Hoisting construction system for curtain wall flower stand beam cornice modeling aluminum plate construction

Through the construction method of combining the spider car and the wind rope, the problem of special shape of the aluminum plate of the eaves of the flower frame beam is solved, and efficient combination of lifting and installation is achieved, and construction efficiency and safety is improved. It is suitable for curtain wall flower frame beam eaves of the aluminum plate of the aluminum plate of the curtain wall flower frame beam eaves shape construction.

CN221971107UActive Publication Date: 2024-11-08DECORATION CO LTD OF CHINA CONSTR 3RD ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420223112.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-30
Publication Date
2024-11-08
Estimated Expiration
2034-01-30

AI Technical Summary

Technical Problem

In construction, it is difficult to use traditional lifting to the eaves of the aluminum plates on the eaves of the flower frame beams for installation. The lack of efficient lifting and installation technology, resulting in low construction efficiency and high safety risks.

Method used

Using the construction method of combining lifting spider cart and wind rope, the special-shaped aluminum plate is hoisted to the position to be installed through the hoist lifting device and the hand-pull hoist lifting device on both sides, and fixed with the embedded parts to achieve the combination of lifting and installation. construction.

Benefits of technology

It improves construction efficiency, reduces construction period and safety risks, enhances construction flexibility and accuracy, reduces personnel working at high altitudes, shortens construction cycles, and reduces cross-operation, ensuring the safety and applicability of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221971107U_ABST
    Figure CN221971107U_ABST
Patent Text Reader

Abstract

A hoisting construction system for curtain wall flower stand beam cornice modeling aluminum plate construction comprises a hoisting spider car, a winch lifting device and a chain block lifting device which are arranged on the hoisting spider car, and a wind cable used for assisting construction. Lifting ropes of the winch lifting device and the chain block lifting device are located on the two sides of the hoisting spider car correspondingly, and the ends of the lifting ropes are fixedly bound to the two sides of the modeling aluminum plate correspondingly after being hoisted downwards; the hoisting spider car comprises a bottom support plate, L-shaped wing frames arranged on the two sides of the top face of the bottom support plate and a balancing weight placed on the bottom support plate. The roof moving trolley adopted by the hoisting construction system is flexible, convenient to move and high in hoisting efficiency, meanwhile, the construction period can be greatly shortened by adopting integral assembly type hoisting with a surface layer, and the hoisting construction system can be widely applied to construction of curtain wall flower stand beam cornice modeling aluminum plates.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building construction, and specifically to a hoisting construction system for the construction of curtain wall flower rack beam eaves aluminum plates. Background Art

[0002] The aluminum plate at the bottom of the eaves of the flower rack beam is hoisted for construction. A tire frame is made on the ground and welded to a steel frame, and then the surface aluminum plate is installed to assemble it into a hoisting unit. The aluminum plate unit is generally designed into a special shape according to the shape of the eaves of the flower rack beam. The traditional technical solution of first hoisting it to the eaves and then laying it cannot be used. Utility Model Content

[0003] The purpose of the utility model is to provide a hoisting construction system for the construction of curtain wall flower rack beam eaves shaped aluminum plates, which adopts a hoisting spider car and a wind rope combined construction method, and hoists the special-shaped aluminum plates to the installation position through the winch lifting device and the hand hoist lifting device on the left and right sides, and then installs and fixes them with the embedded parts, thereby realizing a combined construction method of hoisting and installation.

[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0005] A hoisting construction system for the construction of aluminum plate moldings for the eaves of a curtain wall flower rack beam, wherein the main structure of the eaves of the flower rack beam is H-shaped, and the main structure comprises a middle floor deck structure, a left wall structure and a right wall structure located on the top surface of the middle floor deck structure, and a left beam structure and a right beam structure located on the bottom surface of the middle floor deck structure, wherein the bottom elevation of the left beam structure is higher than the bottom elevation of the right beam structure, and the hoisting construction system is arranged between the left wall structure and the right wall structure; the hoisting construction system is characterized in that: the hoisting construction system comprises a hoisting spider car, a winch lifting device and a hand winch lifting device arranged on the hoisting spider car The spider car is provided with a bottom bracket plate, an L-shaped wing frame provided on both sides of the top surface of the bottom bracket plate, and a counterweight block placed on the bottom bracket plate; a solid universal wheel is provided on the bottom surface of the bottom bracket plate; the horizontal parts of the L-shaped wing frames on both sides extend to the outside of the left wall structure and the right wall structure respectively; a reinforcing support is connected between the vertical parts of the L-shaped wing frames on both sides; a winch pulley is provided at the end of the horizontal part extending outward.

[0006] Further preferably, the hoisting spider car is formed by welding 80*60*4mm galvanized square tubes.

[0007] Furthermore, the width of the bottom bracket plate is adapted to the distance between the left wall structure and the right wall structure.

[0008] Furthermore, an auxiliary support device is provided between the vertical portion of the L-shaped wing frame and the left wall structure and the right wall structure, and the auxiliary support device includes a support rod and an auxiliary roller, the auxiliary roller abuts against the left wall structure and the right wall structure, and the support rod is arranged perpendicular to the wall.

[0009] In addition, the bottom bracket plate is 1100mm wide and 1600mm long; the vertical part of the L-shaped wing-spreading frame is 800mm high and the horizontal part is 650mm wide, and the spacing between the vertical parts of the L-shaped wing-spreading frame is 1000mm.

[0010] More preferably, an oblique support is welded between the horizontal portion and the vertical portion of the L-shaped wing-spreading frame.

[0011] Compared with the prior art, the utility model has the following characteristics and beneficial effects:

[0012] The mobile roof trolley used in the hoisting construction system of this application is flexible and has high hoisting efficiency in terms of mobility. At the same time, the overall assembled hoisting with surface layer can greatly save construction time and can be widely used in the construction of curtain wall flower rack beam eaves aluminum plates. Taking advantage of the main structural characteristics of the roof, a self-made mobile small crane can replace the crane for construction. At the same time, it can be fixed on both sides, which greatly reduces the difficulty of construction, can be fine-tuned, improves construction accuracy, and is more convenient to operate. The overall assembly reduces the number of people working at high altitudes on the facade, greatly reducing safety risks. The hoisting construction system of this application has a short construction period and saves construction time. Compared with traditional assembly construction, the overall assembled construction is more flexible in construction and reduces the time for the crane to be in place. At the same time, the roof adjustment is more convenient, which greatly shortens the construction period. It not only ensures safety, but also greatly reduces cross-operation. It has the characteristics of safety and applicability, has good promotion and practical value, and will produce good economic benefits after widespread promotion and application. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 This is a structural schematic diagram of a hoisting construction system for the construction of curtain wall flower stand beam cornice molding aluminum plates;

[0014] Figure 2 This is a schematic diagram of the structure of the spider car hoisting for this application;

[0015] Figure 3 for Figure 2 Top view;

[0016] Figure 4 This is a structural diagram of the aluminum plate construction completed for this application. DETAILED DESCRIPTION

[0017] In order to make the technical means, innovative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below.

[0018] The embodiments described herein are specific embodiments of the present invention, which are used to illustrate the concept of the present invention, are explanatory and exemplary, and should not be interpreted as limiting the embodiments of the present invention and the scope of the present invention. In addition to the embodiments described herein, those skilled in the art can also adopt other obvious technical solutions based on the claims and the contents disclosed in the specification of this application, including technical solutions that adopt any obvious replacement and modification of the embodiments described herein.

[0019] A hoisting construction system for the construction of curtain wall flower stand beam cornice molding aluminum plate, such as Figures 1 to 4 As shown, the main structure 1 of the eaves of the flower rack beam is H-shaped, and the main structure 1 includes a middle floor deck structure 11, a left wall structure 12 and a right wall structure 13 located on the top surface of the middle floor deck structure 11, and a left beam structure 14 and a right beam structure 15 located on the bottom surface of the middle floor deck structure 11. The bottom elevation of the left beam structure 14 is higher than the bottom elevation of the right beam structure 15. The hoisting construction system is arranged between the left wall structure 12 and the right wall structure 13; the hoisting construction system includes a hoisting The spider car 2, a winch lifting device 3 and a hand chain hoist lifting device 4 arranged on the hoisting spider car 2, and a wind rope 5 for auxiliary construction, the lifting ropes of the winch lifting device 3 and the hand chain hoist lifting device 4 are respectively located on both sides of the hoisting spider car 2, and the ends of the lifting ropes are tied and fixed to the two sides of the shaped aluminum plate after being hung down; the hoisting spider car 2 includes a bottom bracket plate 21, an L-shaped wing frame 22 arranged on both sides of the top surface of the bottom bracket plate 21, and a counterweight block 24 placed on the bottom bracket plate 21, and the bottom bracket plate 2 The bottom surface is provided with a solid universal wheel 26, the horizontal parts of the L-shaped wing frames 22 on both sides extend to the outside of the left wall structure 12 and the right wall structure 13 respectively, the vertical parts of the L-shaped wing frames 22 on both sides are connected with a reinforcing support 23, and the ends of the horizontal parts extending outward are provided with a winch pulley 25, the hoisting spider car 2 is formed by welding 80*60*4mm galvanized square tubes, the width of the bottom bracket plate 21 is adapted to the spacing between the left wall structure 12 and the right wall structure 13, and the vertical part of the L-shaped wing frame 22 is connected to the left wall structure 12. An auxiliary supporting device is provided between the structure 12 and the right wall structure 13, and the auxiliary supporting device includes a support rod and an auxiliary roller. The auxiliary roller abuts against the left wall structure 12 and the right wall structure 13. The support rod is arranged perpendicular to the wall. The bottom bracket plate 21 is 1100mm wide and 1600mm long; the vertical part of the L-shaped wing frame 22 is 800mm high and the horizontal part is 650mm wide. The spacing between the vertical parts of the L-shaped wing frame 22 is 1000mm, and an oblique support 27 is welded between the horizontal part and the vertical part of the L-shaped wing frame 22.

[0020] Construction process: measurement and layout → installation of post-embedded parts → assembly and acceptance of spider car → frame steel processing → roof frame assembly → full welding and painting after re-measuring → installation and gluing of aluminum plates → transportation to the bottom of the lifting point → frame hoisting → adjustment and reinforcement → installation of closing aluminum plates → all hoisting is completed → gluing → cleaning and acceptance.

[0021] 1. Preliminary preparation

[0022] After force calculation and analysis, the overall construction process and technology are safe and reliable. The eaves aluminum plate can be installed only after the drawings and plans are completed.

[0023] Due to the restrictions on the use of lifting equipment and the need for movement, the upper operator's safety belt needs to be hung on an independent safety wire rope, and the top lightning protection round steel can be used as a backup hanging point.

[0024] 2. Construction process of overall hoisting of roof eaves aluminum plate

[0025] 1) Post-embedded parts installation

[0026] After measuring and laying out, embedded parts No. 1 and 2 are installed: workers climb up the ladder to the top of the flower rack beam, put on safety belts, and install embedded part No. 1; embedded part No. 2 is installed using a gantry frame, and the safety rope is tied to the guardrail.

[0027] 2) Ground keel assembly:

[0028] Assemble the three divided keels into one frame. After the assembly is completed, organize the acceptance and re-measurement. Only after passing the acceptance can the next step be carried out.

[0029] 3) Aluminum plate installation:

[0030] After the keel is assembled and welded, assemble the outer aluminum plate and the frame together. After the installation is completed, the overall size meets the following requirements. Fix it with glue, and then install the water-proof strips on both sides. The water-proof strips need to be fixed with strong glue.

[0031] 4) Hanging point in place

[0032] After the post-embedded parts are installed, the frame is fixed in position. The adapter is measured and positioned and then installed on the post-embedded parts. After installation, re-measure to ensure that they are all at the same horizontal position, and then weld and fix them.

[0033] 5) Installation of closing board

[0034] After each frame is installed, the elevation and entry and exit reset are carried out. After confirmation, it is reinforced and the closing aluminum plate is installed on the top and roof.

[0035] Both the comprehensive inpatient building and the medical center inpatient building are considered to be hoisted from the southwest corner of the south and installed in a counterclockwise order.

[0036] 6) Installation of closing board

[0037] After each frame is installed, the elevation and entry and exit reset are carried out. After confirmation, it is reinforced and the closing aluminum plate is installed on the top and roof.

[0038] The parts not involved in the present invention are the same as the prior art or can be implemented by using the prior art.

[0039] The above shows and describes the basic principles and main features of the utility model and the advantages of the utility model. For those skilled in the art, it is obvious that the utility model is not limited to the details of the above exemplary embodiments, and can be implemented in other specific forms without departing from the spirit or basic features of the utility model. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the utility model is limited by the attached claims rather than the above description, and it is intended to include all changes within the meaning and scope of the equivalent elements of the claims. Any figure mark in the claims should not be regarded as limiting the claims involved.

[0040] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A hoisting construction system for the construction of aluminum plate moldings for curtain wall flower rack beam eaves, wherein the main structure (1) of the flower rack beam eaves is H-shaped, and the main structure (1) comprises a middle floor deck structure (11), a left wall structure (12) and a right wall structure (13) located on the top surface of the middle floor deck structure (11), and a left beam structure (14) and a right beam structure (15) located on the bottom surface of the middle floor deck structure (11), wherein the bottom elevation of the left beam structure (14) is higher than the bottom elevation of the right beam structure (15), and the hoisting construction system is arranged between the left wall structure (12) and the right wall structure (13); and the characteristics are as follows: The hoisting construction system comprises a hoisting spider vehicle (2), a winch lifting device (3) and a hand chain hoist lifting device (4) arranged on the hoisting spider vehicle (2), and a wind rope (5) for auxiliary construction. The lifting ropes of the winch lifting device (3) and the hand chain hoist lifting device (4) are respectively located on both sides of the hoisting spider vehicle (2). The ends of the lifting ropes are respectively tied and fixed to both sides of the shaped aluminum plate after being lowered. The hoisting spider vehicle (2) comprises a bottom bracket plate (21), a bottom bracket plate (22) and a L-shaped wing frames (22) on both sides of the top surface of the plate (21) and a counterweight (24) placed on the bottom bracket plate (21), the bottom surface of the bottom bracket plate (21) is provided with a solid universal wheel (26), the horizontal parts of the L-shaped wing frames (22) on both sides extend outward of the left wall structure (12) and the right wall structure (13) respectively, and the vertical parts of the L-shaped wing frames (22) on both sides are connected with a reinforcing support (23), and the end of the horizontal part extending outward is provided with a winch pulley (25).

2. A hoisting construction system for the construction of curtain wall flower stand beam cornice molding aluminum plate as claimed in claim 1, characterized in that: The hoisting spider car (2) is formed by welding 80*60*4mm galvanized square tubes.

3. A hoisting construction system for the construction of curtain wall flower stand beam cornice molding aluminum plate as claimed in claim 1, characterized in that: The width of the bottom bracket plate (21) is adapted to the distance between the left wall structure (12) and the right wall structure (13).

4. A hoisting construction system for the construction of curtain wall flower stand beam cornice molding aluminum plate as claimed in claim 1, characterized in that: An auxiliary support device is provided between the vertical portion of the L-shaped wing-spreading frame (22) and the left wall structure (12) and the right wall structure (13), the auxiliary support device comprising a support rod and an auxiliary roller, the auxiliary roller abutting against the left wall structure (12) and the right wall structure (13), and the support rod is arranged perpendicular to the wall.

5. A hoisting construction system for the construction of curtain wall flower stand beam cornice molding aluminum plate as claimed in claim 1, characterized in that: The bottom bracket plate (21) is 1100 mm wide and 1600 mm long; the vertical portion of the L-shaped wing-spreading frame (22) is 800 mm high and the horizontal portion is 650 mm wide; the spacing between the vertical portions of the L-shaped wing-spreading frame (22) is 1000 mm.

6. A hoisting construction system for the construction of curtain wall flower stand beam cornice molding aluminum plate as described in any one of claims 1 to 5, characterized in that: An oblique support (27) is welded between the horizontal portion and the vertical portion of the L-shaped wing-spreading frame (22).