Opening aligning construction device and method for heat distribution pipeline
By designing the counter-end construction device of thermal pipelines, the problems of unstable fixation, inconvenient movement, insufficient operating space and low docking accuracy in the prior art are solved, and efficient and accurate counter-end construction is achieved.
Patent Information
- Application Number
- CN202411611914.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-12
- Publication Date
- 2025-02-14
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing thermal pipeline docking devices have problems such as unstable fixation, inconvenient movement, insufficient operating space and low docking accuracy in large diameter, high temperature and high pressure environments.
A thermal pipe counterpart construction device is designed, including a fixed assembly, a moving assembly, an operating assembly and a counterpart assembly. The sliding function is achieved through the linkage structure, and the multiple structures of the load-bearing ring and the positioning column are used to achieve efficient fixing, providing flexible operating space adjustment, and precise counterparts are achieved through the cooperation of the docking ring and the threaded rod.
The sliding function of the device on the outer wall of the pipeline is realized, the construction efficiency is improved, the precise positioning and stability of the pipeline position is ensured, sufficient operating space is provided, and the accuracy and stability of docking are improved.
Smart Images

Figure CN119435819A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pipeline construction, in particular to a thermal pipeline docking construction device and a construction method. Background Art
[0002] Thermal pipelines are usually used to transport high-temperature media. The quality of pipeline docking directly affects the operating efficiency and safety of the heating system. Poorly docked pipeline interfaces may lead to air leakage, heat loss, and even the risk of bursting under high temperature and pressure, causing safety hazards and economic losses.
[0003] In the construction of thermal pipelines, the existing background technology mainly relies on traditional mechanical and manual docking devices. Although these devices can meet the basic requirements in general pipeline connections, they have many limitations in the specific environments of thermal pipelines such as large diameter, high temperature, and high pressure.
[0004] First of all, the traditional docking device is usually fixed by simple clamps, bolts and other means. In complex construction environments and large-diameter pipeline applications, it is difficult to provide sufficient fixing force and stability. Especially in the case of thermal expansion or large pipeline weight, the fixing components are prone to loosening or displacement, causing the docking interface to shift, affecting the welding accuracy and the sealing effect of the pipeline connection.
[0005] Secondly, after completing the docking of one interface, the existing docking device usually needs to be dismantled and reinstalled to the next interface position. It lacks sliding and quick movement functions. This cumbersome transportation and reinstallation process is not only time-consuming and labor-intensive, but also increases the construction difficulty and safety risks. It is difficult to adapt to the efficient needs of long-distance and multi-interface pipeline construction.
[0006] In addition, existing devices have significant deficiencies in providing operating space. After the device is installed, it usually lacks space adjustment function, which makes it difficult for construction workers to freely weld or perform matching operations at the pipeline interface. This space limitation is particularly obvious in narrow or complex environments, affecting the convenience of construction and the accuracy of welding operations.
[0007] To this end, those skilled in the art provide a thermal pipeline docking construction device and a construction method to solve the problems raised in the above background technology. Summary of the invention
[0008] In view of the deficiencies in the prior art, the present invention provides a thermal pipeline docking construction device and a construction method, which solves the obvious deficiencies in the prior art in terms of fixing stability, mobility convenience, operating space adjustment and docking accuracy control.
[0009] To achieve the above purpose, the present invention is implemented through the following technical scheme: a thermal pipeline docking construction device, comprising:
[0010] The pipeline body is divided into multiple sections, wherein multiple components are arranged on one side close to both ends;
[0011] There are multiple sets of fixing components, two of which are symmetrically arranged on the outer walls of multiple pipe bodies, and are used to fix the pipe bodies on both sides when they are connected;
[0012] The moving component is arranged on one side of the fixed component and provides a sliding function on the outer wall of the pipeline body when the fixed component is in a non-fixed state;
[0013] An operating component is arranged on one side of the fixed component, used for connecting the opposite fixed components and providing a construction operation space;
[0014] The docking component is arranged on one side of the operating component and is used to adjust the docking of the pipeline body.
[0015] Preferably, the motion component includes a accommodating bin, a plurality of the accommodating bins are fixed on one side of the first load-bearing ring, a lead screw rotates inside the accommodating bin, a worm gear is fixed on one side of the lead screw, the worm gear is connected with a worm rotating on one side of the accommodating bin by meshing, and is used to transmit power when the fixed component is adjusted to a non-fixed state, a push plate is threaded on the outer wall of the lead screw, a support plate is installed on one side of the push plate, and one side of the plurality of support plates is connected to the rotating wheel via a bearing, and is used to control the movement of the rotating wheel in the inner cavity of the accommodating bin.
[0016] Preferably, the fixing assembly includes a first load-bearing ring, and multiple first load-bearing rings are sleeved on the outer wall of the pipe body. Multiple positioning columns are installed on one side of the first load-bearing ring, and one side of the positioning column is rotatably connected to a rotating rod. The outer wall of the rotating rod is sleeved with a clamping sleeve, and bolt rods are installed on the upper and lower ends of the clamping sleeve, which are respectively connected to the outer ring and the inner ring, and a gear ring is installed on the outer wall of the inner ring. Multiple gears are rotatably provided on one side of the first load-bearing ring, and a locking ring is installed on one side of the rotating rod for increasing friction after contact with the pipe body.
[0017] Preferably, one side of the gear is connected to a worm for transmitting power to the moving component.
[0018] Preferably, the operating component includes an extension rod, and a plurality of the extension rods are installed on one side of a first load-bearing ring. The inner walls of the plurality of first load-bearing rings are sleeved with a plurality of second load-bearing rings, wherein the plurality of second load-bearing rings slide on one side of the plurality of extension rods, and the change of the construction space is controlled by adjusting the gaps between the plurality of second load-bearing rings.
[0019] Preferably, the docking component includes a docking ring, which is installed on one side of the operating component, the outer wall of the docking ring is threadedly connected to multiple threaded rods, a swivel is fixed on one side of the threaded rod, and an extrusion plate is fixed on one side of the threaded rod for controlling the docking position of the pipe bodies on both sides.
[0020] Preferably, a protruding block is installed on one side of the docking ring, and a docking groove is provided on the side of the protruding block corresponding to the docking ring for completing the connection to the first load-bearing ring.
[0021] Preferably, the plurality of extension rods are aligned with the center of the first load-bearing ring.
[0022] Preferably, a docking block is fixed on one side of the outer wall of the inner ring, a shaft block is rotatably connected to one side of the docking block, a mounting block is rotatably connected to one side of the first load-bearing ring, a screw is rotatably connected to one side of the mounting block, and the screw is threadedly connected to the inner wall of the shaft block. When the inner ring rotates, it drives the gear ring to engage with multiple gears.
[0023] The heat pipe joint construction method, according to the heat pipe joint construction device, comprises the following steps:
[0024] S1. Fix the first load-bearing ring of the device at both ends of the outer wall of the pipeline body, and rotate the screw on the outer wall of the mounting block to cause the shaft block to pull the docking block and the inner ring to rotate clockwise, so as to cooperate with the ferrule to push multiple locking rings to contact the pipeline body, thereby completing the initial fixation and ensuring that the device can fit the pipeline tightly to prevent displacement;
[0025] S2. After the first load-bearing rings on both sides are aligned and fixed on the pipe body, the docking rings connected thereto are connected and locked by the protruding blocks, and the initial adjustment of the docking position is performed by the threaded rods connected by threads, and the docking positions of the pipe bodies on both sides are controlled by the extrusion plates to align them;
[0026] S3. After the alignment is completed, the distance between the corresponding second load-bearing rings is adjusted according to the needs of the staff, so that the staff can probe into the inner cavity of the extension rod and perform construction operations on the joints of multiple pipe bodies inside the docking ring;
[0027] S4. After the construction is completed, the fixing assembly is adjusted to a non-fixed state, specifically, the screw is rotated in the opposite direction, so that the inner ring drives the outer ring to rotate counterclockwise, thereby completing the separation of the locking ring from the pipe body. During the counterclockwise movement of the inner ring, the rotational force is transmitted to the gear through the meshing of the gear ring, and then through the connection between the worm connected to the gear and the worm wheel, the push plate and the connected support plate and the rotating wheel are pushed out from the inner cavity of the accommodation chamber through the threaded connection, and when the screw reaches the limit of movement, the rotating wheel is brought into contact with the pipe body;
[0028] S5. When the fixed component is in a non-fixed state, the pushing device is moved along the axial direction of the pipeline body to the next docking position. After sliding to the target position, steps S1 to S4 are repeated to perform construction.
[0029] The present invention provides a thermal pipeline docking construction device and a construction method, which have the following beneficial effects:
[0030] 1. The present invention utilizes linkage to realize the sliding function of the device on the outer wall of the pipeline, so that the device can be easily moved to the next pair of interface positions, reducing cumbersome disassembly and assembly steps and improving construction efficiency.
[0031] 2. The present invention realizes efficient and stable fixation through the multiple structures of the load-bearing ring and the positioning column. The design of the locking ring increases the friction between the pipeline and the device, ensuring the precise positioning and stability of the pipeline position during the docking construction process.
[0032] 3. The present invention provides a flexible operating space adjustment function through the sliding structure of the extension rod and the second load-bearing ring, so that construction personnel can adjust the size of the operating space as needed, ensuring sufficient operating space during the docking and welding process, and having stronger adaptability.
[0033] 4. The present invention makes the connection of the pipes on both sides more precise through the cooperation of the docking ring, the threaded rod and the extrusion plate. At the same time, the design of the protruding block and the docking groove improves the overall connection strength and docking stability of the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 A perspective view of the present invention;
[0035] Figure 2 It is a schematic diagram of the structure explosion of the present invention;
[0036] Figure 3 It is a schematic diagram of the ferrule structure of the present invention;
[0037] Figure 4 It is a side view structural schematic diagram of the present invention;
[0038] Figure 5 It is a schematic diagram of the cross-sectional structure of the first load-bearing ring of the present invention;
[0039] Figure 6 for Figure 5 A magnified image of point A;
[0040] Figure 7 It is a schematic diagram of the cross-sectional structure of the storage bin of the present invention;
[0041] Figure 8 It is a step diagram of the construction method of the present invention.
[0042] Among them, 1. pipeline body; 2. first load-bearing ring; 3. positioning column; 4. rotating rod; 5. inner ring; 6. outer ring; 7. gear ring; 8. gear; 9. ferrule; 10. bolt rod; 11. locking ring; 12. screw; 13. mounting block; 14. docking block; 15. shaft block; 16. containing chamber; 17. worm; 18. worm wheel; 19. lead screw; 20. push plate; 21. support plate; 22. rotating wheel; 23. extension rod; 24. docking ring; 25. second load-bearing ring; 26. threaded rod; 27. rotating ring; 28. protruding block; 29. extrusion plate. DETAILED DESCRIPTION
[0043] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0044] Embodiment 1:
[0045] The embodiment of the present invention provides a thermal pipeline docking construction device, comprising:
[0046] Please refer to the attached Figure 1 , the pipeline body 1, is divided into multiple sections, wherein multiple components are arranged on one side close to both ends;
[0047] Specifically, the pipeline body 1 is divided into a multi-section structure, and a plurality of structural components are arranged on the adjacent sides of both ends of each section to ensure that the precise docking and firm connection of each section of the pipeline can be effectively completed during the docking process. These components mainly include fixed components, moving components, operating components and matching components, and each component realizes the functionality of the overall docking device through scientific design and tight structural connection. During the pipeline docking process, the first load-bearing ring 2 is sleeved on the outer wall of the pipeline body 1, and its combination with the pipeline body 1 is initially fixed and fitted through the cooperation of the positioning column 3, the rotating rod 4 and the locking ring 11 to ensure that the docking position does not move. In addition, through the locking connection between the docking ring 24 and the protruding block 28, the device realizes the precise alignment of the pipelines on both sides. The connection relationship between the threaded rod 26 of the docking ring 24 and the extrusion plate 29 enables the staff to accurately adjust and positionally control the matching of multiple pipeline bodies 1 inside the docking ring 24, ensuring the sealing and position stability of the two sections of the pipeline when docking.
[0048] Please refer to the attached Figure 2 -Attached Figure 4 , fixing components, there are multiple groups, two of which are symmetrically arranged on the outer walls of multiple pipe bodies 1, and are used to fix the pipe bodies 1 on both sides when they are matched;
[0049] The fixing assembly includes a first load-bearing ring 2, and a plurality of first load-bearing rings 2 are sleeved on the outer wall of the pipe body 1. A plurality of positioning columns 3 are installed on one side of the first load-bearing ring 2. A rotating rod 4 is rotatably connected to one side of the positioning column 3. A clamping sleeve 9 is sleeved on the outer wall of the rotating rod 4. Bolts 10 are installed on both upper and lower ends of the clamping sleeve 9, which are respectively connected to the outer ring 6 and the inner ring 5. A gear ring 7 is installed on the outer wall of the inner ring 5. A plurality of gears 8 are rotatably arranged on one side of the first load-bearing ring 2. A locking ring 11 is installed on one side of the rotating rod 4 to increase the friction after contact with the pipe body 1. One side of the gear 8 is connected to the worm 17 to transmit power to the moving assembly.
[0050] A docking block 14 is fixed to one side of the outer wall of the inner ring 5, and a shaft block 15 is rotatably connected to one side of the docking block 14. A mounting block 13 is rotatably connected to one side of the first load-bearing ring 2, and a screw 12 is rotatably connected to one side of the mounting block 13. The screw 12 is threadedly connected to the inner wall of the shaft block 15. When the inner ring 5 rotates, it drives the gear ring 7 to engage with multiple gears 8.
[0051] Specifically, the fixing components are designed as multiple groups of structures, wherein two groups of fixing components are symmetrically distributed on the outer walls of multiple pipe bodies 1, ensuring that the pipe bodies 1 on both sides can be stably fixed during the docking process, maintaining the stability and accuracy of the docking interface position.
[0052] The core component of the fixing assembly is the first load-bearing ring 2, which is sleeved on the outer wall of the pipe body 1 in multiple ways to provide a stable support. The structure of the first load-bearing ring 2 not only provides a load-bearing function, but also has multiple positioning columns 3 installed on one side. The ends of these positioning columns 3 are connected to the rotating rod 4 by a rotating connection, so that the position can be flexibly adjusted. A sleeve 9 is sleeved on the outer wall of the rotating rod 4, and a bolt rod 10 is installed at the upper and lower ends of the sleeve 9. One end of the bolt rod 10 is respectively connected to the outer ring 6 and the inner ring 5, thereby fixing the inner and outer rings to the first load-bearing ring 2. A gear ring 7 is further installed on the outer wall of the inner ring 5. The gear ring 7 is meshed with multiple gears 8 on one side of the first load-bearing ring 2, and the other side of the gear 8 is connected to the worm 17, forming a stable power transmission path to provide power for the moving assembly.
[0053] By rotating the screw 12 on the outer wall of the mounting block 13, the shaft block 15 pulls the docking block 14 and the inner ring 5 to rotate clockwise, thereby cooperating with the ferrule 9 to push the multiple locking rings 11 to contact the pipe body 1, thereby completing the initial fixation and ensuring that the device can fit tightly to the pipe to prevent displacement.
[0054] Please see attached Figure 5 -Attached Figure 7 , a moving component is arranged on one side of the fixed component, and provides a sliding function on the outer wall of the pipe body 1 when the fixed component is in a non-fixed state;
[0055] The motion component includes a accommodating chamber 16, and multiple accommodating chambers 16 are fixed on one side of the first load-bearing ring 2. A lead screw 19 rotates inside the accommodating chamber 16, and a worm gear 18 is fixed on one side of the lead screw 19. The worm gear 18 is connected to a worm 17 rotating on one side of the accommodating chamber 16 through meshing, and is used to transmit power when the fixed component is adjusted to a non-fixed state. A push plate 20 is threaded on the outer wall of the lead screw 19, and a support plate 21 is installed on one side of the push plate 20. One side of multiple support plates 21 is connected to a rotating wheel 22 through a bearing, which is used to control the movement of the rotating wheel 22 in the inner cavity of the accommodating chamber 16.
[0056] Specifically, after the construction is completed, the fixing assembly is adjusted to a non-fixed state, specifically, the screw 12 is rotated in the opposite direction, so that the inner ring 5 drives the outer ring 6 to rotate counterclockwise, thereby completing the separation of the locking ring 11 from the pipeline body 1. During the counterclockwise movement of the inner ring 5, the rotational force is transmitted to the gear 8 through the meshing of the gear ring 7, and then through the connection between the worm 17 connected to the gear 8 and the worm wheel 18, the push plate 20 and the connected support plate 21 and the rotating wheel 22 are pushed out from the inner cavity of the accommodating chamber 16 through threaded connection, and when the screw 12 reaches the limit of movement, the rotating wheel 22 is brought into contact with the pipeline body 1.
[0057] The core component of the moving component is the storage bin 16. Multiple storage bins 16 are firmly fixed on one side of the first load-bearing ring 2 to provide protection and support for the moving components. The internal structure of the storage bin 16 is designed with a rotatable lead screw 19. A worm wheel 18 is installed at one end of the lead screw 19. The worm wheel 18 is connected to the worm 17 by meshing connection to form a transmission system. When the fixed component is unlocked, the worm 17 starts to rotate driven by the power source, and the rotational force is transmitted to the lead screw 19 through the worm wheel 18, pushing the lead screw 19 to achieve rotational motion.
[0058] The outer wall of the lead screw 19 is provided with a thread, and a push plate 20 is installed on the threaded part. The push plate 20 moves axially along the thread when the lead screw 19 rotates. A support plate 21 is installed on one side of the push plate 20, and the support plate 21 is connected to the runner 22 through a bearing. Such a structural design enables the push plate 20 to push the support plate 21 and the runner 22 to produce a smooth sliding movement in the inner cavity of the storage chamber 16 under the drive of the lead screw 19. The movement of the runner 22 in the inner cavity of the storage chamber 16 is controlled by the support plate 21, thereby realizing the sliding function of the motion component. When the runner 22 contacts the outer wall of the pipeline body 1, the entire device can slide along the pipeline axial direction and easily move from one docking position to the next position. The structural design of the motion component not only ensures the stability of sliding and the accuracy of positioning, but also can greatly reduce the manpower burden during the pipeline docking process, improve construction efficiency, and make the movement of the docking device more convenient and efficient.
[0059] Please see attached Figure 4, an operating component, which is arranged on one side of the fixed component, is used to connect the opposite fixed components and provide construction operation space; the operating component includes an extension rod 23, multiple extension rods 23 are installed on one side of the first load-bearing ring 2, and the inner walls of the multiple first load-bearing rings 2 are sleeved with multiple second load-bearing rings 25, wherein the multiple second load-bearing rings 25 slide on one side of the multiple extension rods 23, and the construction space changes are controlled by adjusting the gaps between the multiple second load-bearing rings 25.
[0060] Specifically, the component is installed on one side of the fixed component, forming a tight connection with the fixed component, and the space can be adjusted according to specific construction requirements. The core component of the operating component is the extension rod 23, and multiple extension rods 23 are firmly installed on one side of the first load-bearing ring 2 to form a support and connection basis. The inner wall of each first load-bearing ring 2 is sleeved with a second load-bearing ring 25, and multiple second load-bearing rings 25 can slide along the extension rod 23 to achieve relative position adjustment.
[0061] The sliding characteristics of the second load-bearing ring 25 give the device flexibility, allowing the staff to control the size of the internal space by adjusting the distance between the second load-bearing rings 25 when more operating space is needed. This design makes it easy for the staff to adjust the optimal working angle and space, so as to more efficiently complete the docking operation of the pipeline body 1 inside the docking ring 24. Specifically, the staff can increase the distance between the second load-bearing rings 25, so as to probe into the inner cavity of the extension rod 23 and perform precise welding, connection or other docking operations inside the docking ring 24. In this way, the operating assembly not only provides sufficient construction space, but also can be flexibly adjusted according to construction needs, adapting to operations in different pipeline docking conditions and positions, and helping to improve construction efficiency and docking accuracy. The design of this structure also further ensures the convenience and safety of construction personnel during docking operations.
[0062] Please see attached Figure 4 , a docking assembly, which is arranged on one side of the operating assembly, is used to adjust the docking of the pipe body 1. The docking assembly includes a docking ring 24, which is installed on one side of the operating assembly. The outer wall of the docking ring 24 is threadedly connected with a plurality of threaded rods 26, a swivel 27 is fixed on one side of the threaded rod 26, and an extrusion plate 29 is fixed on one side of the threaded rod 26, which is used to control the docking position of the pipe bodies 1 on both sides.
[0063] A protruding block 28 is installed on one side of the docking ring 24 , and a docking groove is provided on the side of the protruding block 28 corresponding to the docking ring 24 for completing the connection with the first load-bearing ring 2 .
[0064] The plurality of extension rods 23 are aligned with the center of the first load-bearing ring 2 .
[0065] Specifically, the docking assembly is installed on one side of the operating assembly, and its main function is to adjust and control the docking position of the pipeline body 1 to ensure that the two sections of the pipeline can be accurately aligned when docked to achieve a stable connection. The core part of the docking assembly is the docking ring 24, which is firmly fixed on one side of the operating assembly and realizes an adjustable threaded connection with multiple threaded rods 26 through the threaded structure of the outer wall of the docking ring 24. A swivel 27 is installed at one end of the threaded rod 26. The function of the swivel 27 is to provide an operating fulcrum for the rotation of the threaded rod 26, so that the staff can easily adjust the axial position of the threaded rod 26.
[0066] A squeeze plate 29 is fixed to the other end of the threaded rod 26. By rotating the threaded rod 26, the squeeze plate 29 can move back and forth between the inner and outer walls of the docking ring 24, squeezing or releasing the two sides of the pipe body 1, so that the docking position can be precisely controlled. This adjustable movement mechanism of the squeeze plate 29 ensures that during the docking operation, the two ends of the pipe body 1 always maintain the correct position and docking angle, avoiding welding quality problems or interface leakage caused by position deviation.
[0067] In addition, a protruding block 28 is designed on one side of the docking ring 24, and the protruding block 28 corresponds to the docking groove on one side of the docking ring 24 in structure, so that it can be firmly connected to the first load-bearing ring 2 during the installation process. Through the matching design of the protruding block 28 and the docking groove, a reliable connection structure is formed between the docking ring 24 and the first load-bearing ring 2, further improving the overall stability of the device and preventing loosening or deviation during the docking process.
[0068] The multiple extension rods 23 are aligned with the center of the first load-bearing ring 2. This structural design ensures that the device can maintain symmetry and balance during the pipe docking process, which helps to improve the accuracy and stability of docking. Through the tight and orderly connection design between the various parts of the docking component, the entire device can effectively adapt to the docking requirements of pipes of different diameters and materials, ensuring the smooth docking operation and the reliability of the final connection.
[0069] Embodiment 2:
[0070] Please see attached Figure 8 The embodiment of the present invention provides a thermal pipeline docking construction method, comprising the following steps:
[0071] S1. Fix the first load-bearing ring 2 of the device at both ends of the outer wall of the pipe body 1, and rotate the screw 12 on the outer wall of the mounting block 13 to cause the shaft block 15 to pull the docking block 14 and the inner ring 5 to rotate clockwise, thereby cooperating with the ferrule 9 to push the multiple locking rings 11 to contact the pipe body 1, thereby completing the initial fixation and ensuring that the device can fit the pipe tightly to prevent displacement;
[0072] S2. After the first load-bearing rings 2 on both sides are aligned and fixed on the pipe body 1, the docking rings 24 connected thereto are connected and locked by the protruding blocks 28, and the initial adjustment of the docking position is performed by the threaded rods 26 connected by threads, and the extrusion plates 29 are used to control the docking positions of the pipe bodies 1 on both sides to align them;
[0073] S3. After the alignment is completed, the distance between the corresponding second load-bearing rings 25 is adjusted according to the needs of the staff, so that the staff can probe into the inner cavity of the extension rod 23 and perform construction operations on the joints of multiple pipe bodies 1 inside the docking ring 24;
[0074] S4. After the construction is completed, the fixing assembly is adjusted to a non-fixed state, specifically, the screw 12 is rotated in the opposite direction, so that the inner ring 5 drives the outer ring 6 to rotate counterclockwise, thereby completing the separation of the locking ring 11 from the pipe body 1. During the counterclockwise movement of the inner ring 5, the rotational force is transmitted to the gear 8 through the meshing of the gear ring 7, and then through the connection between the worm 17 connected to the gear 8 and the worm wheel 18, the push plate 20 and the connected support plate 21 and the rotating wheel 22 are pushed out from the inner cavity of the accommodating chamber 16 through threaded connection, and when the screw 12 reaches the limit of movement, the rotating wheel 22 is brought into contact with the pipe body 1;
[0075] S5. When the fixed component is in a non-fixed state, the pushing device is moved axially along the pipeline body 1 to the next docking position. After sliding to the target position, steps S1 to S4 are repeated to perform construction.
[0076] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A heat pipe docking construction device, characterized in that: include: The pipeline body (1) is divided into multiple sections, wherein multiple components are arranged on one side close to both ends; There are a plurality of fixing components, two of which are symmetrically arranged on the outer walls of the plurality of pipe bodies (1) and are used to fix the pipe bodies (1) on both sides when they are aligned; A moving component is arranged on one side of the fixed component and provides a sliding function on the outer wall of the pipe body (1) when the fixed component is in a non-fixed state; An operating component is arranged on one side of the fixed component, used for connecting the opposite fixed components and providing a construction operation space; The docking assembly is arranged on one side of the operating assembly and is used to adjust the docking of the pipeline body (1).
2. The thermal pipeline docking construction device according to claim 1 is characterized in that: The motion component comprises a accommodating chamber (16), a plurality of the accommodating chambers (16) are fixed on one side of the first load-bearing ring (2), a lead screw (19) is rotatable inside the accommodating chamber (16), a worm wheel (18) is fixed on one side of the lead screw (19), the worm wheel (18) is connected to a worm (17) rotating on one side of the accommodating chamber (16) through meshing, and is used to transmit power when the fixed component is adjusted to a non-fixed state, a push plate (20) is threaded on the outer wall of the lead screw (19), a support plate (21) is installed on one side of the push plate (20), and one side of the plurality of support plates (21) is connected to a rotating wheel (22) through a bearing, and is used to control the movement of the rotating wheel (22) in the inner cavity of the accommodating chamber (16).
3. The thermal pipeline docking construction device according to claim 1 is characterized in that: The fixing assembly comprises a first load-bearing ring (2), a plurality of the first load-bearing rings (2) are sleeved on the outer wall of the pipe body (1), a plurality of positioning columns (3) are installed on one side of the first load-bearing ring (2), a rotating rod (4) is rotatably connected to one side of the positioning column (3), a clamping sleeve (9) is sleeved on the outer wall of the rotating rod (4), bolt rods (10) are installed at both upper and lower ends of the clamping sleeve (9), respectively connected to the outer ring (6) and the inner ring (5), a gear ring (7) is installed on the outer wall of the inner ring (5), a plurality of gears (8) are rotatably provided on one side of the first load-bearing ring (2), and a locking ring (11) is installed on one side of the rotating rod (4) for increasing the friction force after contact with the pipe body (1).
4. The thermal pipeline docking construction device according to claim 3 is characterized in that: One side of the gear (8) is connected to a worm (17) for transmitting power to the moving component.
5. The thermal pipeline docking construction device according to claim 3 is characterized in that: The operating assembly comprises an extension rod (23), wherein a plurality of the extension rods (23) are mounted on one side of a first load-bearing ring (2), wherein the inner walls of the plurality of first load-bearing rings (2) are sleeved with a plurality of second load-bearing rings (25), wherein the plurality of second load-bearing rings (25) slide on one side of the plurality of extension rods (23), and the change of the construction space is controlled by adjusting the gaps between the plurality of second load-bearing rings (25).
6. The thermal pipeline docking construction device according to claim 5 is characterized in that: The docking assembly comprises a docking ring (24) which is installed on one side of the operating assembly. The outer wall of the docking ring (24) is threadedly connected with a plurality of threaded rods (26). A swivel (27) is fixed on one side of the threaded rod (26). An extrusion plate (29) is fixed on one side of the threaded rod (26) for controlling the docking positions of the pipeline bodies (1) on both sides.
7. The thermal pipeline docking construction device according to claim 6 is characterized in that: A protruding block (28) is installed on one side of the docking ring (24), and a docking groove is provided on the side of the protruding block (28) corresponding to the docking ring (24) for completing the connection with the first load-bearing ring (2).
8. The thermal pipeline docking construction device according to claim 6, characterized in that: The plurality of extension rods (23) are aligned with the center of the first load-bearing ring (2).
9. The thermal pipeline docking construction device according to claim 3, characterized in that: A docking block (14) is fixed on one side of the outer wall of the inner ring (5), and a shaft block (15) is rotatably connected to one side of the docking block (14). A mounting block (13) is rotatably connected to one side of the first load-bearing ring (2), and a screw rod (12) is rotatably connected to one side of the mounting block (13). The screw rod (12) is threadedly connected to the inner wall of the shaft block (15). When the inner ring (5) rotates, the gear ring (7) is driven to engage with the plurality of gears (8).
10. A method for heat pipe joint construction, according to the heat pipe joint construction device according to any one of claims 1 to 9, characterized in that: The following steps are involved: S1. Fix the first load-bearing ring (2) of the device at the two ends of the outer wall of the pipeline body (1), and by rotating the screw (12) on the outer wall of the mounting block (13), the shaft block (15) pulls the docking block (14) and the inner ring (5) to rotate clockwise, thereby cooperating with the ferrule (9) to push the multiple locking rings (11) to contact the pipeline body (1), thereby completing the initial fixation and ensuring that the device can fit the pipeline tightly to prevent displacement; S2. After the first load-bearing rings (2) on both sides are aligned and fixed on the pipe body (1), the docking rings (24) connected thereto are connected and locked by means of the protruding blocks (28), and the docking position is preliminarily adjusted by means of the threaded rods (26) connected thereto, and the docking positions of the pipe bodies (1) on both sides are controlled by means of the extrusion plates (29) so as to align them; S3. After the alignment is completed, the distance between the corresponding second load-bearing rings (25) is adjusted according to the needs of the staff, so that the staff can probe into the inner cavity of the extension rod (23) and perform construction operations on the joints of the multiple pipe bodies (1) inside the docking ring (24); S4. After the construction is completed, the fixing assembly is adjusted to a non-fixed state, specifically, the screw (12) is rotated in the opposite direction, so that the inner ring (5) drives the outer ring (6) to rotate counterclockwise, thereby completing the separation of the locking ring (11) from the pipeline body (1). During the counterclockwise movement of the inner ring (5), the rotational force is transmitted to the gear (8) through the meshing of the gear ring (7), and then through the connection between the worm (17) connected to the gear (8) and the worm wheel (18), the push plate (20) and the connected support plate (21) and the rotating wheel (22) are pushed out from the inner cavity of the accommodating chamber (16) through a threaded connection, and when the screw (12) reaches the limit of movement, the rotating wheel (22) is brought into contact with the pipeline body (1); S5. When the fixed component is in a non-fixed state, the pushing device is moved axially along the pipeline body (1) to the next docking position. After sliding to the target position, steps S1 to S4 are repeated to carry out construction.