Flower vase pier reinforcement cage integral binding jig frame

By designing an adjustable vase pier reinforced skeleton integrally tied tire frame, the problem that existing equipment cannot adjust the inclination angle of the edge of the reinforced skeleton is solved, improving the construction efficiency and ensuring the tight connection of the reinforced skeleton.

CN222060726UActive Publication Date: 2024-11-26CCCC SHEC DONGMENG ENG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420677480.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-03
Publication Date
2024-11-26
Estimated Expiration
2034-04-03

AI Technical Summary

Technical Problem

The existing vase pier reinforced cage binding equipment cannot adjust the edge inclination angle of the steel skeleton, which affects the construction efficiency of different types of steel skeletons.

Method used

An integral tied tire frame including a bottom frame and an adjustment mechanism is designed. The side adjustment assembly and the bottom adjustment assembly are used to adjust the edge inclination angle and spacing of the steel frame, and the vertical frame is driven by electro-hydraulic push rods and hinged beams. Angle adjustment, and position and support the steel bars with circular tubes and connecting plates.

Benefits of technology

The construction efficiency of different types of steel bar frames is improved, the misalignment and fall off of the bottom beam is avoided, and the tight connection and appropriate adjustment of the steel bar frames is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222060726U_ABST
    Figure CN222060726U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of reinforcement cage binding equipment, in particular to a vase pier reinforcement cage integral binding jig frame which comprises two bottom frames. The adjusting mechanism is arranged between the two bottom frames, and the surface of the adjusting mechanism extends to the position above the bottom frames; wherein the adjusting mechanism comprises a bottom adjusting assembly arranged between the two bottom frames, and a side edge adjusting assembly is arranged above the bottom adjusting assembly; according to the integral binding jig frame for the vase pier steel reinforcement framework, by arranging the side edge adjusting assemblies, the inclination angle of the edge of the steel reinforcement framework can be adjusted under the action of the side edge adjusting assemblies, and the device drives the electric-hydraulic push rods to drive the vertical frames to move under the action of the hinged beams; and the vertical frame moves in a circular arc mode with the rotating center of the hinge base as the axis point, and then the building efficiency of steel reinforcement frameworks of different models is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of steel cage binding equipment, in particular to an integral binding frame for a steel frame of a vase pier. Background Art

[0002] The types of bridge piers on urban road interchange ramps are becoming more and more diverse, especially the large-scale application of special-shaped piers such as vase piers. Although these piers are beautiful in appearance, the corresponding construction difficulty is also very large, especially the binding structure size of the steel cage frame and the control of the protective layer are the key to construction quality control.

[0003] After searching the prior art, it was found that "a positioning frame for tying the steel cage of a vase pier" has a publication number of "CN213104253U". The frame of this device can be recycled repeatedly to improve resource utilization, but the inclination angle of the edge of the steel frame cannot be adjusted, which will affect the construction efficiency of different types of steel frames.

[0004] Therefore, a vase pier steel bar skeleton integrally tied tire frame is proposed to solve the above problems. Utility Model Content

[0005] The purpose of the utility model is to provide a vase pier steel frame integral binding frame in order to solve the above problems, thereby improving the problem that the inclination angle of the edge of the steel frame cannot be adjusted, which affects the construction efficiency of steel frames of different models.

[0006] The utility model achieves the above-mentioned purpose through the following technical scheme: a vase pier steel bar skeleton integral binding tire frame, comprising: two bottom frames; an adjustment mechanism, wherein the adjustment mechanism is arranged between the two bottom frames, and the surface of the adjustment mechanism extends to the top of the bottom frames; wherein the adjustment mechanism comprises a bottom adjustment component arranged between the two bottom frames, a side adjustment component is arranged above the bottom adjustment component, and the side adjustment component is fixedly connected to a side of the bottom frame away from the bottom adjustment component.

[0007] Preferably, the side adjustment assembly includes a side frame fixedly connected to the side of the bottom frame away from the bottom adjustment assembly, the side of the side frame away from the bottom frame is fixedly connected to a bevel frame, the upper end of the side frame away from the bevel frame is fixedly connected to a hinge seat, the hinge seat is hinged to a vertical frame, the inner wall of the vertical frame is fixedly connected to a plurality of round tubes, and the inclination of the skeleton steel bars can be appropriately adjusted through the vertical frame.

[0008] Preferably, the bottom adjustment component includes a bottom beam arranged between the two bottom frames, the upper end of the bottom beam is fixedly connected with a plurality of mounting buckles, the inner wall of the mounting buckles is fixedly connected with a longitudinal plate, the upper end of the longitudinal plate is provided with a plurality of slots, the plurality of slots are distributed in a straight line along the upper end of the longitudinal plate, and the spacing of the steel bars to be placed can be adjusted above the slots.

[0009] Preferably, the plurality of circular tubes are vertically distributed along the inner wall of the vertical frame, the inner wall of the circular tube is slidably connected with a round rod, the end of the round rod close to the bevel frame is fixedly connected with a connecting plate, and the steel skeleton is supported and held by operating the connecting plate in coordination with the round rod.

[0010] Preferably, the inclined surface of the bevel frame is fixedly connected with an electro-hydraulic push rod, and the retracting shaft of the electro-hydraulic push rod is hinged with a hinged beam. The electro-hydraulic push rod can cooperate with the hinged beam to drive the vertical frame to adjust the angle.

[0011] Preferably, the end of the hinged beam away from the electro-hydraulic push rod is hinged to the inner wall of the stand, and the hinged beam is located above the circular tube.

[0012] Preferably, the bottom adjustment assembly also includes a guide plate fixedly connected to the inner wall of the bottom frame, a clamping hole is opened on one side of the bottom frame, and the end of the bottom beam is inserted into the inside of the clamping hole to prevent the bottom beam from falling off.

[0013] Preferably, the plurality of mounting buckles are evenly distributed along the upper end of the bottom beam.

[0014] The beneficial effects of the utility model are:

[0015] 1. The above-mentioned vase pier steel frame is integrally tied to the tire frame. By setting a side adjustment component, the inclination angle of the side of the steel frame can be adjusted under the action of the side adjustment component. The device drives the stand to follow the movement by driving the electro-hydraulic push rod under the action of the hinged beam, so that the stand moves in an arc with the rotation center of the hinged seat as the axis point, thereby facilitating the construction efficiency of different types of steel frames.

[0016] 2. By setting up the bottom adjustment component, the bottom steel bars can be properly adjusted under the action of the bottom adjustment component. The device can position the installation buckles through multiple side frames. Under the action of multiple clamping holes, the bottom beam can be prevented from being misaligned, and the bottom beam is kept tightly connected to the two adjacent bottom frames. Under the action of multiple clamping slots, the spacing of the bottom steel bars of the steel frame can be adjusted. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the structure of the utility model;

[0018] Figure 2This is a schematic diagram of the connection between the bottom beam and the mounting buckle of the utility model;

[0019] Figure 3 A schematic diagram of the opening of the clamping hole of the utility model;

[0020] Figure 4 This is a schematic diagram of the position of the side adjustment component of the utility model;

[0021] Figure 5 It is a cross-sectional view of the exploded structure of the side adjustment component of the utility model.

[0022] In the figure: 1. bottom frame; 2. adjustment mechanism; 21. bottom adjustment assembly; 211. bottom beam; 212. guide plate; 213. clamping hole; 214. mounting buckle; 215. longitudinal plate; 216. clamping slot; 22. side adjustment assembly; 221. side frame; 222. bevel frame; 223. hinged seat; 224. vertical frame; 225. hinged beam; 226. electro-hydraulic push rod; 227. round tube; 228. round rod; 229. connecting plate. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] When implementing: Figure 1-5 As shown, a vase pier steel bar skeleton integral binding tire frame includes: two bottom frames 1; an adjustment mechanism 2, the adjustment mechanism 2 is arranged between the two bottom frames 1, and the surface of the adjustment mechanism 2 extends to the top of the bottom frames 1; wherein the adjustment mechanism 2 includes a bottom adjustment component 21 arranged between the two bottom frames 1, and a side adjustment component 22 is arranged above the bottom adjustment component 21, and the side adjustment component 22 is fixedly connected to a side of the bottom frame 1 away from the bottom adjustment component 21;

[0025] like Figure 1 , Figure 4 and Figure 5As shown, the side adjustment component 22 includes a side frame 221 fixedly connected to the side of the bottom frame 1 away from the bottom adjustment component 21, the side of the side frame 221 away from the bottom frame 1 is fixedly connected to the bevel frame 222, the upper end of the side frame 221 away from the bevel frame 222 is fixedly connected to a hinge seat 223, the hinge seat 223 is hinged to a stand 224, the inner wall of the stand 224 is fixedly connected to a plurality of round tubes 227, the plurality of round tubes 227 are vertically distributed along the inner wall of the stand 224, the inner wall of the round tube 227 is slidably connected to a round rod 228, and the end of the round rod 228 close to the bevel frame 222 is fixedly connected to a connecting rod 228. The connecting plate 229 and the inclined surface of the bevel frame 222 are fixedly connected with an electro-hydraulic push rod 226, and the retracting axis of the electro-hydraulic push rod 226 is hinged with a hinged beam 225. The end of the hinged beam 225 away from the electro-hydraulic push rod 226 is hinged to the inner wall of the stand 224, and the hinged beam 225 is located above the round tube 227; by driving the electro-hydraulic push rod 226, the stand 224 is driven to follow the movement under the action of the hinged beam 225, and at this time, the stand 224 is made to move in an arc with the rotation center of the hinge seat 223 as the axis point, and at the same time, the connecting plate 229 can be operated to drive multiple round rods 228 to pass through the round tube 227 and enter the frame for positioning;

[0026] like Figure 1 , Figure 2 and Figure 3 As shown, the bottom adjustment component 21 includes a bottom beam 211 arranged between the two bottom frames 1, a plurality of mounting buckles 214 are fixedly connected to the upper end of the bottom beam 211, a longitudinal plate 215 is fixedly connected to the inner wall of the mounting buckle 214, a plurality of card slots 216 are opened at the upper end of the longitudinal plate 215, and the plurality of card slots 216 are distributed in a straight line along the upper end of the longitudinal plate 215, the bottom adjustment component 21 also includes a guide plate 212 fixedly connected to the inner wall of the bottom frame 1, a card hole 213 is opened on one side of the bottom frame 1, and the end of the bottom beam 211 is plugged into Inside the clamping hole 213, multiple mounting buckles 214 are evenly distributed along the upper end of the bottom beam 211; wherein the mounting buckles 214 can be positioned by multiple side frames 221, and under the action of multiple clamping holes 213, the bottom beam 211 can be prevented from being misaligned, thereby maintaining the effect of the bottom beam 211 being tightly connected to the two adjacent bottom frames 1, and at the same time, the arranged mounting buckles 214 can play an auxiliary supporting role for the longitudinal plate 215, and under the action of multiple clamping grooves 216, it can be adjusted according to the spacing of the bottom steel bars of the steel skeleton.

[0027] When the utility model is in use, the electro-hydraulic push rod 226 is driven to drive the stand 224 to follow the movement under the action of the hinged beam 225. At this time, the stand 224 moves in an arc with the rotation center of the hinged seat 223 as the axis point. At the same time, the multiple round rods 228 are driven by the operating connecting plate 229 to pass through the round tube 227 to position the steel skeleton, and the mounting buckles 214 are positioned through the multiple side frames 221. Under the action of the multiple clamping holes 213, the mounting buckles 214 set at the same time play an auxiliary supporting role for the longitudinal plate 215, and under the action of the multiple clamping slots 216, they are adjusted according to the spacing of the steel bars at the bottom of the steel skeleton.

[0028] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A vase pier steel frame with integral binding tire frame, It is characterized in that include: two bottom racks (1); An adjustment mechanism (2), the adjustment mechanism (2) being arranged between the two bottom frames (1), and the surface of the adjustment mechanism (2) extending to above the bottom frames (1); The adjustment mechanism (2) comprises a bottom adjustment component (21) arranged between the two bottom frames (1), a side adjustment component (22) is arranged above the bottom adjustment component (21), and the side adjustment component (22) is fixedly connected to a side of the bottom frame (1) away from the bottom adjustment component (21).

2. The integral binding frame of the steel frame of the vase pier according to claim 1, Features: The side adjustment assembly (22) comprises a side frame (221) fixedly connected to a side of the bottom frame (1) away from the bottom adjustment assembly (21); the side of the side frame (221) away from the bottom frame (1) is fixedly connected to an angled frame (222); the upper end of the side frame (221) away from the angled frame (222) is fixedly connected to a hinge seat (223); the hinge seat (223) is hinged to a vertical frame (224); and the inner wall of the vertical frame (224) is fixedly connected to a plurality of circular tubes (227).

3. The steel frame integrally tied to the vase pier according to claim 1, Features: The bottom adjustment component (21) comprises a bottom beam (211) arranged between the two bottom frames (1); the upper end of the bottom beam (211) is fixedly connected to a plurality of mounting buckles (214); the inner wall of the mounting buckle (214) is fixedly connected to a longitudinal plate (215); the upper end of the longitudinal plate (215) is provided with a plurality of slots (216); the plurality of slots (216) are distributed in a straight line along the upper end of the longitudinal plate (215).

4. The integral binding frame of the steel frame of the vase pier according to claim 2, Features: The plurality of circular tubes (227) are vertically distributed along the inner wall of the vertical frame (224); the inner wall of the circular tube (227) is slidably connected to a circular rod (228); and the end of the circular rod (228) close to the bevel frame (222) is fixedly connected to a connecting plate (229).

5. The integral binding frame of the steel frame of the vase pier according to claim 2, Features: The inclined surface of the bevel frame (222) is fixedly connected to an electro-hydraulic push rod (226), and the retractable axis of the electro-hydraulic push rod (226) is hinged to a hinged beam (225).

6. The integral binding frame of the steel frame of the vase pier according to claim 5, Features: The end of the hinged beam (225) away from the electro-hydraulic push rod (226) is hinged to the inner wall of the stand (224), and the hinged beam (225) is located above the circular tube (227).

7. The integral binding frame of the steel frame of the vase pier according to claim 3, Features: The bottom adjustment assembly (21) further comprises a guide plate (212) fixedly connected to the inner wall of the bottom frame (1); a clamping hole (213) is provided on one side of the bottom frame (1); and an end of the bottom beam (211) is inserted into the inside of the clamping hole (213).

8. The integral binding frame of the steel frame of the vase pier according to claim 3, Features: The plurality of mounting buckles (214) are evenly distributed along the upper end of the bottom beam (211).

Citation Information

Cited By

  • Machining and positioning device for vase pier steel reinforcement framework

    CN223902839U