Construction method for spanning diagonal bracing steel trestle in pit
By adopting the cross-supported steel trestle construction method in steel-to-bracket construction, and using the combination of steel and roadbed boxes, the safety of the unearthed paths and support system stability in the steel-to-bracket construction is solved, and the rapid, safe and Economic earth excavation effect.
Patent Information
- Application Number
- CN202411285149.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-13
- Publication Date
- 2024-11-15
AI Technical Summary
During the steel-to-bracket construction process, how to safely cross the unearthed path is to ensure the normal walking of the earth-to-bracket, and avoid contact with the steel-to-bracket below to ensure the safety and stability of the support system.
The steel trestle is built by straddle-to-straight, and the construction is carried out using steel and roadbed boxes. By determining the location of the steel trestle and the specifications of the steel components, combined with welding connections, the safety and stability of the support system are ensured, and guardrails are installed when necessary. To enhance impact resistance.
Fast, safe and economical earth unearthing has been achieved, avoiding the vertical load of steel to support, ensuring the overall safety of the support system and shortening of construction period, and having good economic benefits.
Smart Images

Figure CN118958160A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a construction method of a steel trestle with cross-bracing in a pit. Background Art
[0002] With the continuous development of foundation pit support technology, prefabricated steel supports are increasingly widely used due to their convenient installation and disassembly and flexible modular assembly. Among them, the use of prestressed fish belly beam combined steel support technology can realize a large span space without horizontal support, which provides great convenience for earth excavation. When using this technology for construction, the foundation pit often only needs one horizontal brace to meet the horizontal force transmission requirements. When deploying earth excavation, it can be considered to retreat from the inside to the outside. When the excavation path passes through the brace position, it is necessary to safely cross and lay a vehicle route to meet the excavation requirements.
[0003] A temporary excavation platform is laid on the steel cross-bracing to connect the excavation route, which is necessary to ensure the normal movement of earth-moving vehicles and no contact with the steel cross-bracing below, so as to avoid vertical load on the steel cross-bracing and affect the overall safety of the support system. Summary of the invention
[0004] The present invention aims to provide a method for constructing a steel trestle with cross-bracing in a pit, in view of the deficiencies of the prior art, comprising the following steps: S1. Determination of the steel trestle erection plan: According to the steel support construction plan and earthwork excavation plan, combined with the bearing capacity of the base soil in the geological survey report, the location of the steel trestle erection, the specifications of the steel trestles used in the steel trestle, and the welding requirements are determined; S2. Earthwork excavation: According to the plane positioning of the steel trestle, the earthwork to be replaced on both sides of the steel trestle is positioned and laid out, and excavation construction is carried out; S3, Steel Trestle Foundation Assembly: The steel trestle is 6m wide. First, the bottom pad is constructed. 1.5m away from the steel support, the pad uses a 2*6m roadbed box as the foundation. Then, two steel sections are used as the main beam on both sides of the support, and then a steel secondary beam is set above the main beam across the support. The main beam, secondary beam and roadbed box are connected by welding. S4. Laying of steel trestle surface: After the foundation is completed, sandbags are used to fill the outer side of the foundation to a height of 200mm below the soil surface, leaving a reserved height for the trestle surface level with the soil surface. The steel trestle surface is laid on the secondary beam and the upper part of the sandbag cushion layer using the short side of the roadbed box. The contact area around the sandbags with the original soil is refilled and compacted. After completion, the trestle plane is consistent with the original soil surface height; S5. Guardrail installation: Use standardized mesh to install guardrails on both sides of the trestle. A footboard is set under the mesh. The guardrail is welded and fixed to the roadbed box.
[0005] Preferably, an excavator is used for slope excavation, and the slope meets the coefficient requirement of 1:0.5. When the excavation reaches a height of 300mm from the bottom of the pit, manual excavation is used to level the soil to the designed elevation to protect the steel supporting column piles.
[0006] Preferably, in step S2, the soil quality of the pit bottom is determined to be silty clay according to the geological survey report, ensuring that the bearing layer meets the bearing requirement of the trestle foundation of 65Kpa / m 2 .
[0007] Preferably, in step S2, the main beam is made of H700*300*13*24 steel, the two main beams are 500 apart and are placed centrally in the middle of the pad, the secondary beam is H350*350*12*19 with a spacing of 1250mm, a safety height of 500mm is reserved from the bottom of the secondary beam to the surface of the steel support, and the secondary beam extends 1m beyond the main beam steel.
[0008] Preferably, in step S4, the length of the sandbag is not less than 3 m.
[0009] Preferably, in step S5, the height of the toeboard is 200 mm and the height of the guardrail is 1.2 m.
[0010] Compared with the prior art, the invention has the following beneficial effects: the invention adopts the method of spanning steel bracing to select steel sections and roadbed boxes for steel trestle erection, which is convenient and fast to erect, has a short construction period, is safe and reliable, and can quickly meet the earthwork excavation requirements; at the same time, there is no contact with the steel bracing, which does not affect the safety of the support system. The modular components can be used in a cyclical manner, and have good economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings: Figure 1 This is the plan of the steel trestle; Figure 2 for Figure 1 Cross-section of the middle AA; Figure 3 for Figure 1 Cross-section of the BB.
[0012] In the figure, 1. roadbed box; 2. main beam; 3. secondary beam; 4. sandbag; 5. mesh. DETAILED DESCRIPTION
[0013] The technical solution of the present invention is described in detail below with reference to the accompanying drawings, but the protection scope of the present invention is not limited to the embodiments.
[0014] Reference Figures 1 to 3The present invention provides a method for constructing a steel trestle with cross-span support in a pit, and the construction steps are as follows: determining the steel trestle erection plan, excavating earthwork, assembling the steel trestle foundation, laying the steel trestle surface layer, and installing guardrails. The specific construction process is as follows: S1: Determine the steel trestle erection plan: According to the steel support construction plan and earth excavation plan, combined with the bearing capacity of the base soil in the geological survey report, confirm the location of the steel trestle erection, the specifications of the steel components used, welding requirements, etc.
[0015] S2: Excavation: According to the plane positioning of the steel trestle, the earthwork that needs to be replaced on both sides of the steel trestle is positioned and laid out, and excavation construction is carried out. The PC200 excavator is used for slope excavation, and the slope meets the coefficient requirement of 1:0.5. When the excavation is 300mm above the bottom elevation of the pad, manual excavation is used to level it to the designed elevation. Over-excavation is strictly prohibited. At the same time, attention should be paid to the protection of the steel support column piles. The excavator is strictly prohibited from touching the steel column to avoid affecting the overall safety of the steel support. The soil at the bottom of the pit is determined to be silty clay according to the geological survey report, ensuring that the bearing layer meets the force requirement of the trestle foundation of 65Kpa / m 2 ; S3: Steel trestle foundation assembly: According to the driving requirements of excavators and earth-moving vehicles, the width of the steel trestle is determined to be 6m. According to the actual situation that the width of the steel brace is 9m, the length of the secondary beam of the steel trestle is selected to be 17m. First, the bottom pad is constructed. The horizontal safety distance of the steel brace is reserved. Outside the horizontal distance of 1.5m of the steel brace, the pad uses a 2*6m roadbed box 1 as the foundation. Then, two H700*300*13*24 steel beams are used as the main beam 2 on both sides of the brace. The two main beams 2 are 500 apart and are placed in the middle of the pad to make the vertical load evenly stressed. Then, a steel secondary beam 3 with a specification of H350*350*12*19 and a spacing of 1250 is erected above the main beam across the brace. A safety height of 500 is reserved for the bottom of the secondary beam from the surface of the steel brace, and the secondary beam extends about 1m from the main beam steel. The main and secondary beams are connected to the roadbed box 1 by welding, and the weld lw300,hf=8 is required to ensure the safety and firmness of the trestle foundation.
[0016] S4: Laying of steel trestle surface layer: After the foundation is completed, sandbags 3 are used to backfill and compact the outer side of the foundation to 200 below the soil surface, leaving a reserved height for the trestle surface layer to be level with the soil surface. The length of sandbags 3 shall not be less than 3m to ensure that the trestle base is solid, and the side close to the main beam is fully filled and compacted to at least 0.5m inside the pad. The steel trestle surface layer is laid on the short side of the roadbed box 1 on the secondary beam and the sandbag 3 cushion layer to ensure tight joints and a smooth road surface. The contact area around the sandbags with the original soil is refilled and compacted. After completion, the trestle plane is consistent with the original soil surface height.
[0017] S5: Guardrail installation: Since both sides of the steel trestle are open to the air, the guardrails are installed on both sides of the trestle using the standardized mesh 5. A 200-meter high footboard is set under the mesh 5. The guardrail height is 1.2m and is welded and fixed to the roadbed box to ensure that the impact resistance meets the 1kN standard.
[0018] As above, although the present invention has been shown and described with reference to specific preferred embodiments, it should not be construed as limiting the present invention itself. Various changes may be made to it in form and detail without departing from the spirit and scope of the present invention as defined in the appended claims.
Claims
1. A method for constructing a steel trestle bridge in a pit, characterized in that: The steps include: S1. Determine the steel trestle construction plan: Based on the steel support construction plan and earthwork excavation plan, combined with the bearing capacity of the base soil in the geological survey report, determine the location of the steel trestle, the specifications of the steel trestle components, and the welding requirements; S2. Earthwork excavation: Based on the plane positioning of the steel trestle, the earthwork to be replaced on both sides of the steel trestle is positioned and laid out, and excavation construction is carried out; S3. Steel trestle foundation assembly: The steel trestle is 6m wide. First, the bottom pad is constructed. 1.5m away from the steel support, a 2*6m roadbed box is used as the pad. Then, two steel sections are used as the main beams on each side of the support, and they are arranged in the center. Then, steel secondary beams are erected above the main beams across the support. The main beams, secondary beams and roadbed box are connected by welding. S4. Laying the steel trestle surface: After the foundation is completed, backfill the outer side of the foundation with sandbags to a height of 200mm below the soil surface, leaving a reserved height for the trestle surface to be flush with the soil surface. The steel trestle surface is laid on the upper part of the secondary beam and sandbag cushion using the short side of the roadbed box. The area around the sandbags in contact with the original soil is refilled and compacted. After completion, the trestle plane is aligned with the original soil surface height. S5. Guardrail installation: Use standardized mesh to install guardrails on both sides of the trestle. Set footboards under the mesh. The guardrails are welded and fixed to the roadbed box.
2. The method for constructing a steel trestle bridge in a pit according to claim 1, characterized in that: In step S2, an excavator is used to excavate the slope, and the slope meets the coefficient requirement of 1:0.
5. When the excavation reaches a height of 300 mm from the bottom of the pit, manual excavation is used to level the soil to the designed elevation to protect the steel supporting column piles.
3. The method for constructing a steel trestle bridge in a pit according to claim 2, characterized in that: In step S2, the soil at the bottom of the pit is determined to be silty clay according to the geological survey report, ensuring that the bearing layer meets the trestle foundation load requirement of 65Kpa / m 2 .
4. The method for constructing a steel trestle bridge in a pit according to claim 3, characterized in that: In step S3, the main beam adopts H700*300*13*24 steel, the distance between the two main beams is 500, and they are placed in the middle of the pad. The secondary beam specification is H350*350*12*19, the distance between them is 1250mm, and a safety height of 500mm is reserved from the bottom of the secondary beam to the surface of the steel support. The secondary beam extends 1m from the main beam steel.
5. The method for constructing a steel trestle bridge in a pit according to claim 4, characterized in that: In step S4, the length of the sandbag is not less than 3m.
6. The method for constructing a steel trestle bridge in a pit according to claim 4, characterized in that: In step S5, the height of the toeboard is 200 mm and the height of the guardrail is 1.2 m.