Construction method for foundation pit support of section steel cement soil mixing pile

By adopting repeated stirring and re-spraying grouting and cold seam repairing pile treatment in the foundation pit support of cement soil mixing piles, combined with steel positioning mold and extraction and recycling methods, the insertion and extraction accuracy and cold seam treatment of steel are solved. The problem has achieved improvements in construction quality and safety, while reducing costs.

CN119083424APending Publication Date: 2024-12-06CHINA MCC5 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411315289.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

When the existing technology uses steel cement soil mixing piles for foundation pit support in softer bottom layers, there are problems such as the accuracy of the insertion plane and vertical position of the steel, the extraction and recycling, and the treatment of cold joints in construction, which is difficult to ensure construction quality and safety. High cost.

Method used

The three-axis cement mixing pile is used to inject cement slurry during drilling and lifting. The grouting is repeatedly stirred and grouted at the bottom of the pile through repeated stirring and spraying. The steel surface is painted with abrasive reducer and positioning mold to fix the insertion steel to ensure the insertion accuracy. , and fill in the piles at the cold joints. When the steel is pulled out, use fixtures and jacks for recycling, and use cement slurry or stone chips to fill in the gaps.

Benefits of technology

It improves construction accuracy and quality, ensures the safety of foundation pits, reduces construction costs, and has a high material recycling rate, simplifies processes and facilitates on-site operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083424A_ABST
    Figure CN119083424A_ABST
Patent Text Reader

Abstract

The invention provides a construction method of a foundation pit support of a section steel cement soil mixing pile. The construction method mainly comprises the steps of construction of the cement soil mixing pile, insertion of the section steel, pulling out of the section steel and the like. The cement mixing pile construction sequentially comprises the steps of cement mixing proportion design, cement paste manufacturing, drilling and stirring, cleaning and shifting and construction cold joint treatment. A re-stirring and re-spraying mode is adopted in the overall length of the fender post, and stirring and grouting are repeated at the bottom of the post; and the construction cold joints are treated by complementarily stirring plain piles on the outer sides of the peripheral guard piles at the cold joints after the peripheral guard piles reach certain strength. And profile steel insertion is corrected through positioning profile steel and a plumb bob, so that the construction precision of the profile steel is guaranteed. And the ring beam is used as a counter-force beam to pull and recover the profile steel. The overall construction process is simple, the construction quality and the safety of the foundation pit can be guaranteed, and meanwhile the manufacturing cost is not increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of municipal engineering foundation pit support, in particular to a construction method for steel-cement-soil mixing pile foundation pit support. Background Art

[0002] The supporting foundation pit support projects involved in the construction of underground projects in urban roads are numerous and complex, such as pipeline networks and pipe corridors. These main structures are often buried at a great depth below the ground, and the geological conditions at the locations where these main structures are buried are relatively complex. The depth of the foundation pit excavated during the construction process is relatively deep, and the support of the foundation pit becomes the key to the smooth progress of the project. The quality of the foundation pit support affects the construction progress, quality and safety of the project, and is also a key factor affecting the cost of the project. The utility model patent with application number CN202122667257.0 discloses two rows of parallel steel-cement soil mixing walls, each row of which is provided with a number of steel-cement soil mixing piles arranged in sequence, and the steel-cement soil mixing piles of the two rows of steel-cement soil mixing walls are arranged opposite to each other in pairs. The foundation pit support system has support and water-stopping functions, good integrity and stability, and a small amount of work. The utility model patent with application number CN201922132686.0 discloses a steel-cement soil mixing pile retaining structure system, including a mixing pile, a pit in a pit and a cement wall. A steel-shaped mixing pile is laid inside the mixing pile, and a crown beam is fixed at one end. A reinforced mixing pile is provided on the mixing pile. A reinforced steel is provided inside the reinforced mixing pile. The steel and reinforced steel are coated with foam panels. An underground structure is provided at one end of the mixing pile, and the mixing pile and the underground structure are connected by a force transmission belt. A shotcrete slope protection is provided at one end of the reinforced mixing pile. Cement slurry is provided in the cement wall through a grouting pipe. This scheme greatly improves the bearing capacity of the retaining wall by closely arranged steel and reinforced steel, thereby eliminating the inclined anchor outside the pit and the internal support inside the pit, reducing the impact of the inclined anchor on the surrounding land of the foundation pit, reducing the waste of labor, materials and time, and injecting cement slurry outside the retaining wall to maintain the stability of the soil outside the pit and reduce the risk of water leakage in the pit.

[0003] However, the prior art mostly involves the improvement of the support structure, and no improvement approach has been given to the specific construction method of the steel-cement-soil mixing pile foundation pit support with low cost and guaranteed quality. Summary of the invention

[0004] In view of the above-mentioned defects in the prior art, the present invention provides a construction method for foundation pit support using steel-cement-soil mixing piles, which mainly solves the problems of steel insertion plane, vertical position accuracy, steel pulling and recycling, and cold joint treatment during construction of steel-cement-soil mixing piles when using steel-cement-soil mixing piles for foundation pit support construction on a relatively soft bottom layer. It ensures the construction quality and safety of the foundation pit without increasing the construction cost and simplifies the construction.

[0005] To achieve the above object, the present invention provides a construction method for steel-cement-soil mixing pile foundation pit support, which is characterized by comprising the following steps:

[0006] Step S1, cement soil mixing pile construction, including cement soil mix ratio design, cement slurry production, drilling and mixing, cleaning and displacement, and construction cold joint treatment in sequence: the three-axis cement mixing pile is injected with cement slurry during the drilling and lifting process, and the grouting drilling speed is controlled at 0.5-1m / min, and the lifting speed is controlled at 1-2m / min; during grouting, two grouting pumps and two pipelines are mixed and injected through the same Y-type joint port, and the grouting port pressure is controlled at 0.8-1.5Mpa; the full length of the retaining pile is mixed and sprayed, and the mixing and grouting are repeated at the bottom of the pile; the treatment of the construction cold joint adopts the method of mixing the outer side of the outer retaining pile at the cold joint after reaching a certain strength; the overlap thickness of the plain pile and the retaining pile is 8-12cm;

[0007] Step S2, inserting steel, includes the following sub-steps:

[0008] Step S21: Before using the steel, apply antifriction agent on the surface of the steel, wrap the steel part buried in the beam with a foam plastic sheet, and then open a central circular hole 25 cm away from the top of the steel;

[0009] Step S22, placing the level on the positioning steel, welding the hanging bars on the outer sides of the two webs of the steel according to the height difference between the positioning steel and the top elevation of the steel, and controlling the error; installing the hanging device and the fixing hook, and then lifting the steel with a crane;

[0010] Step S23, setting a steel positioning mold on the groove positioning steel to fix the plane position of the inserted steel; then aligning the bottom center of the steel with the pile center and slowly inserting it vertically into the cement soil mixing pile body along the positioning mold;

[0011] Step S24, after the steel is inserted to the designed depth, the channel steel is passed through the hanging rod and placed on the positioning steel. After the cement soil mixing pile reaches a certain hardening time, the hanging rod and the groove positioning steel are removed;

[0012] Step S3, pulling out the steel: when the corresponding main structure in the foundation pit is completed and the foundation pit is backfilled, the steel in the cement soil mixing pile is pulled out and reused; a clamp and a jack are used, and the ring beam is used as a reaction beam to pull out and recover the steel; when the steel is pulled out, the pile is pulled out while the gap is backfilled with cement slurry or stone chips.

[0013] The grouting method and cold joint treatment method of the cement-soil mixing piles in the construction method are easy to implement and can ensure quality, and the steel positioning measures and pull-out treatment methods are appropriate; the overall construction process is simple, which can ensure the construction quality and the safety of the foundation pit without increasing the cost.

[0014] Furthermore, in the cement-soil mix ratio of the cement slurry, the cement parameter is not less than 25%, and the unconfined compressive strength after 28 days is not less than 0.5Mpa; the cement slurry is used no more than 2 hours after preparation. The design of the cement-soil mix ratio in this limitation ensures the strength of the cement-soil, reduces the replacement rate of the soil, reduces the disturbance effect of the environment, and at the same time ensures that the cement-soil and the inserted steel have good gripping force, and the cement-soil and steel produce good composite force.

[0015] Furthermore, in step S1, the construction interval of adjacent mixing piles in overlapping construction is no more than 6 hours, ensuring that the construction is completed before the initial setting time of cement.

[0016] Furthermore, in the step S1, within the peat soil layer, cement slurry is used to mix and improve the peat soil, so as to ensure that the soil layer has a certain strength after being treated so as to better bond with the steel section.

[0017] Furthermore, in step S1, after the three-axis mixing pile is drilled to the designed embedding depth, it continues to be drilled to a depth of not less than 50 cm to ensure the quality of the pile body at the bottom of the steel section.

[0018] Furthermore, before the implementation of step S3, two reinforcing plates are welded on both sides of the central circular hole at the top of the steel section, and the central openings thereof are aligned with the central circular hole on the steel section to ensure that the steel section is not easily deformed when being pulled out.

[0019] Furthermore, in step S2, if the steel section cannot reach the designed elevation after being inserted, the steel section is repeatedly lifted and inserted until it reaches the designed elevation.

[0020] Furthermore, in step S2, the left and right error of the steel section insertion is no more than 30 mm, it is inserted close to the foundation pit side, the verticality deviation is no more than 1 / 150, and the bottom elevation error is no more than 200 mm, so as to further ensure the quality of the steel section construction.

[0021] Compared with the prior art, the present invention has the following beneficial effects:

[0022] (1) The present invention is suitable for the construction of steel-cement-soil mixing pile foundation pit support, and has the characteristics of simple construction, low cost and strong applicability.

[0023] (2) The present invention can improve construction accuracy, ensure quality and efficiency, and ensure safety.

[0024] (3) The construction process of the present invention is simple, easy for on-site workers to understand and operate, and has a high material recycling rate. It can improve construction quality and efficiency while ensuring safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] The present invention and its features, appearance and advantages will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings. The same reference numerals indicate the same parts in all the drawings. The drawings are not drawn completely to scale, and emphasis is placed on illustrating the subject matter of the present invention.

[0026] Figure 1 It is a construction flow chart of medium-sized steel cement soil mixing pile foundation pit support in one embodiment of the present invention;

[0027] Figure 2 It is an axial cross-sectional view of a medium-sized steel-cement-soil mixing pile in one embodiment of the present invention;

[0028] Figure 3 It is a plan view of a medium-sized steel cement soil mixing pile in one embodiment of the present invention;

[0029] Figure 4 It is a schematic diagram of the cold joint treatment structure during the construction process of cement soil mixing piles in one embodiment of the present invention;

[0030] Figure 5 It is a layout and opening diagram of the top surface reinforcement plate of the section steel in one embodiment of the present invention;

[0031] Among them, 1. Guard piles; 2. Steel sections; 3. Cold joints; 4. Plain piles; 5. Crown beams; 6. Reinforcement plates; 7. Steel purlins; 8. Steel supports; 9. Drainage ditches; 10. Backfill with plain concrete; 21. Center circular holes. DETAILED DESCRIPTION

[0032] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. It should be understood that all of these exemplary embodiments described are only partial embodiments and examples of the present invention, rather than all of them. On the contrary, these exemplary embodiments are provided so that those skilled in the art can more thoroughly understand the present disclosure and can more completely convey the technical content of the present disclosure to those skilled in the art.

[0033] The execution order of actions, steps, etc. in the apparatus and method shown in the claims, the specification and the drawings may be implemented in any order unless otherwise expressly specified and as long as the output of the previous process is not used in the subsequent process. The use of the words "first", "second", "third", etc. for the convenience of description does not mean that the order must be followed.

[0034] Example

[0035] See also Figure 1 This embodiment provides a construction method for steel-cement-soil mixing pile foundation pit support, comprising the following steps:

[0036] S1, cement mixing pile construction, S2, steel section insertion, S3, steel section removal after construction completion.

[0037] More specifically, step S1 includes:

[0038] (1) Cement-soil mix ratio: The cement-soil mix ratio is designed before the construction of cement-soil mixing piles. The design of the cement-soil mix ratio ensures the strength of the cement-soil, reduces the replacement rate of the soil, reduces the impact of environmental disturbance, and at the same time ensures that the cement-soil and the inserted steel have good grip and that the cement-soil and steel produce good composite force. In the cement-soil mix ratio, the cement parameter is not less than 25%, and the unconfined compressive strength after 28 days is not less than 0.5Mpa.

[0039] (2) Preparation of cement slurry: The cement slurry should be prepared within 2 hours and the interval between adjacent mixing piles should be no more than 10 hours. During grouting, the slurry should be mixed and injected through two grouting pumps and two pipelines with the same Y-type joint. The pressure at the grouting port should be controlled at 0.8-1.5 MPa.

[0040] (3) Drilling and mixing: Cement slurry should be injected into the three-axis cement mixing pile during the sinking and lifting process, and the sinking and lifting speeds should be strictly controlled. The spraying sinking speed should be controlled at 0.5-1m / min, and the lifting speed should be controlled at 1-2m / min. Figure 2 and Figure 3 The retaining pile 1 (cement-soil mixing pile inserted into the steel section 2) is mixed and sprayed over the entire length, with special attention paid to the peat soil layer, where the peat soil is improved by mixing the peat soil. Repeat the mixing and grouting at the bottom of the pile, stay for about 1 minute, and make original records. After the three-axis mixing pile is drilled to the designed embedding depth, it is drilled at least 50cm deeper to ensure the quality of the pile body at the bottom of the steel section.

[0041] (4) Cleaning and relocation: Add an appropriate amount of clean water to the aggregate hopper, start the mortar pump to clean the pipelines and all machinery, and then move to the next pile construction.

[0042] (5) Construction cold joint treatment: see Figure 4 If a cold joint 3 appears during the construction process, the outer protective piles at the cold joint are strengthened to a certain extent before the outer plain piles 4 are added to prevent eccentric drilling and achieve reinforcement effect. The overlap thickness of the plain piles and the surrounding protective piles is 8 to 12 cm, preferably about 10 cm.

[0043] More specifically, step S2 includes:

[0044] S21. Apply anti-friction agent to the surface of the steel section where it is inserted into the cement soil: remove dirt and rust from the surface of the steel section. The anti-friction agent must be heated with an electric heating rod until it is completely melted, and stirred with a stirring rod until the thickness is even before it can be applied to the steel section. Otherwise, the coating will be uneven and easy to peel off. If the surface of the steel section is damp, first wipe it dry with a rag and then apply the anti-friction agent, otherwise the anti-friction agent will easily peel off. After the coating is applied to the surface of the steel section, if cracks or peeling of the coating are found, it must be scraped off and the anti-friction agent must be reapplied. When casting the crown beam 5, the steel section buried in the beam is wrapped with a 10mm thick foam plastic sheet to isolate the steel section from the concrete, so as to facilitate the removal of the steel section.

[0045] Insertion of steel 2: After the construction of the three-axis cement mixing pile is completed, the steel surface is coated with anti-friction agent, and the crane is immediately in place to prepare for the placement of steel 2. Before insertion, its flatness and joint weld quality should be checked. Figure 5 Before the steel is used, a central circular hole 21 is opened 25cm from the top of the steel, with a diameter of about 8cm, and two reinforcing plates 6 with a thickness of 2cm are welded on both sides of the steel. The specifications are 400mm×400mm, and the central opening is aligned with the hole on the steel. If the steel is temporarily transferred, the reinforcing plates 6 can be welded before the steel is pulled.

[0046] S22. According to the height control point provided by the designer, use the level to guide the positioning steel (not shown in the figure), and according to the height difference between the positioning steel and the top elevation of the steel, weld the hanging bars on the outside of the two webs of the steel to control the error. Install the hanging tools and fixed hooks, then use the crane to lift the steel and use a plumb bob to check its verticality.

[0047] S23. Set a steel positioning mold on the groove positioning steel to fix the inserted steel plane position. The steel positioning mold must be firm and horizontal. Then align the bottom center of steel 2 with the center of the pile position and slowly insert it vertically into the cement soil mixing pile body along the positioning steel. Use a plumb bob to control the verticality.

[0048] S24, after the steel 2 is inserted to the designed depth, the channel steel is passed through the hanging rod to place it on the positioning steel. After the cement soil mixing pile reaches a certain hardening time, the hanging rod and the groove positioning steel are removed. If the steel cannot reach the designed elevation, it is repeatedly lifted and inserted to reach the designed elevation. During this process, the plumb line is always used to track and control the verticality of the steel. The left and right error of the steel insertion shall not be greater than 30mm. It is advisable to insert it close to the foundation pit. The verticality deviation shall not be greater than 1 / 150, and the bottom elevation error shall not be greater than 200mm.

[0049] See also Figure 2After the construction of the steel-cement mixing piles on both sides of the foundation pit is completed and reaches the deadline, the foundation pit soil layer is excavated to the crown beam height position, and the concrete crown beam and transverse support are set; after the crown beam concrete age reaches the strength, continue to excavate to 30cm below the second steel support 8. First, weld the steel support 8 on the steel on both sides of the foundation pit, and use L80*8 angle steel to set the steel purlin 7; then install 7 double rows of 45C I-beams on the angle steel, and use 32# steel bars to set the lifting ring on the top of the I-beam; then continue to excavate the next layer until the bottom of the foundation pit is excavated, and set drainage ditches 9 with a cross-sectional size of 300*300 on both sides of the foundation pit; carry out the construction of the pipe gallery bottom slab cushion layer and the bottom slab and side wall construction. After the side wall concrete reaches the age, set and pour 1m high C20 plain concrete on the side wall and the foundation pit as backfill plain concrete 10.

[0050] More specifically, step S3 includes:

[0051] After the corresponding main structure process in the foundation pit is completed and the foundation pit is backfilled, the steel 2 in the cement soil mixing pile is pulled out and reused. Special clamps and jacks are used to use the ring beam as the reaction beam to pull out and recover the steel 2. When the steel is pulled out, the pile is pulled out while the gap is backfilled with cement slurry or stone chips.

[0052] From the above construction process, it can be seen that the construction method of the present invention is suitable for foundation pit support construction using steel-cement soil mixing piles in a relatively soft base layer. The grouting method and cold joint treatment method of the cement soil mixing piles are easy to implement and can ensure quality. The steel positioning measures and pull-out treatment methods are appropriate. The overall construction process is simple, which can not only ensure the construction quality and the safety of the foundation pit, but also does not increase the cost.

[0053] In summary, the present application provides a construction method for foundation pit support of steel-cement soil mixing piles, which mainly includes the steps of cement soil mixing pile construction, steel section insertion and steel section extraction. The cement soil mixing pile construction includes cement soil mix ratio design, cement slurry production, drilling and mixing, cleaning and displacement, and construction cold joint treatment in sequence. The full length of the retaining piles is mixed and sprayed repeatedly, and the grouting is repeatedly mixed and sprayed at the bottom of the pile; the treatment of the cold joints is to add plain piles on the outside after the outer retaining piles at the cold joints reach a certain strength. The insertion of the steel section is corrected by positioning the steel section and the plumb bob to ensure the construction accuracy of the steel section. The ring beam is used as the reaction beam to pull out and recover the steel section. The overall construction process of the present invention is simple, which can not only ensure the construction quality and the safety of the foundation pit, but also does not increase the cost.

[0054] In the description of this application, the terms "upper", "lower", "top", "bottom", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present invention.

[0055] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.

Claims

1. A construction method for steel-cement soil mixing pile foundation pit support, characterized in that: The following steps are involved: Step S1, cement soil mixing pile construction, including cement soil mix ratio design, cement slurry production, drilling and mixing, cleaning and displacement, and construction cold joint treatment in sequence: the three-axis cement mixing pile is injected with cement slurry during the drilling and lifting process, and the grouting drilling speed is controlled at 0.5-1m / min, and the lifting speed is controlled at 1-2m / min; during grouting, two grouting pumps and two pipelines are mixed and injected through the same Y-type joint port, and the grouting port pressure is controlled at 0.8-1.5Mpa; the full length of the retaining pile is mixed and sprayed, and the mixing and grouting are repeated at the bottom of the pile; the treatment of the construction cold joint adopts the method of mixing the outer side of the outer retaining pile at the cold joint after reaching a certain strength; the overlap thickness of the plain pile and the retaining pile is 8-12cm; Step S2, inserting steel, includes the following sub-steps: Step S21: Before using the steel, apply antifriction agent on the surface of the steel, wrap the steel part buried in the beam with a foam plastic sheet, and then open a central circular hole 25 cm away from the top of the steel; Step S22, placing the level on the positioning steel, welding the hanging bars on the outer sides of the two webs of the steel according to the height difference between the positioning steel and the top elevation of the steel, and controlling the error; installing the hanging device and the fixing hook, and then lifting the steel with a crane; Step S23, setting a steel positioning mold on the groove positioning steel to fix the plane position of the inserted steel; then aligning the bottom center of the steel with the pile center and slowly inserting it vertically into the cement soil mixing pile body along the positioning mold; Step S24, after the steel is inserted to the designed depth, the channel steel is passed through the hanging rod and placed on the positioning steel. After the cement soil mixing pile reaches a certain hardening time, the hanging rod and the groove positioning steel are removed; Step S3, pulling out the steel: when the corresponding main structure in the foundation pit is completed and the foundation pit is backfilled, the steel in the cement soil mixing pile is pulled out and reused; a clamp and a jack are used, and the ring beam is used as a reaction beam to pull out and recover the steel; when the steel is pulled out, the pile is pulled out while the gap is backfilled with cement slurry or stone chips.

2. The construction method of steel-cement-soil mixing pile foundation pit support according to claim 1 is characterized in that: In the cement-soil mix ratio of the cement slurry, the cement parameter is not less than 25%, and the unconfined compressive strength after 28 days is not less than 0.5Mpa; the cement slurry is used within 2 hours after being prepared.

3. The construction method of steel-cement-soil mixing pile foundation pit support according to claim 2 is characterized in that: In step S1, the construction interval of adjacent mixing piles in overlapping construction shall not exceed 10 hours.

4. The construction method of steel-cement-soil mixing pile foundation pit support according to claim 1 is characterized in that: In the step S1, cement slurry is used to mix and improve the peat soil in the peat soil layer.

5. The construction method of steel-cement-soil mixing pile foundation pit support according to claim 1 is characterized in that: In step S1, after the three-axis mixing pile is drilled to the designed embedding depth, it continues to drill to a depth of not less than 50 cm.

6. The construction method of steel-cement-soil mixing pile foundation pit support according to claim 1 is characterized in that: Before the step S3 is implemented, two reinforcing plates are welded on both sides of the central circular hole on the top of the steel section, and the central opening of the reinforcing plates is aligned with the central circular hole on the steel section.

7. The construction method of steel-cement-soil mixing pile foundation pit support according to claim 1 is characterized in that: In step S2, if the steel section cannot reach the designed elevation, the steel section is repeatedly lifted and inserted until it reaches the designed elevation.

8. The construction method of steel-cement-soil mixing pile foundation pit support according to claim 1 is characterized in that: In step S2, the left and right error of the steel section insertion is no more than 30 mm, and it is inserted close to the foundation pit side, with a verticality deviation no more than 1 / 150 and a bottom elevation error no more than 200 mm.