Outer wall unilateral formwork system
By using a single-sided support mold system of supporting piles, foamed polyurethane spray coating and waterproof coils in the construction of basement exterior walls in narrow areas, the construction difficulty and poor waterproof quality caused by uneven surfaces on the side of the supporting piles are solved. , achieving improved waterproofing effect and construction efficiency, reducing the risk of vertical cracks.
Patent Information
- Application Number
- CN202420567531.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-03-22
AI Technical Summary
In the construction of basement exterior walls in narrow areas, due to the uneven surface of the support pile side, the construction of a single-sided support form is difficult, the waterproof quality is poor, and vertical cracks and leakage problems are prone to occur.
A single-sided support mold system including support piles, foamed polyurethane spray coating, inter-pile reinforced mesh and waterproof coil material is adopted. The continuous overall protection system is formed through MDI foamed polyurethane spray coating and self-adhesive waterproof coil material, and flexible isolation is made. Support piles and exterior walls to reduce constraint stress and achieve rapid crack blockage and waterproofing effects.
Effectively prevent exterior wall cracks and leakage, improve construction safety, reduce concrete usage, improve waterproofing effect, reduce construction difficulty and time, and solve the risk of vertical cracks.
Smart Images

Figure CN222100883U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of single-side formwork, in particular to a single-side formwork system for an external wall. Background Art
[0002] As urban space becomes increasingly limited, the land utilization rate within the red line is increasing, and the structure is expanding outward and downward at the same time, resulting in the basement structure being "close to" the foundation pit support piles. Some design spacings are even as short as 20cm. During the construction of the basement exterior wall in this area, a series of operations such as formwork cannot be performed on the outside, so only one-sided formwork construction can be carried out from the inside.
[0003] At present, the system of cast-in-place piles + water-stop curtains is more common in foundation pit support structures. After excavation, mesh spraying is carried out between piles. Due to factors such as design practices, pile position deviation, and mesh spraying quality, a large number of uneven areas are eventually formed on the side surfaces of the supporting piles, forming a "twisted" shape with poor flatness. The distance between the supporting piles and the basement exterior wall structure is small. At the same time, due to the influence of foundation pit deformation and pile position deviation, it is difficult to operate using conventional leveling methods, making subsequent waterproofing and other processes difficult to construct, and the waterproofing quality difficult to guarantee.
[0004] When single-sided formwork is used for pouring, the side surface of the supporting piles is uneven and "twisted", and after the exterior wall concrete is poured, it "bites" with the side surface of the supporting piles. When the concrete shrinks, a large number of vertical cracks will be generated along the length of the wall due to the restraining effect of the support on the exterior wall.
[0005] Therefore, there is an urgent need for a construction method that can perform single-side formwork on the structural exterior wall in a narrow fertilizer trough area and prevent the exterior wall from cracking and leaking. Summary of the invention
[0006] In view of the above-mentioned prior art, the utility model proposes a single-side formwork system for an exterior wall.
[0007] The utility model provides an external wall single-sided formwork system, comprising a plurality of supporting piles, wherein a first foamed polyurethane spray layer is arranged between adjacent supporting piles, an inter-pile reinforcement net is arranged at the inner end of the first foamed polyurethane spray layer between adjacent supporting piles, a second foamed polyurethane spray layer is arranged at the inner end of the inter-pile reinforcement net and the inner pile surface of the supporting pile, a waterproof membrane layer is arranged at the inner end of the second foamed polyurethane spray layer, and an external wall structure is arranged at the inner end of the waterproof membrane layer.
[0008] Preferably, the first foamed polyurethane spray layer and the second foamed polyurethane spray layer are both MDI foamed polyurethane spray layers.
[0009] Preferably, the inter-pile reinforcement mesh is anchored by L-shaped anchor steel bars.
[0010] Preferably, the waterproof roll material layer is a self-adhesive waterproof roll material.
[0011] Preferably, the specification of the inter-pile reinforcement mesh is T2×50×100.
[0012] Compared with the prior art, the beneficial effects of the utility model are:
[0013] 1. The utility model provides a single-sided formwork system for an external wall, which breaks through the conventional protective structure of sprayed concrete with a mesh between piles in a deep foundation pit, and forms a continuous overall protective system by spraying reinforced polyurethane foam. After the leaking part is exposed to water, it expands rapidly to plug the cracks, thereby achieving the purpose of water stopping. The material is light in weight and has strong adsorption capacity, and is easy to spray the pile surface flat and has strong compressive strength. It can also be used in combination with a small amount of catalyst according to the progress requirements of the external wall construction, and the foaming speed can be adjusted according to the actual construction needs, so as to play a role of flexible isolation between the external wall and the supporting piles of the single-sided formwork structure.
[0014] 2. The utility model not only plays a role in protection and leakage prevention, but also reduces the amount of concrete used. It has strong overall operability, fast construction speed, low difficulty, can improve the safety of the foundation pit, and can solve the risk of a large number of vertical oblique cracks caused by the single-sided formwork outer wall of the narrow fertilizer trough.
[0015] 3. The utility model uses the MDI foamed polyurethane spray layer to level the surface of the supporting piles, so that the outer wall concrete is flexibly isolated from it during pouring, eliminating the constraints of the supporting pile side on the basement outer wall, effectively reducing or even eliminating the shrinkage cracks of the outer wall. At the same time, it also has a waterproof effect, which can enhance the anti-leakage effect of the single-form area of the basement outer wall, and can also plug the support leakage. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a side elevation view of the single-sided formwork system for the exterior wall in an embodiment of the utility model.
[0017] Figure 2 It is a top view of the single-sided formwork system for the exterior wall in an embodiment of the utility model.
[0018] In the figure: 1. Support piles; 2. First foamed polyurethane spray layer; 3. Reinforcement mesh between piles; 4. L-shaped anchor steel bars; 5. Second foamed polyurethane spray layer; 6. Waterproof membrane layer; 7. External wall structure. DETAILED DESCRIPTION
[0019] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below with reference to specific illustrations.
[0020] Example: Figure 1 , 2A single-sided formwork system for an exterior wall is shown, comprising a plurality of supporting piles 1, a first foamed polyurethane spray layer 2 is arranged between adjacent supporting piles 1, an inter-pile reinforcement mesh 3 is arranged at the inner end of the first foamed polyurethane spray layer 2 between adjacent supporting piles 1, the specification of the inter-pile reinforcement mesh 3 is T2×50×100, the inter-pile reinforcement mesh 3 is anchored by an L-shaped anchor steel bar 4, a second foamed polyurethane spray layer 5 is arranged at the inner end of the inter-pile reinforcement mesh 3 and the inner pile surface of the supporting pile 1, a self-adhesive waterproof membrane layer 6 is arranged at the inner end of the second foamed polyurethane spray layer 5, and an exterior wall structure 7 is arranged at the inner end of the waterproof membrane layer 6.
[0021] The first foamed polyurethane spray layer 2 and the second foamed polyurethane spray layer 5 are both MDI foamed polyurethane spray layers, that is, single-liquid foamed polyurethanes using MDI as a main raw material.
[0022] The construction method of the external wall single-side formwork system comprises the following steps:
[0023] Step 1: Excavate the earth and lay out the outer edge of the basement outer wall. The parts where the supporting pile 1 is enlarged or deviated should be chiseled out first to prevent the support from invading the outer wall structure and affecting the later structural construction.
[0024] Step 2: Use MDI foamed polyurethane to seal the leakage points between the piles to prevent the soil between the piles from collapsing and losing.
[0025] Step 3: Carry out the first spraying of polyurethane foam in the depressions between the piles for preliminary leveling.
[0026] Step 4: Hang T2×50×100 reinforcement mesh between piles and drive steel bars with elbows between piles for anchoring.
[0027] Step 5: Spray the second foaming polyurethane according to the edge of the outer wall, and level the large surface, flexibly isolate the outer wall structure 7 and the supporting pile 1; during the process, a small amount of catalyst can be used in combination according to the progress requirements of the outer wall construction, and the foaming speed can be adjusted according to the actual construction needs.
[0028] Step 6: Laying the exterior wall waterproofing membrane. The foamed polyurethane has excellent bonding properties and strong compressive strength. The waterproofing membrane can be directly fixed on the second foamed polyurethane spray layer 5.
[0029] Step 7: Install exterior wall reinforcement, set up single-sided formwork, and pour exterior wall concrete structure.
[0030] In this embodiment, single-liquid foamed polyurethane with MDI as the main raw material is sprayed between the supporting piles 1 and the inner pile surface, and the "twisted" pile surface is sprayed flat, which can not only play the role of anti-seepage and anti-leakage between the supporting piles, but also prevent the structural outer wall and the "twisted" pile surface from biting each other to produce constraint stress, forming a similar isolation layer, and effectively avoiding cracking caused by constraint stress. The formwork system of this embodiment breaks through the conventional deep foundation pit row pile hanging net spraying concrete protection structure, and uses reinforced foamed polyurethane spraying to form a continuous overall protection system. After the leaking point reacts with water, it quickly expands and blocks its cracks to achieve the purpose of water stopping; and it is light in weight and strong in adsorption, so it is easy to spray the pile surface flat and has strong compressive strength. It can also be used in combination with a small amount of catalyst according to the requirements of the external wall construction progress, and the foaming speed can be adjusted according to the actual construction needs, so as to play a role of flexible isolation between the structural external wall and the supporting piles.
[0031] The formwork system of this embodiment not only plays a role in protection and leakage prevention, but also reduces the amount of concrete used. It has strong overall operability, fast construction speed, low difficulty, can improve the safety of the foundation pit, and can solve the risk of a large number of vertical oblique cracks caused by the single-sided formwork exterior wall of the narrow fertilizer trough.
[0032] The above are only implementation methods of the present utility model, and are not intended to limit the patent scope of the present utility model. Any equivalent structure made using the contents of the specification and drawings of the present utility model, directly or indirectly used in other related technical fields, are also within the patent protection scope of the present utility model.
Claims
1. An external wall single-side formwork system, characterized in that: It comprises a plurality of supporting piles, wherein a first foamed polyurethane spray layer is arranged between adjacent supporting piles, an inter-pile reinforcement net is arranged at the inner end of the first foamed polyurethane spray layer between adjacent supporting piles, a second foamed polyurethane spray layer is arranged at the inner end of the inter-pile reinforcement net and the inner pile surface of the supporting pile, a waterproof membrane layer is arranged at the inner end of the second foamed polyurethane spray layer, and an outer wall structure is arranged at the inner end of the waterproof membrane layer.
2. The external wall single-side formwork system according to claim 1, characterized in that: The first foamed polyurethane spray layer and the second foamed polyurethane spray layer are both MDI foamed polyurethane spray layers.
3. The external wall single-side formwork system according to claim 1 or 2, characterized in that: The inter-pile reinforcement mesh is anchored by L-shaped anchor steel bars.
4. The external wall single-side formwork system according to claim 1 or 2, characterized in that: The waterproof coiled material layer adopts a self-adhesive waterproof coiled material.
5. The external wall single-side formwork system according to claim 1 or 2, characterized in that: The specification of the inter-pile reinforcement mesh is T2×50×100.