Flue gas multi-stage cooling device
By adopting a combined structure of a multi-stage spray chamber and a liquid collection assembly in the flue gas multi-stage cooling device, the problem of insufficient flue gas cooling in the prior art is solved, and efficient flue gas cooling and pollutant removal are achieved. Reduces the risk of dust clogging and cooling costs.
Patent Information
- Application Number
- CN202411181998.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-11-12
AI Technical Summary
The cooling system in the existing flue gas multi-pollutant integrated removal system is difficult to cool the flue gas to a lower temperature, resulting in poor pollutant removal effect and large space.
A multi-stage flue gas cooling device was designed. Through the multi-stage spray chamber structure in the tower body, the spray assembly was used to spray coolant step by step, combining the liquid collection assembly and the filler assembly to achieve step-by-step cooling of the flue gas to ensure stability and stability. Control the cooling effect and reduce the risk of dust blockage.
The flue gas temperature is effectively reduced to the sub-zero temperature zone, which improves cooling efficiency, reduces the space and cost of the cooling system, and significantly reduces the dust concentration in the flue gas.
Smart Images

Figure CN118935431A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of low-temperature flue gas purification, and in particular to a flue gas multi-stage cooling device. Background Art
[0002] Coal-fired flue gas and incineration flue gas produce a large amount of pollutants, which is one of the important factors that endanger the atmospheric environment and human health. Coal-fired flue gas pollutants can be divided into two categories according to their emission and degree of harm: main pollutants and other pollutants. The main pollutants include dust, SO 2 and NOx, other pollutants include SO 3 , HCl, HF, Hg and VOCS, etc.
[0003] The related technology proposes a near-zero emission flue gas multi-pollutant integrated removal system and method, which uses the solubility and adsorption characteristics of pollutant components in flue gas at low temperatures to remove pollutants, and can simultaneously remove SO 2 、SO 3 ,NO,NO 2 , HCl, HF, Hg and VOCs, and achieve near-zero emissions. However, the cooling system in the integrated removal system is difficult to cool the flue gas to a lower temperature target, the pollutant removal effect is poor, and it occupies a large space. Summary of the invention
[0004] The present invention aims to solve at least one of the technical problems in the related art to a certain extent. To this end, the present invention proposes a flue gas multi-stage cooling device, which solves the problem that direct cooling is difficult to cool the flue gas to a lower temperature target and occupies a large space.
[0005] The multi-stage flue gas cooling device of the present invention includes a tower body, which has a chamber therein. The tower body is provided with a flue gas inlet and a flue gas outlet. The chamber includes multi-stage spray chambers arranged at intervals. The flue gas entering the chamber through the flue gas inlet can pass through the multi-stage spray chambers in sequence. A spray assembly is provided in the spray chamber. The spray assembly is used to spray cooling liquid to cool the flue gas in the spray chamber. The multi-stage spray chamber includes a first-stage spray chamber located at the upstreammost position in the direction of flue gas flow and the remaining stages of spray chambers except the first-stage spray chamber. The remaining stages of spray chambers are provided with liquid collecting assemblies and filler assemblies. The liquid collecting assembly is used to prevent the spray liquid in the remaining stages of spray chambers from entering the first-stage spray chamber. The filler assembly is located downstream of the liquid collecting assembly in the direction of flue gas flow. The flue gas is reduced to low-temperature flue gas in the sub-zero temperature zone through the multi-stage spray chambers and is discharged from the chamber through the smoke outlet.
[0006] In the multi-stage flue gas cooling device of the present invention, the flue gas passes through the multi-stage spray chamber in sequence, and the coolant sprayed by the spray assembly arranged in each stage of the spray chamber is used to cool the flue gas in a step-by-step manner, and the temperature of the flue gas is gradually reduced to the sub-zero temperature zone, thereby solving the problem that it is difficult to cool the flue gas to a lower temperature target by direct cooling in one step. The first stage spray chamber and the remaining stage spray chambers are separated by the liquid collecting assembly, and under the premise of ensuring the stable flow of the flue gas, the coolant sprayed by the spray assembly in the spray chambers of different stages is prevented from interfering with each other, thereby ensuring a stable and controllable cooling effect.
[0007] In addition, the first-stage spray chamber is an empty tower spray cooling, and the flue gas is in direct contact with the coolant, which reduces the flue gas temperature and washes away the dust in the flue gas. The dust concentration in the washed flue gas is greatly reduced. Compared with the method of setting packing components in each level of spray chamber, the first-stage spray chamber does not have a packing component, which can effectively reduce the problem of dust blocking the tower packing.
[0008] Optionally, the multiple levels of spray chambers are arranged vertically, and the remaining levels of spray chambers are multiple and include a secondary spray chamber, a tertiary spray chamber and a fourth spray chamber arranged in sequence in the flow direction of the smoke, and each of the secondary spray chamber, the tertiary spray chamber and the fourth spray chamber is provided with the liquid collecting assembly and the filler assembly, and in each of the remaining levels of spray chambers, the filler assembly is located downstream of the liquid collecting assembly in the flow direction of the smoke, the smoke inlet is connected to the primary spray chamber, and the smoke outlet is connected to the fourth spray chamber.
[0009] The multi-stage flue gas cooling device of the present invention divides the chamber of the tower body into a primary spray chamber, a secondary spray chamber, a tertiary spray chamber and a quaternary spray chamber. The temperature of the flue gas entering the primary spray chamber through the flue gas inlet is 80°C-90°C, which is cooled to 50°C-60°C in the primary spray chamber, to 20°C-30°C in the secondary spray chamber, to 2°C-5°C in the tertiary spray chamber, and to -20°C--5°C in the quaternary spray chamber, thereby achieving uniform step-by-step cooling of the flue gas and improving the cooling efficiency of the flue gas.
[0010] In addition, the pre-cooling temperature of the flue gas in the first-stage spray chamber is higher than the room temperature, and there is no need to set up a packing component. The pre-cooling temperature of the flue gas in the second-stage spray chamber, the third-stage spray chamber, and the fourth-stage spray chamber is below the room temperature. By setting up a packing component to slow down the flow speed of the flue gas, the contact time between the flue gas and the coolant is increased, so that the flue gas and the coolant can fully exchange heat. In this way, while ensuring the cooling effect, the space occupied by the first-stage spray chamber is reduced, thereby reducing the manufacturing cost.
[0011] In addition, the spray components in the first-stage spray chamber, the second-stage spray chamber and the third-stage spray chamber are cooled by circulating cooling water spray, and the spray components in the fourth-stage spray chamber are cooled by circulating coolant spray. The use category of the coolant is reasonably designed to further reduce the flue gas cooling cost.
[0012] Optionally, the ratio of the height of the first-level spray chamber, the height of the second-level spray chamber, the height of the third-level spray chamber and the height of the fourth-level spray chamber is (2.6-2.8):1:1:(2.7-3).
[0013] In the multi-stage flue gas cooling device of the present invention, since the flue gas inlet and the flue gas outlet are respectively connected to the first-stage spray chamber and the fourth-stage spray chamber, the height of the first-stage spray chamber and the fourth-stage spray chamber needs to be set higher than the height of the second-stage spray chamber and the third-stage spray chamber to ensure that the flue gas has a buffer height when entering and exiting the tower body, thereby improving the uniformity of the flue gas flow after the smoke enters and exits the tower.
[0014] Optionally, the spray assembly has a spray port for spraying coolant, the liquid collecting assembly has a rising port for smoke flow, and the vertical distance between the spray port of the spray assembly in the primary spray chamber and the smoke inlet is a 1 The vertical distance between the spray port of the spray assembly in the secondary spray chamber and the air riser of the liquid collecting assembly in the secondary spray chamber is a 2 The vertical distance between the spray port of the spray assembly in the three-stage spray chamber and the air riser of the liquid collecting assembly in the three-stage spray chamber is a 3 The vertical distance between the spray port of the spray assembly in the four-stage spray chamber and the air riser of the liquid collecting assembly in the four-stage spray chamber is a 4 , and satisfy the following relationship:
[0015] |a 3 -a 2 |=|a 4 -a 3 |, and
[0016] |a 1 -a 2 |=(3~4)×|a 3 -a 2 |.
[0017] In the multi-stage flue gas cooling device of the present invention, the pre-cooling temperature of the flue gas in the secondary spray chamber, the tertiary spray chamber and the quaternary spray chamber is gradually reduced, so that the spray cooling height in the secondary spray chamber, the tertiary spray chamber and the quaternary spray chamber is gradually increased and presents an arithmetic progression, thereby ensuring the cooling effect of the flue gas. In addition, the spray cooling height in the primary spray chamber is much greater than the spray cooling height in the secondary spray chamber, so as to ensure that the dust concentration in the flue gas is fully reduced in the primary spray chamber.
[0018] Optionally, the ratio of the packing height of the packing assembly in the secondary spray chamber, the packing height of the packing assembly in the tertiary spray chamber, and the packing height of the packing assembly in the quaternary spray chamber is 2:1:1.
[0019] In the multi-stage flue gas cooling device of the present invention, since the temperature of the flue gas entering the tower is relatively high, the circulating cooling water sprayed by the spray assembly in the first-stage spray chamber will be carried into the second-stage spray chamber by the flue gas due to evaporation loss, thereby increasing the packing height of the packing assembly in the second-stage spray chamber relative to the packing height of the packing assembly in the third-stage spray chamber and the fourth-stage spray chamber, so that the moisture in the flue gas is condensed in large quantities in the second-stage spray chamber, playing a dehumidifying role, and avoiding the flue gas carrying a large amount of moisture into the spray chamber with a lower cooling temperature, which affects the cooling effect. The packing height of the packing assembly in the third-stage spray chamber and the fourth-stage spray chamber can be a normal height that meets the cooling effect, avoiding increasing the unnecessary packing height, which leads to increased costs.
[0020] Optionally, the distance between the filler assembly in the secondary spray chamber and the spray port of the spray assembly in the secondary spray chamber, the distance between the filler assembly in the tertiary spray chamber and the spray port of the spray assembly in the tertiary spray chamber, and the distance between the filler assembly in the quaternary spray chamber and the spray port of the spray assembly in the quaternary spray chamber are all the same.
[0021] In actual engineering applications, multiple manholes are provided on the tower body to facilitate the replacement and maintenance of the tower internals by the staff. In the multi-stage flue gas cooling device of the present invention, manholes are provided on the tower wall between the spray ports of the spray assemblies in the spray chambers of each stage and the packing assemblies, thereby reserving the same operating space between the spray ports of the spray assemblies in the spray chambers of each stage and the packing assemblies.
[0022] Optionally, the smoke inlet is square, the smoke outlet is circular, and the ratio between the cross-sectional area of the smoke inlet and the cross-sectional area of the smoke outlet is (2.5-3):2.
[0023] In the multi-stage flue gas cooling device of the present invention, the flue gas inlet of the tower body is connected to the flue gas exhaust pipe of the power plant boiler, and the flue gas exhaust pipe is square, so that a booster fan can be arranged in the flue gas exhaust pipe, thereby the flue gas inlet of the tower body is set to be square, so as to be connected to the flue gas exhaust pipe. In addition, since the flue gas inlet is square, the flue gas flow resistance is large, and the flue gas outlet is round, the flue gas flow resistance is small, so the cross-sectional area of the flue gas inlet is larger than the cross-sectional area of the flue gas outlet, so as to ensure that a unit amount of flue gas can reasonably and smoothly enter and exit the tower body.
[0024] Optionally, the liquid collecting component has a plurality of air risers, and the ratio between the sum of the cross-sectional areas of the plurality of air risers of any of the liquid collecting components and the cross-sectional area of the smoke inlet is (15-16):1.
[0025] The multi-stage flue gas cooling device of the present invention ensures that the ratio between the sum of the cross-sectional areas of the multiple air risers of the liquid collecting assembly and the cross-sectional area of the flue gas inlet is within a set range, thereby ensuring that the flow rate and pressure of the flue gas in the tower are maintained within the set range, thereby improving safety.
[0026] Optionally, the spray assembly has a liquid distribution trough, the liquid collecting assembly has a liquid collecting trough, an overflow pipe is provided in the tower body, one end of the overflow pipe is connected to the liquid collecting trough of the liquid collecting assembly in the three-stage spray chamber and is located below the air riser of the liquid collecting assembly in the three-stage spray chamber, and the other end of the overflow pipe is connected to the liquid distribution trough of the spray assembly in the secondary spray chamber.
[0027] In the multi-stage flue gas cooling device of the present invention, after the moisture in the flue gas is condensed, it falls into the liquid collecting tank of the liquid collecting component in the three-stage spray chamber together with the coolant sprayed by the spray component in the three-stage spray chamber. As time goes by, the liquid level of the liquid collecting tank of the liquid collecting component in the three-stage spray chamber rises to the overflow pipe, so that the coolant in the liquid collecting tank of the liquid collecting component in the three-stage spray chamber overflows to the liquid distribution tank of the spray component in the two-stage spray chamber. On the one hand, the coolant can be replenished to the spray component in the two-stage spray chamber, and on the other hand, the cold energy is used to cool the flue gas in the two-stage spray chamber to avoid energy waste.
[0028] Optionally, a pulse suspension component is provided in the first-level spray chamber and is located at the bottom of the first-level spray chamber to disturb the siltation at the bottom of the first-level spray chamber. A defogger component is provided in the fourth-level spray chamber and is located downstream of the spray component in the fourth-level spray chamber in the flow direction of the flue gas to ensure that the amount of droplets carried by the flue gas passing through the flue gas outlet does not exceed a preset threshold.
[0029] The multi-stage flue gas cooling device of the present invention has an empty tower spray in the first-stage spray chamber. The coolant sprayed by the spray component in the first-stage spray chamber carries a large amount of dust and falls to the bottom of the first-stage spray chamber. The coolant at the bottom of the first-stage spray chamber is disturbed by the pulse suspension component so that the captured dust circulates with the circulating coolant, thereby avoiding the dust from being deposited at the bottom of the first-stage spray chamber, causing the problem of difficulty in cleaning. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 Schematic diagram of a multi-stage flue gas cooling device according to an embodiment of the present invention.
[0031] Reference numerals:
[0032] Tower body 1.
[0033] The first-level spray chamber 101, the second-level spray chamber 102, the third-level spray chamber 103, the fourth-level spray chamber 104, the smoke inlet 105, the smoke outlet 106,
[0034] Secondary liquid collecting assembly 11, tertiary liquid collecting assembly 12, quaternary liquid collecting assembly 13,
[0035] The first-level spray assembly 21, the second-level spray assembly 22, the third-level spray assembly 23, the fourth-level spray assembly 24,
[0036] Overflow pipe 31,
[0037] Secondary packing assembly 41, tertiary packing assembly 42, quaternary packing assembly 43,
[0038] Pulse suspension component 51,
[0039] Demisting assembly 61. DETAILED DESCRIPTION
[0040] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.
[0041] The multi-stage flue gas cooling device according to an embodiment of the present invention will be described below with reference to the accompanying drawings.
[0042] like Figure 1 As shown, the flue gas multi-stage cooling device according to the embodiment of the present invention comprises a tower body 1 , wherein the tower body 1 has a chamber, and the tower body 1 is provided with a flue gas inlet 105 and a flue gas outlet 106 .
[0043] The chamber of the tower body 1 includes multi-stage spray chambers arranged at intervals, and the smoke entering the chamber through the smoke inlet 105 can pass through the multi-stage spray chambers in sequence. A spray assembly is provided in the spray chamber, and the spray assembly is used to spray coolant to cool the smoke in the spray chamber. The multi-stage spray chamber includes a first-stage spray chamber 101 located at the upstreammost in the direction of smoke flow and the remaining spray chambers except the first-stage spray chamber 101, and the remaining spray chambers are provided with liquid collecting assemblies and filler assemblies. The liquid collecting assembly is used to prevent the spray liquid in the remaining spray chambers from entering the first-stage spray chamber 101, and the filler assembly is located downstream of the liquid collecting assembly in the direction of smoke flow. The smoke is reduced to low-temperature smoke in the sub-zero temperature zone through the multi-stage spray chamber and discharged from the chamber through the smoke outlet 106.
[0044] Optionally, the spray assembly in the first-level spray chamber 101 is composed of a support beam, a main pipe, multiple branch pipes and multiple DN50 nozzles. The support beam is erected in the first-level spray chamber 101, and the multiple branch pipes are connected to the main pipe and fixed on the support beam. The multiple DN50 nozzles are distributed on the multiple branch pipes at intervals.
[0045] The spray components in the remaining spray chambers are trough-type liquid distributors, which have a distribution pipe, a liquid distribution trough and a shower trough. A number of evenly distributed distribution holes are provided at the bottom of the distribution pipe. The liquid distribution trough is arranged below the distribution pipe and corresponds to the distribution holes up and down. A number of evenly distributed distribution holes are provided at the bottom of the liquid distribution trough. The shower trough is arranged below the liquid distribution trough and corresponds to the distribution holes up and down. A number of evenly distributed shower holes are provided at the bottom of the shower trough.
[0046] The liquid collecting assembly is a trough-plate type liquid collector, which includes a liquid collecting tray and a plurality of air lifting caps arranged on the liquid collecting tray. The liquid collecting tray has a liquid collecting trough for collecting liquid, and the air lifting caps are used to allow smoke to pass through and prevent liquid from passing through. The packing assembly includes a grid-type support plate and a packing, and the packing is arranged on the support plate.
[0047] It can be understood that the first-stage spray chamber 101 is an empty tower spray (without a packing assembly), and the coolant sprayed by the spray assembly in the first-stage spray chamber 101 falls to the bottom of the first-stage spray chamber 101, that is, the bottom of the tower body 1. The coolant sprayed by the spray assembly in the remaining spray chambers falls to the liquid collecting assembly in the remaining spray chambers for collection.
[0048] The tower body 1 is also provided with a coolant inlet and a coolant outlet corresponding to each level of the spray chamber. The coolant inlet is connected to the main pipe of the spray assembly. The coolant outlet of the first-level spray chamber 101 is used to discharge the coolant at the bottom of the tower body 1, and the coolant outlets of the remaining levels of the spray chamber are connected to the liquid collecting tank of the liquid collecting tank to discharge the coolant in the liquid collecting tank.
[0049] Therefore, in the multi-stage flue gas cooling device of the embodiment of the present invention, the flue gas passes through the multi-stage spray chamber in sequence, and the coolant sprayed by the spray assembly arranged in each stage of the spray chamber is used to cool the flue gas in a step-by-step manner, and the temperature of the flue gas is gradually reduced to the sub-zero temperature zone, which solves the problem that it is difficult to cool the flue gas to a lower temperature target by direct cooling in one step. The first-stage spray chamber 101 and the remaining spray chambers are separated by the liquid collecting assembly, and under the premise of ensuring the stable flow of the flue gas, the coolant sprayed by the spray assembly in the spray chambers of different stages is prevented from interfering with each other, thereby ensuring a stable and controllable cooling effect.
[0050] In addition, the first-stage spray chamber 101 is an empty tower spray cooling, and the flue gas is in direct contact with the coolant, which reduces the flue gas temperature and washes away the dust in the flue gas, and the dust concentration in the washed flue gas is greatly reduced. Compared with the method of setting packing components in each level of spray chamber, the first-stage spray chamber 101 does not set packing components, which can effectively reduce the problem of dust blocking the packing of the tower body 1.
[0051] In some embodiments, Figure 1As shown, the multi-stage spray chamber is arranged vertically, and there are multiple remaining stage spray chambers, including a secondary spray chamber 102, a tertiary spray chamber 103 and a quaternary spray chamber 104 arranged in sequence in the flow direction of the smoke.
[0052] Each of the secondary spray chamber 102, the tertiary spray chamber 103 and the quaternary spray chamber 104 is provided with a liquid collecting assembly and a filler assembly, and in each of the remaining spray chambers, the filler assembly is located downstream of the liquid collecting assembly in the flow direction of the flue gas, the flue gas inlet 105 is connected to the primary spray chamber 101, and the flue gas outlet 106 is connected to the quaternary spray chamber 104.
[0053] For the convenience of description, the spray component in the first-level spray chamber 101 is defined as a first-level spray component 21, the spray component, liquid collecting component and filler component in the second-level spray chamber 102 are defined as a second-level spray component 22, a second-level liquid collecting component 11 and a second-level filler component 41 respectively, the spray component, liquid collecting component and filler component in the third-level spray chamber 103 are defined as a third-level spray component 23, a third-level liquid collecting component 12 and a third-level filler component 42 respectively, and the spray component, liquid collecting component and filler component in the fourth-level spray chamber 104 are defined as a fourth-level spray component 24, a fourth-level liquid collecting component 13 and a fourth-level filler component 43 respectively.
[0054] The multi-stage flue gas cooling device of the embodiment of the present invention divides the chamber of the tower body 1 into a primary spray chamber 101, a secondary spray chamber 102, a tertiary spray chamber 103 and a quaternary spray chamber 104. The temperature of the flue gas entering the primary spray chamber 101 through the flue gas inlet 105 is 80°C to 90°C, and is cooled to 50°C to 60°C in the primary spray chamber 101, to 20°C to 30°C in the secondary spray chamber 102, to 2°C to 5°C in the tertiary spray chamber 103, and to -20°C to -5°C in the quaternary spray chamber 104, thereby achieving uniform step-by-step cooling of the flue gas and improving the cooling efficiency of the flue gas.
[0055] In addition, the pre-cooling temperature of the flue gas in the first-stage spray chamber 101 is higher than the room temperature, and there is no need to set up a packing assembly. The pre-cooling temperature of the flue gas in the second-stage spray chamber 102, the third-stage spray chamber 103, and the fourth-stage spray chamber 104 is below the room temperature. By setting up a packing assembly to slow down the flow speed of the flue gas, the contact time between the flue gas and the coolant is increased, so that the flue gas and the coolant can fully exchange heat. In this way, while ensuring the cooling effect, the occupied space of the first-stage spray chamber 101 is reduced, thereby reducing the manufacturing cost.
[0056] In addition, the spray components in the first-level spray chamber 101, the second-level spray chamber 102 and the third-level spray chamber 103 are spray-cooled by circulating cooling water, and the spray components in the fourth-level spray chamber 104 are spray-cooled by circulating coolant (calcium chloride solution). The use category of the coolant is reasonably designed to further reduce the flue gas cooling cost.
[0057] In some embodiments, the ratio of the height of the primary spray chamber 101 , the height of the secondary spray chamber 102 , the height of the tertiary spray chamber 103 and the height of the quaternary spray chamber 104 is (2.6-2.8):1:1:(2.7-3).
[0058] In the flue gas multi-stage cooling device of the embodiment of the present invention, since the flue gas inlet 105 and the flue gas outlet 106 are respectively connected to the first-level spray chamber 101 and the fourth-level spray chamber 104, the height of the first-level spray chamber 101 and the fourth-level spray chamber 104 needs to be set higher than the height of the second-level spray chamber 102 and the third-level spray chamber 103 to ensure that the flue gas has a buffer height when entering and exiting the tower body 1, thereby improving the uniformity of the flue gas flow after the smoke enters and exits the tower.
[0059] In addition, a pulse suspension component 51 is provided in the primary spray chamber 101 at the bottom of the primary spray chamber 101 to disturb the siltation at the bottom of the primary spray chamber 101. It is understandable that the primary spray chamber 101 is an empty tower spray, and the coolant sprayed by the spray component in the primary spray chamber 101 carries a large amount of dust and falls to the bottom of the primary spray chamber 101. The coolant at the bottom of the primary spray chamber 101 is disturbed by the pulse suspension component 51, so that the captured dust circulates with the circulating coolant, thereby avoiding the dust from being deposited at the bottom of the primary spray chamber 101, which causes the problem of being difficult to clean.
[0060] A demisting assembly 61 is provided in the four-stage spray chamber 104 and is located downstream of the spray assembly in the four-stage spray chamber 104 in the flow direction of the smoke, so as to ensure that the amount of droplets carried by the smoke passing through the smoke outlet 106 does not exceed a preset threshold.
[0061] Optionally, the pulse suspension assembly 51 is composed of a plurality of pipelines and nozzles arranged on the pipelines, and the sprayed water flow is used to disturb the siltation at the bottom of the first-stage spray chamber 101. The demisting assembly 61 includes a demisting device and a support beam for erecting the demisting device, and the demisting device is a wire mesh demisting device, a baffle demisting device or any other special high-efficiency demisting device. Therefore, it is also necessary to reserve assembly space for the pulse suspension assembly 51 and the demisting assembly 61 in the first-stage spray chamber 101 and the fourth-stage spray chamber 104.
[0062] In some embodiments, Figure 1 As shown, the vertical distance between the spray port of the first-stage spray assembly 21 (the outlet of the above-mentioned DN50 nozzle) and the smoke inlet 105 is a 1 The vertical distance between the spray port of the secondary spray assembly 22 (the lower port of the spray hole of the above-mentioned spray tank) and the air riser of the secondary liquid collecting assembly 11 is a 2 The vertical distance between the spray port of the third-stage spray assembly 23 and the air riser of the third-stage liquid collecting assembly 12 is a 3The vertical distance between the spray port of the fourth-stage spray assembly 24 and the air riser of the fourth-stage liquid collecting assembly 13 is a 4 , and satisfy the following relationship:
[0063] |a 3 -a 2 |=|a 4 -a 3 |, and
[0064] |a 1 -a 2 |=(3~4)×|a 3 -a 2 |.
[0065] In the multi-stage flue gas cooling device of the present invention, the pre-cooling temperature of the flue gas in the secondary spray chamber 102, the tertiary spray chamber 103 and the quaternary spray chamber 104 is gradually reduced, so that the spray cooling height in the secondary spray chamber 102, the tertiary spray chamber 103 and the quaternary spray chamber 104 is gradually increased and in an arithmetic progression, thereby ensuring the cooling effect of the flue gas. In addition, the spray cooling height in the primary spray chamber 101 is much greater than the spray cooling height of the secondary spray chamber 102, so as to ensure that the dust concentration in the flue gas is fully reduced in the primary spray chamber 101.
[0066] In some embodiments, the ratio between the packing height of the secondary packing assembly 41 , the packing height of the tertiary packing assembly 42 , and the packing height of the quaternary packing assembly 43 is 2:1:1.
[0067] It is understandable that, due to the high temperature of the flue gas entering the tower, the circulating cooling water sprayed by the spray assembly in the first-level spray chamber 101 will be carried into the second-level spray chamber 102 by the flue gas due to evaporation loss, thereby increasing the packing height of the packing assembly in the second-level spray chamber 102 relative to the packing height of the packing assembly in the third-level spray chamber 103 and the fourth-level spray chamber 104, so that the moisture in the flue gas is condensed in large quantities in the second-level spray chamber 102, which plays a dehumidifying role and prevents the flue gas from carrying a large amount of moisture into the spray chamber with a lower cooling temperature, affecting the cooling effect. The packing height of the packing assembly in the third-level spray chamber 103 and the fourth-level spray chamber 104 can be a normal height that meets the cooling effect, avoiding the increase of unnecessary packing height, which leads to increased costs.
[0068] Furthermore, the distance between the secondary filling assembly 41 and the spray port of the secondary spray assembly 22, the distance between the tertiary filling assembly 42 and the spray port of the tertiary spray assembly 23, and the distance between the quaternary filling assembly 43 and the spray port of the quaternary spray assembly 24 are all the same.
[0069] In actual engineering applications, multiple manholes are provided on the tower body 1 to facilitate the replacement and maintenance of the tower internals by the staff. In the flue gas multi-stage cooling device of the embodiment of the present invention, manholes are provided on the tower wall between the spray ports of the spray assemblies in the spray chambers of each stage and the packing assemblies, thereby reserving the same operating space between the spray ports of the spray assemblies in the spray chambers of each stage and the packing assemblies.
[0070] In some embodiments, the smoke inlet 105 is square, the smoke outlet 106 is circular, and the ratio between the cross-sectional area of the smoke inlet 105 and the cross-sectional area of the smoke outlet 106 is (2.5-3):2.
[0071] The flue gas inlet 105 of the tower body 1 is connected to the flue gas exhaust pipe of the power plant boiler. The flue gas exhaust pipe is square in shape so that a booster fan can be arranged in the flue gas exhaust pipe. Therefore, the flue gas inlet 105 of the tower body 1 is set to be square in shape so as to be connected to the flue gas exhaust pipe. In addition, since the flue gas inlet 105 is square in shape, the flue gas flow resistance is large, and the flue gas outlet 106 is round in shape, the flue gas flow resistance is small, so the cross-sectional area of the flue gas inlet 105 is larger than the cross-sectional area of the flue gas outlet 106, so as to ensure that a unit amount of flue gas can reasonably and smoothly enter and exit the tower body 1.
[0072] In some embodiments, the ratio between the sum of the cross-sectional areas of the multiple air risers of any liquid collection component and the cross-sectional area of the smoke inlet 105 is (15-16): 1. The ratio between the sum of the cross-sectional areas of the multiple air risers of the liquid collection component and the cross-sectional area of the smoke inlet 105 is ensured to be within a set range, thereby ensuring that the flow rate and pressure of the smoke in the tower are maintained within the set range, thereby improving safety.
[0073] In some embodiments, Figure 1 As shown, an overflow pipe 31 is provided in the tower body 1, one end of the overflow pipe 31 is connected to the liquid collecting tank of the liquid collecting assembly in the tertiary spray chamber 103 and is located below the air riser of the liquid collecting assembly in the tertiary spray chamber 103, and the other end of the overflow pipe 31 is connected to the liquid distribution tank of the spray assembly in the secondary spray chamber 102.
[0074] It can be understood that after the moisture in the flue gas condenses, it falls into the liquid collecting tank of the tertiary liquid collecting component 12 along with the coolant sprayed by the tertiary spray assembly 23. As time goes by, the liquid level of the liquid collecting tank of the tertiary liquid collecting component 12 rises to the overflow pipe 31, so that the coolant in the liquid collecting tank of the tertiary liquid collecting component 12 overflows to the liquid distribution tank of the secondary spray assembly 22. On the one hand, it can replenish the coolant to the secondary spray assembly 22, and on the other hand, the cold energy is used to cool the flue gas in the secondary spray chamber 102 to avoid energy waste.
[0075] In summary, the 80℃~90℃ flue gas that has been cooled and dust-removed enters the chamber of the tower body 1 through the flue gas inlet 105. In the first-level spray chamber 101, the coolant sprayed by the first-level spray component 21 cools the flue gas to 50℃~60℃, and at the same time removes most of the dust, HCL, HF and other pollutants in the flue gas and discharges them out of the tower with the coolant.
[0076] The flue gas rises through the multiple air lift caps of the secondary liquid collecting assembly 11 and enters the secondary spray chamber 102 , and is fully contacted with the coolant sprayed from the secondary spray assembly 22 in the regular packing of the secondary packing assembly 41 to cool the flue gas to 20°C to 30°C. The small amount of HCL and HF remaining in the flue gas is absorbed by the coolant, and the coolant falls into the liquid collecting tank of the secondary liquid collecting assembly 11 .
[0077] Similarly, the smoke rises and enters the third-level spray chamber 103, where it is cooled to 2°C to 5°C. The smoke rises and enters the fourth-level spray chamber 104, where it is cooled to -20°C to -5°C.
[0078] The inventors have found through research that the lower the flue gas temperature, the more beneficial it is for adsorption purification. However, if the flue gas temperature is too low, the equipment structure will be complicated and the energy consumption will increase. For example, the spray tower, adsorption tower and pipeline will be required to be equipped with an insulation layer, and the sealing requirements will be high, which will increase the cost. In addition, too low temperature conditions will easily lead to condensation water in the adsorption tower, causing the adsorbent to stick and clog, affecting adsorption. Therefore, it is beneficial to cool the flue gas temperature to -20℃~-5℃.
[0079] The flue gas cooled to the sub-zero temperature zone passes through the demister assembly 61, and the droplets in the flue gas are removed by the demister, so that the droplet content in the flue gas is ≤50 mg / Nm3, and enters the subsequent low-temperature adsorption device through the flue gas outlet 106.
[0080] Therefore, the flue gas multi-stage cooling device of the embodiment of the present invention first cools the flue gas through the three-stage spray chamber 103 stepwise to cool the temperature to about 5°C, and removes HCL, HF and part of SO 3 、NO 2 and Hg 2+ The pollutants such as SO2 are dissolved in the coolant and removed, and then cooled to -20℃~-10℃ through the four-stage spray chamber 104, so that the cooled flue gas enters the subsequent low-temperature adsorption process, which is convenient for the subsequent low-temperature adsorption process. 2 And the remaining SO 3 、NO 2 , Hg 2+ It can directly adsorb and remove pollutants such as VOCs. Although NO in flue gas cannot be directly adsorbed and removed, it can be adsorbed and removed by O 2 Under the action of low temperature and adsorbent, NO and O in flue gas are removed through oxidation adsorption mechanism.2 At low temperatures, it accumulates on the adsorbent surface to form a local high concentration, which is then rapidly oxidized to NO. 2 , and then adsorbed on the surface of the adsorbent, achieving near-zero emissions of pollutants through the adsorption process.
[0081] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0082] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0083] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0084] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0085] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0086] Although the above embodiments have been shown and described, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations on the present invention. Changes, modifications, substitutions and variations of the above embodiments by those of ordinary skill in the art are all within the scope of protection of the present invention.
Claims
1. A multi-stage flue gas cooling device, characterized in that: It includes a tower body, which has a chamber. The tower body is provided with a smoke inlet and a smoke outlet. The chamber includes multiple spray chambers arranged at intervals. The smoke entering the chamber through the smoke inlet can pass through the multiple spray chambers in sequence. The spray chamber is provided with a spray assembly. The spray assembly is used to spray coolant to cool the smoke in the spray chamber. The multiple spray chambers include a first-stage spray chamber located at the upstreammost in the smoke flow direction and the remaining spray chambers except the first-stage spray chamber. The remaining spray chambers are provided with liquid collecting assemblies and filler assemblies. The liquid collecting assembly is used to prevent the spray liquid in the remaining spray chambers from entering the first-stage spray chamber. The filler assembly is located downstream of the liquid collecting assembly in the smoke flow direction. The smoke is reduced to low-temperature smoke in the sub-zero temperature zone through the multiple spray chambers and is discharged from the chamber through the smoke outlet.
2. The multi-stage flue gas cooling device according to claim 1, characterized in that: The multiple-stage spray chambers are arranged vertically, and the remaining-stage spray chambers are multiple and include a secondary spray chamber, a tertiary spray chamber and a quaternary spray chamber arranged in sequence in the flow direction of the smoke. Each of the secondary spray chamber, the tertiary spray chamber and the quaternary spray chamber is provided with the liquid collecting assembly and the filler assembly, and in each of the remaining-stage spray chambers, the filler assembly is located downstream of the liquid collecting assembly in the flow direction of the smoke, the smoke inlet is connected to the primary spray chamber, and the smoke outlet is connected to the quaternary spray chamber.
3. The multi-stage flue gas cooling device according to claim 2, characterized in that: The ratio of the height of the first-level spray chamber, the height of the second-level spray chamber, the height of the third-level spray chamber and the height of the fourth-level spray chamber is (2.6-2.8):1:1:(2.7-3).
4. The multi-stage flue gas cooling device according to claim 2, characterized in that: The spray assembly has a spray port for spraying coolant, the liquid collecting assembly has an air riser for flue gas flow, the vertical distance between the spray port of the spray assembly in the first-level spray chamber and the flue gas inlet is a1, the vertical distance between the spray port of the spray assembly in the second-level spray chamber and the air riser of the liquid collecting assembly in the second-level spray chamber is a2, the vertical distance between the spray port of the spray assembly in the third-level spray chamber and the air riser of the liquid collecting assembly in the third-level spray chamber is a3, the vertical distance between the spray port of the spray assembly in the fourth-level spray chamber and the air riser of the liquid collecting assembly in the fourth-level spray chamber is a4, and the following relationship is satisfied: |a3-a2|=|a4-a3|, and |a1-a2|=(3~4)×|a3-a2|.
5. The multi-stage flue gas cooling device according to claim 4, characterized in that: The ratio of the packing height of the packing assembly in the secondary spray chamber, the packing height of the packing assembly in the tertiary spray chamber, and the packing height of the packing assembly in the quaternary spray chamber is 2:1:
1.
6. The multi-stage flue gas cooling device according to claim 5, characterized in that: The distance between the filling assembly in the secondary spray chamber and the spray port of the spray assembly in the secondary spray chamber, the distance between the filling assembly in the tertiary spray chamber and the spray port of the spray assembly in the tertiary spray chamber, and the distance between the filling assembly in the quaternary spray chamber and the spray port of the spray assembly in the quaternary spray chamber are all the same.
7. The multi-stage flue gas cooling device according to claim 4, characterized in that: The smoke inlet is square, the smoke outlet is circular, and the ratio between the cross-sectional area of the smoke inlet and the cross-sectional area of the smoke outlet is (2.5-3):
2.
8. The multi-stage flue gas cooling device according to claim 7, characterized in that: The liquid collecting component has a plurality of air risers, and the ratio between the sum of the cross-sectional areas of the plurality of air risers of any of the liquid collecting components and the cross-sectional area of the smoke inlet is (15-16):
1.
9. The multi-stage flue gas cooling device according to claim 4, characterized in that: The spray assembly has a liquid distribution trough, the liquid collecting assembly has a liquid collecting trough, an overflow pipe is provided in the tower body, one end of the overflow pipe is connected to the liquid collecting trough of the liquid collecting assembly in the three-stage spray chamber and is located below the air riser of the liquid collecting assembly in the three-stage spray chamber, and the other end of the overflow pipe is connected to the liquid distribution trough of the spray assembly in the two-stage spray chamber.
10. The multi-stage flue gas cooling device according to any one of claims 2 to 9, characterized in that: The first-stage spray chamber is provided with a pulse suspension component located at the bottom of the first-stage spray chamber to disturb the siltation at the bottom of the first-stage spray chamber. The fourth-stage spray chamber is provided with a demisting component located downstream of the spray component in the fourth-stage spray chamber in the flow direction of the smoke to ensure that the droplet carrying amount of the smoke passing through the smoke outlet does not exceed a preset threshold.