Mining method tunnel excavation over-break and under-break control construction method
By determining blasting parameters, precise drilling and initial support during mining tunnel excavation construction, the problem of difficult to ensure the medium and high loss rate and construction quality of over-under excavation control is solved, and more efficient blasting effect and cost reduction are achieved.
Patent Information
- Application Number
- CN202411340786.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-25
- Publication Date
- 2024-12-06
AI Technical Summary
During the mining tunnel excavation construction, the existing over-under-excavation control method leads to a high loss rate of injection concrete and a large loss rate of secondary lining concrete, resulting in increased construction costs and difficult to guarantee quality.
System methods to determine the blasting parameter stage, drilling stage and initial support stage, including blasting test to determine the best parameters, precise drilling and hole cleaning, combined with large-diameter spiral groove digging, segment management, section trimming and section trimming and The initial spray concrete is closed to ensure that the tunnel excavation surface is flat and there is no under-excavation.
The mining method tunnel excavation and blasting effect has been improved, the tunnel concrete usage has been reduced, the construction cost has been effectively reduced, and the construction quality has been ensured.
Smart Images

Figure CN119084010A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a mining method tunnel excavation construction method, in particular to a mining method tunnel excavation over-excavation and under-excavation control construction method. Background Art
[0002] With the development of our country's transportation industry, there are more and more transportation tunnels. The construction speed of the mining method tunnel excavation construction method is getting faster and faster due to the investment of large-scale machinery and equipment. Moreover, the mining method tunnel excavation construction method is relatively applicable, especially in mountain tunnels. At present, the control of over-excavation and under-excavation of mining method tunnel excavation in the industry has always been the focus of control of various construction units. According to statistics, the loss rate of shotcrete is generally above 50%, and the loss rate of secondary lining concrete is generally above 70%. This causes a significant increase in construction costs, and the construction quality is difficult to guarantee. Therefore, there is an urgent need for a construction method to solve the control of over-excavation and under-excavation of mining method tunnel excavation, which can reduce construction costs and ensure construction quality.
[0003] Therefore, a simpler and easier-to-implement construction method for controlling over-excavation and under-excavation in mining tunnel excavation is needed, which can overcome the above shortcomings, obtain data that is more in line with the actual situation, and the results are more accurate and reliable. Summary of the invention
[0004] The purpose of the present invention is to improve the deficiencies in existing construction technology methods, provide a systematic construction method, improve the control accuracy of mining tunnel excavation contour, reduce the tunnel concrete loss rate, and ensure the construction quality.
[0005] To achieve the above object, the present invention proposes a mining method tunnel excavation over-break and under-break control construction method, including a blasting parameter determination stage, a drilling stage and an initial support stage.
[0006] Determine the blasting parameters stage
[0007] S1. Determine blasting parameters The stage includes determining the best blasting parameters through blasting tests to ensure rock loosening while reducing rock wall damage.
[0008] S2. The stage of determining blasting parameters is blasting design. In the early stage of blasting, blasting tests are first carried out for the corresponding rock properties and structures, so that the rocks to be blasted are loosened and the rock wall is not damaged or less damaged.
[0009] S3. During the test described above, the blasting effect is analyzed, the characteristic curve of the blasting funnel is drawn, and the critical burial depth, strain energy coefficient, optimal burial depth, unit consumption of explosives and other parameters under the test conditions are obtained.
[0010] Drilling stage
[0011] S4. The drilling stage includes drilling, hole cleaning and charging. Precise drilling and timely hole cleaning technology is used in conjunction with large-diameter spiral slot blasting to improve the blasting effect. During the charging process, segmented and sectioned management is implemented to avoid misoperation, and the amount of explosives is flexibly adjusted when necessary to deal with hole blockage during drilling and hole cleaning.
[0012] S5. Hole cleaning before charging. About half an hour before the explosives reach the face of the head, the hole is cleaned twice manually using a multifunctional trolley. The hole is cleaned using steel bars with elbows. The main purpose is to remove the slag in the hole to prevent the charge from being installed in the designed position. Finally, the hole depth is checked with a blasting stick.
[0013] S6. The charging and blasting described above. Use a multifunctional trolley to manually charge, and use segmented and sectioned charging to avoid mixing up detonators and incorrect installation of explosives.
[0014] Initial support stage
[0015] S7. The initial support stage is to ensure that the tunnel excavation surface is flat and free of under-excavation through section finishing and initial concrete spraying.
[0016] After the blasting is completed, a large excavator with a breaker hammer is used to trim the blasting section and remove loose stones. At the same time, a water pipe is installed on the excavator gun head to reduce the dust generated by the section trimming.
[0017] Preferably, in step S3, a variable-spacing multi-hole same-segment blasting funnel test is carried out with the optimal burial depth as the charging depth to verify and select the hole spacing for deep hole blasting, obtain preliminary blasting parameters, and adjust the design parameters on this basis to improve the design scheme and adopt large-diameter spiral slot blasting technology.
[0018] Preferably, in step S4, after the blasting drilling design drawing is designed by the blasting engineer, it is sent to the surveying engineer as soon as possible. After the surveying engineer verifies and converts it into the format of data uploaded by the three-arm drilling rig, the operator promptly transfers it to the computer of the three-arm drilling rig, and the on-site drilling is carried out according to the latest blasting design drawing.
[0019] Preferably, in step S4, the peripheral hole external insertion angle control is generally determined based on the drilling depth and the residual hole after blasting, and is corrected through multiple on-site tests; the drilling sequence is generally from top to bottom to prevent the mud and debris flowing out during the upper drilling from flowing into the completed hole at the lower part.
[0020] Preferably, in step S4, if there is a residual hole on the face, the drilling position can be appropriately moved to the side by no more than 10 cm to avoid affecting the blasting effect.
[0021] Preferably, in step S4, if there are obvious raised and under-dug parts near the bottom plate holes and the peripheral holes, or parts with harder rocks, 1-3 more holes can be added to this part after the drilling of the designed blasting holes is completed, but no explosives are loaded to ensure the blasting effect; when drilling the peripheral holes, the top beam of the drilling trolley is arranged in the center direction to ensure that the hole opening position is close to the contour line as much as possible.
[0022] Preferably, in step S5, after each hole is drilled, it is necessary to clean the hole in time, and when it is found that the water flowing out of the hole is relatively clear and free of slag, the hole cleaning is completed. Then the next hole is changed to continue drilling.
[0023] Preferably, in step S5, when drilling the bottom plate holes, workers are promptly arranged to plug each hole after it is completed on site. The holes are plugged with plastic pipes, and the pipe heads are wrapped with geotextile to prevent mud and sand from entering the holes and causing plugging.
[0024] Preferably, in step S6, after the charging is completed and the detonating wire is connected, the personnel are evacuated from the working face, and the blasting engineer performs blasting control in the safe house in the cave.
[0025] Preferably, in step S6, during the on-site charging process, if the hole is blocked and the explosives cannot be loaded to the bottom of the hole, 1-3 rolls of explosives can be added to the adjacent hole positions to ensure the overall blasting effect.
[0026] Preferably, in step S7, when the cross section is being trimmed, the surveying engineer performs cross section inspection in real time to ensure that the cross section is not under-excavated. After the cross section is trimmed, the initial spraying of concrete is carried out in time to seal the excavated rock surface.
[0027] The beneficial effects of the present invention based on its technical solution are:
[0028] 1. The present invention optimizes the processes of blasting drilling, hole cleaning, and charging to maximize the blasting effect of tunnel excavation by mining method.
[0029] 2. The present invention effectively controls the tunnel excavation contour line, reduces the amount of tunnel concrete, effectively reduces the tunnel construction cost, and ensures the tunnel construction quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 This is a flow chart of a mining method tunnel excavation over-excavation and under-excavation control construction method of the present invention;
[0031] Figure 2 It is a cross-sectional diagram of the blasting design in the present invention;
[0032] Figure 3 It is the explosion funnel diagram in the present invention;
[0033] Figure 4 This is a diagram of the hole cleaning and charge charging tool in the present invention;
[0034] Figure 5 It is a shotcrete tool diagram of the present invention;
[0035] Peripheral hole; 2-groove hole; 3-bottom plate hole; 4-tunnel outline; 5-explosives; 6-blasting funnel outline; 7-ground; 8-hole cleaning and charging tool vehicle; 9-hole cleaning tools; 10-charging tools; 11-blasting hole; 12-tip face; 13-sprayed concrete tool vehicle; DETAILED DESCRIPTION
[0036] In order to achieve the purpose of the present invention and to better understand the technical solution and effects, the embodiments of the present invention will be further described in conjunction with the accompanying drawings.
[0037] Please refer to Figure 1 , Figure 1 This is a flow chart of a mining method tunnel excavation over-excavation and under-excavation control construction method of the present invention;
[0038] In order to achieve the above objectives,
[0039] 1. The present invention proposes a mining method tunnel excavation over-break and under-break control construction method, including a blasting parameter determination stage, a drilling stage and an initial support stage.
[0040] Determine the blasting parameters stage
[0041] S1. Determine the blasting parameters stage includes determining the best blasting parameters through blasting tests to ensure rock loosening while reducing rock wall damage. Figure 2 , 1 is the peripheral hole, 2 is the slot hole, 3 is the bottom plate hole, and 4 is the tunnel contour line.
[0042] S2. The stage of determining blasting parameters is blasting design. In the early stage of blasting, blasting tests are first carried out for the corresponding rock types and structures, so that the rocks to be blasted are loosened and the rock walls are not damaged or less damaged, mainly involving the peripheral holes 1, the slot holes 2 and the bottom plate holes 3, and ensuring that the blasting effects of the designed blasting parameters are not much different on the blasting contour line 4. Reference Figure 3 , 5 is the explosive, 6 is the outline of the blasting funnel, and 7 is the ground.
[0043] S3. During the test, the explosives 5 are placed, the blasting effect is analyzed on the ground 7, the characteristic curve of the blasting funnel 6 is drawn, and the critical burial depth, strain energy coefficient, optimal burial depth, explosive unit consumption and other parameters under the test conditions are obtained.
[0044] Drilling stage
[0045] S4. The drilling stage includes drilling and cleaning the hole and charging as reference Figure 4, 8 is a hole cleaning and charging tool vehicle, 9 is a hole cleaning tool, 10 is a charging tool, 11 is a blasting hole, and 12 is a heading. The hole cleaning and charging tool vehicle 8 is used to accurately drill and clean the tunnel in time, and large-diameter spiral slot blasting is used to improve the blasting effect. During the charging process, segmented and sectioned management is implemented to avoid misoperation, and the amount of explosives is flexibly adjusted when necessary to cope with hole blockage during drilling and hole cleaning.
[0046] S5. The hole cleaning before charging. About half an hour before the explosives reach the tunnel face 12, the hole cleaning tool 9 is used to manually clean the blasting hole 11 twice before charging, and finally the hole depth is checked with a blasting stick.
[0047] S6. The charging and blasting described above. The charging tool 10 is used to manually charge the explosives, and the charging is carried out in sections and segments to avoid mixing up the detonator segments and installing the wrong amount of explosives.
[0048] Initial support stage
[0049] S7. The initial support stage is completed by section finishing and initial spraying of concrete, see Figure 5 , 13 is a shotcrete tool vehicle. After the hole is cleaned and the section is trimmed, the shotcrete tool vehicle 13 is used to spray concrete on the tunnel section to ensure that the tunnel excavation surface is flat and there is no under-excavation.
[0050] After the blasting is completed, a large excavator with a breaker hammer is used to trim the blasting section and remove loose stones. At the same time, a water pipe is installed on the excavator gun head to reduce the dust generated by the section trimming.
[0051] In this embodiment, a variable-spacing multi-hole same-segment blasting funnel test is carried out with the optimal burial depth as the charging depth to verify and select the hole spacing for deep hole blasting, obtain preliminary blasting parameters, and adjust the design parameters on this basis to improve the design scheme and adopt large-diameter spiral slot blasting technology.
[0052] In this embodiment, after the blasting drilling design drawing is designed by the blasting engineer, it is sent to the surveying engineer as soon as possible. After the surveying engineer verifies and converts it into the format of data uploaded by the three-arm drilling rig, the operator promptly transfers it to the computer of the three-arm drilling rig, and the on-site drilling is carried out according to the latest blasting design drawing.
[0053] In this embodiment, the peripheral hole external insertion angle control is generally determined according to the drilling depth and the residual hole after blasting, and is corrected through multiple on-site tests; the drilling sequence is generally from top to bottom to avoid mud and residue flowing out during the upper drilling into the completed hole at the lower part.
[0054] In this embodiment, if there is a residual hole on the face, the drilling position can be appropriately moved to the side by no more than 10 cm to avoid affecting the blasting effect.
[0055] In this embodiment, if there are obvious raised and under-dug parts near the bottom plate holes and the peripheral holes, or parts with harder rocks, 1-3 more holes can be added to this part after the drilling of the blasting design holes is completed, but no explosives are loaded to ensure the blasting effect; when drilling the peripheral holes, the drilling trolley top beam is arranged in the center direction to ensure that the hole opening position is close to the contour line as much as possible.
[0056] In this embodiment, after each hole is drilled, it is necessary to clean the hole in time, and when it is found that the water flowing out of the hole is relatively clear and free of slag, the hole cleaning is completed. Then the next hole is changed to continue drilling.
[0057] In this embodiment, when drilling the bottom plate holes, workers are promptly arranged to plug the holes after each hole is completed on site. Plastic pipes are used to plug the holes, and the pipe heads are wrapped with geotextile to prevent mud and sand from entering the holes and causing plugging.
[0058] In this embodiment, after the charging is completed and the detonating wire is connected, the personnel are evacuated from the working face, and the blasting engineer controls the blasting in the safe house in the cave.
[0059] In this embodiment, during the on-site charging process, if the hole is blocked and the explosives cannot be loaded to the bottom of the hole, 1-3 rolls of explosives can be added to the adjacent hole positions to ensure the overall blasting effect.
[0060] In this embodiment, when the cross section is being trimmed, the surveying engineer performs cross section inspection in real time to ensure that the cross section is not under-excavated. After the cross section is trimmed, the initial spraying of concrete is carried out in a timely manner to seal the excavated rock surface.
Claims
1. A mining method tunnel excavation over-break and under-break control construction method, including a blasting parameter determination stage, a drilling stage and an initial support stage. Determine the blasting parameters stage S1. Determine blasting parameters The stage includes determining the best blasting parameters through blasting tests to ensure rock loosening while reducing rock wall damage. S2. The stage of determining blasting parameters is blasting design. In the early stage of blasting, blasting tests are first carried out for the corresponding rock properties and structures, so that the rocks to be blasted are loosened and the rock wall is not damaged or less damaged. S3. During the test described above, the blasting effect is analyzed, the characteristic curve of the blasting funnel is drawn, and the critical burial depth, strain energy coefficient, optimal burial depth, unit consumption of explosives and other parameters under the test conditions are obtained. Drilling stage S4. The drilling stage includes drilling, hole cleaning and charging. Precise drilling and timely hole cleaning technology is used in conjunction with large-diameter spiral slot blasting to improve the blasting effect. During the charging process, segmented and sectioned management is implemented to avoid misoperation, and the amount of explosives is flexibly adjusted when necessary to deal with hole blockage during drilling and hole cleaning. S5. Hole cleaning before charging. About half an hour before the explosives reach the face of the head, the hole is cleaned twice manually using a multifunctional trolley. The hole is cleaned using steel bars with elbows. The main purpose is to remove the slag in the hole to prevent the charge from being installed in the designed position. Finally, the hole depth is checked with a blasting stick. S6. The charging and blasting described above. Use a multifunctional trolley to manually charge, and use segmented and sectioned charging to avoid mixing up detonators and incorrect installation of explosives. Initial support stage S7. The initial support stage is to ensure that the tunnel excavation surface is flat and free of under-excavation through section finishing and initial concrete spraying. After the blasting is completed, a large excavator with a breaker hammer is used to trim the blasting section and remove loose stones. At the same time, a water pipe is installed on the excavator gun head to reduce the dust generated by the section trimming.
2. A mining method tunnel excavation over-excavation and under-excavation control construction method according to claim 1, characterized in that: In step S3, a variable hole spacing multi-hole same-segment blasting funnel test is carried out with the optimal burial depth as the charging depth to verify and select the hole spacing of deep hole blasting, obtain preliminary blasting parameters, adjust the design parameters on this basis, improve the design plan, and adopt large-diameter spiral slot blasting technology.
3. The over-excavation and under-excavation control construction method for tunnel excavation by mining method according to claim 1, characterized in that: In step S4, after the blasting drilling design drawing is designed by the blasting engineer, it is sent to the surveying engineer as soon as possible. After the surveying engineer verifies and converts it into the format of data uploaded by the three-arm drilling rig, the operator promptly transfers it to the computer of the three-arm drilling rig, and the on-site drilling is carried out according to the latest blasting design drawing.
4. The over-excavation and under-excavation control construction method for tunnel excavation by mining method according to claim 1, characterized in that: In step S4, the peripheral hole external insertion angle control is generally determined according to the drilling depth and the residual hole after blasting, and is corrected through multiple on-site tests; the drilling sequence is generally from top to bottom to prevent the mud residue flowing out during the upper drilling from flowing into the completed hole at the lower part.
5. The over-excavation and under-excavation control construction method for tunnel excavation by mining method according to claim 1, characterized in that: In step S4, if there is a residual hole on the face, the drilling position can be appropriately moved to the side by no more than 10 cm to avoid affecting the blasting effect.
6. The over-excavation and under-excavation control construction method for tunnel excavation by mining method according to claim 1, characterized in that: In step S4, if there are obvious protruding and under-dug parts near the bottom plate holes and the peripheral holes, or the rock is hard, 1-3 more holes can be added to this part after the drilling of the blasting design hole is completed, but no explosives are loaded to ensure the blasting effect; when drilling the peripheral holes, the drilling trolley top beam is arranged in the center direction to ensure that the hole opening position is close to the contour line as much as possible.
7. The over-excavation and under-excavation control construction method for tunnel excavation by mining method according to claim 1, characterized in that: In step S5, after each hole is drilled, it is necessary to clean the hole in time, and when it is found that the water flowing out of the hole is relatively clear and free of slag, the hole cleaning is completed. Then the next hole is changed to continue drilling.
8. The over-excavation and under-excavation control construction method for tunnel excavation by mining method according to claim 1, characterized in that: In step S5, when drilling the bottom plate holes, workers are arranged to plug the holes in time after each hole is completed on site. Plastic pipes are used to plug the holes, and the pipe heads are wrapped with geotextile to prevent mud and sand from entering the holes and causing plugging.
9. The over-excavation and under-excavation control construction method for tunnel excavation by mining method according to claim 1, characterized in that: In step S6, after the charging is completed and the detonating wire is connected, the personnel withdraw from the working face, and the blasting engineer controls the blasting in the safe house in the cave.
10. The over-excavation and under-excavation control construction method for tunnel excavation by mining method according to claim 1, characterized in that: In step S6, during the on-site charging process, if the hole is blocked and the explosives cannot be loaded to the bottom of the hole, 1-3 rolls of explosives can be added to the adjacent hole positions to ensure the overall blasting effect.
11. A mining method tunnel excavation over-break and under-break control construction method according to claim 1, characterized in that: In step S7, when the cross section is being trimmed, the surveying engineer performs cross section inspection in real time to ensure that the cross section is not under-excavated. After the cross section is trimmed, the initial concrete spraying is carried out in time to seal the excavated rock surface.