Engineering contract management method, system, equipment and medium

Through the key information and deep learning technology in the related engineering contract, real-time data analysis and intelligent identification in the construction stage of the construction project are realized, the problem of low data integration and management efficiency in the existing technology is solved, and the real-time performance of engineering management is improved. Level of informatization.

CN118967005APending Publication Date: 2024-11-15CHINA THREE GORGES CORPORATION

Patent Information

Application Number
CN202410927893.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing construction engineering management software has shortcomings in real-time and informatization, and it is impossible to effectively manage large-scale engineering projects, especially during the construction stage, which is difficult to achieve real-time integration and efficient analysis of data.

Method used

Using an engineering contract management method, by obtaining the correlation between the estimated budget, cost occurrence, progress project volume, unit engineering and fund allocation in the engineering contract, and combining deep learning technology to intelligently identify and analyze the construction progress to form an electronic data report , realize traceable evaluation and management of contracts.

Benefits of technology

A strict comprehensive control system has been established to realize information sharing and appreciation through computer systems, provide managers with high-value analysis and decision-making information, and improve the real-time and informatization of engineering management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118967005A_ABST
    Figure CN118967005A_ABST
Patent Text Reader

Abstract

The invention relates to an engineering contract management method, system and device, and a medium. The method comprises the following steps: obtaining an engineering contract; project acceptance and assessment are executed according to nodes of the contract, and delivery assessment and quality acceptance are executed according to the contract by strictly taking budget as a control reference; determining whether to correct the project contract or not according to project stage assessment, and if yes, obtaining the project contract again; if not, continuing to execute the sub-project in the next stage, and completing acceptance; contract execution and assessment states are obtained, and traceable contract execution evaluation is established; and contract payment is executed when the contract is accepted and accepted. According to the invention, the contract is used as a link, the cost occurrence, the progress engineering amount, the unit engineering and visa, the investment and the fund transfer in the contract implementation process are organically connected, and a strict comprehensive control system which takes the budget as general control and takes contract delivery and quality acceptance as process control is formed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of engineering management, and in particular to an engineering contract management method, system, equipment and medium. Background Art

[0002] In large-scale construction projects, the multi-project management information systems currently used are mostly special management information systems, which are not intuitive enough. Most of the research and application of BIM technology focuses on BIM simulation and coordination communication before project construction, while there are relatively few explorations on the application of BIM technology in project construction phase management and auxiliary communication and coordination. Engineering project management software can use modern large-scale database technology, with advantages such as complete data, clear organization, and traceability; but it also has disadvantages such as low data integration, low data integration and analysis capabilities, and low relevance between data.

[0003] In the entire construction engineering field, there is a lack of effective software and systems for the whole process management of construction engineering. The existing construction engineering management software has low real-time performance: it lacks the ability to obtain information from the Internet in real time and cannot accurately track price information in the construction industry. Its information level is low: most of the management still relies on paper documents and manual management. In process management, manual management factors are heavy, and when the amount of information is large, it is difficult to efficiently complete the management of the entire process.

[0004] Therefore, it is necessary to provide a new engineering contract management method to solve the above technical problems. Summary of the invention

[0005] The purpose of the present disclosure is to provide a construction contract management method, system, device and medium in order to solve the above problems.

[0006] The present invention achieves the above-mentioned purpose through the following technical solutions:

[0007] A construction contract management method comprises the following steps:

[0008] Obtain engineering contracts, including project sub-contracts, with the engineering contract as the main body. In the engineering contract and project sub-contracts, associate the engineering budget, cost incurred during the contract implementation process, progress engineering quantity, unit engineering and visa, investment and fund allocation;

[0009] Carry out project acceptance and assessment according to the contract nodes, strictly use the budget estimate as the control benchmark, and perform delivery assessment and quality acceptance according to the contract;

[0010] Determine whether to revise the engineering contract based on the engineering phase assessment. If yes, re-acquire the engineering contract; if no, continue to execute the next phase of the sub-project and complete the acceptance;

[0011] Obtain contract execution and assessment status and establish traceable contract execution evaluation;

[0012] The contract is completed and passed the acceptance, and the contract payment is executed.

[0013] As a further optimization plan of the present disclosure, the project acceptance and assessment are carried out according to the nodes of the contract, and the delivery assessment and quality acceptance are carried out strictly based on the budget estimate and the contract, including:

[0014] Break down the project implementation plan into monthly and / or daily construction plans according to actual needs; implement follow-up assessment of the completion of the entire design plan according to the actual delivery results of the construction unit, including defining the alarm days for each stage, defining the project estimate / budget details, and setting the project demand date and image progress;

[0015] Collect real-time data on construction plan, construction process and construction progress to form electronic data reports; the construction plan includes: construction management organizational structure, construction cycle, equipment, materials, personnel, acceptance, project leader, quality supervisor, among which the construction management organizational structure includes construction management, technical management, quality management and personnel management departments, which respectively manage the construction progress, technology, quality and personnel; the construction cycle includes the construction cycle of each project of the construction project; the equipment, materials and personnel are attached with detailed lists; the construction process includes material preparation, construction process, construction supervision and quality acceptance; the construction progress includes planned progress, actual progress, advance or delay time and reasons, and daily progress, weekly progress and monthly progress.

[0016] As a further optimization scheme of the present disclosure, real-time data of construction plan, construction process and construction progress are collected to form an electronic data report, which specifically includes:

[0017] A mobile communication device is configured at the construction site, and the mobile communication device is connected to the central server of the construction management system through a communication network; the mobile communication device is installed with application software for receiving instructions from the construction management system to execute daily, weekly and monthly engineering plans and report workload according to actual construction progress;

[0018] Enable the person in charge of each construction site to use the application software of mobile communication devices to report the daily, weekly and monthly completed workload at the construction site. The workload is reported by video, construction photos and milestone pictures to report the progress of the construction site work;

[0019] The central server of the construction management system receives video footage, construction photos and milestone images, compares the above-mentioned images and videos with the project volume and project milestone marks set in the project plan, determines the completion status of the daily workload on the construction site; and automatically generates a daily workload report based on the actual completion volume;

[0020] Weekly and monthly planned tasks are pushed to the application through the central server system of the construction management system. By comparing the construction site video, construction photos and milestone pictures with the project volume and project milestone signs set in the project plan, it is determined whether the construction site has completed the weekly and monthly workload; and weekly and monthly workload reports are automatically generated based on the actual completion volume.

[0021] As a further optimization solution of the present disclosure, obtaining the contract execution and assessment status and establishing a traceable contract execution evaluation includes:

[0022] Obtain contract execution and assessment, the assessment content includes the difference between the construction time and the designed construction time, the difference between the consumption of manpower, machine and materials and the contract provisions, and the difference between the budget and the consumption of funds used; determine the evaluation criteria for the project based on whether the difference is within the prescribed range or whether the overspending is within the limited range.

[0023] As a further optimization solution of the present disclosure, project acceptance and assessment are performed through deep learning, specifically including:

[0024] By acquiring image data of each stage of construction from a database, the image data is obtained from a miniature model of the project, or image data of existing projects with the same structure as the building required for the contract construction obtained through the Internet; and the image data is processed to the same scale to generate a database corresponding to the scale of the actual contract project;

[0025] Extracting a predetermined amount of labeled data from the database, including image data, wherein the label is used to identify the actual construction status corresponding to the image data; performing feature extraction on the data to extract features that can reflect its construction status; selecting a corresponding deep learning model according to the characteristics and objectives of the engineering data specified in the engineering contract; using the prepared data and features, training the selected deep learning model to obtain a minimized loss function, and training the deep learning model to learn the characteristics and laws of the construction status from the data; after the training is completed, adjusting the deep learning model; testing the trained deep learning model to evaluate the performance and effect of the deep learning model;

[0026] Collect image material samples for each stage of construction images, photos and milestone pictures; prepare images and pictures uploaded from the construction site for comparison;

[0027] Classify the construction phase images in the database, and perform calibration on the image materials respectively, and mark each key construction sign in the image with different color boxes or color marks; the key construction sign samples with color boxes or color marks are used as positive samples for algorithm learning; images without key construction signs are negative samples;

[0028] Use a given algorithm to extract the texture features, shape features, and spatial relationship features of the construction image, and perform classification training on the extracted feature information to output a detection model that can identify various key construction signs;

[0029] Based on the calibrated positive and negative samples, autonomous feature learning is performed to optimize the model feature parameters, and deviation correction and calibration are performed according to the detection results. The calibrated materials are retrained to form a highly available analysis model through continuous iteration;

[0030] Through on-site testing, the intelligent identification model of construction workload is verified, the construction progress is intelligently identified, and the completed or delayed project volume is intelligently identified.

[0031] As a further optimization scheme of the present invention, the deep learning model training adopts the improved SSD algorithm for target detection, which predicts the object area on the feature maps of different convolutional layers, outputs discretized multi-scale and multi-ratio default box parallel coordinates, and uses small convolution kernels to predict the border coordinate compensation of a series of candidate boxes and the confidence of each category; and regresses the local feature map border of the multi-scale area at each position on the entire image.

[0032] As a further optimization scheme of the present disclosure, the improved SSD algorithm includes: using multi-scale feature map detection, adding a convolutional feature layer to the end of the truncated basic network, the size of the convolutional feature layer gradually decreases, and the prediction values ​​of multiple scale detections are obtained, and the convolutional model of the detection is different for each convolutional feature layer; the improved SSD algorithm also includes: a convolutional predictor for detection: each added convolutional feature layer or an existing convolutional feature layer of the optional basic network can use a set of convolutional filters to generate a fixed prediction set; the improved SSD algorithm, default box and aspect ratio, associate a set of default bounding boxes with each feature map unit of the top network, the default box performs a convolution operation on the feature map, so that the position of each box instance relative to its corresponding cell is fixed; in each feature mapping unit, predict the offset relative to the default box shape in the cell, and the score of each category of the instance in each box; in feature maps of different resolutions, different default box shapes are used in multiple feature maps.

[0033] A construction contract management system, comprising a business module, wherein the business module comprises:

[0034] The contract entry module is used to obtain engineering contracts, including project sub-contracts. The engineering contract is the main part, and the engineering budget, cost occurrence during contract implementation, progress engineering quantity, unit engineering and visa, investment and fund allocation are associated in the engineering contract and project sub-contracts.

[0035] The acceptance and assessment module is used to perform project acceptance and assessment according to the contract nodes, strictly based on the budget estimate as the control benchmark, and perform delivery assessment and quality acceptance according to the contract;

[0036] The contract amendment module is used to determine whether to amend the contract based on the project phase assessment. If yes, the project contract is re-acquired; if not, the next phase of the sub-project is continued and the acceptance is completed;

[0037] Evaluation module, used to obtain contract execution and assessment status and establish traceable contract execution evaluation;

[0038] The payment module is used to complete the contract acceptance and execute the contract payment.

[0039] An electronic device comprises a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory communicate with each other via the communication bus;

[0040] Memory, for storing computer programs;

[0041] The processor is used to implement the engineering contract management method when executing the program stored in the memory.

[0042] A computer-readable storage medium stores a computer program, wherein the computer program implements a construction contract management method when executed by a processor.

[0043] The beneficial effects of the present disclosure are:

[0044] This disclosure uses the contract as a link to connect the budget estimate, the cost incurred during the contract implementation process, the progress engineering quantity, the unit engineering and visas, the investment and the capital allocation, forming a strict comprehensive control system with the budget estimate as the overall control, contract delivery and quality acceptance as the process control; using the large-scale engineering integrated management system to decompose and supervise the engineering contract; through the computer system to achieve information sharing and information appreciation, and provide managers and decision makers with high-value analysis and decision-making information. BRIEF DESCRIPTION OF THE DRAWINGS

[0045] Figure 1 is a flow chart of the method disclosed herein;

[0046] Figure 2 is a system structure block diagram in an embodiment of the present disclosure;

[0047] Figure 3 It is a block diagram of the device structure in an embodiment of the present disclosure. DETAILED DESCRIPTION

[0048] The present application is further described in detail below in conjunction with the accompanying drawings. It is necessary to point out here that the following specific implementation methods are only used to further illustrate the present application and cannot be understood as limiting the scope of protection of the present application. Technical personnel in this field can make some non-essential improvements and adjustments to the present application based on the above application content.

[0049] like Figure 1 As shown, a construction contract management method comprises the following steps:

[0050] Obtain engineering contracts, including project sub-contracts, with the engineering contract as the main body. In the engineering contract and project sub-contracts, associate the engineering budget, cost incurred during the contract implementation process, progress engineering quantity, unit engineering and visa, investment and fund allocation;

[0051] Carry out project acceptance and assessment according to the contract nodes, strictly use the budget estimate as the control benchmark, and perform delivery assessment and quality acceptance according to the contract;

[0052] Determine whether to revise the contract based on the project phase assessment. If yes, re-acquire the project contract; if not, continue to execute the next phase of the sub-project and complete the acceptance;

[0053] Obtain contract execution and assessment status and establish traceable contract execution evaluation;

[0054] The contract is completed and passed the acceptance, and the contract payment is executed.

[0055] In this embodiment, it specifically includes:

[0056] Step 1: Enter the engineering contract, including project sub-contracts, with the engineering contract as the main body. In the engineering contract and project sub-contracts, the engineering budget, cost incurred during the contract implementation process, progress engineering quantities, unit engineering and visas, investment and fund allocation are linked.

[0057] Contract entry: Contract entry personnel: responsible for basic contract information, quotation classification definition, and quotation information entry. Budget attachment personnel: responsible for attaching budget codes for contract quotation items (BOQ items). Contract approval personnel: after completing the contract information entry, review the entered content, and "approve" the contract after confirming that it is correct. Only after the contract is "approved" can subsequent operations such as contract changes and contract payments be performed; Material and equipment attachment personnel: for contracts that require attachment of material codes, equipment classification codes, and equipment lists, attach materials and equipment after contract entry or contract approval. Budget attachment personnel: if the budget management subsystem is enabled, before the contract is approved, the budget administrator of the finance department needs to attach a budget code to the contract; after the contract is approved, the attached budget code needs to be modified every year.

[0058] In the business module, enter the basic contract information, quotation structure definition, quotation item quantity and price, and complete the "approval" confirmation. The basic contract information entered includes: contract subcontractors, contract bidding currency, definition of quotation structure, quotation quantity and price information, attached materials / equipment, equipment list; during the contract entry process, link the contract with the budget, and set up a list of personnel who approve the entry.

[0059] Step 2: Carry out project acceptance and assessment according to the contract nodes, strictly use the budget estimate as the control benchmark, and perform delivery assessment and quality acceptance according to the contract;

[0060] In order to better manage the design plan and progress, the project implementation plan is broken down into monthly construction plans and even daily construction plans according to actual needs. According to the actual delivery results of the construction unit, the completion of the entire design plan is tracked and evaluated. This includes defining the alarm days for each stage; defining the project estimate / budget details; setting the project demand date and image progress.

[0061] The business module is connected to the design and construction departments of the construction project through the local area network, collects real-time data on the construction plan, construction process, and construction progress, and forms an electronic data report. The construction plan includes: construction management organizational structure, construction cycle, equipment, materials, personnel, acceptance, project leader, quality supervisor, etc. Among them, the construction management organizational structure includes construction management, technical management, quality management, personnel management and other departments, which manage the construction progress, technology, quality, personnel, etc. respectively. The construction cycle includes the construction cycle of each project of the construction project. The equipment, materials, and personnel are attached with a detailed list. The construction process includes material preparation, construction process, construction supervision and quality acceptance, etc. The construction progress includes the planned progress, actual progress, advance or delay time and reasons, and daily progress, weekly progress, and monthly progress.

[0062] The method runs on a large computer in an engineering management system. A business module is established in the computer to execute each step of the management method respectively, and has machine learning and deep learning functions. The business module obtains a large amount of data analysis reports on actual engineering contract management through the network, and establishes judgment thresholds for automatic assessment of project problems and engineering risks through machine learning and deep learning. The management platform automatically issues early warnings for possible risks, and intelligently adjusts and optimizes construction plans and progress, such as adjusting construction cycles, changing construction procedures, standardizing operating procedures, and strengthening supervision and inspection.

[0063] The real-time data of the construction plan, construction process and construction progress are collected to form an electronic data report. It includes the following contents:

[0064] Step 2.1, a mobile communication device is configured at the construction site, and the mobile communication device is connected to the central server of the construction management system through a communication network; the mobile communication device is installed with application software to receive instructions from the construction management system to execute daily, weekly, and monthly engineering plans and report workload according to the actual construction progress;

[0065] Step 2.2, the person in charge of each construction site of the project uses the application software of the mobile communication device to report the daily, weekly and monthly completed workload of the construction site, and the person in charge of each construction site uses video, construction photos and milestone pictures to report the progress of the construction site work;

[0066] Step 2.3, the central server of the construction management system receives the camera video, construction photos and milestone pictures, compares the above-mentioned images and videos with the project quantity and project milestone marks set in the project plan, determines the completion status of the daily workload on the construction site; and automatically generates a daily workload report based on the actual completion volume;

[0067] In step 2.4, the central server system of the construction management system also pushes weekly and monthly planned tasks to the application, and determines whether the construction site has completed the weekly and monthly workload based on the comparison of the construction site video, construction photos and milestone pictures with the project volume and project milestone signs set in the project plan; and automatically generates weekly and monthly workload reports based on the actual completion volume.

[0068] The business management module connects and communicates with the project leaders through the local area network, and the project leaders report the daily, weekly and monthly progress of the project. The collected data is automatically generated into electronic data reports by the business module. The electronic data reports and the daily, weekly and monthly progress reports of the project leaders can be displayed in real time on the terminal of the business module and the mobile client of the management personnel.

[0069] In order to monitor the construction process in real time, it is allowed to install video equipment at the construction site. The business module collects real-time video data of the progress and safety status of the construction project. The video data is loaded into the electronic data report as part of the data collection, so that the progress of the project can be more intuitively understood. The business module integrates and analyzes the collected electronic data to form an electronic data analysis report, which includes the progress of the project, material use, quality supervision, funding status, and the reasons for the project overdue and the existing problems. If the project fails to be completed on schedule or there are quality and safety problems, the abnormalities and reasons in the construction plan, construction process, and construction progress are analyzed and found, such as unqualified materials, non-standard construction, illegal operations, etc.

[0070] The business module automatically assesses the risks and causes of project overdue or existing problems through machine learning data analysis reports. On this basis, the management platform automatically issues early warnings for possible risks and makes intelligent adjustments and optimizations to construction plans and progress, such as adjusting construction cycles, changing construction procedures, standardizing operating procedures, and strengthening supervision and inspection.

[0071] In order to monitor the construction process in real time, it is allowed to install video equipment at the construction site. The business module collects real-time video data of the progress and safety status of the construction project. The video data is converted into data of the project progress and loaded into the electronic data report as part of the data collection, so that the project progress can be understood more intuitively. The business module integrates and analyzes the collected electronic data to form an electronic data analysis report, which includes the project progress, material use, quality supervision, funding status, and the reasons for the project overdue and the existing problems. If the project fails to be completed on schedule or there are quality and safety problems, the abnormalities and reasons in the construction plan, construction process, and construction progress are analyzed and found, such as unqualified materials, non-standard construction, illegal operations, etc.

[0072] The business module automatically assesses the risks and causes of project overdue or existing problems through machine learning data analysis reports. On this basis, the management platform automatically issues early warnings for possible risks and makes intelligent adjustments and optimizations to construction plans and progress, such as adjusting construction cycles, changing construction procedures, standardizing operating procedures, and strengthening supervision and inspection.

[0073] Step 3: Determine whether to amend the contract based on the project phase assessment. If yes, return to step 1. If no, continue to execute the next phase sub-project; and go to step 5;

[0074] Step 4: Enter the contract execution and assessment status, and establish a traceable contract execution evaluation; the engineering contract management method of the present invention first enters the original data required for the project, then extracts, converts, checks data quality and loads the original data, performs data analysis and storage on the loaded related data, and establishes a relational database and a multidimensional database based on the analyzed and stored related data, classifies and integrates the relational database and the multidimensional database according to preset rules, and performs visual conversion on the classified and integrated related data, thereby obtaining various different engineering visualization data. Through real-time collection and online automatic analysis of information data, the front-end and back-end data are linked, the on-site construction situation is clearly presented, and according to the actual situation on site, error correction and dynamic adjustment of the construction process are carried out in a timely manner to ensure that the project progress meets all the requirements of the contract.

[0075] The assessment includes: the difference between the construction time and the designed construction time, the difference between the consumption of manpower, machine and materials and the contract, and the difference between the budget and the consumption of operating funds. The evaluation criteria of the project are determined based on whether the difference is within the specified range or whether the overspending is within the limited range.

[0076] The business module provides an option to modify the project contract under the project acceptance project, and the project acceptance project performs acceptance based on the modified contract.

[0077] The business module reviews the construction tasks and transmits the review results to the material comparison and engineering drawings in the database module.

[0078] Step 5: The contract is completed and accepted, and the contract amount or balance is paid.

[0079] Construction site management based on deep learning also includes the following steps:

[0080] Step S1, deep learning material preparation. Image data of each stage of construction is obtained from the database. These image data can be obtained by photographing a miniature model of the project, or they can be image data of existing projects with the same structure as the building required for the contract construction obtained through the Internet; various image data are processed to the same scale to generate an image database corresponding to the scale of the actual contract project;

[0081] Step S2, extracting a predetermined amount of labeled data from the database of step S1, including image data, wherein the label is used to identify the actual construction status corresponding to the image data; extracting features that can reflect the construction status from each data; selecting an appropriate deep learning model according to the characteristics and objectives of the engineering data specified in the engineering contract; using the prepared data and features, training the selected deep learning model to obtain a minimized loss function, and training the model to learn the characteristics and laws of the construction status from the data; after the training is completed, adjusting the model; testing the trained model to evaluate the performance and effect of the model;

[0082] Step S3, video image sample data collection, collecting image material samples for each stage of construction images, photos and milestone pictures; preparing images and pictures for comparison with those uploaded from the construction site;

[0083] Step S4, manually classify the construction stage images in the database, and perform calibration on the image materials respectively, and mark each key construction mark in the image with different color boxes or color marks; for example: the platform surface or gate slot after construction, spillway;

[0084] The samples of key construction signs with colored boxes or colored marks are used as positive samples for algorithm learning; images without key construction signs are negative samples;

[0085] Step S5, using a given algorithm to extract texture features, shape features, and spatial relationship features of the construction image, and classify and train the extracted feature information to output a detection model that can identify various key construction signs;

[0086] Step S6, autonomous feature learning is performed based on the calibrated positive and negative samples, the model feature parameters are optimized, and deviation correction and calibration are performed according to the detection results. The calibrated materials are retrained to form a highly available analysis model through continuous iteration;

[0087] Step S7, model evaluation, verifies the intelligent identification model of construction workload through field testing, and intelligently identifies the construction progress and completed or delayed engineering workload.

[0088] The sample data collection of the video images of the construction progress needs to ensure the diversity of the materials; the richer the material scenes of each type of construction progress video images, the higher the image quality, and the clearer the construction site pictures, the more conducive to the learning of the algorithm and the higher the recognition accuracy; therefore, if a 3D modeling method is used to establish a construction model, it should be as close as possible to the actual construction drawings.

[0089] The model training in step S6 adopts an improved SSD algorithm for target detection, predicts the object area on the feature maps of different convolutional layers, outputs discretized multi-scale, multi-ratio default box parallel coordinates, and uses a small convolution kernel to predict the frame coordinate compensation of a series of candidate frames and the confidence of each category; and regresses the local feature map frame of the multi-scale region at each position on the entire image.

[0090] The improved SSD algorithm adopts multi-scale feature map detection, adds a convolutional feature layer to the end of the truncated basic network, and gradually reduces the size of the convolutional feature layer to obtain prediction values ​​of multiple scale detections. The convolutional model of the detection is different for each convolutional feature layer; the improved SSD algorithm, the convolutional predictor of the detection: each added convolutional feature layer or the existing convolutional feature layer of the optional basic network can use a set of convolutional filters to generate a fixed prediction set;

[0091] The improved SSD algorithm, default box and aspect ratio: a set of default bounding boxes are associated with each feature map unit of the top network, and the default box performs a convolution operation on the feature map so that the position of each box instance relative to its corresponding cell is fixed; in each feature map unit, the offset relative to the default box shape in the cell is predicted, as well as the per-category score of the instance in each box.

[0092] In feature maps of different resolutions; using different default box shapes in multiple feature maps can effectively discretize the space of possible output box shapes.

[0093] like Figure 2 As shown, an embodiment of the present disclosure provides a construction contract management system, including:

[0094] The contract entry module is used to obtain engineering contracts, including project sub-contracts. The engineering contract is the main part, and the engineering budget, cost occurrence during contract implementation, progress engineering quantity, unit engineering and visa, investment and fund allocation are associated in the engineering contract and project sub-contracts.

[0095] The acceptance and assessment module is used to perform project acceptance and assessment according to the contract nodes, strictly based on the budget estimate as the control benchmark, and perform delivery assessment and quality acceptance according to the contract;

[0096] The contract amendment module is used to determine whether to amend the contract based on the project phase assessment. If yes, the project contract is re-acquired; if not, the next phase of the sub-project is continued and the acceptance is completed;

[0097] Evaluation module, used to obtain contract execution and assessment status and establish traceable contract execution evaluation;

[0098] The payment module is used to complete the contract acceptance and execute the contract payment.

[0099] The implementation process of the functions and effects of each module in the above system is specifically described in the implementation process of the corresponding steps in the above method, which will not be repeated here.

[0100] For the system embodiment, since it basically corresponds to the method embodiment, the relevant parts can refer to the partial description of the method embodiment. The system embodiment described above is only schematic, wherein the modules described as separate components may or may not be physically separated, and the components displayed as modules may or may not be physical modules, that is, they may be located in one place, or they may be distributed on multiple network modules. Some or all of the modules may be selected according to actual needs to achieve the purpose of the disclosed solution. A person of ordinary skill in the art can understand and implement it without paying any creative work.

[0101] In the above-mentioned embodiment, any multiple of all modules can be combined in one module for implementation, or any one of the modules can be split into multiple modules. Alternatively, at least some functions of one or more of these modules can be combined with at least some functions of other modules and implemented in one module. At least one of all modules can be at least partially implemented as a hardware circuit, such as a field programmable gate array (FPGA), a programmable logic array (PLA), a system on a chip, a system on a substrate, a system on a package, an application specific integrated circuit (ASIC), or can be implemented by hardware or firmware such as any other reasonable way of integrating or packaging the circuit, or implemented in any one of the three implementation modes of software, hardware and firmware or in a suitable combination of any of them. Alternatively, at least one of all modules can be at least partially implemented as a computer program module, and when the computer program module is run, the corresponding function can be executed.

[0102] See also Figure 3 , an electronic device provided by an embodiment of the present disclosure includes a processor 1110, a communication interface 1120, a memory 1130 and a communication bus 1140, wherein the processor 1110, the communication interface 1120, and the memory 1130 communicate with each other through the communication bus 1140;

[0103] Memory 1130, for storing computer programs;

[0104] The processor 1110 is used to implement the engineering contract management method as shown below when executing the program stored in the memory 1130.

[0105] The communication bus 1140 may be a Peripheral Component Interconnect (PCI) bus or an Extended Industry Standard Architecture (EISA) bus, etc. The communication bus 1140 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, only one thick line is used in the figure, but it does not mean that there is only one bus or one type of bus.

[0106] The communication interface 1120 is used for communication between the above electronic device and other devices.

[0107] The memory 1130 may include a random access memory (RAM) or a non-volatile memory, such as at least one disk memory. Optionally, the memory 1130 may also be at least one storage device located away from the processor 1110.

[0108] The above-mentioned processor 1110 can be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it can also be a digital signal processor (DSP), an application specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components.

[0109] The embodiment of the present disclosure further provides a computer-readable storage medium. The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the engineering contract management method described above is implemented.

[0110] The computer-readable storage medium may be included in the device / apparatus described in the above embodiment; or it may exist independently without being assembled into the device / apparatus. The above computer-readable storage medium carries one or more programs, and when the above one or more programs are executed, the engineering contract management method according to the embodiment of the present disclosure is implemented.

[0111] According to an embodiment of the present disclosure, a computer-readable storage medium may be a non-volatile computer-readable storage medium, for example, may include but is not limited to: a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination thereof. In the present disclosure, a computer-readable storage medium may be any tangible medium containing or storing a program that may be used by or in conjunction with an instruction execution system, apparatus, or device.

[0112] The above-mentioned embodiments only express several implementation methods of the present disclosure, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present disclosure. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present disclosure, and these all belong to the protection scope of the present disclosure.

Claims

1. A method for engineering contract management, It is characterized in that The following steps are involved: Obtain engineering contracts, including project sub-contracts, with the engineering contract as the main body. In the engineering contract and project sub-contracts, associate the engineering budget, cost incurred during the contract implementation process, progress engineering quantity, unit engineering and visa, investment and fund allocation; Carry out project acceptance and assessment according to the contract nodes, strictly use the budget estimate as the control benchmark, and perform delivery assessment and quality acceptance according to the contract; Determine whether to revise the engineering contract based on the engineering phase assessment. If yes, re-acquire the engineering contract; if no, continue to execute the next phase of the sub-project and complete the acceptance; Obtain contract execution and assessment status and establish traceable contract execution evaluation; The contract is completed and accepted, and the contract payment is executed.

2. A method for project contract management according to claim 1, It is characterized in that Carry out project acceptance and assessment according to the contract nodes, strictly use the budget estimate as the control benchmark, and carry out delivery assessment and quality acceptance according to the contract, including: Break down the project implementation plan into monthly and / or daily construction plans according to actual needs; implement follow-up assessment of the completion of the entire design plan according to the actual delivery results of the construction unit, including defining the alarm days for each stage, defining the project estimate / budget details, and setting the project demand date and image progress; Collect real-time data on construction plan, construction process and construction progress to form electronic data reports; the construction plan includes: construction management organizational structure, construction cycle, equipment, materials, personnel, acceptance, project leader, quality supervisor, among which the construction management organizational structure includes construction management, technical management, quality management and personnel management departments, which respectively manage the construction progress, technology, quality and personnel; the construction cycle includes the construction cycle of each project of the construction project; the equipment, materials and personnel are attached with detailed lists; the construction process includes material preparation, construction process, construction supervision and quality acceptance; the construction progress includes planned progress, actual progress, advance or delay time and reasons, and daily progress, weekly progress and monthly progress.

3. A construction contract management method according to claim 2, It is characterized in that Collect real-time data on construction plans, construction processes, and construction progress to form electronic data reports, including: A mobile communication device is configured at the construction site, and the mobile communication device is connected to the central server of the construction management system through a communication network; the mobile communication device is installed with application software for receiving instructions from the construction management system to execute daily, weekly and monthly engineering plans and report workload according to actual construction progress; Enable the person in charge of each construction site to use the application software of mobile communication devices to report the daily, weekly and monthly completed workload at the construction site. The workload is reported by video, construction photos and milestone pictures to report the progress of the construction site work; The central server of the construction management system receives video footage, construction photos and milestone images, compares the above-mentioned images and videos with the project volume and project milestone marks set in the project plan, determines the completion status of the daily workload on the construction site; and automatically generates a daily workload report based on the actual completion volume; Weekly and monthly planned tasks are pushed to the application through the central server system of the construction management system. By comparing the construction site video, construction photos and milestone pictures with the project volume and project milestone signs set in the project plan, it is determined whether the construction site has completed the weekly and monthly workload; and weekly and monthly workload reports are automatically generated based on the actual completion volume.

4. A method for project contract management according to claim 1, It is characterized in that Obtain contract execution and assessment status and establish traceable contract execution evaluation including: Obtain contract execution and assessment, the assessment content includes the difference between the construction time and the designed construction time, the difference between the consumption of manpower, machine and materials and the contract provisions, and the difference between the budget and the consumption of funds used; determine the evaluation criteria for the project based on whether the difference is within the prescribed range or whether the overspending is within the limited range.

5. A construction contract management method according to claim 1, It is characterized in that Perform project acceptance and assessment through deep learning, including: By acquiring image data of each stage of construction from a database, the image data is obtained from a miniature model of the project, or image data of existing projects with the same structure as the building required for the contract construction obtained through the Internet; and the image data is processed to the same scale to generate a database corresponding to the scale of the actual contract project; Extracting a predetermined amount of labeled data from the database, including image data, wherein the label is used to identify the actual construction status corresponding to the image data; performing feature extraction on the data to extract features that can reflect its construction status; selecting a corresponding deep learning model according to the characteristics and objectives of the engineering data specified in the engineering contract; using the prepared data and features, training the selected deep learning model to obtain a minimized loss function, and training the deep learning model to learn the characteristics and laws of the construction status from the data; after the training is completed, adjusting the deep learning model; testing the trained deep learning model to evaluate the performance and effect of the deep learning model; Collect image material samples for each stage of construction images, photos and milestone pictures; prepare images and pictures uploaded from the construction site for comparison; Classify the construction phase images in the database, and perform calibration on the image materials respectively, and mark each key construction sign in the image with different color boxes or color marks; the key construction sign samples with color boxes or color marks are used as positive samples for algorithm learning; images without key construction signs are negative samples; Use a given algorithm to extract the texture features, shape features, and spatial relationship features of the construction image, and perform classification training on the extracted feature information to output a detection model that can identify various key construction signs; Based on the calibrated positive and negative samples, autonomous feature learning is performed to optimize the model feature parameters, and deviation correction and calibration are performed according to the detection results. The calibrated materials are retrained to form a highly available analysis model through continuous iteration; Through on-site testing, the intelligent identification model of construction workload is verified, the construction progress is intelligently identified, and the completed or delayed project volume is intelligently identified.

6. A construction contract management method according to claim 5, It is characterized in that The deep learning model training uses an improved SSD algorithm for target detection. It predicts the object area on the feature maps of different convolutional layers, outputs discretized multi-scale and multi-ratio default box parallel coordinates, and uses small convolution kernels to predict the border coordinate compensation of a series of candidate boxes and the confidence of each category; the local feature map border of the multi-scale area is regressed at each position on the entire image.

7. A method for project contract management according to claim 6, It is characterized in that The improved SSD algorithm includes: using multi-scale feature map detection, adding a convolutional feature layer to the end of the truncated basic network, the size of the convolutional feature layer is gradually reduced, and the prediction values ​​of multiple scale detections are obtained, and the convolutional model of the detection is different for each convolutional feature layer; the improved SSD algorithm also includes: a convolutional predictor for detection: each added convolutional feature layer or an existing convolutional feature layer of the optional basic network can use a set of convolutional filters to generate a fixed prediction set; the improved SSD algorithm, default box and aspect ratio, associate a set of default bounding boxes with each feature map unit of the top network, the default box performs a convolution operation on the feature map, so that the position of each box instance relative to its corresponding cell is fixed; in each feature mapping unit, predict the offset relative to the default box shape in the cell, and the score of each category of the instance in each box; in feature maps of different resolutions, different default box shapes are used in multiple feature maps.

8. A construction contract management system according to claim 1, It is characterized in that It includes a business module, and the business module includes: The contract entry module is used to obtain engineering contracts, including project sub-contracts. The engineering contract is the main part, and the engineering budget, cost occurrence during contract implementation, progress engineering quantity, unit engineering and visa, investment and fund allocation are associated in the engineering contract and project sub-contracts. The acceptance and assessment module is used to perform project acceptance and assessment according to the contract nodes, strictly based on the budget estimate as the control benchmark, and perform delivery assessment and quality acceptance according to the contract; The contract amendment module is used to determine whether to amend the contract based on the project phase assessment. If yes, the project contract is re-acquired; if not, the next phase of the sub-project is continued and the acceptance is completed; Evaluation module, used to obtain contract execution and assessment status and establish traceable contract execution evaluation; The payment module is used to complete the contract acceptance and execute the contract payment.

9. An electronic device, It is characterized in that It includes a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory communicate with each other via the communication bus; Memory, for storing computer programs; The processor is used to implement the engineering contract management method described in any one of claims 1 to 7 when executing the program stored in the memory.

10. A computer-readable storage medium storing a computer program, It is characterized in that When the computer program is executed by a processor, the engineering contract management method described in any one of claims 1 to 7 is implemented.

Citation Information

Patent Citations

  • On-line management method for engineering project

    CN103136626A

  • Construction site violation intelligent identification method based on deep learning

    CN110826514A

  • Full-process automatic management system for industrial constructional engineering

    CN111274774A

  • External damage image intelligent identification method based on deep learning

    CN111881970A

  • Method and equipment for engineering fund management and control based on rough calculation

    CN112258050A

Cited By

  • High-standard farmland construction whole-process management method and system

    CN119168597A