square error as the loss function and optimize it by gradient descent. Use historical flood data to train the neural network and use the validation set to adjust the hyperparameters. Evaluate the performance of the model on the test set. The survey results include receiving an early warning of a flood defense emergency response notice and initiating a flood disaster survey process for power equipment; The neural network model calculates the flow direction and velocity of the flood based on satellite images, and combines it with the power geographic information map to determine whether it affects the area where the power equipment is located. If it affects the area where the power equipment is located, a warning notice will be issued to the affected area. If the area of power equipment is not affected, the affected area of the flood disaster should be monitored and the power equipment should continue to operate normally; The neural network model determines whether the area where the power equipment is located is within the boundary of the flooded area based on the power geographic information map; if it is not within the boundary of the flooded area, the disaster warning state is maintained and the power equipment continues to operate normally; If it is within the boundary of the waterlogged area, a disaster alarm will be issued, the operation of power equipment in the disaster area will be stopped, the power equipment information in the power grid system will be input into the neural network, and the actual area of the area where the power equipment is located and the area and height of the flood will be calculated; based on the actual area of the power equipment affected by the flood disaster, the flooded area and the water level monitoring data at the location of the power equipment and the water level observation data of the nearby river, the surface conditions of the disaster area will be surveyed, and the survey results of the degree of impact of the flood disaster on the power equipment area, the surface morphology of the terrain and the prediction of the continued impact of the disaster on the power equipment area will be output.
7. The method for power grid flood investigation by analyzing terrain surface morphology according to claim 6, characterized in that: The power supply restoration strategy includes solving a flood sensitive load condition index, expressed as; Among them, FSLI represents the flood sensitive load condition index at any time, T represents the rainfall at the corresponding time, U represents the relative water level at the location of the power equipment at the corresponding time, and V represents the flow velocity of the river near the power equipment at the corresponding time; Solve the flood sensitive electricity consumption condition index, expressed as: Among them, FSPI represents the daily flood-sensitive electricity consumption condition index; represents the daily average rainfall; U represents the daily average water level at the location of the power equipment. Indicates the daily average flow velocity of the river near the power equipment; T max Indicates the daily maximum water level at the location of the power equipment; T min Indicates the daily minimum water level at the location of the power equipment; The neural network model gives strategic guidance for restoring power supply based on the power condition index; the damage to power equipment is determined based on the relationship between the FSPI threshold μ and FSPI based on historical disaster experience, and a disaster relief strategy is formulated; μ includes a low-risk threshold μ0 and a high-risk threshold μ1. When FSPI is higher than the low-risk threshold, floods will flood into the power equipment area, but will not have adverse effects on the power equipment in a short period of time; when FSPI is higher than the high-risk threshold, the power equipment is damaged by the flood and cannot operate normally. When FSPI is less than μ0, the operation of power equipment is not affected, and the flood disaster will not affect the power equipment in the next few hours. In this case, a low-risk strategy is implemented to maintain the original power supply strategy, and continue to monitor the water level of nearby rivers and the disaster situation in the power area; when μ0 is less than FSPI is less than μ1, the operation of power equipment is not affected, but the flood disaster may cause harm in the next few hours. In this case, a medium-risk strategy is implemented, the power equipment disaster warning system is activated, and it is prepared to switch to the power equipment that should be used, and the water level sensing sensor of the power equipment is activated to monitor the water level of nearby rivers and the water level information of the power area; when μ1 is less than FSPI, the operation of the power equipment has been affected by the flood. If it cannot operate normally, a high-risk strategy will be implemented, and power supply will be switched to emergency power equipment. According to the importance of the power supply area of the power grid, the principle of giving priority to hospitals, disaster relief centers and infrastructure, priority will be given to ensuring the power supply of key facilities, and preparations will be made for emergency evacuation and repair plans. When a high-risk strategy is implemented and it is detected that FSPI < μ0, the repair plan will be implemented, and the power equipment sensor functions will be re-tested to see if they are normal, and the investigation will be carried out step by step. If all power equipment in an area is tested to be normal, power supply will be restored. If abnormal equipment is found, it will be repaired, and the power area of the abnormal equipment will continue to use the backup line for power supply until all equipment is tested to be normal.
8. A power grid flood survey system for analyzing terrain surface morphology using the method according to any one of claims 1 to 7, characterized in that: The acquisition module receives rainstorm warnings or typhoon warnings issued by the meteorological station, flood warning notices issued by the hydrological center, and water level monitoring data at the location of power equipment, and inputs relevant information of the power geographic information map; A data storage module for storing data processed by the flood disaster investigation system for electric power equipment; A comprehensive processing module is used to start the investigation process of power equipment suffering from flood disasters after receiving the flood defense emergency response notification; The application module is used to display the flooded area, terrain surface morphology and related data of the area where the power equipment is located output by the processing layer, and transmit the data through the website server.
9. A computer device comprising: Memory and processor; The memory stores a computer program, characterized in that when the processor executes the computer program, the steps of the power grid flood survey method for analyzing the terrain surface morphology are implemented.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of a power grid flood survey method for analyzing terrain surface morphology are implemented.