Construction control system for suspension operation platform of high-altitude large-span suspended ceiling

Through technical means such as suspension point layout, platform assembly, lifting and dismantling and landing, the problems of continuity and stability in the construction of high-altitude large-span cantilever ceiling suspension operation platform have been solved, and the construction accuracy and safety have been improved.

CN119021476APending Publication Date: 2024-11-26ZHONGTIE ELECTRIZATION BUREAU GRP BEIJING CONSTR ENG
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410935332.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

It is difficult to achieve continuous and stable ceiling construction during the construction of the existing high-altitude large-span cantilever ceiling suspension operating platform, resulting in poor construction accuracy, efficiency and safety.

Method used

Using technical means such as suspension point layout, platform assembly, lifting, connecting fixing and disassembly landing, the suspension point layout module, platform assembly module, platform lifting module, connecting fixing module and disassembly landing module are used to ensure the stability of the suspension operation platform. and safety, improve construction accuracy and efficiency.

Benefits of technology

The continuous and stable construction of the high-altitude large-span cantilever ceiling suspension operating platform has been achieved, and the construction accuracy, efficiency and safety have been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021476A_ABST
    Figure CN119021476A_ABST
Patent Text Reader

Abstract

The invention discloses a high-altitude large-span suspended ceiling suspension operation platform construction control system, and relates to the technical field of construction control, and the system comprises a suspension point location laying module which is used for laying suspension point locations; the platform assembling module is used for assembling and hanging the operation platform; the platform lifting module is used for lifting the suspension operation platform to a preset position; the connecting and fixing module is used for connecting and fixing the suspension operation platform at a preset position to obtain an identified suspension operation platform; and the dismounting and landing module is used for carrying out dismounting and landing on the identification suspension operation platform based on the dismounting and landing instruction. The technical problems that continuous and stable suspended ceiling construction is difficult to conduct in construction control of an existing high-altitude large-span suspended ceiling suspension operation platform, and consequently construction precision, efficiency and safety are poor are solved, and the technical effect of improving the construction precision, the construction efficiency and the safety is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field related to construction control, and specifically to a construction control system for a high-altitude large-span cantilevered ceiling suspension operating platform. Background Art

[0002] In the rapid development of today's construction industry, the construction of high-altitude large-span cantilever structures has become a very challenging task. With the increasing complexity and diversification of architectural design, especially those modern buildings that pursue the ultimate visual effects and space utilization, such as large gymnasiums, airport terminals, convention and exhibition centers, etc., their tops and edge areas often need to construct complex and delicate ceiling structures. These structures not only require strong bearing capacity and high construction precision, but also need to achieve efficient and flexible installation and disassembly under the premise of ensuring construction safety. Traditional high-altitude working methods often rely on scaffolding, elevators and other equipment, but these methods are incapable of dealing with large-span and high-altitude operations. There are problems such as long construction period, high cost, and many safety hazards. Especially in the construction of cantilevered ceilings, due to the suspended working surface and large span, traditional construction methods are difficult to ensure the continuity and stability of construction. At the same time, the operating skills of workers are extremely high, which greatly limits the construction efficiency and safety.

[0003] Therefore, in the current technologies related to the construction control of high-altitude large-span cantilevered ceiling suspension operation platforms, there are technical problems that make it difficult to carry out continuous and stable ceiling construction, which in turn leads to poor construction accuracy, efficiency and safety. Summary of the invention

[0004] The present application provides a construction control system for a high-altitude large-span cantilevered ceiling suspension operation platform, which adopts technical means such as suspension point layout, platform assembly, lifting to connection and fixation, and final disassembly and landing, to solve the technical problem of difficulty in continuous and stable ceiling construction in the existing construction control of high-altitude large-span cantilevered ceiling suspension operation platform, which leads to poor construction accuracy, efficiency and safety, and achieves the technical effect of improving construction accuracy, construction efficiency and safety.

[0005] The present application provides a construction control system for a high-altitude large-span cantilevered ceiling suspended operating platform, the system comprising: a suspension point layout module, the suspension point layout module is used to layout the suspension points; a platform assembly module, the platform assembly module is used to assemble the suspension operating platform; a platform lifting module, the platform lifting module is used to lift the suspension operating platform to a predetermined position; a connection and fixing module, the connection and fixing module is used to connect and fix the suspension operating platform at the predetermined position based on the suspension points to obtain an identified suspension operating platform; a disassembly and landing module, the disassembly and landing module is used to disassemble and land the identified suspension operating platform based on a disassembly and landing instruction.

[0006] In a possible implementation, the platform assembly module is used to assemble a suspended operating platform, and also performs the following processing: obtaining a suspended operating platform design drawing and a suspended operating platform component set; collecting basic information of the suspended operating platform component set to obtain a platform component information set; setting a platform assembly plan based on the suspended operating platform design drawing and the platform component information set; assembling the suspended operating platform component set based on the platform assembly plan to obtain the suspended operating platform.

[0007] In a possible implementation, a platform assembly plan is set based on the suspension operating platform design drawing and the platform component information set, and the following processing is also performed: obtaining a suspension operating platform assembly decision record set; building an assembly decision model based on the suspension operating platform assembly decision record set; based on the suspension operating platform design drawing and the platform component information set, generating the platform assembly plan according to the assembly decision model.

[0008] In a possible implementation, the platform lifting module is used to lift the suspended operating platform to a predetermined position, and also performs the following processing: obtaining the real-time position of the suspended operating platform; formulating a platform lifting path based on the real-time position and the predetermined position; the platform lifting module includes a platform lifting device; based on the platform lifting path, the suspended operating platform is lifted to the predetermined position according to the platform lifting device.

[0009] In a possible implementation, the disassembly and landing module is used to disassemble and land the sign suspension operating platform based on the disassembly and landing instruction, and also performs the following processing: perform construction work based on the sign suspension operating platform, and when the construction work is completed, generate a disassembly and landing instruction; based on the disassembly and landing instruction, lower the sign suspension operating platform to the ground according to the platform lifting module; based on the platform disassembly plan, disassemble the sign suspension operating platform.

[0010] In a possible implementation, construction work is performed based on the sign hanging operating platform, and when the construction work is completed, a disassembly and landing instruction is generated, and the following processing is also performed: construction work is performed based on the sign hanging operating platform, and when the construction work is completed, a platform cleaning instruction is generated; the sign hanging operating platform is cleaned based on the platform cleaning instruction, and when the cleaning of the sign hanging operating platform is completed, the disassembly and landing instruction is obtained.

[0011] In a possible implementation, the system includes a quality inspection module, which performs the following processing: performing quality inspection based on the suspension operating platform component set to obtain quality inspection results of each component; setting quality constraints of each component based on the suspension operating platform component set; judging whether the quality inspection results of each component meet the quality constraints of each component; generating component assembly execution instructions if the quality inspection results of each component meet the quality constraints of each component; and assembling according to the suspension operating platform component set based on the component assembly execution instructions.

[0012] In a possible implementation, the system includes a construction control warning module, and the construction control warning module is used to provide full-process warning for the sign hanging operation platform.

[0013] The application proposes a construction control system for a high-altitude large-span cantilevered ceiling suspension operation platform, which includes a suspension point layout module, which is used to layout the suspension points; a platform assembly module, which is used to assemble the suspension operation platform; a platform lifting module, which is used to lift the suspension operation platform to a predetermined position; a connection and fixing module, which is used to connect and fix the suspension operation platform at the predetermined position based on the suspension points to obtain an identified suspension operation platform; and a disassembly and landing module, which is used to disassemble and land the identified suspension operation platform based on a disassembly and landing instruction. The control system solves the technical problem that it is difficult to carry out continuous and stable ceiling construction in the existing construction control of high-altitude large-span cantilevered ceiling suspension operation platforms, which leads to poor construction accuracy, efficiency and safety, and achieves the technical effect of improving construction accuracy, construction efficiency and safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] In order to more clearly illustrate the technical solution of the embodiment of the present disclosure, the accompanying drawings of the embodiment of the present disclosure will be briefly introduced below. A flow chart is used in the present application to illustrate the operations performed by the system according to the embodiment of the present application. It should be understood that the preceding or following operations are not necessarily performed accurately in order. On the contrary, various steps can be processed in reverse order or simultaneously as needed. At the same time, other operations can also be added to these processes, or one or more operations can be removed from these processes.

[0015] Figure 1 A schematic structural diagram of a construction control system for a high-altitude, large-span cantilevered ceiling suspension operating platform provided in an embodiment of the present application.

[0016] Explanation of the reference numerals: suspension point layout module 10 , platform assembly module 20 , platform lifting module 30 , connection and fixing module 40 , disassembly and landing module 50 . DETAILED DESCRIPTION

[0017] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application, it can be implemented in accordance with the contents of the specification. In order to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are listed below.

[0018] In order to make the purpose, technical solutions and advantages of the present application clearer, the present application will be further described in detail below in conjunction with the accompanying drawings. The described embodiments should not be regarded as limiting the present application. All other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of this application.

[0019] In the following description, reference is made to "some embodiments", which describe a subset of all possible embodiments, but it is understood that "some embodiments" may be the same subset or different subsets of all possible embodiments, and may be combined with each other without conflict, and the terms "first\second" involved are merely to distinguish similar objects and do not represent a specific ordering of objects. The terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, system, product, or server that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or modules that are not clearly listed or inherent to these processes, products, or devices. Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those generally understood by technicians in the technical field of this application. The terms used herein are for the purpose of describing the embodiments of the present application only.

[0020] The embodiment of the present application provides a construction control system for a high altitude large span cantilever ceiling suspension operation platform, such as Figure 1 As shown, the system comprises:

[0021] The suspension point layout module 10 is used to layout the suspension points. In the construction control system of the high-altitude large-span cantilever ceiling suspension operation platform, the suspension point layout module specifically refers to the module responsible for determining and setting the key support points or connection points required for the suspension operation platform. These suspension points are the basis for ensuring that the suspension operation platform can be stably and safely suspended at high altitudes and for subsequent construction operations. Specifically, according to the construction design drawings, structural mechanics analysis and actual site conditions, the position, quantity and layout of the suspension points are accurately calculated and determined. These points need to meet the requirements of structural strength, stability and construction convenience; preparations are made for the installation of the suspension points, including on-site investigation, measurement and layout, material preparation, etc., to ensure that the layout process can proceed smoothly. Avoid unnecessary delays or errors; install the suspension points at the designated locations according to the design plan and construction drawings, which usually involves the installation of steel structures, the tightening of connectors and necessary reinforcement measures, etc., and conduct quality inspection and acceptance of the completed suspension points to ensure that they meet the design requirements and relevant standards, including checking the position accuracy, installation quality, stability and load-bearing capacity of the points; during the layout process, pay attention to safety and reliability, take necessary protective measures and reinforcement measures to ensure the safety of construction personnel and the stability and reliability of the suspension points, and flexibly adjust and optimize the suspension points according to the actual situation and needs during the construction process to adapt to different construction requirements and conditions.

[0022] The platform assembly module 20 is used to assemble the suspended operating platform. In the process of constructing the suspended operating platform, the platform assembly module specifically refers to a system or tool set for assembling various parts or components into a complete suspended operating platform according to certain rules and sequence. This module usually covers multiple aspects from design, material preparation, assembly process to quality inspection, etc., aiming to ensure that the suspended operating platform can be built efficiently and safely. Specifically, provide design plans and drawings of the suspended operating platform, clarify the size, shape, connection method, etc. of each component, and provide guidance for subsequent material preparation and assembly; prepare the required materials, including steel, connectors, fasteners, etc. according to the design plan, and ensure that these materials meet the quality requirements; formulate detailed assembly processes and operating procedures to guide construction personnel to assemble the various components into a complete suspended operating platform in a certain order and method, usually including the steps of hoisting, positioning, connecting, and fastening the components; conduct quality inspections on the assembled suspended operating platform to ensure that it meets the design requirements and relevant standards, including checking the structural strength, stability, safety, etc. of the platform; during the assembly process, pay attention to the implementation of safety measures and protective measures to ensure the safety of construction personnel. At the same time, conduct safety performance inspections on the platform itself to ensure that it is safe and reliable during use. The platform assembly module should have a certain degree of flexibility and be able to be adjusted and optimized according to actual needs. For example, in different construction environments, it may be necessary to adjust the size, shape or connection method of the platform.

[0023] In a possible implementation, the platform assembly module 20 also includes obtaining a design drawing of a suspended operating platform and a set of suspended operating platform components; collecting basic information of the set of suspended operating platform components to obtain a set of platform component information; setting a platform assembly plan based on the design drawing of the suspended operating platform and the set of platform component information; assembling the set of suspended operating platform components based on the platform assembly plan to obtain the suspended operating platform. Obtain detailed design drawings of the suspended operating platform, which usually include key information such as the structural layout, size, material specifications, connection method, and location of key components of the platform. The design drawings are usually drawn by CAD (computer-aided design) software and include multiple views such as two-dimensional plan drawings, three-dimensional stereograms, and cross-sectional drawings. The design drawings will be detailed with information such as the load-bearing capacity, safety requirements, and installation steps of the platform, including detailed information such as the size, structure, material, and connection method of the platform. The set of suspended operating platform components refers to a collection of various parts and materials required to constitute a suspended operating platform, which may include steel, slings, safety ropes, fixing bolts, platform plates, guardrails, etc. After obtaining the component set, each component needs to be inspected and recorded in detail to obtain its basic information. This information may include the model, specification, material, weight, size, manufacturer, production date, certificate of conformity, etc. of the component. With this information, the platform component information set can be established. According to the design drawings and component information set, a detailed platform assembly plan is formulated. The plan should include assembly sequence, assembly method, required tools and equipment, safety measures, etc. The assembly plan needs to take into account factors such as the structural characteristics of the platform, construction environment, and personnel configuration to ensure the safety, efficiency, and smooth progress of the assembly process. Under the guidance of the assembly plan, the component set is assembled in a predetermined order and method, which may include cutting, welding, and assembly of steel, installation of slings and safety ropes, laying of platform boards, installation of guardrails, etc. During the assembly process, safety regulations need to be strictly followed to ensure the safety of construction personnel. At the same time, the assembly quality needs to be strictly controlled to ensure that the stability and carrying capacity of the platform meet the design requirements. After a series of assembly processes, a complete suspended operating platform is finally obtained for tasks such as aerial work and construction maintenance, providing a safe and stable working platform for construction personnel.

[0024] In a possible implementation, the platform assembly module 20 also includes obtaining a suspension operation platform assembly decision record set; building an assembly decision model according to the suspension operation platform assembly decision record set; and generating the platform assembly plan according to the assembly decision model based on the suspension operation platform design drawing and the platform component information set. By consulting historical project documents, interviewing experienced engineers and technicians, and the suspension operating platform assembly database, the suspension operating platform assembly decision record set is obtained. The suspension operating platform assembly decision record set refers to a collection of decision information, experience summary, problem solutions, etc. in the suspension operating platform assembly process in similar projects in the past; the assembly decision model aims to extract the key factors affecting assembly efficiency and quality by analyzing and summarizing past decision records, forming a scientific decision support system to help decision makers make reasonable decisions quickly when facing similar problems, and improve the standardization and predictability of the assembly process. Specifically, data analysis is performed on the decision record set to identify common decision points, decision factors and their relationships. Decision analysis, data mining and other technologies and methods are used to construct model structures such as decision trees and rule bases; the overall structure of the platform and the positional relationship of each component are determined according to the design drawing, and the platform component information set is used to select appropriate components and materials. According to the decision rules and best practices in the assembly decision model, detailed assembly steps, methods and safety measures are formulated. Finally, a complete platform assembly plan is formed.

[0025] In a possible implementation, the platform assembly module 20 also includes: performing quality inspection based on the suspension operation platform component set to obtain quality inspection results of each component; setting quality constraints of each component based on the suspension operation platform component set; judging whether the quality inspection results of each component meet the quality constraints of each component; if the quality inspection results of each component meet the quality constraints of each component, generating component assembly execution instructions; and assembling according to the suspension operation platform component set based on the component assembly execution instructions. All components of the suspended operating platform are carefully inspected for quality. The inspection contents may include material strength, dimensional accuracy, surface quality, functional integrity and other aspects. The inspection methods may include physical testing (such as tensile testing, hardness testing), dimensional measurement (such as using micrometers, projectors), visual inspection, etc., to obtain the quality inspection results of each component; clear quality constraints are set for each component of the suspended operating platform. These constraints are the criteria for judging whether the component quality is qualified or not. Quality constraints may include the minimum strength requirements of the material, the maximum and minimum deviation ranges of the size, the acceptable standards for surface quality, etc., to ensure that the assembled suspended operating platform can meet the design requirements and safety standards for use; after completing the quality inspection, the quality inspection results of each component need to be compared with the preset quality constraints. If the quality inspection results of any component do not meet the quality constraints, corresponding measures need to be taken, such as replacing the component, repairing the defects or re-inspecting, etc.; if the quality inspection results of all components meet the corresponding quality constraints, these components are considered qualified and can be used for subsequent assembly work, and a component assembly execution instruction is generated, which contains the specific steps, sequence, precautions and other information of the assembly, to guide the operator to assemble the components according to the predetermined plan.

[0026] The platform lifting module 30 is used to lift the suspended operating platform to a predetermined position. The platform lifting module, during the construction process of the suspended operating platform, specifically refers to a set of mechanical equipment or systems used to lift the suspended operating platform from the initial position to the predetermined height or position. This module is a key part to ensure that the suspended operating platform can reach the designated working position safely and accurately. Specifically, the core function of the platform lifting module is to provide sufficient lifting force to lift the suspended operating platform and the construction personnel, equipment, materials, etc. on it from the ground or the initial position to the predetermined construction height; during the lifting process, the module needs to ensure the stability of the suspended operating platform to prevent shaking or tilting caused by factors such as wind and vibration, so as to ensure the safety of construction personnel and construction efficiency; the module should have a precise positioning function to ensure that the suspended operating platform can accurately stay at the predetermined construction position to meet the construction requirements; during the lifting process, the module should also have a safety protection mechanism, such as overload protection, emergency stop device, etc., to prevent accidents and ensure construction safety; the module should be equipped with an advanced control system that can realize automatic or semi-automatic lifting operations to improve construction efficiency. At the same time, the control system should also have fault detection, alarm and automatic protection functions to ensure safety during construction.

[0027] In a possible implementation, the platform lifting module 30 also includes obtaining the real-time position of the suspended operating platform; formulating a platform lifting path based on the real-time position and the predetermined position; the platform lifting module includes a platform lifting device; based on the platform lifting path, the suspended operating platform is lifted to the predetermined position according to the platform lifting device. Positioning equipment (such as GPS receivers, Beidou receivers, etc.) is installed on the suspended operating platform to receive satellite signals in real time and calculate the precise location information of the platform. After obtaining the real-time position of the suspended operating platform, it is necessary to compare it with the predetermined position to determine the direction and distance the platform needs to move, which is achieved through professional path planning algorithms. These algorithms will consider multiple factors, such as terrain, obstacles, safety distance, etc., to generate the optimal or feasible lifting path. The platform lifting module is a key part of performing the platform lifting task. It usually includes a series of mechanical and electrical components, such as motors, reducers, chains, pulleys, slings, etc., which work together to form a platform lifting device. After determining the platform lifting path and preparing the platform lifting device, the platform lifting operation can be started. The operator needs to control the operation of the platform lifting device according to the predetermined path and instructions to ensure that the platform can be lifted to the predetermined position smoothly and safely. In order to ensure the safety of the lifting operation, a series of safety control measures need to be taken, such as setting a safety limit device to prevent the platform from exceeding the predetermined range; installing an emergency brake device to deal with emergencies; providing training and guidance to operators to enhance their safety awareness and operating skills, etc.

[0028] The connecting and fixing module 40 is used to connect and fix the hanging operation platform at the predetermined position based on the hanging point position to obtain an identified hanging operation platform. The connection and fixing module, in the construction scenario of the suspended operating platform, specifically refers to a set of mechanical equipment or systems used to connect and fix the suspended operating platform that has been lifted to the predetermined position with the suspension point in the building structure. The main purpose of this module is to ensure the stability and safety of the suspended operating platform at the predetermined position so that construction personnel can perform various high-altitude operations on this platform. Specifically, the connection and fixing module connects the suspended operating platform with the suspension point in the building structure (such as a suspension rod, a suspension ring, etc.) through specific connectors or devices to achieve the fixation of the platform. The weight, size, and use conditions of the suspended operating platform are fully considered, and a reasonable fixing method (such as welding, bolt connection, etc.) is adopted to ensure the stability of the platform at the predetermined position; on the basis of ensuring a firm connection, the module also needs to provide sufficient fixing force to prevent the suspended operating platform from shaking, tilting, or falling off during the construction process. Unsafe situations; through reliable connection and fixation, the connection and fixing module can significantly improve the safety of the suspended operating platform, ensure the life safety of construction personnel and the smooth progress of construction. Before the connection and fixing module is put into use, a safety performance evaluation should be carried out, including connection strength test, stability analysis, etc., to ensure that the module can meet the construction safety requirements.

[0029] The disassembly and landing module 50 is used to disassemble and land the identification suspended operating platform based on the disassembly and landing instructions. During the construction and maintenance of the suspended operating platform, the disassembly and landing module specifically refers to a set of mechanical equipment or systems used to disassemble and safely land the suspended operating platform that has completed its mission or needs to be moved according to the disassembly and landing instructions. This module integrates functions such as disassembly, landing and safety control to ensure that the suspended operating platform can be disassembled and landed according to the predetermined plan and safety requirements. Specifically, the disassembly and landing module first needs to release the connection between the suspended operating platform and the building structure, including removing the connectors, loosening the fixings, etc., so as to separate the platform from the suspension point. After the disassembly is completed, the module needs to control the suspended operating platform to slowly and steadily land on the ground or other designated locations. Advanced control technologies need to be used during the landing process, such as Hydraulic control, motor drive, etc., to achieve precise control of the platform's motion state. At the same time, buffer devices and limit devices need to be set to prevent the platform from impacting or exceeding the travel range during the landing process, ensuring the stability and safety of the platform and preventing accidents. The disassembly and landing module should have a complete safety control mechanism, including real-time monitoring of the platform's motion state, detecting potential safety hazards, timely issuing alarms and taking necessary emergency measures, etc., to ensure the safety of construction personnel and the smooth progress of the construction process. The disassembly and landing module should be equipped with a complete safety detection and protection system, such as sensors, surveillance cameras, etc., to monitor the platform's motion state and changes in the surrounding environment in real time. Once an abnormal situation is found, the system should immediately issue an alarm and take corresponding protective measures. In the fields of building construction, bridge construction, high-altitude operations, etc., the disassembly and landing module is an indispensable part of the construction and maintenance of the suspended operating platform. It can not only ensure the safety and stability of the suspended operating platform during the disassembly and landing process, but also improve the construction efficiency and quality.

[0030] In a possible implementation, the disassembly and landing module 50 also includes: performing construction work based on the identification suspension operation platform, generating a disassembly and landing instruction when the construction work is completed; based on the disassembly and landing instruction, the identification suspension operation platform is lowered to the ground according to the platform lifting module; based on the platform disassembly plan, the identification suspension operation platform is disassembled. The identification suspension operation platform is usually used in scenes such as high-altitude operations, construction, and equipment maintenance. When the construction work is completed, the suspension operation platform needs to be lowered from a high altitude to the ground and disassembled for storage or transportation, and a disassembly and landing instruction is generated, which contains specific requirements, steps, precautions and other information for the platform landing; after receiving the disassembly and landing instruction, the operator will use the platform lifting module to perform the platform landing operation. The platform lifting module usually includes components such as motors, reducers, and slings, which can generate the necessary lifting or lowering force. During the landing process, the platform's descending speed and stability need to be strictly controlled to ensure that the platform lands smoothly on the ground; after the platform lands on the ground, it needs to be disassembled according to the predetermined platform disassembly plan, and the various components and assemblies of the platform are gradually removed. After the disassembly is completed, the components need to be cleaned, inspected, and classified for storage.

[0031] In a possible implementation, the disassembly and landing module 50 further includes: performing construction work based on the identification hanging operation platform, generating a platform cleaning instruction when the construction work is completed; cleaning the identification hanging operation platform based on the platform cleaning instruction, and obtaining the disassembly and landing instruction when the cleaning of the identification hanging operation platform is completed. The identification hanging operation platform is used in scenes such as high-altitude operations, construction, and equipment maintenance, and provides a stable working platform for construction personnel. When the construction work is completed, in order to ensure the safety and cleanliness of the platform during subsequent use or disassembly, it is necessary to generate a platform cleaning instruction to guide the operator to thoroughly clean the platform, including removing garbage, residues, tools, etc., as well as possible stains and oil stains; after receiving the platform cleaning instruction, the operator will clean the platform according to the requirements of the instruction, which may include using tools such as brooms, rags, vacuum cleaners, etc. to remove garbage and stains on the surface of the platform, and returning or removing tools, materials, etc. After the platform cleaning work is completed, the operator will obtain a disassembly and landing instruction, which indicates that the platform is about to enter the disassembly and landing stage.

[0032] In a possible implementation, the construction control system of a high-altitude large-span cantilevered ceiling suspension operation platform also includes a construction control early warning module, and the construction control early warning module is used to provide full-process early warning for the sign suspension operation platform. The construction control warning module is used to provide full-process warning for the sign hanging operation platform. Specifically, it refers to the early identification, evaluation, warning and response of possible risks, problems or abnormal situations through a series of technical means and management measures during the entire construction, use and maintenance process of the sign hanging operation platform to ensure the safety, stability and efficiency of the construction process. The construction control warning module covers the entire life cycle of the sign hanging operation platform. The warning content mainly includes the following, such as safety risks such as falling from high altitude, being hit by objects, electric shock, quality problems such as unqualified materials and substandard construction technology, such as equipment failures such as motor failure and control system failure, and the impact of environmental changes such as excessive wind, rain and snow on the construction and use of the platform; the construction control warning module uses sensors, cameras and other monitoring equipment to monitor the construction site in real time, collect relevant data, process and analyze the monitoring data, identify abnormal data or trends, and evaluate potential risks. When potential risks are found, early warning prompts are issued to relevant personnel in a timely manner through sound and light alarms, SMS notifications, email reminders, etc.

[0033] Although the present application makes various references to certain modules in the system according to the embodiments of the present application, any number of different modules may be used and run on the user terminal and / or server, and the various units and modules included are only divided according to functional logic, but are not limited to the above division, as long as the corresponding functions can be achieved; in addition, the specific names of the functional units are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of the present invention.

[0034] The above specific implementations do not constitute a limitation on the protection scope of this application. It should be understood by those skilled in the art that various modifications, combinations and substitutions can be made according to design requirements and other factors. Any modifications, equivalent substitutions and improvements made within the spirit and principles of this application should be included in the protection scope of this application.

Claims

1. A construction control system for a high-altitude, large-span cantilevered ceiling suspension operation platform, characterized in that: The system comprises: A suspension point layout module, wherein the suspension point layout module is used to layout the suspension points; A platform assembly module, wherein the platform assembly module is used to assemble a suspended operating platform; A platform lifting module, the platform lifting module is used to lift the suspended operating platform to a predetermined position; A connection and fixing module, the connection and fixing module is used to connect and fix the suspension operation platform at the predetermined position based on the suspension point position to obtain an identified suspension operation platform; A disassembly and landing module is used to disassemble and land the identification suspension operating platform based on a disassembly and landing instruction.

2. A high altitude large span cantilever ceiling suspension operation platform construction control system as claimed in claim 1, characterized in that: The platform assembly module is used to assemble the suspended operating platform, including: Obtain the design drawing of the suspended operating platform and the component set of the suspended operating platform; Collect basic information of the suspension operation platform component set to obtain a platform component information set; Based on the design drawing of the suspended operating platform and the platform component information set, setting a platform assembly plan; The suspended operating platform component set is assembled based on the platform assembly plan to obtain the suspended operating platform.

3. A high altitude large span cantilever ceiling suspension operation platform construction control system as claimed in claim 2, characterized in that: Based on the design drawing of the suspended operating platform and the platform component information set, a platform assembly plan is set, including: Obtain the assembly decision record set of the suspension operation platform; Building an assembly decision model according to the assembly decision record set of the suspension operation platform; Based on the design drawing of the suspended operating platform and the platform component information set, the platform assembly plan is generated according to the assembly decision model.

4. A high altitude large span cantilever ceiling suspension operation platform construction control system as claimed in claim 1, characterized in that: The platform lifting module is used to lift the suspended operating platform to a predetermined position, and includes: Obtaining the real-time position of the suspended operating platform; formulating a platform lifting path based on the real-time position and the predetermined position; The platform lifting module includes a platform lifting device; Based on the platform lifting path, the suspended operating platform is lifted to the predetermined position according to the platform lifting device.

5. A high altitude large span cantilever ceiling suspension operation platform construction control system as claimed in claim 1, characterized in that: The disassembly and landing module is used to disassemble and land the identification suspension operating platform based on the disassembly and landing instruction, and includes: Perform construction work based on the identification hanging operation platform, and generate a disassembly and landing instruction when the construction work is completed; Based on the disassembly and landing instruction, the identification hanging operation platform is lowered to the ground according to the platform lifting module; Based on the platform disassembly plan, the sign hanging operation platform is disassembled.

6. A high altitude large span cantilever ceiling suspension operation platform construction control system as claimed in claim 5, characterized in that: The construction work is performed based on the identification suspension operation platform, and when the construction work is completed, a disassembly and landing instruction is generated, including: Perform construction work on the operating platform based on the identification, and generate a platform cleaning instruction when the construction work is completed; The identification hanging operation platform is cleaned based on the platform cleaning instruction, and when the cleaning of the identification hanging operation platform is completed, the disassembly and landing instruction is obtained.

7. A high altitude large span cantilever ceiling suspension operation platform construction control system as claimed in claim 2, characterized in that: The system includes a quality detection module, which is used to: Performing quality inspection based on the suspension operating platform component set to obtain quality inspection results of each component; Based on the suspension operating platform component set, setting mass constraints for each component; Determining whether the quality inspection results of each component meet the quality constraints of each component; If the quality inspection results of each component meet the quality constraints of each component, generate a component assembly execution instruction; Based on the component assembly execution instructions, assembly is performed according to the suspension operating platform component set.

8. A high altitude large span cantilever ceiling suspension operation platform construction control system as claimed in claim 1, characterized in that: The system comprises a construction control warning module, and the construction control warning module is used for providing a full-process warning to the sign hanging operation platform.

Citation Information

Patent Citations

  • Construction method and construction structure of symmetrical cantilever steel truss of high-rise building

    CN113250468A

  • High-altitude mounting method for steel structure

    CN115977401A

  • Concrete bridge tower construction informatization control system

    CN116245322A

  • Construction method of suspended steel frame for suspended ceiling

    JP2017197960A