TBM (Tunnel Boring Machine) construction wall back three-time grouting construction process

By adopting three grouting processes in TBM construction, the problem of difficult to control the grouting filling density is solved, the precise control of the slurry and the improvement of construction quality are achieved, and economic losses and construction risks are reduced.

CN119041923APending Publication Date: 2024-11-29CHINA FIRST HIGHWAY ENGINEERING CO LTD +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411323880.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

During TBM construction, the density of grouting filling is difficult to control, resulting in waste of slurry, floating pipe sheets and hidden quality risks. In addition, the traditional synchronous grouting form is prone to cause uneven ground settlement, tunnel deviation and water leakage, which increases the number of problems of Construction difficulty and economic losses.

Method used

The three grouting construction process after the TBM construction wall is adopted, including the simultaneous grouting of shield tail, the secondary slurry replenishment and the three slurry replenishment. Through geological survey, the grouting plan is formulated, the grouting hole position and slurry formula are optimized, and the slurry is reduced to prevent the slurry from slurry, ensuring that The vault slurry is filled with full filling to prevent the floating of the molded tunnels and improve construction quality and safety.

Benefits of technology

Accurate control of slurry filling is achieved, slurry waste and cost is reduced, construction quality and safety is improved, economic losses are reduced, and the stability and quality of the molded tunnel is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041923A_ABST
    Figure CN119041923A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of shield tunnel grouting construction, in particular to a TBM (Tunnel Boring Machine) construction wall back three-time grouting construction process which comprises shield tail synchronous grouting, secondary grout supplementing and third grout supplementing which are carried out in sequence. By the adoption of the TBM construction wall back three-time grouting construction technology, a traditional synchronous grouting mode is changed, shield tail grouting and secondary grouting are optimized into shield tail synchronous primary grouting, trolley tail secondary grouting and third-time grout supplementing, grout waste caused by grout forward channeling and potential quality hazards caused by non-dense wall back filling are reduced to the maximum extent, and the construction efficiency is improved. The method is highly suitable for hard rock stratum geology, is combined with TBM equipment to carry out TBM grouting construction under the hard rock stratum, can ensure full filling of vault grout, avoids post-construction floating of a formed tunnel, improves the quality of the formed tunnel, reduces the cost, reduces the economic loss, and is safe and environment-friendly.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of shield tunnel grouting construction, in particular to a TBM construction wall back three grouting construction process. Background Art

[0002] Shield construction is a highly mechanized dark tunnel construction method that uses the support provided by the shield and cutterhead to stabilize the face. Workers install lining support under the protection of the shield, ensuring efficient excavation while ensuring the safety of construction workers. At present, shield construction has become the most important method for urban tunnel construction due to its many advantages such as being unaffected by weather factors, fast excavation speed, controllable construction risks, and low labor intensity. It is increasingly used in the construction of urban rail transit. However, with the rapid development of domestic shield construction technology, its construction conditions have become increasingly complex, and the overall trend is towards deeper burial depths, longer lines, larger diameters, and more complex geological conditions.

[0003] Chongqing is a municipality built on the mountain, and its geological environment is mostly hard rock formations. This geological condition is of great benefit to the construction of urban underground space projects. However, due to the good geological conditions and low permeability, the problem of grouting behind the wall during TBM construction is difficult to control. Insufficient grouting pressure will cause more cavities in the wall thickness, and excessive grouting pressure will cause slurry to rush forward, which can easily bring great economic losses. Therefore, ensuring the forming posture of the pipe segment and post-construction stability is the top priority in Chongqing TBM construction.

[0004] At present, in TBM construction at home and abroad, the common shield tail filling forms are bean-grain stone blowing and grouting. Synchronous grouting of the shield tail is still the mainstream grouting method, and the grouting position is not considered to be moved to the rear tail trolley. The existing problems are: (1) the density of grouting filling is difficult to control. According to past construction experience, due to different grouting coefficients under different geological conditions, slurry backflow into the soil bin, shield tail leakage, slurry reflux, over-excavation and other factors, the grouting amount under different geological conditions of the same line is difficult to control. Excessive grouting may cause slurry waste, and insufficient grouting may cause loose filling behind, resulting in floating of the pipe segment and time-consuming and labor-intensive secondary grouting. (2) Leakage of shield tail Deformation of the shield tail brush, quality problems of shield tail grease, excessive grouting, improper adjustment of the hinge stroke, etc. are all prone to cause leakage of the shield tail. It is easy to cause uneven ground settlement, left and right deviation of the tunnel, misalignment of the pipe segment, water leakage and other defects. Leakage of grout causes waste of resources and increases the difficulty of civilized construction. Therefore, it is urgent to improve the construction process to solve the above problems. Summary of the invention

[0005] The purpose of the present invention is to provide a three-time grouting construction process behind the wall of TBM construction, which changes the traditional synchronous grouting form, optimizes the shield tail grouting and the secondary grouting into a synchronous one-time grouting of the shield tail, the secondary grouting of the trolley tail, and the three-time grouting, thereby minimizing the slurry waste caused by the forward slurry rushing and the quality hidden danger caused by the loose filling behind the wall to the greatest extent, and is highly suitable for the geology of hard rock formations. Combined with TBM equipment, TBM grouting construction under hard rock formations can ensure that the vault slurry is fully filled, and the floating of the formed tunnel after construction is prevented, so as to improve the quality of the formed tunnel, reduce costs and economic losses, and be safe and environmentally friendly.

[0006] To achieve the above object, the present invention provides a three-time grouting construction process behind the TBM construction wall, including synchronous grouting of the shield tail, secondary grouting, and tertiary grouting performed in sequence, and the specific steps are as follows:

[0007] S1 shield tail synchronous grouting

[0008] S11 Before grouting, geological survey shall be conducted in the area to be grouted. According to the geological survey results and construction requirements, a grouting plan shall be formulated, including the location of the synchronous grouting holes, the selection of grouting fluid, the grouting pressure and the grouting volume;

[0009] S12 transports the grouting liquid into the hole using a mortar truck with a mixer, and delivers it to the mortar tank at the No. 1 trolley of the shield machine. Connect the grouting pipeline and pressure sensor on the shield machine for grouting, and fill the slurry to the liquid level positions at points 5 and 7 of the segment. After the grouting is completed, perform hole opening verification near the synchronous grouting hole;

[0010] S2 Secondary Grouting

[0011] S21 determines the positions of the secondary grouting hole, observation hole 1 and drainage hole and drills the holes. The initial position of the secondary grouting hole is 60-70m away from the synchronous grouting hole. The secondary grouting hole is located 0.45m or 1.7m below the arch. The secondary grouting amount is calculated according to the position of the secondary grouting hole.

[0012] S22 connects the trolley at the corresponding position on the shield machine with the mortar tank at trolley No. 1 through the grouting pipeline, performs grouting from the secondary grouting hole, fills the slurry to the liquid level positions at points 11 and 1 of the segment, observes the grouting situation through observation hole 1, and drains water through the drain hole;

[0013] S3 three times filling

[0014] According to the segment forming posture, the positions of the third grouting holes and the second observation hole are selected and drilled. Grouting is performed at the 1 o'clock and 11 o'clock positions of the tunnel through the grouting auxiliary equipment to completely block the karst cave gaps and plug the water seepage at the formed tunnel;

[0015] 5 o'clock, 7 o'clock, 1 o'clock, 11 o'clock, and 12 o'clock all refer to the positions divided according to the clock scale.

[0016] Preferably, the grouting liquid in S11 includes the following components in parts by weight: 120 parts of cement, 400 parts of fly ash, 80 parts of bentonite, 800 parts of sand, 450 parts of water and an admixture, wherein the admixture is one of a coagulant, a drought-strengthening agent and a water-reducing agent, and the admixture is selectively added according to the results of geological survey.

[0017] Preferably, the positions of the synchronous grouting holes in S11 are arranged alternately on the left and right sides of the upper part of the pipe segment, and the pressure range at the synchronous grouting holes is between 0.19MPa-0.30Mpa.

[0018] Preferably, the calculation formula for the grouting amount of the synchronous grouting in S11 is:

[0019] Theoretical grouting volume per ring: Q = K × π × (D 2 -d 2 )×L / 4;

[0020] The synchronous grouting volume of each ring is 30%-45% of the theoretical grouting volume of each ring;

[0021] Where K=1.5 is the grouting rate, D is the cutting outer diameter of the TBM, d is the outer diameter of the segment, and L is the width of the segment.

[0022] Preferably, the secondary grouting hole in S21 is opened at the hole position with the highest elevation 3 rings of the segment backward from the working platform at the rear of the trolley, and the opening positions of two adjacent secondary grouting holes are staggered left and right. The position of observation hole one is selected according to the hole position of the secondary grouting hole, and the height position of observation hole one is equal to the height position of the secondary grouting hole. The hole intervals of the secondary grouting holes and observation hole one are both 5 rings of the segment.

[0023] Preferably, the opening position of the drainage hole in S21 is higher than the position of the synchronous grouting hole, and is located at 3 o'clock and 9 o'clock behind the shield tail. After the trolley connected to the shield tail passes over the above drainage holes, drainage holes continue to be set at the same height.

[0024] Preferably, the calculation formula for the secondary grouting amount in S22 is: Q2 = (D 2 -d 2 )×K×π×(α / 360°)×β; where Q2 is the secondary grouting volume, D is the cutting outer diameter of the TBM, d is the outer diameter of the segment, K=1.5 is the grouting rate, α is the slurry unfilled angle, and β=1.3 is the slurry filling coefficient.

[0025] Preferably, the grouting auxiliary equipment in S3 includes a grouting machine, a mixer, a grouting pipe, a grouting head, a ball valve and a grouting pressure gauge.

[0026] Preferably, the calculation formula for the grouting volume of the three groutings in S3 is: Q3=βQ(α / 360°).

[0027] Beneficial effects of the present invention:

[0028] (1) Guaranteed construction progress and improved construction quality: The construction process of the present invention is highly adaptable to the geological conditions of hard rock formations. Combined with the characteristics of the TBM equipment itself, such as the height of the synchronous grouting hole, the proportion of the synchronous grouting slurry, the permeability coefficient of the formation, and the longitudinal slope of the tunnel line, the construction process can be flexibly adjusted within a certain range. Through this method of TBM grouting construction under hard rock formations, it can be ensured that the vault slurry is fully filled and the floating of the formed tunnel after construction is prevented. The posture of the formed tunnel can be fixed faster, which is conducive to the control of the excavation posture and makes the TBM excavation axis better fit the line shape. Control the quality of the formed tunnel.

[0029] (2) Reduce costs and reduce economic losses: The construction process of the present invention only uses 30-40% of the grouting volume during synchronous grouting at the shield tail, which only supports the pipe segment firmly. Most of the slurry is injected during the second grouting to reduce the problem of slurry rushing forward and causing waste when grouting in a sloped tunnel. During the third grouting, the gap between the pipe segment and the soil is filled to control the buoyancy of the pipe segment, the posture of the pipe segment, etc., and the leaking parts of the formed tunnel are plugged at the same time. The three-time grouting process can greatly reduce the labor cost and material cost of the secondary grouting, reduce the cost, reduce the amount of slurry rushing forward, effectively reduce the time spent on cleaning the soil bin, and reduce the economic losses caused by it. In addition, the grouting filling can be precisely controlled, reducing the water passage while minimizing the amount of secondary grouting with a higher unit price.

[0030] (3) Safety and environmental protection: The construction process of the present invention can effectively reduce the forward flow of synchronous grouting slurry, reduce the slurry in the cutter head soil bin, and thus reduce the pollution to the soil after excavation. The entire grouting process is completed within the range of the trolley, reducing the construction time of other unstable platforms and reducing construction risks. After grouting, the formed tunnel has a stable posture and low risk in later operation.

[0031] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 It is a schematic diagram of the hole positions of the synchronous grouting holes of the present invention;

[0033] Figure 2 It is a schematic diagram of the position of synchronous grouting slurry at the shield tail of the present invention;

[0034] Figure 3 It is a schematic diagram of the slurry position when the secondary grouting hole of the present invention is 0.45m below the arch;

[0035] Figure 4 It is a schematic diagram of the grout filling area when the secondary grouting hole of the present invention is 0.45m below the arch;

[0036] Figure 5 It is a schematic diagram of the slurry position when the secondary grouting hole of the present invention is 1.7m below the arch;

[0037] Figure 6 It is a schematic diagram of the slurry filling area when the secondary grouting hole of the present invention is 1.7m below the arch. DETAILED DESCRIPTION

[0038] The present invention is further described below in conjunction with embodiments. Unless otherwise defined, the technical terms or scientific terms used in the present invention should be the common meanings understood by people with ordinary skills in the field to which the present invention belongs. The above-mentioned features or features mentioned in the specific examples mentioned in the present invention can be combined arbitrarily, and these specific embodiments are only used to illustrate the present invention and are not used to limit the scope of the present invention.

[0039] Example 1

[0040] A three-stage grouting construction process behind a TBM construction wall includes synchronous grouting of the shield tail, secondary grouting, and tertiary grouting in sequence, and the specific steps are as follows:

[0041] S1 shield tail synchronous grouting

[0042] S11 Before grouting, geological survey shall be conducted in the area to be grouted. According to the geological survey results and construction requirements, a grouting plan shall be formulated, including the location of the synchronous grouting holes, the selection of grouting fluid, the grouting pressure and the grouting volume;

[0043] The grouting liquid for synchronous grouting adopts cement mortar, which has the characteristics of short setting time, high strength, good durability and good corrosion resistance. During the trial excavation construction, the grouting liquid is optimized and adjusted accordingly according to the actual situation of synchronous grouting and the monitoring of surface settlement. The formula of the grouting liquid includes the following components by weight: 120 parts of cement, 400 parts of fly ash, 80 parts of bentonite, 800 parts of sand, 450 parts of water and admixtures. The admixture is one of accelerator, drought strength agent and water reducer. The admixture is selectively added according to the geological survey results. The physical and mechanical indicators of the slurry with this ratio are as follows: the setting time is generally 20-12h. According to the formation conditions and excavation speed, the setting time is adjusted by adding accelerators and changing the ratio through field tests. For highly permeable formations, small curves and other sections, the ratio can be further adjusted and early strength agents or water reducers can be added through field tests to further shorten the gel time, obtain early strength, and ensure good grouting effect.

[0044] Figure 1 Schematic diagram of the hole positions of the synchronous grouting holes of the present invention, such as Figure 1As shown, the positions of the synchronous grouting holes are alternately arranged on the upper left and right sides of the segment, and the synchronous grouting holes at the 1# and 2# positions are used for grouting to avoid the grouting slurry flowing toward the cutter head at the lower part of the segment. The pressure range at the synchronous grouting holes is between 0.19MPa-0.30Mpa.

[0045] The calculation formula of synchronous grouting volume is:

[0046] Theoretical grouting volume per ring Q: Q = K × π × (D 2 -d 2 )×L / 4;

[0047] The synchronous grouting volume of each ring is 30%-45% of the theoretical grouting volume of each ring;

[0048] Where K=1.5 is the grouting rate, D is the cutting outer diameter of the TBM, d is the outer diameter of the segment, and L is the width of the segment.

[0049] Taking D = 6.88m, d = 6.6m, L = 1.5m as an example, Q = 1.5 × 3.14 × (6.88 2 -6.6 2 )×1.5 / 4=6.7m 3 .

[0050] The volume of slurry used to fill the space below the segment is calculated as follows: βQ1 = (1-A)Q 尾 ;

[0051] Among them, β = 1.3 is the slurry filling coefficient, A = 10% is the loss rate of slurry after injection, Q1 is the volume of slurry in the gap after grouting to fill the wall of the pipe segment, Q 尾 is the assumed shield tail grouting volume.

[0052] Assume that the shield tail grouting volume is 2.5m 3 , the loss rate of slurry after injection is 10%, and the slurry filling coefficient is 1.3, then the volume of slurry used to fill the lower space of the pipe segment is Q1 = 2.5 × (1-10%) ÷ 1.3 = 1.7m 3 At this time, the filling liquid level is h = 1.6m. According to the slurry volume and liquid level, the following calculation can be made:

[0053] The length of the gap behind the wall filled with pipe segments

[0054] Slurry filling angle α = l ÷ (πd) × 360° = 118°

[0055] Figure 2 Schematic diagram of the synchronous grouting slurry position of the shield tail of the present invention, as shown in Figure 2 As shown, the liquid level is above the 5 and 7 o'clock positions at this time.

[0056] The calculation formula of slurry buoyancy on the segment is: F 浮 =ρ 液 V 排 =PV 排

[0057] Among them, F 浮 is the buoyancy of the slurry on the segment, ρ 液 is the slurry density, V 排 is the volume of the pipe segment immersed in the slurry, and P is the density of the slurry.

[0058] The entire segment is immersed in volume V 排 =π×(R 2 -r 2 )×L;

[0059] in is the radius of the TBM cutting outer diameter, r = 3.09 is the radius of the segment inner diameter, V 排 =π×(3.44 2 -3.09 2 )×1.5=10.77m 3 .

[0060] Slurry density P = 1.88t / m 3 , then the buoyancy F = 1.88 × 10.77 = 20.25t.

[0061] That is, the buoyancy of the slurry on the segment is 20.25t, which is greater than the deadweight of the segment. At the same time, due to the tightening effect of the front and rear segment bolts, the tail grouting volume is 2.5m 3 It fully meets the requirements of the segment’s posture fixation. Therefore, the shield tail grouting volume is 2.5 to 3m 3 To reduce slurry loss.

[0062] S12 uses a mortar truck with a mixer to transport the grouting liquid into the hole, minimizes the static time of the slurry, prevents mortar segregation, and delivers it to the mortar tank at the No. 1 trolley of the shield machine. Connect the grouting pipeline and pressure sensor on the shield machine for grouting, and fill the slurry to the liquid level positions at 5 and 7 o'clock on the segment, so that it can fix the posture of the segment and support the segment. It can also prevent the grouting liquid from rushing forward and reduce the waste of grouting liquid. Grouting is carried out simultaneously with excavation. The grouting speed should be adapted to the excavation speed and kept synchronized. The fullness of the grouting is controlled by both the grouting pressure and the grouting volume.

[0063] After the grouting is completed, hole opening verification is carried out at the 5-point and 7-point directions near the synchronous grouting holes to check whether the slurry has reached the predetermined height and whether the initial setting and final setting times are consistent with the designed setting time.

[0064] S2 Secondary Grouting

[0065] S21 determines the positions of the secondary grouting hole, observation hole 1 and drainage hole and drills them. The initial position of the secondary grouting hole is 60-70m away from the synchronous grouting hole. The position of the secondary grouting hole is opened at the hole with the highest elevation of the 3 ring segment position backward from the working platform at the rear of the trolley to avoid the trolley passing over the ring grouting pipeline and being unable to be removed during the excavation process. At the same time, attention should be paid to minimize unnecessary openings to reduce the risk of water leakage in the later stage. The opening positions of two adjacent secondary grouting holes are staggered left and right to offset the horizontal lateral pressure brought by the slurry surface on the segment. The position of observation hole 1 is selected according to the hole position of the secondary grouting hole. The height position of observation hole 1 is slightly lower than the height position of the secondary grouting hole. The hole intervals of the secondary grouting hole and observation hole 1 are both 5 ring segments.

[0066] The opening position of observation hole 1 is selected according to the position of secondary grouting hole. When observation hole 1 is at the same horizontal plane as the top elevation of the excavation surface where the secondary grouting hole is opened, due to the limitation of slurry fluidity, the observation hole is moved to the position of 5 rings in the direction of the large ring number. The position of observation hole 1 is also opened at the highest position on the top of the arch, that is, when slurry appears in observation hole 1, the upper building gaps located at the first 10 rings should be basically filled. However, considering the elevation position deviation of observation hole 1 of each ring segment, when slurry comes out of observation hole 1, the outer edge of the lining directly above the 12 o'clock position at the first 10 rings may not be effectively filled, and the height of the secondary grouting hole may have a large difference with the arch height of the excavation surface at this position, and the grouting pressure is too large. Therefore, observation hole 1 can be slightly lower than the arch position elevation of the grouting hole. At this time, the grouting hole should be closed and grouting should be continued.

[0067] Due to the limitation of the segment assembly point and the position of the secondary grouting hole, the injection amount of grouting liquid depends on the empty elevation position, and the injection amount should be determined by the position of the secondary grouting hole. According to the drilling of a hole every 5 rings, the secondary grouting hole is located 0.45m or 1.7m below the arch. The purpose of the secondary grouting of the No. 7 trolley is to fill the grouting liquid to the liquid level position of the segment 11-1. The secondary grouting amount can be calculated according to the liquid level position after the first grouting and the planned grouting hole height; the calculation formula for the secondary grouting amount is:

[0068] Where Q2 is the secondary grouting volume, D is the cutting outer diameter of the TBM, d is the outer diameter of the segment, K=1.5 is the grouting rate, α is the slurry unfilled angle, and β=1.3 is the slurry filling coefficient.

[0069] Figure 3 It is a schematic diagram of the slurry position when the secondary grouting hole of the present invention is 0.45m below the arch. Figure 4 Schematic diagram of the grout filling area when the secondary grouting hole of the present invention is 0.45m below the arch, as shown in Figure 3-4As shown, when the assembly points are 1 / 3 / 5 / 8 / 10 and the secondary grouting hole is 0.45m below the arch, the chord length l of the outer diameter of the cutter disc can be calculated to be 3.44m based on the geometric relationship (Pythagorean theorem) and the liquid level height position, and then the slurry unfilled angle α can be calculated to be 60°, and the filling angle is 360°-118°-60°=182°.

[0070] Based on this, we can calculate that Q2 = (3.44 2 -3.3 2 )×π×(182° / 360°)×1.5×1.3=2.95m 3 ;

[0071] At this time, the amount of slurry required to fill the five rings is 2.95*5=14.75m 3 .

[0072] Figure 5 It is a schematic diagram of the slurry position when the secondary grouting hole of the present invention is 1.7m below the arch. Figure 6 Schematic diagram of the grout filling area when the secondary grouting hole of the present invention is 1.7m below the arch, as shown in Figure 5-6 As shown, when the assembly point is 2 / 4 / 7 / 9 / 11, the secondary grouting hole is 1.7m below the arch. According to the geometric relationship (Pythagorean theorem) and the liquid level height position, the chord length l of the outer diameter of the cutter head can be calculated to be 5.93m, and then the grout unfilled angle α can be calculated to be 119°, and the filling angle is 360°-118°-119°=123°;

[0073] Based on this, we can calculate Q2 = (3.44 2 -3.3 2 )×π×(123° / 360°)×1.5×1.3=1.96m 3 ;

[0074] At this time, the amount of slurry required to fill the five rings is 1.96×5=9.8m 3 .

[0075] It should be noted that the secondary grouting is only for the empty space behind the opening. Because the amount of grouting in the first opening is large, one side needs to be filled before the grouting liquid overflows the vault and reaches the other side. If the grouting liquid is to cover the vault, a large amount of grouting liquid is required. Therefore, the opening grouting needs to be carried out on both sides at the same time to meet the filling injection volume requirements. The impact of the secondary grouting point sometimes causes the grouting volume to be greater than the calculated amount. This time, the 5-ring filling needs to supplement the grouting void at the low point in the rear. Therefore, double control is used during grouting. When the grouting volume is greater than the calculated amount, continue grouting until the grouting pressure increases. The minimum injection volume should be greater than the calculated amount at this point.

[0076] S22 connects the trolley at the corresponding position on the shield machine with the mortar tank at trolley No. 1 through a grouting pipeline, and grouting is carried out from the secondary grouting hole. The slurry is filled to the liquid level positions at points 11 and 1 of the segment. The grouting situation is observed through observation hole 1, and the water is drained through the drain hole.

[0077] Due to the existence of fissure water in the tunnel, after excavation, the fissure water converges to the building space behind the wall, and the water seal needs to be removed to avoid affecting the physical properties of the slurry. The opening position of the drainage hole is higher than the position of the synchronous grouting hole. According to the aforementioned shield tail synchronous grouting 2.5m 3 According to calculation, the elevation of the synchronous grouting liquid surface at the shield tail should be lower than the 3 o'clock and 9 o'clock positions. Therefore, drainage holes are opened at 3 o'clock and 9 o'clock positions behind the shield tail. After the trolley connected to the shield tail passes over the drainage hole, holes continue to be opened at the same position to drain water.

[0078] S3 three times grouting

[0079] According to the forming posture of the pipe segment, the positions of the three grouting holes and the second observation hole are selected and drilled. After the holes are opened, grouting is carried out at the 1 o'clock and 11 o'clock positions of the tunnel through the auxiliary grouting equipment to completely block the karst cave gaps and plug the leaks in the formed tunnel. If there is a lot of fissure water, the second observation hole will continue to flow, and grouting should be continued at this time. After the slurry flows out of the second observation hole, stop grouting, close the ball valve of the grouting hole, clean the pipeline, and start the next cycle of grouting. The position of the new cycle of grouting holes is the position of the second observation hole in the previous cycle. The auxiliary grouting equipment includes a grouting machine, a mixer, a grouting pipe, a grouting head, a ball valve and a grouting pressure gauge.

[0080] The opening points of the three grouting holes and observation holes are 1 or 11. First, the selection is made according to the posture of the formed tunnel segment. If the segment is offset to the right, select point 1, and if it is offset to the left, select point 11. Secondly, the adjacent holes are staggered left and right as much as possible to offset the lateral pressure to avoid secondary displacement of the segment caused by the grouting pressure. According to the actual grouting situation on site, the hole spacing of 5 rings can ensure the fullness of the slurry. For example: the opening sequence is shown as: the 10th ring (grouting hole) → the 15th ring (observation hole) → the 15th ring (grouting hole) → the 20th ring (observation hole), and it is extended in this order. If there is a water stop ring or the grouting pressure is too high at the beginning of grouting and cannot be injected, the appropriate hole position of the previous and next ring can be selected.

[0081] The above-mentioned 5 o'clock, 7 o'clock, 1 o'clock, 11 o'clock, and 12 o'clock all refer to the positions divided according to the clock scale.

[0082] The calculation formula for the single-ring grouting volume for three groutings is: Q3=βQ(α / 360°).

[0083] According to the position of the liquid level after the second grouting and the theoretical value of the gap behind the pipe wall, the theoretical filling volume Q3 of the slurry for the third grouting can be obtained. When the second injection hole is 0.45m below the arch, the filling volume of the slurry for the third grouting single ring is Q3 = 1.3 × 6.7 × (60 / 360) = 1.45m 3 , the filling volume for every 5 rings is 7.25m 3 When the secondary grouting hole is 1.7m below the arch, the theoretical single-ring grouting volume for the third grouting is Q3 = 1.3 × 6.7 × (119 / 360) = 2.88m 3 , each five rings fill volume is 14.4m 3 .

[0084] According to the total design volume and the volume of simultaneous grouting and secondary grouting, it can be calculated that the secondary injection hole is 0.45m below the arch, and the theoretical single ring filling volume of the third grouting is 1.45m 3 , the filling volume for every 5 rings is 7.25m 3 When the secondary grouting hole is 1.7m below the arch, the theoretical filling volume of a single ring of the third grouting is 2.88m 3 , each five rings fill volume is 14.4m 3 In the actual construction process, due to the fluidity of the slurry and the influence of the grouting effect on the porosity and slurry loss, the grouting amount is controlled in two ways: one is to change the grouting position after the slurry flows out of the observation hole; the other is that the grouting pressure is too high and the minimum injection amount should be greater than the calculated amount at that point.

[0085] Example 2

[0086] During the TBM construction of Chongqing Rail Transit Line 18 North Extension Project Chongqing Station to Terminal Section, the designed grouting volume per ring is about 5.8m 3 , the actual construction on site injected 6m 3 For each ring, according to the radar scanning and hole inspection results, 6m 3 / ring, the actual filling liquid level is only at 2 o'clock-10 o'clock. Excluding the normal loss of slurry, 20% of the grouting volume rushes forward into the cutter head and causes waste. According to the 5000 ring engineering volume of this project, the grouting material waste caused by the original process is 5000×5.8×0.2=5800m 3 By using the grouting construction process of the present invention, the cost of raw materials can be directly saved by 5800×450=2610000 yuan.

[0087] Example 3

[0088] The second phase of Chongqing Rail Transit Line 9 is generally laid in a north-south direction, starting from Xingke Avenue Station of Line 9 Phase I, and going north through Chunhua Avenue, Langgui Avenue, Central Park East, Congyan Temple and ending at Huashigou Station. The total length of the line is about 7.8 kilometers, with a total of 5 stations. Among them, the section between Chongqing Central Park East Station and Congyan Temple Station adopts the construction process of the present invention for wall grouting construction. The total construction mileage of the project is 3.8 km. The construction process of the present invention is used for systematic and scientific wall grouting construction, and the construction effect is good. The forming posture of the pipe segment meets the design and specification requirements. The amount of synchronous grouting and secondary grouting materials is reduced by 10% compared with before use. At present, the line has been opened for operation, and the monitoring data of the forming tunnel is stable. The economy and reliability of this process have been verified.

[0089] Example 4

[0090] The North Extension Project of Chongqing Rail Transit Line 18 starts from Xiaoshizi Station in the east and ends at Fuhua Road Station (not included) of Line 18 Project (Fuhua Road ~ Tiaodeng South) in the west, passing through Huguang Guild Hall, Kaixuan Road, Shibati, Qixinggang, Caiyuanba Railway Hub, Huangshaxi, Shidai Tianjie and other places. The total length of the line is 10.61km, all of which are underground lines, with a total of 8 stations, all of which are underground stations. The grouting construction process of the present invention is applied to the TBM section between Daping West Station and the terminal, with a total length of 1011.792m. The TBM section is 981.792m long, with a circular cross-section, a minimum turning radius of 550m, a maximum slope of 44‰, and a buried depth of 27m to 73m. There is one connecting channel in the section. Along the Huangda section, it passes under the Caiyuan Road overpass, crosses the power tunnel, continues under No. 147 Changjiang 2nd Road, Metro Line 2, No. 138 Changjiang 2nd Road, Building 25 of Daping Meijian New Village, No. 12-1 Daping Branch Road, Juneng (Sichuan Coal) employee housing, Yuzhong District Personnel Bureau military-to-civilian cadre resettlement housing project, and Yuzhong 110 kV Qipaifang transmission and transformation project before entering Daping West Station.

[0091] The project applied the construction technology of the present invention to carry out grouting construction. At present, the posture of the pipe segment is stable, the pipe segment has not floated up, and the synchronous grouting and secondary grouting materials are reduced by 13% compared with the conventional experience grouting method. The effect of the process application is remarkable.

[0092] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.

Claims

1. A three-time grouting construction process behind a TBM construction wall, characterized in that: It includes synchronous grouting of the shield tail, secondary grouting, and tertiary grouting in sequence. The specific steps are as follows: S1 shield tail synchronous grouting S11 Before grouting, geological survey shall be conducted in the area to be grouted. According to the geological survey results and construction requirements, a grouting plan shall be formulated, including the location of the synchronous grouting holes, the selection of grouting fluid, the grouting pressure and the grouting volume; S12 transports the grouting liquid into the hole using a mortar truck with a mixer, and delivers it to the mortar tank at the No. 1 trolley of the shield machine. Connect the grouting pipeline and pressure sensor on the shield machine for grouting, and fill the slurry to the liquid level positions at points 5 and 7 of the segment. After the grouting is completed, perform hole opening verification near the synchronous grouting hole; S2 Secondary Grouting S21 determines the positions of the secondary grouting hole, observation hole 1 and drainage hole and drills the holes. The initial position of the secondary grouting hole is 60-70m away from the synchronous grouting hole. The secondary grouting hole is located 0.45m or 1.7m below the arch. The secondary grouting amount is calculated according to the position of the secondary grouting hole. S22 connects the trolley at the corresponding position on the shield machine with the mortar tank at trolley No. 1 through the grouting pipeline, performs grouting from the secondary grouting hole, fills the slurry to the liquid level positions at points 11 and 1 of the segment, observes the grouting situation through observation hole 1, and drains water through the drain hole; S3 three times filling According to the segment forming posture, the positions of the third grouting holes and the second observation hole are selected and drilled. Grouting is performed at the 1 o'clock and 11 o'clock positions of the tunnel through the grouting auxiliary equipment to completely block the karst cave gaps and plug the water seepage at the formed tunnel; 5 o'clock, 7 o'clock, 1 o'clock, 11 o'clock, and 12 o'clock all refer to the positions divided according to the clock scale.

2. A three-time grouting construction process after TBM construction wall according to claim 1, characterized in that: The grouting liquid in S11 includes the following components by weight: 120 parts of cement, 400 parts of fly ash, 80 parts of bentonite, 800 parts of sand, and 450 parts of water.

3. A three-time grouting construction process after TBM construction wall according to claim 1, characterized in that: The positions of the synchronous grouting holes in S11 are alternately arranged on the left and right sides of the upper part of the pipe segment, and the pressure range at the synchronous grouting holes is between 0.19MPa-0.30Mpa.

4. A three-time grouting construction process after TBM construction wall according to claim 1, characterized in that: The calculation formula for the grouting volume of synchronous grouting in S11 is: Theoretical grouting volume per ring Q: Q = K × π × (D 2 -d 2 )×L / 4; The synchronous grouting volume of each ring is 30%-45% of the theoretical grouting volume of each ring; Where K=1.5 is the grouting rate, D is the cutting outer diameter of the TBM, d is the outer diameter of the segment, and L is the width of the segment.

5. The three-time grouting construction process after TBM construction wall according to claim 1 is characterized in that: The secondary grouting hole in S21 is opened at the hole position with the highest elevation 3 rings of segments backward from the working platform at the rear of the trolley. The opening positions of two adjacent secondary grouting holes are staggered left and right. The position of observation hole one is selected according to the hole position of the secondary grouting hole. The height position of observation hole one is slightly lower than that of the secondary grouting hole. The hole intervals of the secondary grouting holes and observation hole one are both 5 rings of segments.

6. A three-time grouting construction process after TBM construction wall according to claim 1, characterized in that: The opening position of the drainage holes in S21 is higher than that of the synchronous grouting holes and is located at 3 o'clock and 9 o'clock behind the shield tail. After the trolley connected to the shield tail passes over the above drainage holes, drainage holes continue to be set at the same height.

7. The three-time grouting construction process after TBM construction wall according to claim 1 is characterized in that: The calculation formula for the secondary grouting amount in S22 is: Q2 = (D 2 -d 2 )×K×π×(α / 360°)×β, where Q2 is the secondary grouting volume, D is the cutting outer diameter of the TBM, d is the outer diameter of the segment, K=1.5 is the grouting rate, α is the slurry unfilled angle, and β=1.3 is the slurry filling coefficient.

8. The three-time grouting construction process after TBM construction wall according to claim 1 is characterized in that: The auxiliary equipment for grouting in S3 includes grouting machine, mixer, grouting pipe, grouting head, ball valve and grouting pressure gauge.

9. The three-time grouting construction process after TBM construction wall according to claim 1 is characterized in that: The calculation formula for the grouting volume Q3 of the three groutings in S3 is: Q3=βQ(α / 360°).