Vertical shaft bottom fine ore treatment device

By designing a shaft bottom powder ore treatment device including a sedimentation box and a collection disk, the problem of inability to effectively separate useful minerals and waste ore in the prior art is solved, and effective recycling of useful minerals and shortening of powder ore treatment time is achieved. , improve production efficiency and safe production level.

CN222489022UActive Publication Date: 2025-02-18XIKUANG SHANXING ANTIMONY CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202421273288.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-05
Publication Date
2025-02-18
Estimated Expiration
2034-06-05

AI Technical Summary

Technical Problem

The existing vertical shaft bottom powder ore treatment device is extensive and simple, and it is impossible to effectively separate useful minerals and waste ore, resulting in some useful ore loss, and the treatment time is long, affecting production.

Method used

A vertical bottom powder ore treatment device including a sedimentation box and a collection disk is designed to achieve instant separation of useful minerals and waste ore through multi-stage sedimentation box and centralized collection of collection disks.

Benefits of technology

Effective recycling of useful minerals reduces the processing time of powder ore, improves production efficiency, and reduces the pollution risk of bottom-hole powder ore on bottom-hole tunnels, and improves the level of safe production.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222489022U_ABST
    Figure CN222489022U_ABST
Patent Text Reader

Abstract

The utility model discloses a vertical shaft bottom fine ore treatment device which comprises a settling tank, the settling tank is installed at the bottom of a vertical shaft, the settling tank is formed by combining a first tank body, a second tank body and a third tank body side by side, and the top of the first tank body is connected with the top of the second tank body through a first water inlet pipe; the top of the second box body is connected with the top of the third box body through a second water inlet pipe, ore discharging openings are formed in the bottoms of the three box bodies, a collecting disc is arranged above the first box body and fixedly installed on the shaft wall of the vertical shaft, and a bottom outlet of the collecting disc is connected with the first box body through a pipeline. A water outlet pipe is arranged at the top of the third box; according to the vertical shaft bottom fine ore treatment device, by arranging the settling box and the collecting disc, fine ore collection can be achieved, meanwhile, useful minerals and waste ores can be separated in time, the useful minerals are effectively recycled, the time for centralized treatment of the shaft bottom fine ore is shortened, the time for vertical shaft ore conveying is indirectly prolonged, and positive influences are brought to production.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of vertical shaft bottom powder ore processing, in particular to a vertical shaft bottom powder ore processing device. Background Art

[0002] Underground mining is an important method for obtaining mineral resources. The development methods of underground mining include horizontal tunnels, inclined shafts and vertical shafts. The collection and treatment of fine ore at the bottom of horizontal tunnels and inclined shafts during hoisting is relatively simpler than that of vertical shafts. Mines developed and hoisted by vertical shafts are troubled by the difficulty in collecting and treating fine ore at the bottom of the shaft. The design of fine ore at the bottom of the vertical shaft in the mining design manual only uses a primary sedimentation tank for treatment. At present, most mines treat fine ore at the bottom of the vertical shaft according to the mining design manual. The existing treatment of fine ore at the bottom of the vertical shaft is a rough and simple treatment device. When the device is in use, ore and waste rock are mixed. The generation and properties of fine ore are not handled according to different situations, and fine treatment cannot be carried out, resulting in the loss of some useful ore. In addition, several working days are required every month to process the fine ore, which has a great impact on production.

[0003] For this purpose, we design a powder ore processing device at the bottom of a vertical shaft. Utility Model Content

[0004] The utility model aims to provide a device for processing powder ore at the bottom of a vertical shaft in view of the deficiencies of the prior art, so as to solve the problems raised in the background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a device for processing powder ore at the bottom of a vertical shaft, comprising a sedimentation box, which is installed at the bottom of the vertical shaft. The sedimentation box is composed of a first box body, a second box body and a third box body arranged side by side. The top of the first box body is connected to the top of the second box body by a first water inlet pipe, and the top of the second box body is connected to the top of the third box body by a second water inlet pipe. The bottoms of the three boxes are all provided with ore unloading ports, a collecting tray is provided above the first box body, the collecting tray is fixedly installed on the wall of the vertical shaft, the bottom outlet of the collecting tray is connected to the first box body by a pipe, and the top of the third box body is provided with a water outlet pipe.

[0006] Preferably, a bucket bracket is installed on the shaft wall of the vertical shaft, the bucket bracket is located above the collecting plate, a bucket is installed on the bucket bracket, rollers are installed on the shaft wall of the vertical shaft, a funnel trough is installed on the rollers, and the funnel trough is located above the bucket.

[0007] Preferably, the diameters of the first water inlet pipe, the second water inlet pipe and the water outlet pipe are increased step by step, and the water outlet elevations of the pipes are gradually increased.

[0008] Preferably, the skip is a shaft skip.

[0009] Preferably, the funnel trough is a retractable funnel trough, and a hydraulic rod for controlling its retraction and extension is installed on the funnel trough.

[0010] Compared with the prior art, the utility model provides a device for processing fine ore at the bottom of a vertical shaft, which has the following beneficial effects:

[0011] The fine ore processing device at the bottom of the vertical shaft can collect fine ore by setting a sedimentation box and a collecting tray. At the same time, useful minerals and waste ore can be separated immediately, and useful minerals can be effectively recovered, which reduces the time for centralized processing of fine ore at the bottom of the shaft, indirectly increases the time for transporting ore from the shaft, and has a positive impact on production. Moreover, the fine ore is not processed on the ground, and the fine ore will not pollute the shaft bottom tunnel, which brings an essential improvement to safe production. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0013] Figure 2 This is a schematic diagram of the structure of the sedimentation box of the utility model.

[0014] Figure numerals: 1, sedimentation box; 1-1, first box body; 1-2, second box body; 1-3, third box body; 2, collecting tray; 3, first water inlet pipe; 4, second water inlet pipe; 5, water outlet pipe; 6, unloading port; 7, skip bracket; 8, skip; 9, funnel trough; 10, vertical shaft. DETAILED DESCRIPTION

[0015] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0016] See also Figure 1-Figure 2In this embodiment: a device for processing fine ore at the bottom of a vertical shaft comprises a sedimentation box 1, wherein the sedimentation box 1 is installed at the bottom of the vertical shaft 10, and the sedimentation box 1 is composed of a first box body 1-1, a second box body 1-2 and a third box body 1-3 arranged side by side, the top of the first box body 1-1 is connected to the top of the second box body 1-2 by a first water inlet pipe 3, the top of the second box body 1-2 is connected to the top of the third box body 1-3 by a second water inlet pipe 4, and the bottoms of the three boxes are all provided with an unloading port 6, a collecting tray 2 is provided above the first box body 1-1, and the collecting tray 2 is fixedly installed on the wall of the vertical shaft 10, the bottom outlet of the collecting tray 2 is connected to the first box body 1-1 by a pipeline, and the collecting tray 2 The shape of the well is funnel-shaped. The powder ore and turbid water falling in the well can be collected by the collecting plate 2 and then enter the sedimentation box 1. An outlet pipe 5 is arranged on the top of the third box body 1-3. The sedimentation box 1 and the inlet and outlet pipes form a set of tubular multi-stage sedimentation devices for graded sedimentation. The diameters of the first inlet pipe 3, the second inlet pipe 4 and the outlet pipe 5 are gradually increased, and the outlet elevation of the pipe is gradually increased. The elevation of the outlet pipe 5 is lower than the outlet elevation of the collecting plate 2, ensuring that the wastewater entering the sedimentation box 1 has enough sedimentation time. The three boxes separate the useful ore and the waste rock, thereby recovering the useful ore. When the sedimentation box 1 is settled to 2 / 3 of the effective volume, the ore is unloaded from the unloading port 6 to the transportation equipment in the horizontal tunnel.

[0017] See also Figure 1 A skip bracket 7 is installed on the wall of the shaft 10, and the skip bracket 7 is located above the collecting plate 2. A skip 8 is installed on the skip bracket 7. Rollers are installed on the wall of the shaft 10, and a funnel trough 9 is installed on the rollers. The funnel trough 9 is located above the skip 8. The skip 8 adopts a shaft skip, and the funnel trough 9 adopts a retractable funnel trough. A hydraulic rod for controlling its retraction is installed on the funnel trough 9. When working, the inlet of the funnel trough 9 is connected to the outlet of the ore distribution metering funnel at the upper part of the shaft 10, and a container is installed on the ore unloading platform at the upper part of the shaft 10. The volume measuring instrument is used to measure the instantaneous volume of the skip 8 and transmit the measured data to the ore-discharging control console at the bottom of the shaft, and then the ore-discharging control console issues a command to the ore-feeding system at the bottom of the shaft 10, so that the ore-feeding amount of the ore-discharging metering funnel is instantly matched with the volume of the skip 8. A distance meter is installed below the ore-discharging metering funnel to measure the distance between the ore-discharging metering funnel and the skip 8, and transmit the measured data to the ore-discharging control console, and then the ore-discharging control console adjusts the length of the funnel slot 9 by controlling the hydraulic rod to make the outlet of the funnel slot 9 close to the entrance of the skip 8.

[0018] The working principle and use process of the utility model are as follows: when the powder ore processing device at the bottom of the vertical shaft is used, the turbid water and powder ore falling in the vertical shaft 10 can be collected by the collecting plate 2 and enter the first box 1-1, and then the heavy objects are precipitated, and the supernatant enters the second box 1-2 through the first water inlet pipe 3. Then, according to the same principle, the clearer supernatant enters the third box 1-3 through the second water inlet pipe 4, and finally the supernatant is discharged from the outlet pipe 5. The ore, waste ore and mud containing no useful minerals are respectively precipitated in the three boxes. The ore unloading ports 6 of the three boxes can be opened to remove the ore, waste ore and mud containing no useful minerals in the sedimentation box 1.

[0019] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A device for processing fine ore at the bottom of a vertical shaft, comprising a sedimentation box (1), characterized in that: The sedimentation box (1) is installed at the bottom of a vertical shaft (10). The sedimentation box (1) is composed of a first box body (1-1), a second box body (1-2) and a third box body (1-3) which are arranged side by side. The top of the first box body (1-1) is connected to the top of the second box body (1-2) via a first water inlet pipe (3), the top of the second box body (1-2) is connected to the top of the third box body (1-3) via a second water inlet pipe (4), the bottoms of the three boxes are all provided with an ore discharge port (6), a collection tray (2) is provided above the first box body (1-1), the collection tray (2) is fixedly installed on the wall of the vertical shaft (10), the bottom outlet of the collection tray (2) is connected to the first box body (1-1) via a pipeline, and the top of the third box body (1-3) is provided with a water outlet pipe (5).

2. A device for processing fine ore at the bottom of a vertical shaft according to claim 1, characterized in that: A bucket bracket (7) is installed on the wall of the vertical shaft (10), the bucket bracket (7) is located above the collecting plate (2), a bucket (8) is installed on the bucket bracket (7), a roller is installed on the wall of the vertical shaft (10), a funnel groove (9) is installed on the roller, and the funnel groove (9) is located above the bucket (8).

3. A device for processing fine ore at the bottom of a vertical shaft according to claim 1, characterized in that: The diameters of the first water inlet pipe (3), the second water inlet pipe (4) and the water outlet pipe (5) are gradually increased, and the water outlet elevations of the pipes are gradually increased.

4. A device for processing fine ore at the bottom of a vertical shaft according to claim 2, characterized in that: The skip (8) is a vertical shaft skip.

5. A device for processing fine ore at the bottom of a vertical shaft according to claim 2, characterized in that: The funnel trough (9) is a telescopic funnel trough, and a hydraulic rod for controlling its telescopic movement is installed on the funnel trough (9).

Citation Information

Cited By

  • Mine underground low-position catchment silt accumulation area ore collection drainage system and drainage method

    CN122728713A