Underground diaphragm wall construction period optimization method

By reasonably selecting the combination of grooved machinery and optimizing construction planning, the problem of mismatch between machinery replacement and design and construction in underground continuous wall construction is solved, and the construction period is shortened and cost is reduced, ensuring the project is completed on schedule and the construction efficiency is improved.

CN119066745APending Publication Date: 2024-12-03NO 1 ENG COMPANY CO LTD OF CCCC FIRST HARBOR ENG COMPANY +1

Patent Information

Application Number
CN202411105969.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

In the construction of underground continuous walls under complex geological conditions, the mismatch between mechanical replacement and design and construction leads to uncontrollable construction period and high cost.

Method used

By reasonably selecting the trough-forming machinery combination, we optimize construction planning and construction period control, including listing equipment combinations, construction planning, secondary design, alternative equipment combinations, trough-forming work efficiency statistics, construction period analysis and construction plan to ensure equipment utilization and construction efficiency.

Benefits of technology

Effectively shorten the construction period, reduce construction costs, ensure that the project is completed on schedule, and improve construction efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119066745A_ABST
    Figure CN119066745A_ABST
Patent Text Reader

Abstract

The invention relates to an underground diaphragm wall construction period optimization method, and belongs to the technical field of underground diaphragm wall construction. The underground diaphragm wall construction period optimization method comprises the following steps that according to geological survey data, the thickness and the soil property of each soil layer are counted, and feasible grooving machine combinations are listed; according to a supporting structure design scheme of the underground diaphragm wall, a construction area and a construction sequence are planned; carrying out secondary design on the underground diaphragm wall; the secondary design comprises groove section splitting, joint arrangement and groove forming width adjustment; analyzing and counting the work efficiency of each grooving machine combination, and determining an alternative grooving machine combination; obtaining the construction efficiency of each alternative grooving machine combination under different groove sections; key procedures and resource investment under different grooving machine combinations are analyzed, and grooving machines are selected; and making a construction plan. According to the method, through reasonable equipment selection, optimized construction planning and accurate construction period control, the construction efficiency is effectively improved, the construction period is shortened, and meanwhile the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of underground continuous wall construction, and in particular relates to a method for optimizing the construction period of an underground continuous wall. Background Art

[0002] Underground continuous walls have the characteristics of high structural rigidity, integrity, good impermeability and durability. They can be used as permanent soil retaining, water retaining and load-bearing structures. Their construction process is very complicated, especially in areas where soft soil layers such as site silt and silty soil are widely distributed. Since such soils have low bearing capacity, low permeability and high water content, the construction of underground continuous walls under such complex geological conditions requires reasonable arrangements for various construction processes to effectively control the construction period.

[0003] Generally speaking, the construction of underground continuous walls includes the following steps: trench wall reinforcement construction, guide wall construction, pavement reinforcement construction, trenching construction, steel cage processing and hoisting, and underwater concrete pouring; among them, trenching construction and steel cage processing can be carried out simultaneously, and these two processes are time-consuming. Therefore, the construction plan and resource allocation of trenching construction and steel cage processing are crucial to ensuring the project is completed on schedule.

[0004] In the prior art, Chinese invention patent CN110984132B provides a construction method for underground continuous wall trenching under complex geological conditions. The patent selects trenching machinery according to soil layer characteristics, formulates a function analysis table of corresponding trenching machinery, selects the optimal trenching machinery for each soil layer for construction, and provides a reasonable basis for the selection of trenching construction machinery; according to the construction plan of this method, in order to adapt to each soil layer, it is necessary to replace and use different trenching machinery, and the replacement of machinery requires time for disassembly, transportation and installation, which will extend the construction time and generate additional transportation costs, equipment costs, labor costs, etc. Therefore, this method is not conducive to the guarantee of construction progress and the control of construction costs. In addition, in actual projects, the design and construction of underground continuous walls are undertaken by different teams. The construction machinery often requires the construction party to analyze the on-site situation and make the most appropriate choice. It is difficult for the design party to refine the design scheme in combination with the construction machinery when designing. The design scheme lacks guidance on actual construction to a certain extent, which will also lead to uncontrollable construction period.

[0005] Therefore, how to provide a method for optimizing the construction period of underground continuous walls is a technical problem that urgently needs to be solved. Summary of the invention

[0006] In view of the shortcomings of the prior art, the present invention provides a method for optimizing the construction period of an underground continuous wall, which effectively improves construction efficiency, shortens construction period and reduces construction costs through reasonable equipment selection, optimized construction planning and precise construction period control.

[0007] The present invention provides a method for optimizing the construction period of an underground continuous wall, which is applicable to a soft soil layer area with low bearing capacity, and comprises the following steps:

[0008] List equipment combinations: Based on geological survey data, count the thickness of each soil layer and soil characteristics, and list feasible trenching machinery combinations;

[0009] Construction planning: Plan the construction area and construction sequence according to the design of the underground continuous wall support structure;

[0010] Secondary design: Conduct secondary design of underground continuous wall; secondary design includes slot segment splitting and joint arrangement, adjusting slot width, and obtaining statistical tables of slot segment forms of underground continuous wall of various structural forms;

[0011] Alternative equipment combination: Analyze and count the work efficiency of each slotting machine combination to determine the alternative slotting machine combination;

[0012] Trenching efficiency statistics: Analyze the construction efficiency of each candidate trenching machine combination in different soil layers, and obtain the construction efficiency of each candidate trenching machine combination in different trench sections;

[0013] Construction period analysis: Compare the construction efficiency of the alternative troughing machinery combinations in different trough sections with the corresponding steel cage processing period, analyze the key processes and resource inputs under different troughing machinery combinations, and select the troughing machinery;

[0014] Develop construction plan: Develop underground continuous wall construction plan based on on-site conditions and determine the construction period.

[0015] This technical solution effectively shortens the construction period and reduces costs through reasonable equipment selection, optimized construction planning and precise construction period control. It can be applied to areas with soft soil layers with low bearing capacity, effectively cope with complex geological conditions, and ensure that the project is completed on schedule.

[0016] In some of the embodiments, in the secondary design step, the slot sections are split and the slot width is adjusted in combination with the minimum operating width of the slotting machine; the joints are arranged according to the space influence of the joints and the weight balance principle, the joint size adjustment amount of each slot section is determined, and the sizes of the first opening width, connecting width, and closing width are adjusted.

[0017] This technical solution can achieve the beneficial effect of optimizing equipment utilization and improving trenching construction efficiency.

[0018] In some of the embodiments, in the step of listing the equipment combination, the slotting machine combination is selected according to the characteristics of the soil layer, including a double-wheel slotting machine, a square impact drill, a slotting machine, and a circular rotary drill. By selecting the most suitable slotting machine according to the characteristics of different soil layers, the construction efficiency and quality can be improved, the number of machine replacements and the related time loss can be reduced, and the overall construction period can be shortened.

[0019] In some embodiments, when a square impact drill is used for grooving construction, the groove width is adjusted according to formula (1), and the expression of formula (1) is:

[0020] L = L0 + L1 = A × B (1);

[0021] In formula (1), L is the adjusted trench width, L0 is the design width of the middle section of the support structure design scheme of the underground continuous wall, L1 is the adjustment amount of the joint size, B is the minimum operating width of the square impact drill, and A is the number of square impact drill operations.

[0022] When the present technical solution uses a square impact drill for grooving construction, the calculation of the grooving width can improve the accuracy of the construction plan, which is beneficial to improving the construction efficiency.

[0023] In some of the embodiments, when a circular rotary drill is used for trenching construction, a double-wheel slotting machine is used for secondary slotting after the rotary drill leads the hole, and the hole is expanded into a rectangular cross-section; when the trench sections are split, they are first divided according to the minimum operating width of the double-wheel slotting machine, and then the hole-leading point of the circular rotary drill is set.

[0024] When the circular rotary drill is used for trenching construction in the present technical solution, the trench sections are divided according to the minimum operating width of the double-wheel slot milling machine, and the guide holes of the circular rotary drill are set on this basis. This can optimize the layout of the trench sections, reduce unnecessary construction adjustments, and thus improve the overall construction efficiency.

[0025] In some of the embodiments, in the secondary design step, the statistical table of the trench sections of underground continuous walls of various structural forms includes the supporting structure of the underground continuous wall, the total number of trench sections after the underground continuous walls of various supporting structures are disassembled, and the trench section thickness and number of trench sections of underground continuous walls of different structural forms.

[0026] This technical solution can better grasp the specific needs during the construction process and ensure close coordination between design and actual construction.

[0027] In some of the embodiments, in the trenching efficiency statistics step, the method for obtaining the construction efficiency of each alternative trenching machine combination in different trench sections includes: calculating the estimated trenching time in different soil layers according to the average soil thickness of each soil layer and the average trenching efficiency of the trenching equipment in different soil layers under different structural forms of the trench sections, and combining the mobile equipment positioning time, steel cage installation time, trench cleaning time, and concrete pouring time to obtain the complete operating efficiency of the underground continuous wall in each structural form.

[0028] This technical solution can obtain the complete operating efficiency of underground continuous walls of various structural forms, which is helpful for accurately evaluating the construction progress and resource allocation.

[0029] In some of the embodiments, in the construction period analysis step, under each grooving machine combination, the construction period of the grooving process is compared with the steel cage processing process, and the process that takes a longer construction period is selected as the key process.

[0030] This technical solution regards the process that takes up a long construction period as the key process, and rationally arranges the steel bar processing site and resource input to avoid the stagnation time of "grooving without cage".

[0031] In some of the embodiments, in the construction planning step, the supporting structure forms of the underground continuous wall include a W-shaped underground continuous wall, an I-shaped underground continuous wall, a rectangular frame underground continuous wall, and a I-shaped underground continuous wall.

[0032] This technical solution provides flexibility for construction through a variety of structural forms, and the most suitable support structure can be selected according to geological conditions and construction requirements.

[0033] In some of the embodiments, in the secondary design step, the split slot segments of the underground continuous wall include T-shaped slot segments, L-shaped slot segments, cross-shaped slot segments, I-shaped slot segments, Z-shaped slot segments, and [-shaped slot segments.

[0034] This technical solution enables the underground continuous wall to adapt to various complex underground spaces and structural requirements through different slot segment forms, ensuring the precise docking of each part and uniform stress on the overall structure.

[0035] Based on the above scheme, the underground continuous wall construction period optimization method in the embodiment of the present invention effectively improves the construction efficiency, shortens the construction period, and also reduces the cost, ensuring the quality and safety of the project through reasonable equipment selection, optimized construction planning and accurate construction period control. This method is particularly suitable for areas with soft soil layers with low bearing capacity, and can effectively cope with complex geological conditions to ensure that the project is completed on schedule. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0037] Figure 1 It is a flow chart of the method for optimizing the construction period of underground continuous wall of the present invention;

[0038] Figure 2 Schematic diagram of the supporting structure of the underground continuous wall in Example 1 of the present invention;

[0039] Figure 3 This is a schematic diagram of the trench section form of the underground continuous wall in Example 1 of the present invention;

[0040] Figure 4 It is a schematic diagram of calculation of joint division and adjustment into groove width when using square impact drill for construction in an embodiment of the method for optimizing construction period of underground continuous wall of the present invention;

[0041] Figure 5 A schematic diagram of the division of joints and adjustment of groove widths when a square impact drill is used for construction in Example 1 of the present invention;

[0042] Figure 6 It is a schematic diagram of the division of joints and adjustment of groove widths when a rotary drill is used for construction in Example 1 of the present invention. DETAILED DESCRIPTION

[0043] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0044] In the description of the present invention, it should be understood that the terms "center", "lateral", "longitudinal", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0045] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features.

[0046] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0047] like Figure 1 As shown, in one embodiment of the underground continuous wall construction period optimization method of the present invention, the underground continuous wall construction period optimization method is applicable to soft soil layer areas with low bearing capacity, and includes the following steps:

[0048] List equipment combinations: According to geological survey data, the thickness of each soil layer and soil characteristics are counted, and feasible trenching machinery combinations are listed. In this step, the thickness of each soil layer and soil characteristics are counted through detailed geological survey data, so as to list all feasible trenching machinery combinations. This step ensures that the most suitable machinery can be selected during the construction process to cope with different geological conditions.

[0049] Construction planning: Plan the construction area and construction sequence according to the design scheme of the support structure of the underground continuous wall. In this step, according to the design scheme of the support structure of the underground continuous wall, combined with the construction depth, construction difficulty, natural environment characteristics of the construction area and project management requirements, the construction area and construction sequence are reasonably planned, which helps to optimize the construction process and reduce unnecessary waste of time. As an illustrative embodiment, the division of the construction area should give priority to the impact of the natural environment on the construction. The construction area can be preliminarily divided according to whether the construction site is near water or affected by high groundwater levels; then the area of ​​each construction area is limited according to the deployment and jump construction of the operating equipment. Specifically, each construction area should ensure the movement and alternating operation of a set of operating equipment within the area. When each construction area is assigned a set of operating equipment, the number of operating sections should be no less than 15 sections. At this time, the operating equipment and its flow construction can operate smoothly. According to the division of construction areas, the construction sequence should give priority to areas near water or with high groundwater levels. On this basis, according to the support structure design of the underground continuous wall, the construction sequence should be arranged according to the principle of deep construction depth first and shallow construction depth later, and easy construction difficulty first and difficult construction later. When there are special requirements for construction priority in project management, the construction sequence should be adjusted according to project management needs.

[0050] Secondary design: secondary design of the underground continuous wall; the secondary design includes the splitting of the trench segments and the arrangement of the joints, which are adjusted to the trench width, and a statistical table of the trench segment forms of underground continuous walls of various structural forms is obtained. In this step, a secondary design of the underground continuous wall is performed, including the splitting of the trench segments and the arrangement of the joints, which are adjusted to the trench width. This step can optimize the design according to actual construction conditions and improve construction efficiency. It should be noted that after the secondary design, the construction sequence in each construction area can be carried out according to the construction difficulty of the trench segments and joints, starting with the easy ones and then the difficult ones, gradually overcoming the difficult points of the operation.

[0051] Alternative equipment combination: Analyze and count the work efficiency of each slotting machine combination to determine the alternative slotting machine combination. In this step, analyze and count the work efficiency of each slotting machine combination to determine the alternative combination. This can predict the efficiency of various equipment combinations before construction and provide a reliable basis for construction.

[0052] Trenching efficiency statistics: Analyze the construction efficiency of each candidate trenching machine combination in different soil layers to obtain the construction efficiency of each candidate trenching machine combination in different trench sections. In this step, analyze the construction efficiency of each candidate trenching machine combination in different soil layers to obtain construction efficiency data. This helps to make quick adjustments during the construction process to maintain high efficiency.

[0053] Construction period analysis: Compare the construction efficiency of the alternative troughing machinery combination in different trough sections with the corresponding steel cage processing period, analyze the key processes and resource inputs under different troughing machinery combinations, and select the troughing machinery. In this step, compare the construction efficiency of the alternative troughing machinery combination with the steel cage processing period, analyze the key processes and resource inputs, and select the most suitable troughing machinery. This step helps to shorten the construction period and reduce costs.

[0054] Develop a construction plan: Develop an underground continuous wall construction plan based on the on-site conditions and determine the construction period. In this step, develop an underground continuous wall construction plan based on the on-site conditions and determine the construction period. This step ensures time management throughout the construction process and avoids unnecessary delays.

[0055] In the above exemplary embodiments, through reasonable equipment selection, optimized construction planning and precise construction period control, the construction efficiency is effectively improved, the construction period is shortened, the cost is reduced, and the project quality and safety are ensured. This method is particularly suitable for areas with soft soil layers with low bearing capacity, and can effectively cope with complex geological conditions to ensure that the project is completed on schedule.

[0056] In some embodiments, in the secondary design step, the slot sections are divided and the slot width is adjusted in combination with the minimum operating width of the slot forming machine; the joints are arranged according to the space influence of the joints and the weight balance principle, the joint size adjustment amount of each slot section is determined, and the size of each first opening width, connecting width, and closing width is adjusted. The slot section division and slot width adjustment according to the minimum operating width of the slot forming machine can optimize the construction process according to actual conditions to adapt to different construction conditions and requirements; the optimization of the joint arrangement can foresee and solve possible construction problems before construction by determining the joint size adjustment amount of each slot section, and ensure the structural stability and construction safety of the underground continuous wall; the size optimization of the first opening width, connecting width, and closing width can enable each part of the underground continuous wall to be accurately connected, avoiding construction difficulties and potential risks caused by size mismatch, and can optimize equipment utilization and improve slot forming construction efficiency.

[0057] It should be noted that the minimum working width of the troughing machine is determined according to the parameters of the troughing machine. Generally, the grab width of the troughing machine is the minimum working width. In order to facilitate construction, the width of each trough section should be equal to an integer multiple of the minimum working width of the troughing machine. Therefore, in the above embodiment, the trough section is split in combination with the minimum working width of the troughing machine; if the construction section to be split cannot be split into an integer multiple of the minimum working width of the troughing machine, it can be adjusted when adjusting the size of the first opening width, the connecting width, and the closing width to simplify the construction process. Specifically, when adjusting the size of the first opening width, the connecting width, and the closing width, the size of each width section should be designed as an integer multiple of the minimum working width of the troughing machine; when a width section that is not an integer multiple of the minimum working width of the troughing machine appears, it is necessary to perform equipment overlapping operations. At this time, the two ends of the trough section should be used as the closed width, and the standard trough section or other simple structure trough section in the middle of the trough section should be used as the first opening width.

[0058] In some embodiments, in the step of listing the equipment combinations, the trenching machine combination is selected according to the characteristics of the soil layer, including a double-wheel slotting machine, a square impact drill, a trenching machine, and a circular rotary drill.

[0059] In some embodiments, Figure 4 As shown, when a square impact drill is used for grooving construction, the groove width is adjusted according to formula (1), and the expression of formula (1) is:

[0060] L = L0 + L1 = A × B (1);

[0061] In formula (1), L is the adjusted trench width, L0 is the design width of the middle section in the design scheme of the underground continuous wall support structure, L1 is the joint size adjustment, B is the minimum operating width of the square impact drill, and A is the number of square impact drill operations. When a square impact drill is used for trenching construction, the calculation of the trench width can improve the accuracy of the construction plan and help improve construction efficiency.

[0062] In some embodiments, Figure 6 As shown, when a circular rotary drill is used for trenching construction, a double-wheel slot milling machine is used for secondary slot milling after the rotary drill leads the hole, and the hole is expanded into a rectangular section; when the slot section is split, it is first divided according to the minimum operating width of the double-wheel slot milling machine, and then the lead hole point of the circular rotary drill is set; the lead hole is used to process the rock formation in advance to reduce the workload of the slot milling machine and improve the operating efficiency. It has nothing to do with the division of the slot section. The layout of the lead hole point should be determined in combination with the hardness of the rock formation. For harder rock formations, the number of lead hole points can be increased and the spacing can be reduced to reduce the construction time. When a circular rotary drill is used for trenching construction, the slot section is divided according to the minimum operating width of the double-wheel slot milling machine, and the lead hole point of the circular rotary drill is set on this basis. The layout of the slot section can be optimized, unnecessary construction adjustments can be reduced, and the overall construction efficiency can be improved.

[0063] In some embodiments, in the secondary design step, the statistical table of the slot sections of underground continuous walls of various structural forms includes the supporting structure of the underground continuous wall, the total number of slot sections after the underground continuous walls of various supporting structures are disassembled, and the slot section thickness and number of slot sections of underground continuous walls of different structural forms. This embodiment can better grasp the specific needs during the construction process and ensure close coordination between the design and actual construction.

[0064] In some embodiments, in the trenching efficiency statistics step, the method for obtaining the construction efficiency of each candidate trenching machine combination in different trench sections includes: calculating the estimated trenching time in different soil layers according to the average soil thickness of each soil layer and the average trenching efficiency of the trenching equipment in different soil layers under different structural forms of the trench sections, and combining the mobile equipment position time, steel cage installation time, trench cleaning time, and concrete pouring time to obtain the complete operation efficiency of underground continuous walls in various structural forms. This embodiment can obtain the complete operation efficiency of underground continuous walls in various structural forms, which is helpful for accurately evaluating the construction progress and resource allocation.

[0065] In some embodiments, in the construction period analysis step, under each combination of slotting machines, the construction period of the slotting process is compared with the steel cage processing process, and the process with a longer construction period is selected as the key process. By selecting the process with a longer construction period as the key process, the steel processing site and resource input are reasonably arranged to avoid the stagnation time of "slotting without cage".

[0066] In some embodiments, Figure 2 As shown in the figure, in the construction planning steps, the supporting structures of underground continuous walls include W-shaped underground continuous walls, I-shaped underground continuous walls, rectangular frame underground continuous walls, and I-shaped underground continuous walls. The various structural forms provide flexibility for construction, and the most suitable supporting structure can be selected according to geological conditions and construction requirements, which helps to improve the stability and impermeability of the structure, while also optimizing material usage and construction costs.

[0067] In some embodiments, Figure 3 As shown in the figure, in the secondary design step, the split slot sections of the underground continuous wall include T-shaped slot sections, L-shaped slot sections, cross-shaped slot sections, straight-shaped slot sections, Z-shaped slot sections, and [-shaped slot sections. Different slot section forms enable the underground continuous wall to adapt to various complex underground spaces and structural requirements, ensuring the precise docking of each part and the uniform force of the overall structure, thereby improving the accuracy of construction and the stability of the structure.

[0068] Example 1

[0069] The method for optimizing the construction period of underground continuous wall provided by the present invention is described below in conjunction with the underground continuous wall construction of a certain inland river immersed tube tunnel project in the Pearl River Delta region:

[0070] The geological conditions at the site of the project in this embodiment are complex, the groundwater level is high, and the project construction is very difficult. After investigation, the soil layers in the site are distributed as follows: artificial fill, silt, silty clay, silty fine sand, fine sand, medium sand, strongly weathered muddy siltstone, and moderately weathered muddy siltstone. The cohesion, internal friction angle, and water content of the soil bodies between the rock layers vary greatly, and it is difficult to control the uniformity and verticality of the pile body, and it is difficult to control the construction quality; among them,

[0071] Artificial fill layer: layer thickness 0.50-5.00m, average layer thickness 1.65m, Class I loose soil;

[0072] Silt layer: layer thickness 1.00~18.30m, average layer thickness 7.29m, Class I loose soil;

[0073] Silty clay layer: burial depth 10.80-36.80m, layer thickness 0.80-13.90m, average layer thickness 4.44m, Class II ordinary soil;

[0074] Silt-like fine sand layer: burial depth 0.40-27.80m, layer thickness 2.20-24.50m, average layer thickness 9.87m, Class I loose soil;

[0075] Fine sand layer: burial depth 1.80~33.40m, layer thickness 2.20~32.10m, average layer thickness 10.22m, Class I loose soil;

[0076] Medium sand layer: burial depth 1.60~40.60m, layer thickness 1.70~17.30m, average layer thickness 6.01m, Class I loose soil;

[0077] Strongly weathered muddy siltstone layer: most of the buried depth is 17.40-38.70m, the layer thickness is 1.40-16.90m, the average layer thickness is 7.92m, some of the boreholes have not been exposed, and it is Class IV soft rock;

[0078] Moderately weathered muddy siltstone layer: The rock is relatively soft, RQD=40%~80%, buried at a depth of 20.40~45.60m, this layer has not been exposed, and is a Grade V secondary hard rock.

[0079] The underground continuous wall construction period optimization method in this embodiment includes the following steps:

[0080] 1. List equipment combinations: According to geological survey data, count the thickness of each soil layer and soil characteristics, and list feasible trenching machinery combinations;

[0081] In this embodiment, the thickness of each soil layer and the soil properties are as described above. The surface soft soil in this area has low bearing capacity, the rock is soft rock, the hardness is low due to strong weathering, and the standard penetration number of medium weathered rock layers is greater than 50. The trenching machine combination is selected according to the soil layer properties, including a double-wheel milling machine, a square impact drill, a trenching machine, and a circular rotary drill.

[0082] 2. Construction planning: Plan the construction area and construction sequence according to the design of the underground continuous wall support structure;

[0083] In this embodiment, Figure 2 As shown, the supporting structure forms of the underground continuous wall include a W-shaped underground continuous wall, an I-shaped underground continuous wall, and a I-shaped underground continuous wall; the construction area is divided into area one and area two, and during construction, the construction of area one is carried out first, and then the construction of area two is carried out.

[0084] 3. Secondary design: Conduct secondary design of underground continuous wall; secondary design includes slot segment splitting and joint arrangement, adjusting slot width, and obtaining statistical tables of slot segment forms of underground continuous wall of various structural forms;

[0085] In this step, the trench sections are split and the trench width is adjusted in combination with the minimum operating width of the trenching machine; the joints are arranged according to the space influence of the joints and the weight balance principle, the joint size adjustment amount of each trench section is determined, and the size of each first opening width, connecting width, and closing width is adjusted; the statistical table of trench sections of underground continuous walls of various structural forms includes the supporting structure of the underground continuous wall, the total number of trench sections after the underground continuous wall of each supporting structure is disassembled, and the trench section thickness and number of trench sections of underground continuous walls of different structural forms;

[0086] When using a square impact drill for grooving construction, Figure 4 As shown, according to formula (1), it is adjusted to the slot width. The expression of formula (1) is:

[0087] L = L0 + L1 = a × B (1);

[0088] In formula (1), L is the adjusted trench width, L0 is the design width of the middle section of the support structure design of the underground continuous wall, L1 is the joint size adjustment amount, B is the minimum operating width of the square impact drill, and A is the number of square impact drill operations; in this embodiment, Figure 5 As shown in the left figure, in the original design of the T-slot segment, the I-beam and cross steel plate at the joint are arranged at the protruding ends of T1 and T2 of the T-slot segment, and the Y1 section of the middle I-shaped slot segment adopts a closed structure. The arrangement form results in a narrow slot size of the Y1 section, insufficient equipment space, and a large number of T1 and T2 joints, resulting in a heavy lifting weight. During the secondary design, if Figure 5 As shown in the right figure, the Y1 section is set as the first opening width, cross steel plate joints are installed at both ends, and I-beam joints are set to connect T1 and T2 horizontally as the connecting width to balance the lifting weight. At the same time, the groove size of the Y1 section is increased to facilitate construction.

[0089] When a circular rotary drill is used for trenching construction, a double-wheel slot milling machine is used to mill the slots for the second time after the rotary drill leads the hole, and the hole is expanded into a rectangular section; when the slot sections are split, they are first divided according to the minimum operating width of the double-wheel slot milling machine, and then the leading hole points of the circular rotary drill are set; in this embodiment, Figure 6 As shown in the left figure, the cross steel plate at the joint is set in the Y1 section of the I-shaped groove section. Figure 6 As shown in the figure on the right, secondary design is performed based on the minimum operating width of the rotary drilling rig.

[0090] In this embodiment, Figure 3 As shown in the figure, the split slot sections of underground continuous walls include T-shaped slot sections, L-shaped slot sections, cross-shaped slot sections, and straight-shaped slot sections. The statistical table of slot sections of underground continuous walls of various structural forms is as follows:

[0091] Table 1 Statistics of underground continuous wall trench sections of various structural forms

[0092]

[0093] The weight balance principle needs to consider the balance of joint weight in order to balance the lifting weight. At the same time, the joints should be concentrated on a certain section as little as possible.

[0094] 4. Alternative equipment combination: Analyze and count the work efficiency of each slotting machine combination to determine the alternative slotting machine combination;

[0095] In this embodiment, the work efficiency analysis table of each slotting machine combination is as follows:

[0096] Table 2 Analysis of the ergonomics of various slotting machine combinations

[0097]

[0098] It should be noted that the impact drilling slotting is related to the width and section size, hole position arrangement, etc. A single slot section is generally operated by a single machine, but multiple sets and multiple sections can be arranged according to the overall plane to operate simultaneously to shorten the overall construction period; the rotary drilling hole-leading scheme is mostly used in hard rock areas to improve the efficiency of double-wheel slot milling machines, but the construction cost and equipment investment are large, and the site requirements are high; the first section hole-leading is the key construction period for slotting, and the subsequent section hole-leading is operated at the same time as the double-wheel slot milling machine but in different sections. The hole-leading is the overlap time, which does not affect the overall construction period progress, but a sufficient number of hole-leading equipment should be configured to ensure that the hole-leading speed matches the speed of the double-wheel slot milling machine;

[0099] It should also be noted that the determination of the combination of alternative slotting machines is affected by many factors. In addition to work efficiency, it is also restricted by many factors such as site, economic cost, technical quality and safety risks;

[0100] In this embodiment, the underground continuous wall is a key construction period control link for the project. The construction period is relatively tight, so impact drilling is excluded first. There are many uncertain factors in the construction period and the single trenching time is long, which has high geological requirements. In addition, due to the large site restrictions, the construction in the river bank tidal flat area is in a narrow strip, and the equipment space is relatively tight, so it is not suitable to use rotary drilling to lead the hole.

[0101] 5. Trenching efficiency statistics: Analyze the construction efficiency of each candidate trenching machine combination in different soil layers, and obtain the construction efficiency of each candidate trenching machine combination in different trench sections;

[0102] In this step, the method for obtaining the construction efficiency of each candidate trenching machine combination in different trench sections includes: calculating the estimated trenching time in different soil layers according to the average soil thickness of each soil layer and the average trenching efficiency of the trenching equipment in different soil layers under different structural forms of the trench sections, and combining the mobile equipment position time, steel cage installation time, trench cleaning time, and concrete pouring time to obtain the complete operation efficiency of underground continuous walls in various structural forms;

[0103] In this embodiment, the alternative slotting machine is a double-wheel slotting machine. The construction efficiency of the double-wheel slotting machine in different soil layers is shown below. The slotting efficiency table of different slotting machines can be estimated according to the construction parameters of the slotting machines, and verified and modified in the on-site construction test. In this embodiment, only the slotting efficiency table of the I-shaped slot section using different slotting machines is listed, and typical machines are selected for the T / L-shaped slot section and the cross-shaped slot section for illustration:

[0104] Table 3 The efficiency of double-wheel slot milling machine for underground continuous wall with I-shaped slot

[0105]

[0106] Table 4 Performance table of impact drilling for underground continuous wall with I-shaped groove

[0107]

[0108] Table 5 Efficiency table of rotary drilling trenching for underground continuous wall of I-shaped trench section

[0109]

[0110] Table 6 T / L type slot section underground continuous wall double wheel slot milling machine slotting efficiency table

[0111]

[0112] Table 7 The efficiency of double-wheel slot milling machine for underground continuous wall of cross-shaped slot section

[0113]

[0114] 6. Construction period analysis: Compare the construction efficiency of the alternative troughing machinery combination in different trough sections with the corresponding steel cage processing period, analyze the key processes and resource inputs under different troughing machinery combinations, and select the troughing machinery;

[0115] In this step, under each slotting machine combination, the slotting process is compared with the steel cage processing process, and the process that takes up a longer construction period is selected as the key process;

[0116] It should be noted that the selection of troughing machinery determines the construction process and construction time of troughing construction. After the troughing machinery is determined, the steel bar processing site and resource investment should be reasonably arranged, and the steel bar processing period should be determined simultaneously to avoid the stagnation time of "troughing without cage". Considering the construction cost, the resource investment of troughing equipment per unit time is higher, and its reduced utilization rate will lead to a high cost waste. Therefore, most projects shorten the steel bar processing cycle by adding processing sites and staff, making it less than the troughing time of a single trough section, forming a flow operation mode in which the steel bar cage can be lowered after the trough is formed.

[0117] 7. Develop a construction plan: Develop an underground continuous wall construction plan based on the on-site conditions and determine the construction period.

[0118] Through the description of multiple embodiments of the underground continuous wall construction period optimization method of the present invention, it can be seen that the embodiment of the underground continuous wall construction period optimization method of the present invention has at least one or more of the following advantages:

[0119] 1. The underground continuous wall construction period optimization method provided by the present invention effectively improves the construction efficiency, shortens the construction period, reduces the cost, and ensures the quality and safety of the project through reasonable equipment selection, optimized construction planning and accurate construction period control;

[0120] 2. The underground continuous wall construction period optimization method provided by the present invention divides the trench sections and adjusts the trench width according to the minimum operating width of the trenching machine, and can optimize the construction process according to actual conditions to adapt to different construction conditions and requirements;

[0121] 3. The underground continuous wall construction period optimization method provided by the present invention and the size optimization of the first opening width, the connecting width and the closing width can enable each part of the underground continuous wall to be accurately connected, avoiding the construction difficulty and potential risks caused by size mismatch, and can optimize the equipment utilization rate and improve the trenching construction efficiency.

[0122] Finally, it should be noted that: the various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0123] The above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the present invention can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the present invention, which should be included in the scope of the technical solution for protection of the present invention.

Claims

1. A method for optimizing the construction period of underground continuous wall, suitable for soft soil areas with low bearing capacity, characterized in that: The following steps are involved: List equipment combinations: Based on geological survey data, count the thickness of each soil layer and soil characteristics, and list feasible trenching machinery combinations; Construction planning: Plan the construction area and construction sequence according to the design of the underground continuous wall support structure; Secondary design: Conduct secondary design of underground continuous wall; secondary design includes slot segment splitting and joint arrangement, adjusting slot width, and obtaining statistical tables of slot segment forms of underground continuous wall of various structural forms; Alternative equipment combination: Analyze and count the work efficiency of each slotting machine combination to determine the alternative slotting machine combination; Trenching efficiency statistics: Analyze the construction efficiency of each candidate trenching machine combination in different soil layers, and obtain the construction efficiency of each candidate trenching machine combination in different trench sections; Construction period analysis: Compare the construction efficiency of the alternative troughing machinery combinations in different trough sections with the corresponding steel cage processing period, analyze the key processes and resource inputs under different troughing machinery combinations, and select the troughing machinery; Develop construction plan: Develop underground continuous wall construction plan based on on-site conditions and determine the construction period.

2. The underground continuous wall construction period optimization method according to claim 1, characterized in that: In the secondary design step, the slot sections are split and the slot width is adjusted based on the minimum operating width of the slotting machine; the joints are arranged according to the space influence of the joints and the weight balance principle, the joint size adjustment amount of each slot section is determined, and the sizes of the first opening width, connecting width, and closing width are adjusted.

3. The underground continuous wall construction period optimization method according to claim 2, characterized in that: In the steps of listing the equipment combination, the trenching machinery combination is selected according to the characteristics of the soil layer, including a double-wheel slotting machine, a square impact drill, a trenching machine, and a circular rotary drilling rig.

4. The underground continuous wall construction period optimization method according to claim 3 is characterized in that: When a square impact drill is used for grooving construction, the groove width is adjusted according to formula (1). The expression of formula (1) is: L = L0 + L1 = A × B (1); In formula (1), L is the adjusted trench width, L0 is the design width of the middle section of the support structure design scheme of the underground continuous wall, L1 is the adjustment amount of the joint size, B is the minimum operating width of the square impact drill, and A is the number of square impact drill operations.

5. The underground continuous wall construction period optimization method according to claim 3, characterized in that: When a circular rotary drill is used for trenching construction, a double-wheel slotting machine is used to mill the trench a second time after the rotary drill has bored the hole, expanding the hole into a rectangular cross-section. When the trench sections are split, they are first divided according to the minimum operating width of the double-wheel slotting machine, and then the boring point of the circular rotary drill is set.

6. The underground continuous wall construction period optimization method according to claim 1, characterized in that: In the secondary design step, the statistical table of the trench sections of underground continuous walls of various structural forms includes the supporting structure of the underground continuous wall, the total number of trench sections after the underground continuous walls of various supporting structures are disassembled, and the trench section thickness and number of trench sections of underground continuous walls of different structural forms.

7. The underground continuous wall construction period optimization method according to claim 1, characterized in that: In the trenching efficiency statistics step, the method for obtaining the construction efficiency of each alternative trenching machine combination in different trench sections includes: calculating the estimated trenching time in different soil layers according to the average soil thickness of each soil layer and the average trenching efficiency of the trenching equipment in different soil layers under different structural forms of the trench section, and combining the mobile equipment positioning time, steel cage installation time, trench cleaning time, and concrete pouring time to obtain the complete operation efficiency of underground continuous walls in various structural forms.

8. The method for optimizing the construction period of underground continuous wall according to claim 1, characterized in that: In the construction period analysis step, under each grooving machine combination, the construction period of the grooving process is compared with the steel cage processing process, and the process that takes up a longer construction period is selected as the key process.

9. The underground continuous wall construction period optimization method according to claim 1, characterized in that: In the construction planning steps, the supporting structure forms of the underground continuous wall include W-shaped underground continuous wall, I-shaped underground continuous wall, rectangular frame underground continuous wall and I-shaped underground continuous wall.

10. The underground continuous wall construction period optimization method according to claim 1, characterized in that: In the secondary design step, the split slot sections of the underground continuous wall include T-shaped slot sections, L-shaped slot sections, cross-shaped slot sections, I-shaped slot sections, Z-shaped slot sections, and [-shaped slot sections.

Citation Information

Patent Citations

  • Construction methods for trenching of diaphragm walls under complex geological conditions

    CN110984132B

Cited By

  • Method for calculating grooving efficiency of diaphragm wall of ultra-deep circular vertical shaft in complex stratum with soft upper part and hard lower part

    CN120672002A