Double-tubular-pile combined end plate
By designing the joint end plate of the double-pipe pile and using the combined structure of the joint plate and the steel bar positioning end plate, the problem of difficulty in maintaining parallelism during the laying process is solved, and the parallel state and seismic resistance of the pipe piles are improved, and the simplification of the simplification of the simplification of the simplification of the simplification of the simplification of the simplification of the simplification of the simplification of the simplification of Construction and production processes.
Patent Information
- Application Number
- CN202411182893.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-11-22
AI Technical Summary
In the case of complex geological conditions or irregular building shapes, it is difficult for pipe piles to maintain parallel state during laying, which affects their seismic resistance and foundation integrity. It is difficult for the prior art to ensure parallel state of pipe piles during production and manufacturing. Increased construction difficulty.
Design a joint end plate of double-tube piles, including a joint plate, a steel bar positioning end plate and a fixed end plate. By fixing the outer plate and the inner plate, ensure that the pipe piles are in parallel after forming and are embedded The grooves, steel bar fixing holes and bolt fixing realize parallel laying of pipe piles.
This technology effectively reduces the difficulty of construction, ensures that the pipe piles are in parallel during transportation and on-site construction, improves the seismic performance and integrity of the pipe piles, and simplifies the production and operation process.
Smart Images

Figure CN118997131A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pipe pile end plates, in particular to a double pipe pile combined end plate. Background Art
[0002] The pipe pile end plate is a disc-shaped part, which is most common in pipeline engineering. Flanges are used in pairs, and pipe piles are mainly used in the foundation construction of infrastructure projects such as buildings, bridges, and roads. Pipe piles are a prefabricated concrete component made of prestressed or high-strength concrete. They have high bearing capacity and stability. Prefabricated pipe piles are widely used in residential projects, which can effectively improve the bearing capacity and stability of the foundation. In infrastructure projects such as bridges, roads, and tunnels, prefabricated pipe piles also play an important role, improving the quality and efficiency of the project.
[0003] In some special cases, in areas with complex geological conditions and large differences, in order to more effectively control uneven settlement. For example, in areas near rivers, with solid land on one side and soft riverbed on the other, double-pipe piles laid horizontally and in parallel can enhance the ability to resist uneven settlement. In areas prone to earthquakes, in order to improve the seismic performance of the structure, double-pipe piles laid horizontally and in parallel can increase the integrity and lateral stiffness of the foundation and better resist seismic forces. In addition, if the shape of the building is irregular or the load distribution is uneven, the double-pipe piles laid horizontally and in parallel can be used to adjust and balance the force.
[0004] During the laying process of pipe piles, the posture and position of the pipe piles need to be adjusted in sequence to ensure the relative position of each pipe pile. In order to reduce the difficulty of parallel laying of pipe piles, a double-pipe pile joint end plate is designed to make the prefabricated stressed pipe piles in a parallel state when they are transported to the site, which is convenient for transportation and on-site construction. Therefore, we propose a new type of double-pipe pile joint end plate to achieve the above purpose. Summary of the invention
[0005] The object of the present invention is to provide a double-tube pile combined end plate to solve the problems raised in the above background technology.
[0006] To achieve the above object, the present invention provides the following technical solution: a double-tube pile combined end plate, comprising: Joint plates, reinforcement positioning end plates and fixed end plates; The combined plate comprises two plate bodies, and the steel bar positioning end plates and the fixed end plates are provided in two groups, and each group of steel bar positioning end plates and the fixed end plates are installed on one side of the two plate bodies after the pipe piles are formed; The plates are fixed by an outer plate and an inner plate, and after the two plates are fixed, the pipe piles are placed horizontally and in parallel.
[0007] Further to this solution, one side of the two plate bodies is provided with an embedded groove, the inner wall of the embedded groove is adapted to the diameter of the steel bar positioning end plate and the fixed end plate, and the steel bar positioning end plate and the fixed end plate are installed in the embedded groove.
[0008] Further to this solution, the steel bar positioning end plate includes end plate one, on which a circle of steel bar fixing holes are circumferentially equidistantly provided, the steel bar fixing holes include circular holes and arc grooves, the arc grooves are connected to the circular holes and have a diameter smaller than the circular holes.
[0009] Further to this solution, the fixed end plate includes end plate 2, on which reinforcement holes are equidistantly opened in a circle, the reinforcement holes are adapted to the diameter of the circular holes, and each group of reinforcement holes is provided with two.
[0010] Further to this solution, two outer embedding grooves corresponding to the positions of the inner embedding grooves are provided on the side of the plate body away from the inner embedding groove, and a positioning hole is provided on the plate body.
[0011] Further to this solution, the combined plate formed after the plate bodies are butt-jointed is in an "H" shape, both sides of the combined plate are concave surfaces, and the outer plate and the inner plate are both arranged at the concave surfaces.
[0012] Further to this solution, the plate body is provided with a plurality of bolt holes, and holes are provided on the outer plate and the inner plate at positions corresponding to the bolt holes to facilitate fixing the outer plate and the inner plate to the plate body.
[0013] Furthermore, regarding this solution, a rubber strip is fixed around one side of the plate body, and the inner plate is tightly attached to the rubber strip to improve the fit.
[0014] Further to this solution, a plurality of suspension members are arranged on the top of the combined plate, and the suspension members are fixed by fixing bolts at the bolt holes.
[0015] Further to this scheme, one end of the arc groove is in an arc shape, each group of the reinforcement holes is divided into a hole and b hole, and each group of the positioning holes is divided into a1 hole and b1 hole, wherein the distance between the a hole and the b hole of the reinforcement hole is smaller than the distance between the a hole and the b1 hole. In the use state, the steel bar is inserted from the round hole of the steel bar fixing hole and then dialed into the end of the arc groove, and then the steel bar passes through the b hole and the b hole, the steel bar positioning end plate is moved in the first direction and then the fixed end plate is moved in the first direction to position the steel bar, and after the positioning is completed, bolts are used to pass through the a hole, the a1 hole and the round hole to Fixation is performed. Since the diameters of the positioning hole and the reinforcement hole are both larger than the diameter of the steel bar rod, in order to further fix the steel bar, the steel bar is pushed in the first direction so that one end of the arc groove is against the inner wall of the b1 side. At this time, the circular holes are coaxial with the circular holes. Then the fixed end plate is also pushed in the first direction to make the plate body, the fixed end plate and the steel bar positioning end plate fit tightly. At this time, the a hole, the a1 hole and the circular hole are coaxial and can be fixed with bolts. After the pipe pile is completed, the two plates can be connected together with the pipe pile. The two plates are fixed by the outer plate and the inner plate. After the fixation is completed, the double pipe pile combination is realized.
[0016] Compared with the prior art, the present invention has the following beneficial effects: The double pipe pile joint end plate is provided with a joint plate, a steel bar positioning end plate and a fixed end plate. The joint end plate will not affect the cement pouring of the pipe piles during the production and manufacturing process of the pipe piles, so that the pipe piles can be produced smoothly. During the joint installation process, it can effectively ensure the strength of the pipe piles while allowing the pipe piles to be in a parallel state when leaving the factory, which is convenient for on-site construction and transportation.
[0017] At the same time, the double-tube pile combined end plate structure is relatively simple and easy to produce. While reducing the difficulty of on-site construction, it has low requirements for production process support. During use, the operating requirements for workers are relatively clear, and production operations can be carried out after simple training, with good results. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 It is a schematic diagram of the combined plate structure of the present invention; Figure 3 This is a schematic diagram of the structure of the combined plate after being fixed according to the present invention; Figure 4 This is a schematic diagram of the steel bar positioning end plate structure of the present invention; Figure 5 It is a schematic diagram of the fixed end plate structure of the present invention; Figure 6 It is a schematic structural diagram of the corresponding positions of the steel bar positioning end plate, the fixed end plate and the holes on the plate body 101 of the present invention.
[0019] In the figure: 1. Joint plate; 101. Plate body; 102. Rubber strip; 103. Bolt hole; 104. Inner groove; 105. Positioning hole; 106. External groove; 2. External plate; 3. Internal plate; 4. Steel bar positioning end plate; 401. End plate one; 402. Steel bar fixing hole; 4021. Round hole; 4022. Arc groove; 5. Fixed end plate; 501. End plate two; 502. Reinforcement hole; 6. Suspension piece. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0021] The buried double-tube piles are widely used in many engineering fields. In bridge construction, especially large and important bridges, double-tube piles can provide a solid foundation support, effectively resisting the dynamic loads generated by the passage of vehicles and the effects of natural forces such as wind and water flow. For example, the large cable-stayed bridge on the Yangtze River, the buried double-tube piles ensure the stability and safety of the bridge in long-term use. Double-tube piles have a higher bearing capacity and can withstand greater vertical and horizontal loads. Secondly, double-tube piles have excellent bending and shear resistance and perform well under complex stress conditions. Furthermore, the construction of double-tube piles is relatively flexible and can adapt to different geological conditions and engineering requirements. Therefore, in order to reduce the construction difficulty and transfer conditions of double-tube pile burial, double-tube pile joint end plates are set.
[0022] like Figure 1 As shown, the present invention provides a technical solution: a double-pipe pile combined end plate, comprising a combined plate 1, an outer plate 2, an inner plate 3, a steel bar positioning end plate 4 and a fixed end plate 5, wherein the combined plate 1 comprises two plate bodies 101, the outer plate 2 and the inner plate 3 are used to fix the two plate bodies 101, the steel bar positioning end plate 4 is used to combine the steel bars of the pipe piles, and is fixed to the plate body 101 in combination with the fixed end plate 5, and the double-pipe pile combined installation is completed after the two plate bodies 101 are jointly installed.
[0023] like Figure 2 and Figure 3As shown, the plate body 101 is provided with an inner groove 104 on one side and an outer groove 106 on the other side, the steel bar positioning end plate 4 is installed at the inner groove 104, and the fixed end plate 5 is installed at the outer groove 106, and the fixed end plate 5 and the steel bar positioning end plate 4 are installed on the plate body 101 by bolts and adjusting the positioning. After the plate body 101 is combined to form a combined plate 1, both sides of the combined plate 1 are concave, and the outer plate 2 and the inner plate 3 are respectively installed in the concave portions on both sides for fixing the combined plate 1, and the inner groove 104 and the outer groove 106 are both configured to adapt to the steel bar positioning end plate 4 and the fixed end plate 5, and the depth of the inner groove 104 is greater than the thickness of the steel bar positioning end plate 4 to facilitate installation.
[0024] like Figure 2 As shown, a circle of rubber strip 102 is provided on one side of the plate body 101 located at the embedded groove 104, which can increase the tightness between the plate body 101 and the inner plate 3 during the installation process, thereby improving the fitting effect.
[0025] like Figure 4 and Figure 5 As shown, the steel bar positioning end plate 4 includes an end plate 401, and a circle of steel bar fixing holes 402 are formed on the end plate 401. The steel bar fixing holes 402 are divided into two parts, namely a circular hole 4021 and an arc groove 4022. The diameter of the circular hole 4021 is larger than the width of the arc groove 4022. When inserting the steel bar, the steel bar is inserted from the circular hole 4021 and dialed into the arc groove 4022. The steel bars used in the pipe pile steel bar frame are usually thickened at the end. After being dialed into the arc groove 4022, the arc groove 4022 The diameter at the part is smaller than the diameter at the thickened part of the steel bar, which can reduce the steel bar from detaching from the steel bar positioning end plate 4 to a certain extent. The fixed end plate 5 includes an end plate 2 501, and a circle of reinforcement holes 502 is opened on the end plate 2 501. Each group of reinforcement holes 502 is provided with at least two hole positions. The positions of the reinforcement holes 502 are adapted to the positions of the steel bar fixing holes 402 on the steel bar positioning end plate 4. Among them, a circle of positioning holes 105 is also opened on the plate body 101, and the positioning holes 105 are also provided with at least two.
[0026] like Figure 6 As shown, the two hole positions of each group of reinforcement holes 502 on the steel bar fixing end plate 5 are a and b, and the two hole positions of each group of positioning holes 105 on the plate body 101 are a1 and b1. In the actual installation process, when the steel bar is inserted from the round hole 4021, it is inserted into the end of the arc groove 4022, and then passes through the b1 hole and then the b hole. Since the diameters of the positioning hole 105 and the reinforcement hole 502 are larger than the diameter of the steel bar rod, in order to further fix the steel bar, as shown in FIG. Figure 6As shown, the steel bar is pushed in the first direction so that one end of the arc groove 4022 is against the inner wall of the side b1. At this time, the circular hole 4021 is coaxial with the circular hole 4021. Then, the fixed end plate 5 is also pushed in the first direction, so that the plate body 101, the fixed end plate 5 and the steel bar positioning end plate 4 can be tightly fitted. At this time, the a hole, the a1 hole and the circular hole 4021 are coaxial, and they can be fixed with bolts. After the pipe piles are completed, the two plate bodies 101 can be connected together with the pipe piles. The two plate bodies 101 are fixed by the outer plate 2 and the inner plate 3. After the fixation is completed, the double pipe pile combination is realized. In order to ensure that the above process can be carried out accurately, it is necessary to know that the distance h between the a hole and the b hole is slightly smaller than the distance h1 between the a1 hole and the b1 hole. In this way, after rotating the fixed end plate 5, the a hole and the a1 hole can be coaxial, and the steel bar is clamped and limited by the fixed end plate 5 and the steel bar positioning end plate 4 to maintain stability.
[0027] In summary, the use of the pipe pile end plate is as follows: During the production of the pipe pile, in order to ensure the smooth pouring of concrete of the pipe pile and the shaping of the pipe pile, the plate body 101 is fixed together after the pipe pile is formed. Before that, in order to facilitate the fixation between the plate bodies 101 and ensure the strength of the front end, during the weaving process of the steel cage, one end of the steel bar is inserted from the round hole 4021 of the steel bar fixing hole 402 and then dialed into the end of the arc groove 4022, and then the steel bar passes through the b1 hole and the b hole, the steel bar positioning end plate 4 is moved along the first direction, and then the fixed end plate 5 is moved along the first direction. Move the steel bar to position it. After positioning, use bolts to pass through hole a, hole a1 and round hole 4021 to fix it, and complete the installation of the single pipe pile end plate. Then, the two plate bodies 101 are combined by installing the inner plate 3 and the outer plate 2. The plate body 101 is provided with a plurality of bolt holes 103. Holes are provided at the corresponding bolt holes 103 on the outer plate 2 and the inner plate 3 to facilitate the fixation of the outer plate 2 and the inner plate 3 with the plate body 101. Finally, the suspension member 6 is installed. The suspension member 6 can be a hook or a hanging ring to facilitate the transfer of the pipe pile.
[0028] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is limited by the attached embodiments and their equivalents.
Claims
1. A double-tube pile joint end plate, It is characterized in that include: A joint plate (1), a steel bar positioning end plate (4) and a fixed end plate (5); The combined plate (1) comprises two plate bodies (101), and the steel bar positioning end plates (4) and the fixed end plates (5) are provided in two groups, and each group of steel bar positioning end plates (4) and fixed end plates (5) is installed on one side of the two plate bodies (101) after the pipe piles are formed; The plate bodies (101) are fixed by an outer plate (2) and an inner plate (3), and after the two plate bodies (101) are fixed, the pipe piles are placed horizontally and in parallel.
2. A double-tube pile combined end plate according to claim 1, Features: One side of each of the two plate bodies (101) is provided with an embedded groove (104), the inner wall of the embedded groove (104) being adapted to the diameter of the steel bar positioning end plate (4) and the fixed end plate (5), and the steel bar positioning end plate (4) and the fixed end plate (5) are installed at the embedded groove (104).
3. A double-tube pile combined end plate according to claim 1, Features: The steel bar positioning end plate (4) comprises an end plate 1 (401), the end plate 1 (401) is provided with a circle of steel bar fixing holes (402) equidistantly arranged in a circle, the steel bar fixing holes (402) comprise a circular hole (4021) and an arc groove (4022), the arc groove (4022) is connected to the circular hole (4021) and has a diameter smaller than the circular hole (4021), the fixed end plate (5) comprises an end plate 2 (501), the end plate 2 (501) is provided with reinforcement holes (502) equidistantly arranged in a circle, the reinforcement holes (502) are adapted to the diameter of the circular hole (4021), and each group of reinforcement holes (502) is provided with two, and a positioning hole (105) is provided on the plate body (101).
4. A double-tube pile combined end plate according to claim 1, Features: Two outer embedding grooves (106) corresponding to the positions of the inner embedding grooves (104) are provided on the side of the plate body (101) facing away from the inner embedding grooves (104).
5. A double-tube pile combined end plate according to claim 1, Features: The combined plate (1) formed after the plate bodies (101) are butt-jointed is in an "H" shape, and both sides of the combined plate (1) are concave surfaces, and the outer plate (2) and the inner plate (3) are both arranged at the concave surfaces.
6. A double-tube pile joint end plate according to claim 1, Features: The plate body (101) is provided with a plurality of bolt holes (103), and holes are provided on the outer plate (2) and the inner plate (3) at locations corresponding to the bolt holes (103) to facilitate fixing the outer plate (2) and the inner plate (3) to the plate body (101).
7. A double-tube pile combined end plate according to claim 1, Features: A rubber strip (102) is fixed around one side of the plate body (101), and the inner plate (3) is tightly attached to the rubber strip (102) to improve the fit.
8. A double-tube pile combined end plate according to claim 1, Features: A plurality of suspension members (6) are arranged on the top of the combined plate (1), and the suspension members (6) are fixed by fixing bolts at the bolt holes (103).
9. A double-tube pile combined end plate according to claim 3, Features: One end of the arc groove (4022) is in an arc shape, each group of the reinforcement holes (502) is divided into holes a and holes b, and each group of the positioning holes (105) is divided into holes a1 and holes b1, wherein the distance between holes a and holes b of the reinforcement holes (502) is smaller than the distance between holes a1 and holes b1. In a use state, a steel bar is inserted from the circular hole (4021) of the steel bar fixing hole (402) and then inserted into the end of the arc groove (4022), and then the steel bar passes through the holes b1 and b, the steel bar positioning end plate (4) is moved in a first direction, and then the fixing end plate (5) is moved in the first direction to position the steel bar, and after positioning is completed, bolts are used to pass through the holes a, a1 and the circular hole (4021) to fix the steel bar.