Construction decision method and system for early insertion and closure of post-cast strips in super high-rise building structures

By using construction simulation analysis and settlement difference monitoring combined with Pearson correlation coefficient evaluation methods in ultra-high-rise buildings, the post-pouring belt closure strategy is determined in advance, and the construction period delay caused by settlement difference in ultra-high-rise buildings is solved, and the construction efficiency is improved and the construction period is shortened.

CN119397665BActive Publication Date: 2025-03-14CSCEC INT CONSTR
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202510002156.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-01-02
Publication Date
2025-03-14
Estimated Expiration
2045-01-02

AI Technical Summary

Technical Problem

During the construction of super high-rise buildings, due to the large settlement deformation, the settlement difference between the podium and the main building is to wait for the main structure to end and the settlement is basically stable before pouring the settlement after the sinking is poured, resulting in delays in the construction period and affecting the delivery of the overall structure.

Method used

The whole process construction simulation analysis was carried out using standard construction simulation methods to monitor the settlement difference between the podium and the main building, and the correlation between the simulation value of the settlement difference and the measured value was evaluated using the Pearson correlation coefficient formula. The post-pouring belt enclosed construction strategy was determined based on the correlation coefficient, and the post-pouring belt was inserted in advance.

Benefits of technology

By interspersing and closing the post-pouring strip in advance, the stability of the building structure is ensured, and the problems such as harmful cracks caused by settlement differences are avoided, and construction efficiency is improved and construction period is shortened.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119397665B_ABST
    Figure CN119397665B_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of super high-rise building construction, and discloses a construction decision method and system for early insertion and closure of post-cast strips of super high-rise building structures, comprising S1, adopting a standard construction simulation method to perform full-process construction simulation analysis on the super high-rise building, and obtaining a change trend of a simulated value of a settlement difference between a podium and a main building; S2, monitoring the settlement difference between the podium and the main building, and determining a change trend of a measured value of the settlement difference between the podium and the main building according to the monitoring data; S3, adopting a Pearson correlation coefficient formula to evaluate a change trend of a simulated value of the settlement difference between the podium and the main building and a change trend of a measured value of the settlement difference, and obtaining a correlation coefficient between a change trend of a simulated value of the settlement difference between the podium and the main building and a change trend of a measured value of the settlement difference; S4, determining a post-cast strip closure construction strategy according to the correlation coefficient; the method and system ensure that the super high-rise building and its podium will not produce harmful cracks and other problems due to the settlement difference, and improve the construction efficiency and shorten the construction period.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of super high-rise building construction, and in particular to a construction decision method and system for early insertion and closure of post-cast strips of super high-rise building structures. Background Art

[0002] During the construction of super high-rise buildings, curtain walls and secondary structures are often interspersed, and settlement post-casting strips are the key to affecting the construction of secondary structures. However, due to the large settlement deformation of super high-rise buildings, it is easy to cause a settlement difference between the podium and the main building. In order to avoid the settlement problem caused by the settlement post-casting strip, the strategy adopted by the existing technology is to wait until the main structure is completed and the settlement is basically stable before pouring the settlement post-casting strip, but this strategy will delay the construction period for a long time and affect the delivery of the overall structure. Summary of the invention

[0003] In view of the deficiencies in the prior art, the purpose of the present invention is to provide a method and system for making decisions on the early insertion and closure of post-cast strips in super high-rise building structures, which improves construction efficiency and shortens construction period.

[0004] In order to achieve the above object, the present invention provides the following technical solutions:

[0005] The decision-making method for the early insertion and closure of the post-cast strip of the super-high-rise building structure includes: S1, using a standard construction simulation method to conduct a full-process construction simulation analysis of the super-high-rise building, and obtain the change trend of the simulated value of the settlement difference between the podium and the main building; S2, monitoring the settlement difference between the podium and the main building, and determining the change trend of the actual measured value of the settlement difference between the podium and the main building according to the monitoring data; S3, using the Pearson correlation coefficient formula, evaluating the change trend of the simulated value of the settlement difference between the podium and the main building and the change trend of the actual measured value of the settlement difference, and obtaining the correlation coefficient between the change trend of the simulated value of the settlement difference between the podium and the main building and the change trend of the actual measured value of the settlement difference; S4, determining the post-cast strip closure construction strategy according to the correlation coefficient; the post-cast strip closure construction strategy includes : If the correlation coefficient is in the highly correlated section, and the remaining settlement difference is not greater than the closed construction threshold, all post-cast strips are directly closed; if the correlation coefficient is in the moderately correlated section, and the remaining settlement difference is not greater than the closed construction threshold, the horizontal section of the post-cast strip is closed, and the post-cast strips at the four corners are reserved without closing, and the closure is carried out after the overall construction is completed; if the correlation coefficient is in the weakly correlated section, and the remaining settlement difference is not greater than the closed construction threshold, the horizontal section of the post-cast strip is closed at every other span, and the post-cast strips at the four corners are reserved without closing, and the horizontal section and the four corners are closed after the overall construction is completed; if the correlation coefficient is in the uncorrelated section, and the remaining settlement difference is not greater than the closed construction threshold, the post-cast strip is closed after the overall construction is completed.

[0006] In the present invention, preferably, assuming that the correlation coefficient is P, the highly correlated segment is 0.8≤|P|≤1, the moderately correlated segment is 0.5≤|P|<0.8, the weakly correlated segment is 0.3≤|P|<0.5, and the uncorrelated segment is 0≤|P|<0.3.

[0007] In the present invention, preferably, the S1 includes: S11, establishing a construction simulation analysis model, applying loads and specifying boundary conditions; S12, establishing a structure group according to the construction plan, specifying the components to be constructed simultaneously as a structure group, and establishing a load group and a boundary group according to the construction step; S13, specifying the shrinkage creep coefficient and the concrete strength development function, and connecting them to the corresponding components; S14, defining the construction stage analysis data according to the actual construction plan, the construction stage analysis data including the construction step and the corresponding structure group, load group and boundary group; S15, performing construction simulation analysis, and performing load combination to determine the settlement difference between the building podium and the main building.

[0008] In the present invention, preferably, in said S2, the settlement difference between the podium and the main building is monitored, and the number of monitoring points is at least two.

[0009] In the present invention, preferably, the closed construction threshold is one two thousandth of the span of the post-cast strip.

[0010] The construction decision system for early insertion and closure of post-cast strips of super-high-rise building structures includes: a simulation module, which is used to adopt a standard construction simulation method to conduct a full-process construction simulation analysis of super-high-rise buildings, and obtain the changing trend of the simulated value of the settlement difference between the podium and the main building; a monitoring module, which is used to monitor the settlement difference between the podium and the main building, and determine the changing trend of the actual measured value of the settlement difference between the podium and the main building according to the monitoring data; a correlation evaluation module, which is used to adopt the Pearson correlation coefficient formula to evaluate the changing trend of the simulated value of the settlement difference between the podium and the main building and the changing trend of the actual measured value of the settlement difference, and obtain the correlation coefficient of the changing trend of the simulated value of the settlement difference between the podium and the main building and the changing trend of the actual measured value of the settlement difference; a decision module, which is used to determine the construction strategy for closing the post-cast strips according to the correlation coefficient; the post-cast strips are closed by the post-cast strips. The belt closure construction strategy includes: if the correlation coefficient is in the highly correlated section and the remaining settlement difference is not greater than the closure construction threshold, all post-cast strips are directly closed; if the correlation coefficient is in the moderately correlated section and the remaining settlement difference is not greater than the closure construction threshold, the horizontal section of the post-cast strip is closed, and the post-cast strips at the four corners are reserved without closure, and the closure is performed after the overall construction is completed; if the correlation coefficient is in the weakly correlated section and the remaining settlement difference is not greater than the closure construction threshold, the horizontal section of the post-cast strip is closed at every other span, and the post-cast strips at the four corners are reserved without closure, and the horizontal section and the four corners are closed after the overall construction is completed; if the correlation coefficient is in the uncorrelated section and the remaining settlement difference is not greater than the closure construction threshold, the post-cast strip is closed after the overall construction is completed.

[0011] In the present invention, preferably, assuming that the correlation coefficient is P, the highly correlated segment is 0.8≤|P|≤1, the moderately correlated segment is 0.5≤|P|<0.8, the weakly correlated segment is 0.3≤|P|<0.5, and the uncorrelated segment is 0≤|P|<0.3; the closed construction threshold is one two thousandth of the span of the post-casting strip.

[0012] In the present invention, preferably, the simulation module includes: a modeling unit, which is used to establish a construction simulation analysis model, apply loads and specify boundary conditions; a grouping unit, which is used to establish a structure group according to the construction plan, specify the components to be constructed simultaneously as a structure group, and establish a load group and a boundary group according to the construction step; a connection unit, which is used to specify the shrinkage creep coefficient and the concrete strength development function, and connect to the corresponding components; a definition unit, which is used to define the construction stage analysis data according to the actual construction plan, and the construction stage analysis data includes the construction step and the corresponding structure group, load group and boundary group; an analysis unit, which is used to perform construction simulation analysis, and perform load combination to determine the settlement difference between the building podium and the main building.

[0013] In the present invention, preferably, in the monitoring module, the settlement difference between the podium and the main building is monitored, and there are at least two monitoring points.

[0014] A computer-readable storage medium, characterized in that the computer-readable storage medium includes instructions, and when the instructions are executed on a computer, the computer is caused to execute the construction decision method for early insertion and closure of post-cast strips of a super-high-rise building structure as described in any of the above items.

[0015] Compared with the prior art, the present invention has the following beneficial effects:

[0016] The method and system are based on the settlement deformation of super high-rise buildings and their podium structures. From the perspective of settlement deformation monitoring, the method and system combine theoretical analysis data with on-site monitoring data for real-time comparative analysis. Combined with the settlement deformation trend, the post-cast strips of the building structure are closed in advance, which not only ensures that super high-rise buildings and their podiums will not produce harmful cracks and other problems due to settlement differences, but also improves construction efficiency and shortens construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 The present invention is a flowchart of a method for making decisions on early insertion and closure of post-cast strips in super high-rise building structures according to an embodiment of the present invention.

[0018] Figure 2 This is a flowchart of S1 in a construction decision method for early insertion and closure of post-cast strips of a super-high-rise building structure according to an embodiment of the present invention.

[0019] Figure 3It is a schematic diagram of a closure method that meets height-related requirements in a construction decision method for early insertion and closure of post-cast strips of a super-high-rise building structure according to an embodiment of the present invention.

[0020] Figure 4 It is a schematic diagram of a closure method that meets moderately relevant requirements in a construction decision method for early insertion and closure of post-cast strips of a super-high-rise building structure according to an embodiment of the present invention.

[0021] Figure 5 It is a schematic diagram of a closure method that meets weak correlation requirements in a construction decision method for early insertion and closure of post-cast strips of a super-high-rise building structure according to an embodiment of the present invention.

[0022] Figure 6 It is a schematic diagram of a closure method that meets non-related requirements in a construction decision method for early insertion and closure of post-cast strips of a super-high-rise building structure according to an embodiment of the present invention.

[0023] Figure 7 This is a graph showing the monitoring results of monitoring point No. 1 in a construction decision method for early insertion and closure of a post-cast strip of a super-high-rise building structure according to an embodiment of the present invention.

[0024] Figure 8 This is a graph showing the monitoring results of monitoring point No. 2 in a construction decision method for early insertion and closure of a post-cast strip of a super-high-rise building structure according to an embodiment of the present invention.

[0025] Fig. 9 It is a structural schematic diagram of a construction decision system for early insertion and closure of post-cast strips in super high-rise building structures according to an embodiment of the present invention.

[0026] Fig.10 It is a structural schematic diagram of a simulation module in a construction decision system for early insertion and closure of post-cast strips of a super-high-rise building structure according to an embodiment of the present invention.

[0027] In the attached figure: 1. simulation module; 11. modeling unit; 12. grouping unit; 13. connection unit; 14. definition unit; 15. analysis unit; 2. relevant evaluation module; 3. monitoring module; 4. decision module. DETAILED DESCRIPTION

[0028] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0029] It should be noted that when a component is referred to as being "fixed to" another component, it may be directly on the other component or there may also be a component centered. When a component is considered to be "connected to" another component, it may be directly connected to the other component or there may also be a component centered. When a component is considered to be "set on" another component, it may be directly set on the other component or there may also be a component centered. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.

[0030] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which the present invention belongs. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more of the related listed items.

[0031] Please also see Figure 1 to Figure 2 A preferred embodiment of the present invention provides a construction decision method for early insertion and closure of post-cast strips of super high-rise building structures, comprising:

[0032] S1, using the standard construction simulation method, conducts a full-process construction simulation analysis of super high-rise buildings to obtain the changing trend of the simulated settlement difference between the podium and the main building.

[0033] This process is super high-rise construction simulation analysis, which can be performed using the structural analysis software MIDAS / GEN, or other software with construction simulation analysis functions. Figure 2 As shown, the main steps of S1 are as follows:

[0034] S11, establish a construction simulation analysis model, apply loads and specify boundary conditions.

[0035] S12, establishing a structure group according to the construction plan, designating the components to be constructed simultaneously as a structure group, and establishing a load group and a boundary group according to the construction step.

[0036] S13, specifies shrinkage creep coefficient and concrete strength development function, and connects to the corresponding components.

[0037] S14, defining construction phase analysis data according to the actual construction plan, the construction phase analysis data including the construction step and the corresponding structure group, load group and boundary group.

[0038] S15, conduct construction simulation analysis and load combination to determine the settlement difference between the building podium and the main building.

[0039] S2, monitor the settlement difference between the podium and the main building, and determine the changing trend of the measured value of the settlement difference between the podium and the main building based on the monitoring data.

[0040] This process is the post-casting belt construction monitoring, and the static level and other devices can be used to monitor the internal and external settlement difference of the post-casting belt of the main building and the podium of the super high-rise building. Monitoring can set one monitoring point, and the data obtained is relatively accurate. If more accurate data is to be obtained, more than two monitoring points can be set. By combining the data of each monitoring point, the actual measured data of the settlement difference will be more accurate. This embodiment uses two monitoring points, and the monitoring results are as follows: Figure 7 , 8 The monitoring results show that as the construction progresses, the difference in settlement between the main building and the podium continues to increase. Since March 1, the growth rate of the difference in settlement between the main building and the podium has significantly accelerated. Figure 7 The maximum settlement difference measured at measuring point 1 is 11.879 mm. Figure 8 The maximum settlement difference measured at the measuring point No. 2 is about 11.239mm. It is also found that between September 19 and September 23, the settlement value of point No. 2 increased, with the maximum increase of 1.030mm.

[0041] S3, using the Pearson correlation coefficient formula, evaluate the changing trend of the simulated settlement difference value between the podium and the main building and the changing trend of the measured settlement difference value, and obtain the correlation coefficient between the changing trend of the simulated settlement difference value between the podium and the main building and the changing trend of the measured settlement difference value.

[0042] This process is the comparison of settlement trends. Combined with the construction simulation analysis data, the settlement deformation trend of the structure is predicted. The calculated settlement deformation of the structure (simulated settlement difference value) is consistent with the measured settlement deformation (actual settlement difference value). The trend is evaluated using the Pearson correlation coefficient.

[0043] The Pearson correlation coefficient, also known as the product-moment correlation coefficient, was first proposed by Karl Pearson. It is mainly used to analyze the linear correlation between time series data and is widely used in signal analysis, fault diagnosis, numerical prediction and other fields. The Pearson correlation coefficient can be represented by P.

[0044] S4, determine the post-cast strip closure construction strategy based on the correlation coefficient.

[0045] Among them, the post-casting belt closure construction strategies include:

[0046] If the correlation coefficient is in the highly correlated section and the residual settlement difference is not greater than the closure construction threshold, all post-casting strips are directly closed, such as Figure 3 shown.

[0047] If the correlation coefficient is in the moderate correlation section and the residual settlement difference is not greater than the closed construction threshold, the horizontal section of the post-casting strip is closed, and the post-casting strips at the four corners are reserved and not closed until the overall construction is completed. Figure 4 shown.

[0048] If the correlation coefficient is in the weak correlation section and the residual settlement difference is not greater than the closed construction threshold, the horizontal section of the post-cast strip is closed, and the post-cast strips at the four corners are not closed. After the overall construction is completed, the horizontal section and the four corners are closed. Figure 5 shown.

[0049] If the correlation coefficient is in the non-correlated section and the remaining settlement difference is not greater than the closed construction threshold, the post-casting strip will be closed after the overall construction is completed and the settlement trend tends to be stable, such as Figure 6 shown.

[0050] The plan shapes of the main building and the podium are both rectangular. The podium is surrounded by the outer circle of the main building. A post-cast joint is set between the main building and the podium. Therefore, the post-cast joint includes four sides and four corners. The four sides are the aforementioned horizontal sections. The horizontal section of the post-cast joint is closed by spanning, which means dividing the horizontal section into several unconnected small sections. Each small section is separated by a certain distance, and each small section is closed first.

[0051] The Pearson correlation coefficient P is a constant between 0 and 1. The closer it is to 1, the higher the correlation between the two quantities, and the closer it is to 0, the lower the correlation between the two quantities. The highly correlated segment (meeting the highly correlated requirement), the moderately correlated segment (meeting the moderately correlated requirement), the weakly correlated segment (meeting the weakly correlated requirement), and the non-correlated segment (meeting the non-correlated requirement) are all pre-set and set according to the empirical values ​​obtained from actual construction. In this embodiment, the highly correlated segment is set to 0.8≤|P|≤1, the moderately correlated segment is set to 0.5≤|P|<0.8, the weakly correlated segment is set to 0.3≤|P|<0.5, and the non-correlated segment is set to 0≤|P|<0.3.

[0052] The closed construction threshold is also an empirical value, which is expressed as a fraction of the span of the post-casting strip, that is, the ratio of the remaining settlement difference to the span of the post-casting strip is within a relatively small range, which can ensure that the post-casting strip will not have cracks and the like. In this embodiment, the closed construction threshold is set to one two thousandth of the span of the post-casting strip, that is, the span of the post-casting strip is L, and the remaining settlement difference does not exceed L / 2000. If the remaining settlement difference does not reach below the closed construction threshold, the closed construction conditions of the post-casting strip are not met, and it is necessary to wait for the main building and the podium to continue to settle until the remaining settlement difference meets the closed construction threshold.

[0053] Before the construction of a super high-rise building, it is necessary to survey the construction site to predict the extent of the settlement of the super high-rise building and monitor the settlement of the super high-rise building in real time during the construction process. This will allow a relatively accurate prediction of the remaining settlement of the main building and the podium during the construction process, and then estimate the remaining settlement difference to determine whether the remaining settlement difference mentioned above reaches the conditions for the post-pouring zone closure construction.

[0054] like Fig. 9 As shown, the embodiment of the present invention also provides a construction decision system for early insertion and closure of post-cast strips of super high-rise building structures, including:

[0055] The simulation module is used to conduct a full-process construction simulation analysis of super-high-rise buildings using standard construction simulation methods to obtain the change trend of the simulated settlement difference between the podium and the main building;

[0056] The monitoring module is used to monitor the settlement difference between the podium and the main building, and determine the change trend of the measured value of the settlement difference between the podium and the main building based on the monitoring data;

[0057] A correlation evaluation module is used to evaluate the change trend of the simulated settlement difference value between the podium and the main building and the change trend of the measured settlement difference value by using the Pearson correlation coefficient formula, and obtain the correlation coefficient of the change trend of the simulated settlement difference value between the podium and the main building and the change trend of the measured settlement difference value;

[0058] The decision module is used to determine the post-casting strip closure construction strategy based on the correlation coefficient.

[0059] Post-cast strip closure construction strategies include:

[0060] If the correlation coefficient is in the highly correlated section and the residual settlement difference is not greater than the closure construction threshold, all post-casting strips are directly closed;

[0061] If the correlation coefficient is in the moderate correlation section and the residual settlement difference is not greater than the closed construction threshold, the horizontal section of the post-casting strip is closed, and the post-casting strips at the four corners are reserved and not closed until the overall construction is completed;

[0062] If the correlation coefficient is in the weak correlation section and the residual settlement difference is not greater than the closed construction threshold, the horizontal section of the post-cast strip is closed, and the post-cast strips at the four corners are not closed. After the overall construction is completed, the horizontal section and the four corners are closed;

[0063] If the correlation coefficient is in the non-correlated section and the remaining settlement difference is not greater than the closed construction threshold, the post-casting strip will be closed after the overall construction is completed and the settlement trend becomes stable.

[0064] Among them, let the correlation coefficient be P, the highly correlated segment is 0.8≤|P|≤1, the moderately correlated segment is 0.5≤|P|<0.8, the weakly correlated segment is 0.3≤|P|<0.5, the uncorrelated segment is 0≤|P|<0.3, and the closed construction threshold is one two thousandth of the span of the post-casting strip.

[0065] Among them, Fig.10 As shown, the analog module includes:

[0066] Modeling unit, used to establish construction simulation analysis model, apply loads and specify boundary conditions;

[0067] The grouping unit is used to establish structure groups according to the construction plan, designate components to be constructed simultaneously as a structure group, and establish load groups and boundary groups according to the construction steps;

[0068] Connection elements, which are used to specify shrinkage creep coefficients and concrete strength development functions and are connected to the corresponding components;

[0069] Definition unit, used to define construction phase analysis data according to the actual construction plan. The construction phase analysis data includes construction step length and corresponding structure group, load group and boundary group;

[0070] The analysis unit is used to conduct construction simulation analysis and load combination to determine the settlement difference between the building's podium and main building.

[0071] Among them, in the monitoring module, the settlement difference between the podium and the main building is monitored, and there are at least two monitoring points.

[0072] The embodiment of the present invention also provides a computer-readable storage medium, on which a computer program is stored, and when the computer program is executed by a processor, each process of the above-mentioned super high-rise building structure post-casting strip early insertion and closure construction decision method embodiment can be achieved, and the same technical effect can be achieved. Among them, the computer-readable storage medium is, for example, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, etc.

[0073] The above description is a detailed description of the preferred feasible embodiments of the present invention, but the embodiments are not intended to limit the scope of the patent application of the present invention. All equivalent changes or modified changes completed under the technical spirit suggested by the present invention should fall within the patent scope covered by the present invention.

Claims

1. A construction decision method for early insertion and closure of post-cast strips of super high-rise building structures, characterized in that: include: S1, using standard construction simulation methods, conducts full-process construction simulation analysis on super high-rise buildings to obtain the change trend of the simulated settlement difference between the podium and the main building; S2, monitor the settlement difference between the podium and the main building, and determine the change trend of the measured value of the settlement difference between the podium and the main building based on the monitoring data; S3, using the Pearson correlation coefficient formula, evaluate the change trend of the simulated settlement difference value between the podium and the main building and the change trend of the measured settlement difference value, and obtain the correlation coefficient between the change trend of the simulated settlement difference value between the podium and the main building and the change trend of the measured settlement difference value; S4, determining a post-cast strip closure construction strategy according to the correlation coefficient; The post-casting strip closure construction strategy includes: If the correlation coefficient is in the highly correlated section and the residual settlement difference is not greater than the closure construction threshold, all post-casting strips are directly closed; If the correlation coefficient is in the moderate correlation section and the residual settlement difference is not greater than the closed construction threshold, the horizontal section of the post-casting strip is closed, and the post-casting strips at the four corners are reserved and not closed until the overall construction is completed; If the correlation coefficient is in the weak correlation section and the residual settlement difference is not greater than the closed construction threshold, the horizontal section of the post-cast strip is closed, and the post-cast strips at the four corners are not closed. After the overall construction is completed, the horizontal section and the four corners are closed; If the correlation coefficient is in the non-correlated section and the residual settlement difference is not greater than the closed construction threshold, the post-casting strip will be closed after the overall construction is completed.

2. The method for early insertion and closure of post-cast strips of super high-rise building structures according to claim 1 is characterized in that: The correlation coefficient is P, the highly correlated segment is 0.8≤|P|≤1, the moderately correlated segment is 0.5≤|P|<0.8, the weakly correlated segment is 0.3≤|P|<0.5, and the uncorrelated segment is 0≤|P|<0.

3.

3. The method for early insertion and closure of post-cast strips of super high-rise building structures according to claim 1 is characterized in that: The S1 includes: S11, establish a construction simulation analysis model, apply loads and specify boundary conditions; S12, establishing a structure group according to the construction plan, designating the components to be constructed simultaneously as a structure group, and establishing a load group and a boundary group according to the construction step; S13, specifies shrinkage creep coefficient and concrete strength development function, and connects to the corresponding components; S14, defining construction phase analysis data according to the actual construction plan, wherein the construction phase analysis data includes construction step length and corresponding structure groups, load groups and boundary groups; S15, conduct construction simulation analysis and load combination to determine the settlement difference between the building podium and the main building.

4. The method for early insertion and closure of post-cast strips of super high-rise building structures according to claim 1 is characterized in that: In S2, the settlement difference between the podium and the main building is monitored, with at least two monitoring points.

5. The method for early insertion and closure of post-cast strips of super high-rise building structures according to claim 1 is characterized in that: The closed construction threshold is one two thousandth of the span of the post-cast strip.

6. The construction decision system for early insertion and closure of post-cast strips in super high-rise building structures is characterized by: include: The simulation module is used to conduct a full-process construction simulation analysis of super-high-rise buildings using standard construction simulation methods to obtain the change trend of the simulated settlement difference between the podium and the main building; The monitoring module is used to monitor the settlement difference between the podium and the main building, and determine the change trend of the measured value of the settlement difference between the podium and the main building based on the monitoring data; A correlation evaluation module is used to evaluate the change trend of the simulated settlement difference value between the podium and the main building and the change trend of the measured settlement difference value by using the Pearson correlation coefficient formula, and obtain the correlation coefficient of the change trend of the simulated settlement difference value between the podium and the main building and the change trend of the measured settlement difference value; A decision module, used for determining a post-casting strip closing construction strategy according to the correlation coefficient; The post-casting strip closure construction strategy includes: If the correlation coefficient is in the highly correlated section and the residual settlement difference is not greater than the closure construction threshold, all post-casting strips are directly closed; If the correlation coefficient is in the moderate correlation section and the residual settlement difference is not greater than the closed construction threshold, the horizontal section of the post-casting strip is closed, and the post-casting strips at the four corners are reserved and not closed until the overall construction is completed; If the correlation coefficient is in the weak correlation section and the residual settlement difference is not greater than the closed construction threshold, the horizontal section of the post-cast strip is closed, and the post-cast strips at the four corners are not closed. After the overall construction is completed, the horizontal section and the four corners are closed; If the correlation coefficient is in the non-correlated section and the residual settlement difference is not greater than the closed construction threshold, the post-casting strip will be closed after the overall construction is completed.

7. The construction decision system for early insertion and closure of post-cast strips of super high-rise building structures according to claim 6 is characterized in that: Assuming the correlation coefficient is P, the highly correlated segment is 0.8≤|P|≤1, the moderately correlated segment is 0.5≤|P|<0.8, the weakly correlated segment is 0.3≤|P|<0.5, and the non-correlated segment is 0≤|P|<0.3; The closed construction threshold is one two thousandth of the span of the post-cast strip.

8. The construction decision system for early insertion and closure of post-cast strips of super high-rise building structures according to claim 6 is characterized in that: The simulation module comprises: Modeling unit, used to establish construction simulation analysis model, apply loads and specify boundary conditions; The grouping unit is used to establish structure groups according to the construction plan, designate components to be constructed simultaneously as a structure group, and establish load groups and boundary groups according to the construction step length; Connection elements, which are used to specify shrinkage creep coefficients and concrete strength development functions and are connected to the corresponding components; A definition unit is used to define construction stage analysis data according to an actual construction plan, wherein the construction stage analysis data includes a construction step and corresponding structure groups, load groups and boundary groups; The analysis unit is used to conduct construction simulation analysis and load combination to determine the settlement difference between the building's podium and main building.

9. The construction decision system for early insertion and closure of post-cast strips of super high-rise building structures according to claim 6 is characterized in that: In the monitoring module, the settlement difference between the podium and the main building is monitored, and there are at least two monitoring points.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes instructions, and when the instructions are executed on a computer, the computer is caused to execute the construction decision method for early insertion and closure of the post-cast strips of a super-high-rise building structure according to any one of claims 1 to 5.

Citation Information

Patent Citations

  • Safety verification method and device based on mouse track and computer equipment

    CN113806824A

  • Structure and mold for closing post-cast strip of basement in advance and construction method

    CN114991217A