Arsenic trioxide purification treatment equipment
By designing arsenic trioxide purification treatment equipment, using the reasonable layout and desulfurization treatment of settlement and cooling devices, the problems of unstable purity of arsenic trioxide products and blockage of cooling equipment in the existing technology are solved, and the three types of high purity and low impurities are achieved The production of arsenic oxide crystals improves the safety of the process flow and the reliability of the equipment.
Patent Information
- Application Number
- CN202411272786.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-11
- Publication Date
- 2024-11-12
AI Technical Summary
The use of electric furnace heating and water cooling in the prior art results in unstable purity of arsenic trioxide products, many impurities, and unreasonable design of cooling equipment, easy to block, difficult maintenance, and affect the product's pass rate and process safety.
A kind of arsenic trioxide purification treatment equipment was designed, including a purification furnace, a settlement device and a cooling device. Through the rational design of the settlement chamber and cooling chamber, carbon steel material and refractory castable layer are used, combined with alkali desulfurization and wet dust collector. Achieve preliminary purification and cooling of purified flue gas, reduce impurity residues, and improve product purity and appearance quality.
It effectively improves the purity and stability of arsenic trioxide products, reduces impurity residues, improves the purity of the chemical composition and appearance quality of the product, and ensures the safety of the production process and the reliability of the equipment.
Smart Images

Figure CN118925261A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of arsenic trioxide post-processing, and in particular to an arsenic trioxide purification processing device. Background Art
[0002] Arsenic trioxide is one of the by-products in the gold and copper smelting processes. The production of arsenic trioxide products generally adopts the pyrometallurgical process for purification.
[0003] At present, the collection and treatment of arsenic trioxide in arsenic-containing flue gas discharged from the pyrometallurgical process after cooling and crystallization is often neglected. The existing technology generally uses electric furnace heating and water cooling to collect the arsenic trioxide. However, the qualified rate of arsenic trioxide products obtained in this way is low, and there are many impurities, resulting in the purity and whiteness of arsenic trioxide not meeting the standards. In addition, water cooling is prone to blockage and difficult to repair and maintain. Summary of the invention
[0004] The main purpose of the present invention is to provide an arsenic trioxide purification treatment device to solve the problem of unstable arsenic trioxide content in the product caused by using electric furnace heating and water cooling in the prior art.
[0005] In order to achieve the above object, according to one aspect of the present invention, there is provided an arsenic trioxide purification treatment device, comprising:
[0006] A purification furnace, the purification furnace having a first inlet and a first outlet, and the purification furnace is used to purify the crude arsenic trioxide therein to obtain purified flue gas;
[0007] A settling device, the settling device is connected to the purification furnace through the first inlet, and is used to perform settling treatment on the purified flue gas entering the inner cavity of the settling device to obtain settling flue gas;
[0008] The cooling device is connected to the settling device and is used to reduce the temperature of the settling flue gas flowing from the inner cavity of the settling device to the cooling device to a second preset temperature to obtain arsenic trioxide crystals.
[0009] Further, the sedimentation device further comprises: a sedimentation chamber, the sedimentation chamber being connected to the purification furnace through the first inlet;
[0010] The first collecting device includes a plurality of first collecting buckets arranged in a horizontal direction, each of which is connected to the sedimentation chamber and is located below the sedimentation chamber, and is used to collect the product system obtained after sedimentation in the sedimentation chamber.
[0011] Furthermore, the first collecting bucket is conical, the large-mouth end of the first collecting bucket is connected to the sedimentation chamber, and the angle formed by the generatrix of the first collecting bucket and the plane where the small-diameter end thereof is located is a first preset angle.
[0012] Further, the cooling device further comprises: a cooling chamber, the cooling chamber being in communication with the settling device;
[0013] The second collecting device includes a plurality of second collecting buckets arranged in a horizontal direction, each of which is connected to the cooling chamber and is located below the cooling chamber, and is used to collect the product system after cooling in the cooling chamber.
[0014] Furthermore, the second collecting bucket is conical, the large-diameter end of the second collecting bucket is connected to the cooling chamber, and the angle formed by the generatrix of the second collecting bucket and the plane where the small-diameter end thereof is located is a second preset angle.
[0015] Furthermore, there are multiple cooling chambers, which are arranged in a horizontal direction, and each cooling chamber is connected to a second collecting bucket.
[0016] Furthermore, a plurality of first guide plates are provided in the cooling chamber, one end of each first guide plate is connected to the first inner wall of the cooling chamber, and the other end of each first guide plate is provided with a gap with the first plane, which is the plane where the large-diameter end of the second collecting bucket is located.
[0017] Furthermore, a plurality of second guide plates are provided on the first plane, a free end of each second guide plate is provided with a gap with the first inner wall, and the plurality of second guide plates and the plurality of first guide plates are alternately arranged in the horizontal direction in the cavity of the cooling chamber.
[0018] Furthermore, there are multiple cooling chambers, and the multiple cooling chambers are divided into a first cooling chamber group and a second cooling chamber group. The first cooling chamber group includes multiple cooling chambers arranged along a first direction, and the second cooling chamber group includes multiple cooling chambers arranged along a second direction; wherein, each cooling chamber in the first cooling chamber group and each cooling chamber in the second cooling chamber group are respectively provided with a second collecting bucket connected thereto below; wherein the first direction is perpendicular to the second direction.
[0019] Furthermore, a third guide plate is provided in each cooling chamber of the first cooling chamber group, one end of the third guide plate is connected to the second inner wall of the cooling chamber, and the other end of the third guide plate is set in a gap with the second plane, and the second plane is the plane where the large-diameter end of the second collecting bucket is located; a fourth guide plate is provided in each cooling chamber of the second cooling chamber group, one end of the fourth guide plate is connected to the third inner wall of the cooling chamber, and the other end of the fourth guide plate is set in a gap with the fourth inner wall of the cooling chamber, and the third inner wall and the fourth inner wall are arranged opposite to each other.
[0020] Furthermore, the sedimentation chamber and the first collecting device are both made of carbon steel, and the inner wall of the sedimentation chamber and the inner wall of the first collecting device are both provided with a refractory castable layer or refractory bricks.
[0021] Furthermore, the purification treatment equipment also includes: a desulfurization device, which is connected to the cooling device, and is used to use alkali liquid as a desulfurization agent to desulfurize the product system from the cooling device to obtain a desulfurized product.
[0022] Furthermore, the purification treatment equipment also includes: a wet dust collector, which is connected to the desulfurization device and is used to remove particulate matter in the desulfurization product;
[0023] The smoke exhaust device is connected to the wet dust collector and is used to discharge the product system of the wet dust collector.
[0024] Furthermore, the purification treatment equipment further comprises: a transport device, which is arranged below the second collecting device and is used to transport the product system obtained from the second collecting device;
[0025] The packaging device is connected to the transportation device and is used to collect and package the product system output by the transportation device.
[0026] Further, the desulfurization device comprises: a desulfurization unit, the desulfurization unit is connected to the sedimentation chamber, and is used to desulfurize the product system obtained in the sedimentation chamber;
[0027] The cooling unit is connected to the desulfurization unit and is used to transport cooling medium into the settling chamber during the desulfurization process in the desulfurization unit to cool the product system in the settling chamber.
[0028] Furthermore, the desulfurizing agent is any one of sodium hydroxide, sodium carbonate or sodium bicarbonate. Preferably, the desulfurizing agent is sodium hydroxide.
[0029] By applying the technical solution of the present invention, the crude arsenic trioxide is first heated by a purification furnace to obtain purified flue gas, and the purified flue gas is input into a settling device to fully burn the unburned substances contained in the purified flue gas, and at the same time, large particle impurities in the purified flue gas are settled in the settling device to achieve preliminary purification of the purified flue gas to obtain settled flue gas, and the settled flue gas is input into a cooling device to cool it to obtain arsenic trioxide crystals;
[0030] Compared with the prior art, the arsenic trioxide purification equipment provided by the present application effectively improves the purity of the arsenic trioxide product. Through reasonable purification and sedimentation steps, the residual impurities are reduced, making the chemical composition of the product purer. The process flow of the present application helps to remove impurities that affect the color, so that the product has better appearance quality. In addition, a series of improvements from purification to cooling enable the produced arsenic trioxide crystals to reach a high and stable level in key indicators such as purity, content, and whiteness. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:
[0032] Figure 1 The overall schematic diagram of the purification equipment in the embodiment of the present application is shown;
[0033] Figure 2 A schematic diagram showing a cooling chamber arranged in a straight line is shown;
[0034] Figure 3 A schematic diagram showing an L-shaped arrangement of the cooling chamber in an embodiment of the present application is shown.
[0035] The above drawings include the following reference numerals:
[0036] 1. Purification furnace; 101. First inlet; 102. First outlet; 2. Sedimentation device; 201. Sedimentation chamber; 202. First collecting hopper; 3. Cooling device; 301. Cooling chamber; 302. Second collecting hopper; 4. Guide plate; 5. Desulfurization device; 501. Desulfurization unit; 502. Cooling unit; 6. Wet dust collector; 7. Smoke exhaust device; 8. Transport device; 9. Packaging device; 10. Fan; 11. Second guide plate; 12. Third guide plate; 13. Fourth guide plate. DETAILED DESCRIPTION
[0037] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0038] Arsenic trioxide is one of the by-products in gold smelting and copper smelting processes. The arsenic-containing flue gas produced by roasting gold concentrate or smelting copper passes through a quenching tower to obtain crude arsenic trioxide dust, which is generally purified by pyrometallurgical process.
[0039] At present, the collection and flue gas treatment of arsenic trioxide in the arsenic-containing flue gas discharged from the pyrometallurgical process after cooling and crystallization are often neglected. Due to the unreasonable design of the subsequent cooling equipment, the content of arsenic trioxide in the product is unstable. Harmful substances such as arsenic and sulfur in the flue gas need to be removed. Traditional flue gas treatment requires equipment such as bag filters, wet desulfurization towers and electrostatic precipitators. The process is long and the equipment is complex. Due to the toxicity of arsenic trioxide, the health of workers is also harmed during the transportation, packaging and replacement of filter bags and other equipment maintenance.
[0040] The collected arsenic trioxide has low purity and whiteness, and cannot be used directly as a product. It needs to be purified. Purification of crude arsenic trioxide is to utilize its easy sublimation and volatilization characteristics. The crude arsenic trioxide is heated above its boiling point in a specific furnace to volatilize the arsenic trioxide into the flue gas, and then cooled to obtain arsenic trioxide with higher purity. At present, there are three main types of furnaces for purifying crude arsenic trioxide: reverberatory furnace, rotary kiln and steel belt furnace. For the above three pyrometallurgical purification processes, the development and design optimization of furnace types are more, and the process development is relatively mature. However, the collection of arsenic trioxide in the arsenic-containing flue gas after cooling and crystallization and the treatment of arsenic and sulfur-containing flue gas are often neglected. Due to the unreasonable design of subsequent cooling and crystallization equipment, the quality of arsenic trioxide in the product is unstable, with many impurities, and the purity and whiteness are not up to standard. Flue gas contains harmful substances such as arsenic and sulfur. Traditional flue gas treatment uses a process route that combines bag filters and wet flue gas desulfurization. Arsenic trioxide easily forms glass arsenic that blocks the filter bags, greatly shortening the life of the filter bags. Wet flue gas desulfurization also requires a wet electrostatic precipitator to ensure that particulate matter meets emission standards, which prolongs the flue gas treatment process and complicates the equipment. As arsenic trioxide is toxic, it can also harm the health of workers during product transportation, packaging, and equipment maintenance such as changing filter bags.
[0041] Therefore, the purpose of this application is to provide an arsenic trioxide purification treatment device to solve the above problems. The purification treatment device includes:
[0042] A purification furnace 1, the purification furnace 1 having a first inlet 101 and a first outlet 102, and the purification furnace 1 is used to purify the crude arsenic trioxide therein to obtain purified flue gas;
[0043] The settling device 2 is connected to the purification furnace 1 through the first inlet 101, and is used to perform settling treatment on the purified flue gas entering the inner cavity of the settling device 2 to obtain settling flue gas;
[0044] The cooling device 3 is connected to the settling device 2 and is used to reduce the temperature of the settling flue gas flowing from the inner cavity of the settling device 2 to the cooling device 3 to a second preset temperature to obtain arsenic trioxide crystals.
[0045] When using, Figures 1 to 3As shown, the generated crude arsenic trioxide enters the purification furnace 1 from the first inlet 101 and volatilizes into flue gas to obtain purified flue gas. At this time, the temperature of the purified flue gas is 600°C. The purified flue gas enters the settling device 2 from the first outlet 102, and the flow rate slows down. The unburned substances in the purified flue gas are fully burned in the settling device 2. At the same time, large particles of impurities are precipitated in the settling device 2. At this time, the purified flue gas is preliminarily purified and the settling flue gas is obtained. The temperature of the settling flue gas is 400°C to 450°C. The settling flue gas is passed into the cooling device 3. The cooling device 3 is used to reduce the temperature of the settling flue gas at the current moment to a second preset temperature. The second preset temperature in this embodiment is 130°C to 160°C. The settling flue gas gradually changes from a gaseous state to a solid crystal, that is, arsenic trioxide crystals are obtained.
[0046] By applying the technical solution of the present application, the crude arsenic trioxide is first heated by the purification furnace 1 to obtain purified flue gas, and the purified flue gas is input into the settling device 2 to fully burn the unburned substances contained in the purified flue gas, and at the same time, the large particle impurities in the purified flue gas are settled in the settling device 2 to achieve preliminary purification of the purified flue gas to obtain settled flue gas, and the settled flue gas is input into the cooling device 3 to cool it to obtain arsenic trioxide crystals;
[0047] Compared with the prior art, the arsenic trioxide purification equipment provided by the present application effectively improves the purity of the arsenic trioxide product. Through reasonable purification and sedimentation steps, the residual impurities are reduced, making the chemical composition of the product purer. The process flow of the present application helps to remove impurities that affect the color, so that the product has better appearance quality. In addition, a series of improvements from purification to cooling enable the produced arsenic trioxide crystals to reach a high and stable level in key indicators such as purity, content, and whiteness.
[0048] Furthermore, the sedimentation device 2 further comprises: a sedimentation chamber 201, the sedimentation chamber 201 is connected to the purification furnace 1 through the first inlet 101;
[0049] The first collecting device includes a plurality of first collecting buckets 202 arranged in a horizontal direction. Each of the first collecting buckets 202 is connected to the settling chamber 201 and is located below the settling chamber 201 , and is used to collect the product system obtained after settling in the settling chamber 201 .
[0050] By providing the settling chamber 201, large particle impurities in the purified flue gas can settle in the settling chamber 201 and fall into the first collecting device, which collects the large particle impurities, thereby preventing the large particle impurities from falling into the environment and causing harm to the environment.
[0051] Furthermore, the first collecting bucket 202 is conical, the large-mouth end of the first collecting bucket 202 is connected to the sedimentation chamber 201, and the angle formed by the generatrix of the first collecting bucket 202 and the plane where the small-diameter end thereof is located is a first preset angle.
[0052] The first collecting bucket 202 is conical in shape. The large-diameter end of the first collecting bucket 202 is connected to the sedimentation chamber 201. The small-diameter end of the first collecting bucket 202 forms a first plane. The angle between the busbar of the first collecting bucket 202 and the first plane is 62 degrees, which is conducive to the smooth entry of large particles of impurities into the bottom of the first collecting bucket 202. In this process, the large particles of impurities will not adhere to the inner wall of the first collecting bucket 202.
[0053] Furthermore, the cooling device 3 further comprises: a cooling chamber 301, the cooling chamber 301 being in communication with the settling device 2;
[0054] The second collecting device includes a plurality of second collecting buckets 302 arranged in a horizontal direction. Each second collecting bucket 302 is connected to the cooling chamber 301 and is located below the cooling chamber 301 , and is used to collect the product system after cooling in the cooling chamber 301 .
[0055] A second collecting device is provided below the cooling chamber 301 , and the second collecting device includes a plurality of second collecting buckets 302 arranged in a horizontal direction. The second collecting buckets 302 are used to collect the product system after cooling in the cooling chamber 301 .
[0056] Furthermore, the second collecting bucket 302 is conical, the large-diameter end of the second collecting bucket 302 is connected to the cooling chamber 301, and the angle formed by the generatrix of the second collecting bucket 302 and the plane where the small-diameter end thereof is located is a second preset angle.
[0057] The second collecting bucket 302 is conical in shape. The large-diameter end of the second collecting bucket 302 is connected to the cooling chamber 301, and the small-diameter end of the second collecting bucket 302 forms a second plane. The angle between the generatrix of the second collecting bucket 302 and the second plane is 62 degrees, which is conducive to the product system after cooling to smoothly enter the bottom of the second collecting bucket 302, and in this process, the product system in the cooling chamber 301 will not adhere to the inner wall of the second collecting bucket 302.
[0058] Furthermore, there are multiple cooling chambers 301 , which are arranged in a horizontal direction, and each cooling chamber 301 is connected to a second collecting hopper 302 .
[0059] Furthermore, a plurality of first guide plates 4 are provided in the cooling chamber 301, one end of each first guide plate 4 is connected to the first inner wall of the cooling chamber 301, and the other end of each first guide plate 4 is provided with a gap with the first plane, which is the plane where the large-diameter end of the second collecting bucket 302 is located.
[0060] By providing a plurality of cooling chambers 301 and a plurality of first guide plates 4 in each cooling chamber 301, the plurality of first guide plates 4 can be arranged in the inner cavity of the cooling chamber 301 at equal intervals, or can be arranged in the inner cavity of the cooling chamber 301 at unequal intervals, one end of each first guide plate 4 is connected to the first inner wall of the cooling chamber 301, and a gap is provided between the other end of each first guide plate 4 and the first plane, wherein the first plane is the plane where the large-diameter end of the second collecting hopper 302 is located, and each cooling chamber 301 is connected to a second collecting hopper 302 at the bottom, respectively, so as to prolong the residence time of the settling flue gas in the cooling chamber 301, and thereby to settle the arsenic trioxide in the settling flue gas as much as possible, so as to increase the yield and quality of arsenic trioxide crystals.
[0061] Furthermore, a plurality of second guide plates 11 are provided on the first plane, a free end of each second guide plate 11 is provided with a gap with the first inner wall, and the plurality of second guide plates 11 and the plurality of first guide plates 4 are alternately arranged in the horizontal direction in the cavity of the cooling chamber 301 .
[0062] By providing a plurality of second guide plates 11 on the first plane, and staggering the plurality of second guide plates 11 and the first guide plates 4 in the horizontal direction in the chamber of the cooling chamber 301, the residence time of the settling flue gas in the cooling chamber 301 can be further extended, thereby settling arsenic trioxide in the settling flue gas as much as possible, thereby increasing the yield and quality of arsenic trioxide crystals.
[0063] Further, there are multiple cooling chambers 301, and the multiple cooling chambers 301 are divided into a first cooling chamber group and a second cooling chamber group. The first cooling chamber group includes multiple cooling chambers 301 arranged along a first direction, and the second cooling chamber group includes multiple cooling chambers 301 arranged along a second direction; wherein each cooling chamber 301 in the first cooling chamber group and each cooling chamber 301 in the second cooling chamber group are respectively provided with a second collecting bucket 302 in communication therewith below; wherein the first direction is perpendicular to the second direction;
[0064] A third guide plate 12 is provided in each cooling chamber 301 in the first cooling chamber group, one end of the third guide plate 12 is connected to the second inner wall of the cooling chamber 301, and the other end of the third guide plate 12 is set in a gap with the second plane, and the second plane is the plane where the large-diameter end of the second collecting bucket 302 is located. A fourth guide plate 13 is provided in each cooling chamber 301 in the second cooling chamber group, one end of the fourth guide plate 13 is connected to the third inner wall of the cooling chamber 301, and the other end of the fourth guide plate 13 is set in a gap with the fourth inner wall of the cooling chamber 301, and the third inner wall and the fourth inner wall are arranged opposite to each other.
[0065] The first cooling chamber group and the second cooling chamber group are together L-shaped. By arranging multiple cooling chambers 301 into an L-shape and providing a third guide plate 12 and a fourth guide plate 13, the residence time of the settling flue gas in the cooling chamber 301 can be increased to increase the yield and quality of arsenic trioxide crystals.
[0066] Furthermore, the sedimentation chamber 201 and the first collecting device are both made of carbon steel, and the inner wall of the sedimentation chamber 201 and the inner wall of the first collecting device are both provided with a refractory castable layer or refractory bricks.
[0067] By providing refractory castables or refractory bricks on the inner wall of the settling chamber 201 and the inner wall of the first collecting device, in the present embodiment, the refractory castables and refractory bricks are made of high-aluminum refractory castables or high-aluminum refractory bricks with alumina as the main material, wherein the material of the refractory castable is relatively cheap, and the construction difficulty of the refractory brick material is low. By providing refractory castables or refractory bricks on the inner wall of the first collecting device, it is possible to withstand the higher temperature during the settling process, prevent the inner wall from being deformed or damaged due to high temperature, and ensure the stability and integrity of the structure in the settling chamber 201 and the first collecting device. At the same time, it can also effectively resist the scouring and wear of particulate matter in the settling flue gas, extend the service life of the settling chamber 201 and the first collecting device, and resist the erosion and corrosion of chemical substances in the flue gas, maintaining the performance and structural stability of the inner wall. At the same time, the material of the settling chamber 201 and the first collecting device is carbon steel, which can ensure that the settling chamber 201 and the first collecting device have higher strength, can withstand the pressure and mechanical stress in the settling chamber 201, and ensure the stability and safety of the structure.
[0068] Furthermore, the purification treatment equipment also includes: a desulfurization device 5, which is connected to the cooling device 3, and is used to use alkali liquid as a desulfurization agent to desulfurize the product system from the cooling device 3 to obtain a desulfurized product.
[0069] The desulfurizing agent is any one of sodium hydroxide, sodium carbonate or sodium bicarbonate. Preferably, the desulfurizing agent is sodium hydroxide.
[0070] Using alkali solution as a desulfurizer can improve the efficiency of desulfurization. Alkali solution has strong alkalinity and can more effectively absorb sulfur dioxide, metal particles and residual arsenic in flue gas. Compared with other desulfurizers, the price of alkali solution is relatively low, which can effectively reduce operating costs. At the same time, the product generated by the reaction of alkali solution and sulfur dioxide has a large solubility and is not easy to form waste residue, reducing the cost of waste residue treatment and disposal. In this application, the desulfurizer is selected as sodium hydroxide with a mass concentration of 5%. Sodium hydroxide is a strong base and can effectively absorb sulfur dioxide, thereby improving the efficiency of desulfurization.
[0071] Furthermore, the purification treatment equipment further comprises: a wet dust collector 6, which is connected to the desulfurization device 5 and is used to remove particulate matter in the desulfurization product;
[0072] The smoke exhaust device 7 is connected to the wet dust collector 6 and is used to discharge the product system of the wet dust collector 6.
[0073] By providing a wet dust collector 6, particulate matter in the desulfurization product can be removed, and the product system in the wet dust collector 6 can be discharged to the outside through the smoke exhaust device 7, wherein the smoke exhaust device 7 can be a chimney.
[0074] Furthermore, the purification treatment equipment further comprises: a transport device 8, which is arranged below the second collecting device and is used to transport the product system obtained from the second collecting device;
[0075] The packaging device 9 is connected to the transportation device 8 and is used for collecting and packaging the product system output by the transportation device 8.
[0076] The product system collected by the second collecting device directly enters the transport device 8 from the second collecting device, and the transport device 8 transports the product system to the packaging device 9, which collects and packages it. The second collecting device and the transport device 8, as well as the transport device 8 and the packaging device 9 are all sealed to form a fully sealed structure to prevent dust leakage. In the entire process, full automation is achieved, and there is no need for direct contact between people and arsenic trioxide, thereby avoiding its harm to the human body.
[0077] Furthermore, the desulfurization device 5 comprises: a desulfurization unit 501, which is connected to the settling chamber 201 and is used to desulfurize the product system obtained in the settling chamber 201;
[0078] The cooling unit 502 is connected to the desulfurization unit 501 and is used to transport cooling medium into the settling chamber 201 during the desulfurization process of the desulfurization unit 501 to cool the product system in the settling chamber 201 .
[0079] Eight dual-fluid physicochemical spray guns are used in the desulfurization unit 501, and the medium of the cooling unit 502 is industrial circulating water, which can cool the product system of the settling chamber 201 during the desulfurization process.
[0080] Example 1
[0081] The generated crude arsenic trioxide enters the purification furnace 1 through the first inlet 101 for purification. The crude arsenic trioxide is heated in the purification furnace 1 to form purified flue gas. At this time, the temperature of the purified flue gas is 600°C, and the dust contained in the purified flue gas is about 10g / Nm 3 , SO2 is about 400mg / Nm 3 , crude arsenic trioxide enters the settling chamber 201 along with the purified flue gas. The size of the settling chamber is 9000mm*4000mm*6000mm (length*width*height). A single layer of corundum refractory bricks is provided on the inner wall of the settling chamber 201. The inclination angle of the first collecting bucket 202 located below the settling chamber 201 is 62 degrees (the inclination angle is the angle between the plane formed by the small-diameter end of the first collecting bucket 202 and the generatrix of the first collecting bucket 202). Within this range, the unburned large particles of impurities in the purified flue gas can be The purified flue gas is collected by the first collecting hopper 202. At this time, the purified flue gas is preliminarily purified, and the temperature of the purified flue gas is reduced to 400°C to 450°C. The settling flue gas rich in arsenic trioxide enters the cooling chamber 301 in a straight line or L-shaped arrangement in sequence. A plurality of first guide plates 4 are provided in the cooling chamber 301. The plurality of first guide plates 4 in the cooling chamber 301 cool the settling flue gas, and the temperature of the settling flue gas is slowly reduced to 130°C to 160°C. The specification of the cooling chamber is 4000 The second collecting hopper 302 below the cooling chamber 301 has an inclination angle of 62 degrees (the inclination angle is the angle between the plane formed by the small-diameter end of the second collecting hopper 302 and the generatrix of the second collecting hopper 302). Arsenic trioxide crystals enter the transport device 8 below from the second collecting hopper 302, and the transport device 8 transports the arsenic trioxide crystals to the packaging device 9, which packages the collected arsenic trioxide crystals. The other end of the settling chamber 201 is also connected to a desulfurization unit 501. The flue gas from which arsenic trioxide is removed enters the desulfurization unit 501 for desulfurization treatment. The desulfurizer is a diluted sodium hydroxide solution with a mass fraction of 5%. During the desulfurization process, the cooling unit 502 transports a cooling medium into the settling chamber 201 to cool the product system of the settling chamber 201, and the final flue gas is discharged through a chimney. The purity of the arsenic trioxide product obtained by the embodiment of the present application is greater than or equal to 99.5%.
[0082] Example 2
[0083] The generated crude arsenic trioxide enters the purification furnace 1 through the first inlet 101 for purification. The crude arsenic trioxide is heated in the purification furnace 1 to form purified flue gas. At this time, the temperature of the purified flue gas is 350°C-400°C, and the dust contained in the purified flue gas is about 8g / Nm 3 , SO2 is about 300mg / Nm 3 , crude arsenic trioxide enters the settling chamber 201 along with the purified flue gas. The size of the settling chamber is 4000mm*3000mm*3000mm (length*width*height). A single layer of refractory castable is provided on the inner wall of the settling chamber 201. The first collecting bucket 202 located below the settling chamber 201 has an inclination angle of 63 degrees (the inclination angle is the angle between the plane formed by the small-diameter end of the first collecting bucket 202 and the busbar of the first collecting bucket 202). Within this range, large particles of impurities that are not completely burned in the purified flue gas can be collected by the first collecting bucket 202. At this time, the purified flue gas is preliminarily purified, and the temperature of the purified flue gas is reduced to 300°C. The settling flue gas rich in arsenic trioxide enters the cooling chamber 301 in a straight line or L-shaped arrangement in turn (such as Figure 3 As shown, it is a top view of a plurality of cooling chambers 301 in an L shape. A plurality of first guide plates 4 are provided in each cooling chamber 301. The plurality of first guide plates 4 cool the settling flue gas. The temperature of the settling flue gas slowly decreases to 140°C to 160°C. The specification of the cooling chamber is 3000mm*3000mm*3000mm (length*width*height). The inclination angle of the second collecting hopper 302 located below the cooling chamber 301 (the inclination angle is the angle between the plane formed by the small-diameter end of the second collecting hopper 302 and the generatrix of the second collecting hopper 302) is 62 degrees. Arsenic trioxide crystals enter the transport device 8 below from the second collecting hopper 302. The transport device 8 transports the arsenic trioxide crystals to the packaging device 9, and the packaging device 9 packages the collected arsenic trioxide crystals. At the same time, the other end of the sedimentation chamber 201 is also connected to the desulfurization unit 501, and the flue gas from which arsenic trioxide is removed enters the desulfurization unit 501 for desulfurization treatment. The desulfurizer is a dilute sodium hydroxide solution with a mass fraction of 5%. During the desulfurization process, the cooling unit 502 transports a cooling medium into the sedimentation chamber 201 to cool the product system of the sedimentation chamber 201, and the final flue gas is discharged through the chimney. The purity of the arsenic trioxide product obtained by the embodiment of the present application is greater than or equal to 99.9%.
[0084] The arsenic trioxide purification treatment equipment provided in the present application includes a purification furnace 1, crude arsenic trioxide enters the purification furnace 1 from a first inlet 101 for purification, and purified flue gas is obtained, the purified flue gas enters a straight-line or L-shaped settling chamber 201 from a first outlet 102, and the settling chamber 201 performs sedimentation treatment on the purified flue gas in its inner cavity to remove large particles of impurities in the purified flue gas as much as possible, in the process of settling the purified flue gas in the settling chamber 201, the large particles of impurities contained therein will enter the first collecting bucket 202, and will be collected by the first collecting bucket 202, and settled flue gas will be obtained after collection, and the settled flue gas will enter the cooling chamber 301, and the cooling chamber 301 will cool the settled flue gas so that the temperature of the settled flue gas in the cooling chamber 301 is reduced to a second preset temperature, and arsenic trioxide crystals are obtained, and the obtained arsenic trioxide crystals are The arsenic trioxide crystals are transported to the packaging device 9 by the transportation device 8, and the arsenic trioxide crystals are collected and packaged by the packaging device 9. At the same time, the other end of the sedimentation chamber 201 is also connected to the desulfurization unit 501, which is used to spray sodium hydroxide solution into the sedimentation chamber 201 to desulfurize the product system obtained in the sedimentation chamber 201. During the desulfurization process, the cooling unit 502 transports a cooling medium into the sedimentation chamber 201 to cool the product system in the sedimentation chamber 201, wherein industrial water is selected as the cooling medium. A fan 10 is also provided between the desulfurization device 5 and the cooling chamber 301, and the fan 10 is used to transport the product system in the cooling chamber 301 to the desulfurization device 5 for desulfurization, and discharge the flue gas after desulfurization from the chimney.
[0085] From the above description, it can be seen that the above embodiments of the present invention achieve the following technical effects:
[0086] By applying the technical solution of the present application, the crude arsenic trioxide is first heated by the purification furnace 1 to obtain purified flue gas, and the purified flue gas is input into the settling device 2 to fully burn the unburned substances contained in the purified flue gas, and at the same time, the large particle impurities in the purified flue gas are settled in the settling device 2 to achieve preliminary purification of the purified flue gas to obtain settled flue gas, and the settled flue gas is input into the cooling device 3 to cool it to obtain arsenic trioxide crystals;
[0087] Compared with the prior art, the arsenic trioxide purification equipment provided by the present application effectively improves the purity of the arsenic trioxide product. Through reasonable purification and sedimentation steps, the residual impurities are reduced, making the chemical composition of the product purer. The process flow of the present application helps to remove impurities that affect the color, so that the product has better appearance quality. In addition, a series of improvements from purification to cooling enable the produced arsenic trioxide crystals to reach a high and stable level in key indicators such as purity, content, and whiteness.
[0088] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0089] Unless otherwise specifically stated, the relative arrangement of the parts and steps described in these embodiments, numerical expressions and numerical values do not limit the scope of the present invention. At the same time, it should be understood that, for ease of description, the sizes of the various parts shown in the accompanying drawings are not drawn according to the actual proportional relationship. The technology, method and equipment known to ordinary technicians in the relevant field may not be discussed in detail, but in appropriate cases, the technology, method and equipment should be regarded as a part of the authorization specification. In all examples shown and discussed here, any specific value should be interpreted as being merely exemplary, rather than as a limitation. Therefore, other examples of exemplary embodiments may have different values. It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once a certain item is defined in an accompanying drawing, it does not need to be further discussed in subsequent drawings.
[0090] In the description of the present invention, it is necessary to understand that the directions or positional relationships indicated by directional words such as "front, back, up, down, left, right", "lateral, vertical, perpendicular, horizontal" and "top, bottom" are usually based on the directions or positional relationships shown in the drawings. They are only for the convenience of describing the present invention and simplifying the description. Unless otherwise specified, these directional words do not indicate or imply that the devices or elements referred to must have a specific direction or be constructed and operated in a specific direction. Therefore, they cannot be understood as limiting the scope of protection of the present invention. The directional words "inside and outside" refer to the inside and outside relative to the contours of each component itself.
[0091] For ease of description, spatially relative terms such as "above", "above", "on the upper surface of", "above", etc. may be used here to describe the spatial positional relationship between a device or feature and other devices or features as shown in the figure. It should be understood that spatially relative terms are intended to include different orientations of the device in use or operation in addition to the orientation described in the figure. For example, if the device in the accompanying drawings is inverted, the device described as "above other devices or structures" or "above other devices or structures" will be positioned as "below other devices or structures" or "below other devices or structures". Thus, the exemplary term "above" can include both "above" and "below". The device can also be positioned in other different ways (rotated 90 degrees or in other orientations), and the spatially relative descriptions used here are interpreted accordingly.
[0092] In addition, it should be noted that the use of terms such as "first" and "second" to limit components is only for the convenience of distinguishing the corresponding components. If not otherwise stated, the above terms have no special meaning and therefore cannot be understood as limiting the scope of protection of the present invention.
[0093] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. An arsenic trioxide purification treatment device, characterized in that: include: A purification furnace (1), the purification furnace (1) having a first inlet (101) and a first outlet (102), the purification furnace (1) being used for purifying crude arsenic trioxide therein to obtain purified flue gas; A settling device (2), the settling device (2) being connected to the purification furnace (1) via the first inlet (101), and being used for performing a settling treatment on the purified flue gas entering the inner cavity of the settling device (2) to obtain settling flue gas; A cooling device (3), the cooling device (3) is connected to the settling device (2), and is used to reduce the temperature of the settling flue gas flowing from the inner cavity of the settling device (2) to the cooling device (3) to a second preset temperature, so as to obtain arsenic trioxide crystals.
2. The arsenic trioxide purification treatment equipment according to claim 1, characterized in that: The sedimentation device (2) further comprises: a settling chamber (201), the settling chamber (201) being in communication with the purification furnace (1) via the first inlet (101); A first collecting device, the first collecting device comprises a plurality of first collecting buckets (202) arranged in a horizontal direction, each of the first collecting buckets (202) is connected to the sedimentation chamber (201) and is located below the sedimentation chamber (201), and is used to collect a product system obtained after sedimentation from the sedimentation chamber (201).
3. The arsenic trioxide purification treatment equipment according to claim 2, characterized in that: The first collecting bucket (202) is conical in shape, the large-mouth end of the first collecting bucket (202) is connected to the sedimentation chamber (201), and the angle formed by the generatrix of the first collecting bucket (202) and the plane where the small-mouth end thereof is located is a first preset angle.
4. The arsenic trioxide purification treatment equipment according to claim 3, characterized in that: The cooling device (3) further comprises: a cooling chamber (301), the cooling chamber (301) being in communication with the settling device (2); The second collecting device comprises a plurality of second collecting buckets (302) arranged in a horizontal direction, each of the second collecting buckets (302) is connected to the cooling chamber (301) and is located below the cooling chamber (301), and is used to collect the product system after cooling from the cooling chamber (301).
5. The arsenic trioxide purification treatment equipment according to claim 4, characterized in that: The second collecting bucket (302) is conical in shape, the large-diameter end of the second collecting bucket (302) is connected to the cooling chamber (301), and the angle formed by the generatrix of the second collecting bucket (302) and the plane where the small-diameter end thereof is located is a second preset angle.
6. The arsenic trioxide purification treatment equipment according to claim 4, characterized in that: There are a plurality of cooling chambers (301), and the plurality of cooling chambers (301) are arranged along the horizontal direction, and each cooling chamber (301) is connected to a second collecting bucket (302).
7. The arsenic trioxide purification treatment equipment according to claim 6, characterized in that: A plurality of first guide plates (4) are provided in the cooling chamber (301), one end of each of the first guide plates (4) being connected to the first inner wall of the cooling chamber (301), and the other end of each of the first guide plates (4) being provided with a gap with a first plane, wherein the first plane is the plane where the large-diameter end of the second collecting hopper (302) is located.
8. The arsenic trioxide purification treatment equipment according to claim 7, characterized in that: A plurality of second guide plates (11) are provided on the first plane, and a free end of each second guide plate (11) is provided with a gap with the first inner wall. The plurality of second guide plates (11) and the plurality of first guide plates (4) are staggeredly arranged along the horizontal direction in the cavity of the cooling chamber (301).
9. The arsenic trioxide purification treatment equipment according to claim 4, characterized in that: There are multiple cooling chambers (301), and the multiple cooling chambers (301) are divided into a first cooling chamber group and a second cooling chamber group. The first cooling chamber group includes multiple cooling chambers (301) arranged along a first direction, and the second cooling chamber group includes multiple cooling chambers (301) arranged along a second direction; wherein each cooling chamber (301) in the first cooling chamber group and each cooling chamber (301) in the second cooling chamber group are respectively provided with a second collecting bucket (302) connected thereto below; wherein the first direction is perpendicular to the second direction.
10. The arsenic trioxide purification treatment equipment according to claim 9, characterized in that: A third guide plate (12) is provided in each cooling chamber (301) in the first cooling chamber group, one end of the third guide plate (12) is connected to the second inner wall of the cooling chamber (301), and the other end of the third guide plate (12) is arranged in a gap with a second plane, and the second plane is the plane where the large-diameter end of the second collecting bucket (302) is located; a fourth guide plate (13) is provided in each cooling chamber (301) in the second cooling chamber group, one end of the fourth guide plate (13) is connected to the third inner wall of the cooling chamber (301), and the other end of the fourth guide plate (13) is arranged in a gap with the fourth inner wall of the cooling chamber (301), and the third inner wall and the fourth inner wall are arranged opposite to each other.
11. The arsenic trioxide purification treatment equipment according to claim 2, characterized in that: The sedimentation chamber (201) and the first collecting device are both made of carbon steel, and the inner wall of the sedimentation chamber (201) and the inner wall of the first collecting device are both provided with a refractory castable layer or refractory bricks.
12. The arsenic trioxide purification treatment equipment according to claim 11, characterized in that: The purification treatment equipment also includes: A desulfurization device (5), the desulfurization device (5) is connected to the cooling device (3), and the desulfurization device (5) is used to use alkali liquid as a desulfurizing agent to desulfurize the product system from the cooling device (3) to obtain a desulfurized product.
13. The arsenic trioxide purification treatment equipment according to claim 12, characterized in that: The purification treatment equipment also includes: A wet dust collector (6), the wet dust collector (6) being connected to the desulfurization device (5) and used for removing particulate matter in the desulfurization product; A smoke exhaust device (7), wherein the smoke exhaust device (7) is connected to the wet dust collector (6) and is used to discharge the product system of the wet dust collector (6).
14. The arsenic trioxide purification treatment equipment according to claim 4, characterized in that: The purification treatment equipment also includes: a transport device (8), the transport device (8) being arranged below the second collecting device and being used for transporting the product system obtained from the second collecting device; A packaging device (9), the packaging device (9) is connected to the transportation device (8) and is used to collect and package the product system output by the transportation device (8).
15. The arsenic trioxide purification treatment equipment according to claim 12, characterized in that: The desulfurization device (5) comprises: A desulfurization unit (501), the desulfurization unit (501) being in communication with the settling chamber (201) and being used for desulfurizing the product system obtained in the settling chamber (201); A cooling unit (502) is connected to the desulfurization unit (501) and is used to transport a cooling medium into the settling chamber (201) during the desulfurization process in the desulfurization unit (501) to cool the product system in the settling chamber (201).
16. The arsenic trioxide purification treatment equipment according to claim 12, characterized in that: The desulfurizing agent is any one of sodium hydroxide, sodium carbonate or sodium bicarbonate. Preferably, the desulfurizing agent is sodium hydroxide.