Pair twisting and packaging integrated production line
By designing an integrated twisting and packaging production line, integrating the twisting and packaging processes, and using portal wire storage racks and tension adjustment mechanisms, the problem of cumbersome processes in cable production has been solved, and production efficiency has been improved and labor intensity reduced.
Patent Information
- Application Number
- CN202420569597.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-03-22
AI Technical Summary
The stranding and packaging process in cable production is cumbersome, resulting in low production efficiency, high cost, and high labor intensity. The existing technology requires multiple reel rotations and multiple processes, resulting in low production efficiency.
Design an integrated twisting and packaging production line, including a pay-off device, a twisting unit and a baling unit. It uses a portal wire storage rack and a tension adjustment mechanism to shorten the length of the production line, integrate twisting and packaging in the same process, and eliminate the need for rewinding. process, using space to increase line body functions.
The twisting and packaging can be completed at one time, which simplifies the production process and reduces the original 5 processes and 4 reel rotations to 3 processes and 2 reel rotations, greatly improving production efficiency and reducing personnel labor intensity. .
Smart Images

Figure CN221916741U_ABST
Abstract
Description
Technical Field
[0001] The invention relates to equipment used in twisting and packaging processes in cable production, specifically a twisting and packaging integrated machine production line. Background Art
[0002] Cable is a general term for cable reels such as optical cables and electrical cables. Cables have many uses, mainly used for controlling installation, connecting equipment, transmitting electricity, and other multiple functions. They are common and indispensable in daily life.
[0003] The production process of cables with classic structure is: conductor drawing, wire core extrusion, rewinding, twisting and packaging. According to the functional structure of the cable, additional processes can be added on the basis of the above.
[0004] For example, the existing two-color twisted pair production process is as follows Figure 1 ,include:
[0005] 1. The wire drawing process processes the copper wire conductor of the required wire diameter and winds it onto a wire reel (mostly 630 wire reels);
[0006] 2. The wire reel with the conductor is transferred to the wire core extrusion process to process the insulation layer; the wire core made by the wire core extrusion process is wound onto the wire reel (mostly 800 wire reels or 1000 wire reels);
[0007] 3. The wire reel with the wire core is transferred to the rewinding process for turning and printing. The processed cable is wound onto the reel (mostly 630 reel).
[0008] 4. The wire reel with the cable wound around it is transferred to the twisting process, and the two wire reels are twisted into a two-color wire and then collected on the reel;
[0009] 5. The two-color wires made by twisting are transferred to the packaging process for segmentation and packaging, and the finished products are put into storage.
[0010] The entire process involves five steps: conductor wire drawing, wire core extrusion, rewinding, twisting and packaging, and the wire reel is rotated four times. The production process is too complicated, resulting in low production efficiency, high production costs and high labor intensity for employees.
[0011] refer to Figure 2 The prior art twinning process production line includes a pay-off device (pay-off frame) 7, a twinning machine group 1, a traction machine (wheel traction machine) 6 and a take-up machine 8 which are sequentially arranged along the cable forward direction. Figure 3 The packaging process production line in the prior art includes a pay-off device (pay-off rack) 7, a storage device (storage rack) 3 and a packaging unit 2 arranged in sequence along the forward direction of the cable. In the twisting and packaging processes, the length needs to be recorded by a meter 4 and other equipment. Summary of the invention
[0012] In order to shorten the length of the production line (simplify the process) and improve production efficiency, the utility model proposes a twisting and baling integrated production line, including a wire-releasing device, a twisting machine group and a baling machine group; according to the processing direction, from back to front, they are the wire-releasing device, the twisting machine group and the baling machine group. It also includes a wire storage device;
[0013] The wire storage device is a gantry wire storage rack; a wire pay-off device is placed on the ground behind the gantry wire storage rack; a pair twisting unit is placed in the space below the gantry wire storage rack; and a packing unit is placed on the ground in front of the gantry wire storage rack;
[0014] The structure of the gantry wire storage rack includes: a column, a longitudinal beam, an inlet wire guide wheel, a wire storage wheel group, an outlet wire guide wheel and a tension adjustment mechanism of the wire storage wheel group;
[0015] There are two wire storage wheel groups, namely a first wheel group and a second wheel group;
[0016] The longitudinal beam is connected above the column; the first wheel group, the second wheel group and the inlet guide wheel are connected to the longitudinal beam in sequence from back to front; the outlet guide wheel is below the inlet guide wheel and connected to the column; the first wheel group and the second wheel group are respectively slidably connected to the longitudinal beam, and the sliding direction is the length direction of the longitudinal beam; the positions of the inlet guide wheel and the outlet guide wheel are fixed;
[0017] The tension adjustment mechanism includes a reduction motor, a steel cable, a wire drum, a first fixed guide wheel and a second fixed guide wheel; the first fixed guide wheel is connected to the longitudinal beam and is located behind the first wheel group; the second fixed guide wheel is connected to the longitudinal beam and is located in front of the wire inlet guide wheel;
[0018] The rotating output shaft of the reduction motor is connected to and drives the wire drum; the reduction motor and the wire drum are both connected to the longitudinal beam and between the first fixed guide wheel and the second fixed guide wheel; there are two wire drums, which rotate synchronously and in opposite directions; steel cables are respectively wound on the two wire drums; the steel cable on one wire drum passes around the first fixed guide wheel to connect to the first wheel group, and the steel cable on the other wire drum passes around the second fixed guide wheel to connect to the second wheel group; the two wire drums rotate towards or away from each other, and the first and second wheel groups move away from or close to each other;
[0019] A traction machine is arranged in front of the twisting unit and below the longitudinal beam. The outlet position of the traction machine is obliquely rearward and below the inlet guide wheel.
[0020] By using a specific wire storage device, the space on the production site is fully utilized, the length of the production line is shortened, and the two strandings and packaging are integrated into the same process.
[0021] Furthermore, between the wire storage device and the packaging unit, from back to front, there are meter counters and spark machines. In the production line, space is used rationally to increase the function of the line.
[0022] Specifically, the longitudinal beam is connected to a track; the first wheel set and the second wheel set are respectively connected to the pulleys, and the two pulleys cooperate with the track. A block is connected in the middle of the track to prevent the two pulleys from directly colliding; buffers (such as spring buffers) are respectively connected at the head and tail ends of the track to prevent the two pulleys from leaving the track.
[0023] The flow process of this production line is: twisting unit->traction machine->inlet guide wheel->storage wheel unit->outlet guide wheel->meter meter->spark machine->packing unit.
[0024] Compared with the prior art, the beneficial effects of this production line are: twisting and packaging can be completed at one time, the production process of twisting and packaging wires is optimized, and the rewinding process can be omitted.
[0025] Taking the production of two-color twisted pair wire as an example, after using the utility model, the original Figure 1 The 5 processes and 4 turns of the wire reel are simplified into Fig.10 The three working procedures and the reel transfer are performed twice, which greatly improves the production efficiency and reduces the labor intensity of the personnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the production process of two-color twisted pair wire in the prior art;
[0027] Figure 2 This is a twisting process production line in the prior art (top view);
[0028] Figure 3 This is a packaging process production line in the prior art (top view);
[0029] Figure 4 It is a schematic diagram of the production line of the utility model (main perspective);
[0030] Figure 5 It is a schematic diagram of the production line of the utility model (top view);
[0031] Figure 6 It is a schematic diagram of the wire storage device of the utility model (main perspective);
[0032] Figure 701 and Figure 702 They are partial structural schematic diagrams of the wire storage device;
[0033] Figure 8 This is a schematic diagram of the position principle of the second wheel group, the incoming wire guide wheel and the outgoing wire guide wheel (from a bird's-eye view), with the arrow pointing to the forward direction of the stranded wire;
[0034] Fig. 9 This is a schematic diagram of the position principle of the second wheel group, the incoming wire guide wheel and the outgoing wire guide wheel (main perspective), and the arrow points to the forward direction of the stranded wire;
[0035] Fig.10 This is a schematic diagram of the production process of two-color twisted pair wires after adopting the production line of the utility model;
[0036] In the figure: a twisting unit 1, a baling unit 2 (in this case, it includes a baling machine 201 and a film winding machine 202), a wire storage device 3, a meter 4, a spark machine 5, a traction machine 6, a wire pay-off device (in this case, an active wire pay-off frame) 7, a wire take-up machine 8, a tension wheel frame 9, a column 301, a longitudinal beam 302, an inlet guide wheel 303, an outlet guide wheel 304, a tension adjustment mechanism 305, a first wheel group 306, a second wheel group 307, a pulley 308, a block 309, a spring buffer 310, a reduction motor 3051, a steel cable 3052, a wire drum 3053, a first fixed guide wheel 3054, and a second fixed guide wheel 3055. DETAILED DESCRIPTION
[0037] The utility model is further described below in conjunction with the accompanying drawings and specific implementation methods.
[0038] refer to Figure 4-5 , a twine-twisting and baling integrated production line, comprising a wire-releasing device 7, a twine-twisting unit 1 and a baling unit 2; according to the processing direction, from back to front, there are the wire-releasing device, the twine-twisting unit and the baling unit, and also a wire-storing device 3. In this example, between the wire-storing device and the baling unit, from back to front, there are a meter 4 and a spark machine 5. A tension wheel frame 9 is also placed between the rear of the twine-twisting unit and the front of the wire-releasing device.
[0039] Further references Figure 6 The wire storage device 3 is a gantry wire storage rack; a wire pay-off device 7 is placed on the ground behind the gantry wire storage rack; a pair twisting unit 1 is placed in the space below the gantry wire storage rack; a packing unit 2 is placed on the ground in front of the gantry wire storage rack;
[0040] The structure of the gantry wire storage rack includes: a column 301, a longitudinal beam 302, a wire inlet guide wheel 303, a wire storage wheel group, a wire outlet guide wheel 304 and a tension adjustment mechanism 305 of the wire storage wheel group;
[0041] There are two wire storage wheel groups, namely a first wheel group 306 and a second wheel group 307;
[0042] Further references Figure 701 and Figure 702 , the longitudinal beam 302 is connected above the column 301; the first wheel group 306, the second wheel group 307 and the incoming wire guide wheel 303 are connected to the longitudinal beam from back to front in sequence; the outgoing wire guide wheel 304 is below the incoming wire guide wheel and connected to the column; the first wheel group and the second wheel group are respectively slidably connected to the longitudinal beam, and the sliding direction is the length direction of the longitudinal beam; the positions of the incoming wire guide wheel and the outgoing wire guide wheel are fixed;
[0043] The tension adjustment mechanism 305 includes a reduction motor 3051, a steel cable 3052, a wire drum 3053, a first fixed guide wheel 3054 and a second fixed guide wheel 3055; the first fixed guide wheel is connected to the longitudinal beam and is located behind the first wheel group 306; the second fixed guide wheel is connected to the longitudinal beam and is located in front of the inlet guide wheel 303;
[0044] The rotating output shaft of the reduction motor 3051 is connected to and drives the wire drum 3053; the reduction motor and the wire drum are both connected to the longitudinal beam and between the first fixed guide wheel 306 and the second fixed guide wheel 307; there are two wire drums, which rotate synchronously and in opposite directions; steel cables 3052 are respectively wound around the two wire drums; the steel cable on one wire drum passes around the first fixed guide wheel 3054 to connect to the first wheel group 306, and the steel cable on the other wire drum passes around the second fixed guide wheel 3055 to connect to the second wheel group 307; the two wire drums rotate towards or away from each other, and the first and second wheel groups move away from or close to each other;
[0045] A traction machine 6 is arranged in front of the twisting machine group 1. The traction machine is below the longitudinal beam, and the outlet position of the traction machine is obliquely rearward and below the inlet guide wheel 303.
[0046] In this example, the longitudinal beam is connected to a track; the first wheel set 306 and the second wheel set 307 are respectively connected to a pulley 308, and the two pulleys cooperate with the track. A stopper 309 is connected in the middle of the track to prevent the two pulleys from directly colliding; spring buffers 310 are respectively connected at the head and tail ends of the track to prevent the two pulleys from leaving the track.
[0047] refer to Figure 8 and Fig. 9 In this example, the path of the stranded wire on the wire storage device is: from the wire outlet of the traction machine, it goes obliquely upward, enters the wire inlet guide wheel from the front of the wire inlet guide wheel 303, and then enters the lower edge of the first wheel groove of the second wheel group 307 from the upper edge of the wire inlet guide wheel 303; after the stranded wire is wound around the second wheel group 307 and the first wheel group 306 for multiple turns, it goes obliquely downward from the upper edge of the last wheel groove of the second wheel group 307 into the lower edge of the wire outlet guide wheel 304, and finally leaves the wire storage device.
Claims
1. A twinning and baling integrated production line, comprising a pay-off device, a twinning unit and a baling unit; according to the processing direction, from back to front, the pay-off device, the twinning unit and the baling unit are arranged in sequence, and the characteristics are: Also included is a line storage device; The wire storage device is a gantry wire storage rack; a wire pay-off device is placed on the ground behind the gantry wire storage rack; and a pair twisting unit is placed in the space below the gantry wire storage rack; The baling unit is placed on the ground in front of the door-type wire storage rack; The structure of the gantry wire storage rack includes: a column, a longitudinal beam, an inlet wire guide wheel, a wire storage wheel group, an outlet wire guide wheel and a tension adjustment mechanism of the wire storage wheel group; There are two wire storage wheel groups, namely a first wheel group and a second wheel group; The longitudinal beam is connected above the column; the first wheel group, the second wheel group and the inlet guide wheel are connected to the longitudinal beam in sequence from back to front; the outlet guide wheel is below the inlet guide wheel and connected to the column; the first wheel group and the second wheel group are respectively slidably connected to the longitudinal beam, and the sliding direction is the length direction of the longitudinal beam; the positions of the inlet guide wheel and the outlet guide wheel are fixed; The tension adjustment mechanism includes a reduction motor, a steel cable, a wire drum, a first fixed guide wheel and a second fixed guide wheel; the first fixed guide wheel is connected to the longitudinal beam and is located behind the first wheel group; the second fixed guide wheel is connected to the longitudinal beam and is located in front of the wire inlet guide wheel; The rotating output shaft of the reduction motor is connected to and drives the wire drum; the reduction motor and the wire drum are both connected to the longitudinal beam and between the first fixed guide wheel and the second fixed guide wheel; there are two wire drums, which rotate synchronously and in opposite directions; steel cables are respectively wound on the two wire drums; the steel cable on one wire drum passes around the first fixed guide wheel to connect to the first wheel group, and the steel cable on the other wire drum passes around the second fixed guide wheel to connect to the second wheel group; the two wire drums rotate towards or away from each other, and the first and second wheel groups move away from or close to each other; A traction machine is arranged in front of the twisting unit and below the longitudinal beam. The outlet position of the traction machine is obliquely rearward and below the inlet guide wheel.
2. The twisted-to-pack integrated production line according to claim 1 is characterized in that Between the wire storage device and the packaging unit, from back to front, are the meter counter and spark machine.
3. The twisted-to-pack integrated production line according to claim 1 is characterized in that The longitudinal beam is connected with a track; the first wheel group and the second wheel group are respectively connected to the pulleys, and the two pulleys cooperate with the track.
4. The twisted-to-pack integrated production line according to claim 1 is characterized in that A stopper for preventing the two pulleys from directly colliding with each other is connected to the middle position of the track; buffers for preventing the two pulleys from leaving the track are respectively connected to the head and tail ends of the track.
5. The twisted-to-pack integrated production line according to claim 4 is characterized in that The buffer is a spring buffer.