Construction method of high and large cornice aluminum plate curtain wall
通过塔吊和吊篮组件安装骨架和铝扣板组件的方法,解决了高大挑檐铝板幕墙施工成本和周期高的问题,实现了不依赖脚手架的快速施工,降低成本并保证了施工效率和美观性 .
Patent Information
- Application Number
- CN202411182104.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-12-06
AI Technical Summary
The construction cost and cycle of tall eaves aluminum panel curtain walls are relatively high, and the existing technology is difficult to effectively reduce.
A construction method that does not rely on scaffolding is adopted. The skeleton and hanging basket assembly are installed through tower cranes, and the aluminum buckle plate assembly is installed using wire ropes and hoists. Combined with the self-controlled lifting basket and guide wheel, the rapid fixing and connection of the skeleton and aluminum buckle plate assembly is achieved. .
It reduces construction costs, saves construction cycle, improves construction efficiency, and ensures the appearance and stability of the aluminum buckle assembly through U-shaped buckle strips and sealant.
Smart Images

Figure CN119083735A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of aluminum plate curtain wall construction, and in particular to a construction method of a tall overhanging aluminum plate curtain wall. Background Art
[0002] Aluminum curtain wall is a component used for exterior decoration of buildings, including embedded panels, panels, frames and corners. The embedded panels are connected to the building through bolts; the corners are used to connect the panels; the frames are used to connect the panels and embedded panels. The overhanging aluminum curtain wall is an aluminum curtain wall that extends outward from the building. There are two cases of overhanging aluminum curtain wall: case one, the building itself has an overhanging concrete structure, and the aluminum curtain wall covers the overhanging structure; case two, the building itself does not have an overhanging concrete structure, but adds an overhanging shape through the aluminum curtain wall; usually, the frame also has a certain inclination angle. The commonly used overhanging aluminum curtain wall is the second case. The construction of the overhanging aluminum curtain wall is carried out by building scaffolding. However, for some tall overhanging aluminum curtain walls with large overhanging dimensions, the erection and dismantling of the scaffolding requires a lot of work, which increases the construction cost and prolongs the construction period. The prior art urgently needs a construction method that can reduce the construction cost and construction period of tall overhanging aluminum curtain walls. Summary of the invention
[0003] The purpose of the present invention is to solve the above problems and provide a construction method for a tall overhanging eaves aluminum plate curtain wall.
[0004] The technical solution of the present invention is: a construction method of a tall overhanging eaves aluminum plate curtain wall, comprising the following steps: ① Preliminary installation of the frame The skeleton includes a right-angled triangle main keel and a horizontal secondary keel; the main keel is hoisted by a tower crane so that the right-angle side of the main keel abuts against the outer wall of the building; an embedded plate is pre-buried on the side of the top of the building; the main keel is adjusted so that the main keel is in a vertical state and the right-angle side of the main keel abuts against the embedded plate; the embedded plate close to the top of the building is fixedly connected to the right-angle side of the main keel by welding, so as to realize the preliminary installation of the skeleton; ②Install the hanging basket assembly A hanging basket assembly is installed on the top of the building; the hanging basket assembly includes a self-controlled lifting hanging basket with steel wire ropes A extending upward from both ends, a lifting frame, a load A, and a load B; the top of the lifting frame is connected to a guide wheel A for vertical rotation; the lifting frame is hoisted to the top of the building by a tower crane; a part of the lifting frame extends out of the edge of the top of the building, and the other part extends into the interior of the top of the building; the extended end of the lifting frame is connected to a guide wheel B for vertical rotation; the load A is hoisted to the top of the building by a tower crane; the load A is connected to the part of the lifting frame extending into the interior of the top of the building; then the end of the steel wire rope A is fixed to the lifting frame; the fixed end of the steel wire rope A is close to the edge of the top of the building; so Use an automatic lifting basket to transport construction workers to the lower end of the right-angled side of the main keel; construction workers fix the lower end of the main keel to the embedded plate by welding; use a tower crane to lift the secondary frame to the extended end of the main frame; construction workers connect the main frame and the secondary frame by welding; install a vertically rotating guide wheel B at the position where the secondary frame is opposite to the guide wheel A; use a tower crane to lift load B, winch A and winch B to the top of the building; winch A and winch B need to fall behind the hoisting frame when they fall to the top of the building, and be located symmetrically with respect to the hoisting frame; when load B falls to the top of the building, it is directly connected with winch A and winch B; ③Assemble aluminum gusset components on the ground The aluminum gusset assembly includes a grid frame and an aluminum gusset; a welded fence is provided at one end of the grid frame, a plurality of arrayed grids are provided in the middle, and a plurality of extended welded columns are provided at the other end; the aluminum gusset is buckled into the grid and fixed to the grid frame by automatic screws; a front hanging ear A and a rear hanging ear B are welded in the middle of the grid frame; ④Install the aluminum gusset assembly under the eaves Winch A retracts and releases wire rope B; Winch B retracts and releases wire rope C; Wire rope B is wound around a guide wheel A and guide wheel B on the secondary keel and then connected to lifting ear A; Wire rope C is wound around another guide wheel B and guide wheel C on the horizontal tripod and then connected to lifting ear B; Winch A is started before Winch B; After Winch A is started for a period of time, the inclination angle of the aluminum gusset assembly relative to the horizontal plane is greater than the inclination angle of the hypotenuse of the main frame relative to the horizontal plane, and then Winch B is started, and the rope retraction speed of Winch B is controlled to be equal to that of Winch A; the aluminum gusset assembly is lifted vertically at the fixed inclination angle; when the lifting ear A rises to a height that exceeds the self-controlled lifting height, the lifting ear A is lifted vertically. After the basket is lowered to a certain height, the winch A is temporarily stopped, and the winch B continues to reel in the rope; the rear end of the grid frame deflects toward the building, so that the welding column is close to the automatic lifting basket; the construction workers on the automatic lifting basket pull the rear end of the grid frame, so that the end of the welding column is against the embedded plate of the building; then, the winch A and the winch B cooperate with each other to reel in the rope, so that the grid frame is parallel to the hypotenuse of the main frame; then the winch A and the winch B lift the grid frame at the same speed; the welding column is maintained against the embedded plate until the welding fence also rests on the secondary keel, and the upper and lower ends of the grid frame are welded to connect the aluminum gusset plate assembly with the frame; ⑤ After removing the hanging basket assembly, install the corresponding aluminum gusset assembly on the top of the frame. After removing the hanging basket assembly, use the tower crane to transport the aluminum gusset assembly corresponding to the top of the frame to the corresponding position of the building; connect the top of the frame with the corresponding aluminum gusset assembly by welding.
[0005] Preferably, a concrete wall is provided on the top of the building; the lifting frame in step ② also includes an inner high leg matching the concrete wall; the load A is installed on the inner high leg; the inner high leg enables the lifting frame to adapt to the use environment of the concrete wall.
[0006] Preferably, there is a material transport step before step ①; the main keel, secondary keel and lifting frame required for step ① are transported to the site to make preparations in advance; the main keel and secondary keel also need to be rust-proofed and painted to ensure the beauty of the surface.
[0007] Preferably, measurement and laying out are required before step ①; laying out is performed on the top of the building to determine the installation positions of the main keel and the lifting frame, and to provide a reference for the installation of the main keel and the lifting frame.
[0008] Preferably, step ③ also requires applying sealant and cleaning the board surface; the sealant is applied to the periphery of the aluminum gusset plate after being fixed to the grid frame to reduce the gap between adjacent aluminum gusset plates; cleaning the board surface is the treatment of the outer surface of the aluminum gusset plate after applying the sealant to ensure surface smoothness.
[0009] Furthermore, the aluminum gusset plate assembly also includes a connecting extension plate, a U-shaped buckle strip, and a mounting piece; the connecting extension plate is connected to the edge of the aluminum gusset plate by rivets; the mounting piece includes a connected mounting strip and a mounting block; the U-shaped buckle strip is fastened to the rib of the grid frame; the U-shaped buckle strip is connected to the rib of the grid frame by self-tapping screws; the self-tapping screws pass through the mounting strip; the automatic screws for installing the aluminum gusset plate pass through the connecting extension plate and the mounting block; sealant is filled in the gap between the U-shaped buckle strip and the aluminum gusset plate; the U-shaped buckle strip fills the gap between adjacent aluminum gusset plates to ensure the beautiful appearance of the aluminum gusset plate assembly; the connecting extension plate and the mounting piece realize the connection between the U-shaped buckle strip and the aluminum gusset plate.
[0010] Preferably, the welding columns are arranged obliquely relative to the grid frame to stabilize the connection between the grid frame and the building.
[0011] Preferably, there are two symmetrically arranged lifting ears A and two symmetrically arranged lifting ears B; the symmetrical arrangement planes of the lifting ears A and the symmetrical arrangement planes of the lifting ears B coincide with each other; the two lifting ears A are connected through the steel wire rope D; the two lifting ears B are connected through the steel wire rope E; the end of the steel wire rope B is connected to the midpoint of the steel wire rope D; the end of the steel wire rope C is connected to the midpoint of the steel wire rope E; the lifting stability of the aluminum gusset plate assembly is greatly increased.
[0012] Preferably, the lifting frame includes a horizontal tripod at the front end, a horizontal frame in the middle, and a vertical tripod; the horizontal tripod is an isosceles triangle; the bottom of the vertical tripod is connected to the horizontal tripod and the horizontal frame; a guide wheel assembly A is provided at the top of the vertical tripod; the guide wheel assembly A includes two guide wheels A connected vertically for rotation; a guide wheel assembly B is installed at the top of the horizontal tripod; the guide wheel assembly B includes a guide wheel B connected vertically for rotation.
[0013] Furthermore, the lifting frame also includes a load-bearing beam; the load-bearing beam and the secondary keel are both horizontally arranged steel with wing plates; the guide wheel assembly B includes a guide wheel seat; the guide wheel seat includes a connected vertical plate and a horizontal plate; there are two guide wheels B, which are respectively installed on the vertical plate and the horizontal plate; the end of the horizontal plate is provided with a flange corresponding to the wing plate; the guide wheel assembly B can be detachably installed on the load-bearing beam or the secondary keel, which is convenient for replacement and maintenance. Furthermore, the load-bearing beam is made of channel steel; the load-bearing beam is integrated with the lifting frame and can be reused, so the channel steel has a simpler structure; the secondary keel is a part of the frame and is also subject to the limitations of the frame; considering the structural strength of the frame; the secondary keel is made of I-beam.
[0014] Preferably, the horizontal tripod is provided with a centerline beam; the vertical tripod is provided with a high column; the centerline beam increases the structural strength of the horizontal tripod; the high column increases the structural strength of the vertical tripod.
[0015] The beneficial effects of the present invention are as follows: the construction method of the tall overhanging eaves aluminum plate curtain wall of the present invention has the following advantages: (1) The present invention provides a construction method that does not rely on scaffolding, reduces construction costs, and saves construction period. The construction method relies on two lifting points formed by steel wire rope B and steel wire rope C on the aluminum gusset assembly, so that the rear end of the aluminum gusset assembly is tilted toward the automatic lifting basket, which is beneficial to the construction personnel on the automatic lifting basket to move the rear end of the aluminum gusset assembly; the construction personnel on the automatic lifting basket operate the rear end of the aluminum gusset assembly so that the rear end of the aluminum gusset assembly rests on the embedded plate on the outer wall of the building; steel wire rope B and steel wire rope C cooperate with each other to make the aluminum gusset assembly buckle on the skeleton from bottom to top, which is convenient for construction personnel to construct; (2) The present invention also requires measurement and setting out before step ①; setting out the lines on the top of the building to determine the installation positions of the main keel and the hanging frame, and providing a reference for the installation of the main keel and the hanging frame; (3) The U-shaped buckle strip of the present invention fills the gap between adjacent aluminum buckle plates, ensuring the beautiful appearance of the aluminum buckle plate assembly; the U-shaped buckle strip is connected to the aluminum buckle plate by connecting the extension plate and the mounting piece. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a construction schematic diagram of the construction method of the tall overhanging eaves aluminum plate curtain wall of the present invention; Figure 2 yes Figure 1 I magnified view; Figure 3 yes Figure 1 II enlarged view; Figure 4 yes Figure 1 III magnified view; Figure 5 yes Figure 1 Side view of Figure 6 is a three-dimensional diagram of guide wheel assembly B; Figure 7 It is a three-dimensional diagram of a single-section aluminum gusset assembly; Figure 8 yes Figure 7 Schematic diagram of connection nodes in ; In the figure: 0. Building, 01. Concrete fence, 1. Frame, 11. Main keel, 12. Secondary keel, 21. Automatic lifting basket, 22. Lifting frame, 221. Horizontal tripod, 221. Centerline beam, 222. Horizontal frame, 223. Vertical tripod, 2231. High column, 24. Winch A, 225. Winch B, 226. Inner high leg, 227. Bearing beam, 23. Load A, 24. Load B, 31. Wire rope A, 32. Wire rope B, 33. Wire rope C , 34. Steel wire rope D, 35. Steel wire rope E, 41. Guide wheel assembly A, 411. Guide wheel A, 42. Guide wheel assembly B, 421. Guide wheel B, 422. Guide wheel seat, 4221. Vertical plate, 4222. Horizontal plate, 42221. Flanging, 5. Aluminum gusset plate assembly, 51. Grid frame, 511. Welded fence, 512. Grid, 513. Welded column, 514. Lifting ear A, 515. Lifting ear B, 52. Aluminum gusset plate, 53. Sealant, 54. Connecting extension plate, 55. U-shaped buckle strip, 56. Mounting piece, 561. Mounting strip, 562. Mounting block. DETAILED DESCRIPTION
[0017] Example 1: See Figure 1-8 A construction method for a tall overhanging aluminum curtain wall comprises the following steps: ①Install the frame 1 The skeleton 1 includes a right-angled triangle main keel 11 and a horizontal secondary keel 12; the main keel 11 is hoisted by a tower crane so that the right-angle side of the main keel 11 abuts against the outer wall of the building 0; an embedded plate is pre-buried on the top side of the building 0; the main keel 11 is adjusted so that the main keel 11 is in a vertical state and the right-angle side of the main keel 11 abuts against the embedded plate; the embedded plate close to the top of the building 0 is fixedly connected to the right-angle side of the main keel 11 by welding, so as to realize the preliminary installation of the skeleton 1; ②Install the hanging basket assembly A hanging basket assembly is installed on the top of the building 0; the hanging basket assembly includes an automatic lifting hanging basket 21 with steel wire ropes A 31 extending upward from both ends, a lifting frame 22, a load A 23, and a load B 24; the top of the lifting frame 22 is connected to a guide wheel A 411 for vertical rotation; the lifting frame 22 is hoisted to the top of the building 0 by a tower crane; a part of the lifting frame 22 extends out of the top edge of the building 0, and the other part extends into the top interior of the building 0; the extended end of the lifting frame 22 is connected to a guide wheel B 421 for vertical rotation; the load A 23 is hoisted to the top of the building 0 by a tower crane; the load A 23 is connected to the part of the lifting frame 22 extending into the top interior of the building 0; then the end of the steel wire rope A 31 is fixed to the lifting frame 22; the fixed end of the steel wire rope A 31 is close to the top edge of the building 0; the automatic lifting hanging basket 21 is used to transport the construction personnel to the main keel 11 The lower end of the right angle side; the construction personnel fix the lower end of the main keel 11 to the embedded plate by welding; the tower crane is used to lift the secondary frame 1 to the extended end of the main frame 1; the construction personnel connect the main frame 1 with the secondary frame 1 by welding; the vertically rotating guide wheel B 421 is installed at the position where the secondary frame 1 is opposite to the guide wheel A 411; the tower crane is used to lift the load B 24, the hoisting machine A 224 and the hoisting machine B 225 to the top of the building 0; when the hoisting machine A 224 and the hoisting machine B 225 fall to the top of the building 0, they need to fall to the rear of the lifting frame 22 and be located at a symmetrical position with respect to the lifting frame 22; when the load B 24 falls to the top of the building 0, it is directly connected with the hoisting machine A 224 and the hoisting machine B 225; ③ Assemble the aluminum gusset assembly 5 on the ground. The aluminum gusset assembly 5 includes a grid frame 51 and an aluminum gusset 52; a welded fence 511 is provided at one end of the grid frame 51, a plurality of arrayed grids 512 are provided in the middle, and a plurality of extended welded columns 513 are provided at the other end; the aluminum gusset 52 is buckled into the grid 512 and fixed to the grid frame 51 by automatic screws; a front lifting ear A 514 and a rear lifting ear B 515 are welded in the middle of the grid frame 51; ④Install the aluminum gusset assembly under the eaves 5 The winch A 224 retracts and releases the steel wire rope B 32; the winch B 225 retracts and releases the steel wire rope C 33; the steel wire rope B 32 is wound around a guide wheel A 411 and a guide wheel B 421 on the secondary keel 12, and then connected to the lifting ear A 514; the steel wire rope C 33 is wound around another guide wheel B 421 and a guide wheel C on the horizontal tripod 221, and then connected to the lifting ear B 515; the winch A 224 is started before the winch B 225; after the winch A 224 is started for a period of time, the inclination angle of the aluminum gusset assembly 5 relative to the horizontal plane is greater than the inclination angle of the hypotenuse of the main frame 1 relative to the horizontal plane, and then the winch B 225 is started, and the rope retraction speed of the winch B 225 is controlled to be equal to that of the winch A 224; the aluminum gusset assembly 5 is vertically lifted at the fixed inclination angle; when the lifting ear A 514 rises to a height exceeding the automatic lifting basket 21 After a certain height, the winch A 224 is temporarily stopped, and the winch B 225 continues to reel in the rope; the rear end of the grid frame 51 deflects toward the building 0, so that the welding column 513 is close to the automatic lifting basket 21; the construction personnel on the automatic lifting basket 21 pull the rear end of the grid frame 51, so that the end of the welding column 513 is against the embedded plate of the building 0; then, the winch A 224 and the winch B 225 cooperate with each other to reel in the rope, so that the grid frame 51 is parallel to the hypotenuse of the main frame 1; then the winch A 224 and the winch B 225 lift the grid frame 51 at the same speed; so that the welding column 513 is maintained against the embedded plate until the welding fence 511 is against the secondary keel 12; the upper and lower ends of the grid frame 51 are welded to connect the aluminum gusset assembly 5 with the frame 1 as a whole; ⑤ After removing the hanging basket assembly, install the corresponding aluminum gusset assembly 5 on the top of the frame 1. After removing the hanging basket assembly, use the tower crane to transport the aluminum gusset assembly 5 corresponding to the top of the frame 1 to the corresponding position of the building 0; connect the top of the frame 1 and the corresponding aluminum gusset assembly 5 into one by welding.
[0018] Compared with the prior art, the present invention provides a construction method that does not rely on scaffolding, reduces construction costs, and saves construction period. The construction method relies on the two hanging points formed by the steel wire rope B 32 and the steel wire rope C 33 on the aluminum gusset assembly 5, so that the rear end of the aluminum gusset assembly 5 is tilted toward the automatic lifting basket 21, which is beneficial to the construction personnel on the automatic lifting basket 21 to move the rear end of the aluminum gusset assembly 5; the construction personnel on the automatic lifting basket 21 operate the rear end of the aluminum gusset assembly 5 so that the rear end of the aluminum gusset assembly 5 is against the embedded plate of the outer wall of the building 0; the steel wire rope B 32 and the steel wire rope C 33 cooperate with each other to make the aluminum gusset assembly 5 buckle on the frame 1 from bottom to top, which is convenient for the construction personnel to construct.
[0019] A concrete wall 01 is provided on the top of the building; the lifting frame 22 in step ② further comprises an inner high leg 226 matching the concrete wall 01; the load A 23 is mounted on the inner high leg 226; the inner high leg 226 enables the lifting frame 22 to adapt to the use environment of the concrete wall 01.
[0020] Before step ①, there is a material transport step; the main keel 11, secondary keel 12, and lifting frame 22 required for step ① are transported to the site to prepare in advance; the main keel 11 and secondary keel 12 also need to be rust-proofed and painted to ensure the beauty of the surface.
[0021] Before step ①, it is also necessary to measure and lay out the lines; lay out the lines on the top of the building 0 to determine the installation positions of the main keel 11 and the hanging frame 22, and provide a reference for the installation of the main keel 11 and the hanging frame 22.
[0022] Step ③ also requires applying sealant 53 and cleaning the board surface; the sealant 53 is applied to the periphery of the aluminum gusset plate 52 fixed to the grid frame 51 to reduce the gap between adjacent aluminum gusset plates 52; cleaning the board surface is the treatment of the outer surface of the aluminum gusset plate 52 after applying the sealant 53 to ensure the surface smoothness.
[0023] The aluminum gusset assembly 5 also includes a connecting extension plate 54, a U-shaped buckle strip 55, and a mounting member 56; the connecting extension plate 54 is connected to the edge of the aluminum gusset plate 52 by rivets; the mounting member 56 includes a connected mounting strip 561 and a mounting block 562; the U-shaped buckle strip 55 is buckled on the rib of the grid frame 51; the U-shaped buckle strip 55 is connected to the rib of the grid frame 51 by self-tapping screws; the self-tapping screws pass through the mounting strip 561; the automatic screws for installing the aluminum gusset plate 52 pass through the connecting extension plate 54 and the mounting block 562; the sealant 53 is filled in the gap between the U-shaped buckle strip 55 and the aluminum gusset plate 52; the U-shaped buckle strip 55 fills the gap between adjacent aluminum gusset plates 52 to ensure the beautiful appearance of the aluminum gusset assembly 5; the connecting extension plate 54 and the mounting member 56 realize the connection between the U-shaped buckle strip 55 and the aluminum gusset plate 52.
[0024] The welding column 513 is arranged to be inclined relative to the grid frame 51 to stabilize the connection between the grid frame 51 and the building 0.
[0025] There are two symmetrically arranged lifting ears 514, and there are two symmetrically arranged lifting ears 515; the symmetrical arrangement planes of the lifting ears 514 and the symmetrical arrangement planes of the lifting ears 515 coincide with each other; the two lifting ears 514 are connected through the steel wire rope D 34; the two lifting ears B 515 are connected through the steel wire rope E 35; the end of the steel wire rope B 32 is connected to the midpoint of the steel wire rope D 34; the end of the steel wire rope C 33 is connected to the midpoint of the steel wire rope E 35; the lifting stability of the aluminum gusset plate assembly 5 is greatly increased.
[0026] The end of the steel wire rope B 32 is connected to the steel wire rope D 34 through a steel wire rope clamp; the end of the steel wire rope C 33 is connected to the steel wire rope E 35 through a steel wire rope clamp.
[0027] The lifting frame 22 includes a horizontal tripod 221 at the front end, a horizontal frame 222 in the middle, and a vertical tripod 223; the horizontal tripod 221 is an isosceles triangle; the bottom of the vertical tripod 223 connects the horizontal tripod 221 and the horizontal frame 222; a guide wheel assembly A 41 is provided at the vertex of the vertical tripod 223; the guide wheel assembly A 41 includes two guide wheels A 411 connected vertically for rotation; a guide wheel assembly B 42 is installed at the vertex of the horizontal tripod 221; the guide wheel assembly B 42 includes a guide wheel B 421 connected vertically for rotation.
[0028] Embodiment 2: Embodiment 2 is basically the same as Embodiment 1, and the similarities are not repeated here. The differences are as follows: the lifting frame 22 also includes a load-bearing beam 227; the load-bearing beam 227 and the secondary keel 12 are both horizontally arranged steel with wing plates; the guide wheel assembly B 42 includes a guide wheel seat 422; the guide wheel seat 422 includes a connected vertical plate 4221 and a horizontal plate 4222; there are two guide wheels B 421, which are respectively installed on the vertical plate 4221 and the horizontal plate 4222; the end of the horizontal plate 4222 is provided with a flange 42221 corresponding to the wing plate; the guide wheel assembly B 42 can be detachably installed on the load-bearing beam 227 or the secondary keel 12, so as to facilitate replacement and maintenance.
[0029] The load-bearing beam 227 is made of channel steel; the load-bearing beam 227 is integrated with the lifting frame and can be reused, so the structure is simpler; the secondary keel 12 is a part of the frame 1 and is also restricted by the frame 1; considering the structural strength of the frame 1; the secondary keel 12 is made of I-beam.
[0030] The horizontal tripod 221 is provided with a centerline beam 2211 ; the vertical tripod 223 is provided with a high column 2231 ; the centerline beam 2211 increases the structural strength of the horizontal tripod 221 ; the high column 2231 increases the structural strength of the vertical tripod 223 .
Claims
1. A construction method for a tall overhanging aluminum curtain wall, comprising the following steps: ① Preliminary installation of the frame The skeleton includes a right-angled triangle main keel and a horizontal secondary keel; the main keel is hoisted by a tower crane so that the right-angle side of the main keel abuts against the outer wall of the building; an embedded plate is pre-buried on the side of the top of the building; the main keel is adjusted so that the main keel is in a vertical state and the right-angle side of the main keel abuts against the embedded plate; the embedded plate close to the top of the building is fixedly connected to the right-angle side of the main keel by welding, so as to realize the preliminary installation of the skeleton; ②Install the hanging basket assembly A hanging basket assembly is installed on the top of the building; the hanging basket assembly includes a self-controlled lifting hanging basket with steel wire ropes A extending upward from both ends, a lifting frame, a load A, and a load B; the top of the lifting frame is connected to a guide wheel A for vertical rotation; the lifting frame is hoisted to the top of the building by a tower crane; a part of the lifting frame extends out of the edge of the top of the building, and the other part extends into the interior of the top of the building; the extended end of the lifting frame is connected to a guide wheel B for vertical rotation; the load A is hoisted to the top of the building by a tower crane; the load A is connected to the part of the lifting frame extending into the interior of the top of the building; then the end of the steel wire rope A is fixed to the lifting frame; the fixed end of the steel wire rope A is close to the edge of the top of the building; so Use an automatic lifting basket to transport construction workers to the lower end of the right-angled side of the main keel; construction workers fix the lower end of the main keel to the embedded plate by welding; use a tower crane to lift the secondary frame to the extended end of the main frame; construction workers connect the main frame and the secondary frame by welding; install a vertically rotating guide wheel B at the position where the secondary frame is opposite to the guide wheel A; use a tower crane to lift load B, winch A and winch B to the top of the building; winch A and winch B need to fall behind the hoisting frame when they fall to the top of the building, and be located symmetrically with respect to the hoisting frame; when load B falls to the top of the building, it is directly connected with winch A and winch B; ③Assemble aluminum gusset components on the ground The aluminum gusset assembly includes a grid frame and an aluminum gusset; a welded fence is provided at one end of the grid frame, a plurality of arrayed grids are provided in the middle, and a plurality of extended welded columns are provided at the other end; the aluminum gusset is buckled into the grid and fixed to the grid frame by automatic screws; a front hanging ear A and a rear hanging ear B are welded in the middle of the grid frame; ④Install the aluminum gusset assembly under the eaves Winch A retracts and releases wire rope B; Winch B retracts and releases wire rope C; Wire rope B is wound around a guide wheel A and guide wheel B on the secondary keel and then connected to lifting ear A; Wire rope C is wound around another guide wheel B and guide wheel C on the horizontal tripod and then connected to lifting ear B; Winch A is started before Winch B; After Winch A is started for a period of time, the inclination angle of the aluminum gusset assembly relative to the horizontal plane is greater than the inclination angle of the hypotenuse of the main frame relative to the horizontal plane, and then Winch B is started, and the rope retraction speed of Winch B is controlled to be equal to that of Winch A; the aluminum gusset assembly is lifted vertically at the fixed inclination angle; when the lifting ear A rises to a height that exceeds the self-controlled lifting height, the lifting ear A is lifted vertically. After the basket is lowered to a certain height, the winch A is temporarily stopped, and the winch B continues to reel in the rope; the rear end of the grid frame is deflected toward the building, so that the welding column is close to the automatic lifting basket; the construction workers on the automatic lifting basket pull the rear end of the grid frame, so that the end of the welding column is against the embedded plate of the building; then, the winch A and winch B cooperate with each other to reel in the rope, so that the grid frame is parallel to the hypotenuse of the main frame; then the winch A and winch B lift the grid frame at the same speed; so that the welding column is maintained against the embedded plate until the welding fence also rests on the secondary keel; the upper and lower ends of the grid frame are welded to connect the aluminum gusset plate assembly with the frame; ⑤After removing the hanging basket assembly, install the corresponding aluminum gusset assembly on the top of the frame After dismantling the hanging basket assembly, use a tower crane to transport the aluminum gusset assembly corresponding to the top of the frame to the corresponding position of the building; connect the top of the frame and the corresponding aluminum gusset assembly into one by welding.
2. The construction method of the tall overhanging eaves aluminum curtain wall according to claim 1 is characterized by: A concrete wall is provided on the top of the building; the lifting frame in step ② also includes an inner high leg matching the concrete wall; and the load A is installed on the inner high leg.
3. The construction method of the tall overhanging eaves aluminum curtain wall according to claim 1 is characterized by: Before step ①, there is a material transportation step; the main keel, secondary keel and lifting frame required for step ① are transported to the site; the main keel and secondary keel also need to be rust-proofed and painted.
4. The construction method of the tall overhanging eaves aluminum curtain wall according to claim 1 is characterized by: Before step ①, it is necessary to measure and lay out the lines; lay out the lines on the top of the building to determine the installation positions of the main keel and the hoisting frame.
5. The construction method of the tall overhanging eaves aluminum curtain wall according to claim 1 is characterized by: Step ③ also requires applying sealant and cleaning the board surface; the sealant is applied around the aluminum gussets that are fixed to the grid frame to reduce the gap between adjacent aluminum gussets; Cleaning the board surface is the treatment performed on the outer surface of the aluminum gusset plate after applying the sealant to ensure the surface smoothness.
6. The construction method of the tall overhanging eaves aluminum curtain wall according to claim 5 is characterized by: The aluminum gusset plate assembly also includes a connecting extension plate, a U-shaped buckle strip, and a mounting piece; the connecting extension plate is connected to the edge of the aluminum gusset plate by rivets; the mounting piece includes a connected mounting strip and a mounting block; the U-shaped buckle strip is buckled on the rib of the grid frame; the U-shaped buckle strip is connected to the rib of the grid frame by self-tapping screws; the self-tapping screws pass through the mounting strips; the automatic screws for installing the aluminum gusset plate pass through the connecting extension plate and the mounting block; and sealant is filled in the gap between the U-shaped buckle strip and the aluminum gusset plate.
7. The construction method of the tall overhanging eaves aluminum curtain wall according to claim 1 is characterized by: The welding column is arranged obliquely relative to the grid frame.
8. The construction method of the tall overhanging eaves aluminum curtain wall according to claim 1 is characterized by: There are two symmetrically arranged lifting ears A, and there are two symmetrically arranged lifting ears B; the symmetrical arrangement planes of the lifting ears A and the symmetrical arrangement planes of the lifting ears B coincide with each other; the two lifting ears A are connected through the steel wire rope D; the two lifting ears B are connected through the steel wire rope E; the end of the steel wire rope B is connected to the midpoint of the steel wire rope D; the end of the steel wire rope C is connected to the midpoint of the steel wire rope E.
9. The construction method of the tall overhanging eaves aluminum curtain wall according to claim 1 is characterized by: The lifting frame includes a horizontal tripod at the front end, a horizontal frame in the middle, and a vertical tripod; the horizontal tripod is an isosceles triangle; the bottom of the vertical tripod is connected to the horizontal tripod and the horizontal frame; a guide wheel assembly A is provided at the top of the vertical tripod; the guide wheel assembly A includes two guide wheels A connected vertically for rotation; a guide wheel assembly B is installed at the top of the horizontal tripod; the guide wheel assembly B includes a guide wheel B connected vertically for rotation.
10. The construction method of the tall overhanging aluminum curtain wall according to claim 1 is characterized by: The lifting frame also includes a load-bearing beam; the load-bearing beam and the secondary keel are both horizontally arranged steel with wing plates; the guide wheel assembly B includes a guide wheel seat; the guide wheel seat includes a connected vertical plate and a horizontal plate; there are two guide wheels B, which are respectively installed on the vertical plate and the horizontal plate; the end of the horizontal plate is provided with a flange corresponding to the wing plate.