A design method for reinforced anchor support in the leading section of mining tunnel

Through the strengthening support design of anchor cables, the problems of insufficient support strength and high labor intensity in the front section of the re-mining tunnel are solved, more efficient surrounding rock control and space utilization are achieved, and coal mining efficiency and safety are improved.

CN111581833BActive Publication Date: 2024-12-03CHINA UNIV OF MINING & TECH
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202010403260.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-05-13
Publication Date
2024-12-03
Estimated Expiration
2040-05-13

AI Technical Summary

Technical Problem

The support methods of the existing back-mining tunnels have problems such as insufficient support strength, large labor intensity, high space occupancy rate and low support efficiency, resulting in safety hazards and low coal mining efficiency.

Method used

The anchor cable reinforcement support design method is adopted to determine the roof support range through on-site measurement and theoretical analysis of the mine, and optimize the anchor cable layout density in combination with numerical simulation, improve the surrounding rock control efficiency, and reduce the tunnel space occupancy and labor intensity.

Benefits of technology

It significantly improves the support efficiency of the front section of the mining tunnel, reduces roof damage, reduces space occupancy, improves coal mining, transportation and ventilation capabilities, and ensures the safety and stability of the tunnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111581833B_ABST
    Figure CN111581833B_ABST
Patent Text Reader

Abstract

The present invention discloses a design method for anchor cable reinforcement support of the advanced section of a mining tunnel. The method determines the stress concentration coefficient of the advanced section roof of the mining tunnel through field measurement in the mine, obtains the distribution of elastic tangential stress and plastic tangential stress in rock layers with different cohesion and thickness based on the elastic-plastic theory, determines the development of the plastic zone of the advanced section roof of the mining tunnel, and obtains a preliminary design scheme for the advanced support of the mining tunnel based on this; further demonstrates the theoretical analysis by numerical simulation, analyzes the damage and destruction characteristics of the design scheme, and determines the final design scheme for the advanced support of the mining tunnel; applies the final advanced support design scheme of the mining tunnel to the actual site, and adjusts the anchor cable arrangement density according to the test results until the support design requirements are met. The present invention realizes that the advanced section support method of the mining tunnel occupies a small space and has low labor costs, greatly improves the construction efficiency, and ensures the safe operation of the working face.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of advance support of mining tunnels, and in particular to a design method for anchor cable reinforcement support of an advance section of a mining tunnel. Background Art

[0002] The advanced section of the mining tunnel in the coal mining face is the hub for coal transportation, pedestrian and equipment transportation. For a long time, due to the small working space, many transportation equipment, and frequent personnel flow, there are huge safety hazards in this area. At the same time, the mine pressure affected by the advanced mining and support pressure is relatively complex, making the tunnel maintenance difficult. Its safe and effective support has always been a difficult point in mine safety production in my country. With the increase in mining depth, the influence of ground stress and tectonic stress has increased significantly. Problems such as coal wall shedding and floor bulging in the advanced section of the tunnel have emerged one after another, resulting in increased convergence of the tunnel section, causing ventilation and transportation difficulties.

[0003] There are two main types of advanced support methods commonly used in my country: single pillar + π-beam and self-moving hydraulic support. The disadvantages of using π-beam and single pillar combined support in actual production process: 1) Insufficient support strength, when subjected to large roof pressure, it is easy to cause damage to the pillar; 2) Difficult to recover, frequent bottom drilling occurs during use, resulting in difficulty in withdrawal; 3) Low support efficiency, high labor intensity, seriously reducing the coal mining rate and output. With the increasing development of mechanized and intelligent comprehensive mining technology, this support method can no longer meet the needs of safe and efficient production. Compared with single pillar + π-beam support, the support strength and support efficiency of self-moving hydraulic support have been improved, but there are still some defects: 1) Repeated support of the roof during the frame moving process causes the roof to break, which is not conducive to the maintenance and management of the roof; 2) The labor intensity of workers is high, the installation, maintenance and disassembly procedures of the support are complicated, and more labor resources are consumed; 3) The effective use space of the tunnel is reduced, and the hydraulic support occupies more tunnel space, causing problems such as difficulty in equipment movement and excessive wind speed.

[0004] Based on the problems existing in the current traditional advance support, the present invention proposes a surrounding rock control technology that uses reinforced anchor cables to strengthen the advance section of the tunnel. Compared with the support of single pillars + π-shaped beams and self-moving hydraulic supports, it can greatly reduce labor intensity, reduce the occupancy rate of tunnel space, and improve the effectiveness of surrounding rock control. Summary of the invention

[0005] Based on the problems existing in the current traditional advance support, the present invention proposes a design method for anchor cable reinforcement support in the advance section of the mining tunnel. Compared with the support of single pillar + π-shaped beam and self-moving hydraulic support, it can greatly reduce labor intensity, reduce the space occupancy rate of the tunnel, and improve the surrounding rock control effect.

[0006] To achieve the above object, the technical solution adopted by the present invention is as follows: a design method for anchor cable reinforcement support of the leading section of a mining tunnel, the specific steps of which include:

[0007] (1) Through on-site measurement and theoretical analysis, the range of roof support for the advanced section of the mining roadway is determined, providing a theoretical basis for the advanced support of the mining roadway and determining the preliminary design scheme for the advanced support of the mining roadway;

[0008] (2) Through numerical simulation, the accuracy of theoretical analysis is further demonstrated, the damage characteristics of the tunnel roof in the preliminary design are analyzed, and the final design scheme of the advanced support of the mining tunnel is determined;

[0009] (3) Apply the final design scheme to the actual site and adjust the density of anchor cables according to the field test results until the support design requirements are met.

[0010] Furthermore, in step (1), the stress concentration coefficient of the roof of the leading section of the mining tunnel is determined by actual measurement at the mine site.

[0011] Furthermore, in step (1), the theoretical analysis uses elastic-plastic theory to obtain the distribution of elastic tangential stress and plastic tangential stress in rock layers of different cohesion and thickness, and determines the development of the plastic zone in the roof of the leading section of the mining tunnel.

[0012] Furthermore, in step (1), based on the obtained plastic zone semi-distribution expression and according to the suspension theory, a series of preliminary design schemes that meet the support requirements are obtained.

[0013] Furthermore, in step (2), the numerical simulation uses FLAC 3D Simulate and pre-design the roof damage safety threshold S a , the damage value S of the tunnel roof is obtained through simulation b , if S a b , then readjust and optimize the relevant theoretical design support parameters until S a >S b , if S a >S b On this basis, we simulate various design schemes, select the best design scheme and apply it to the actual site.

[0014] Furthermore, in step (3), when applied on site, the actual crack development safety threshold L of the roof leading section is set a After the paving is completed according to the design plan, a crack detector is arranged on the leading section of the mining roadway roof to detect the maximum value L of the crack development in the leading section of the roadway roof. b , if L a <L b ​, then the anchor cables are appropriately arranged in this area to increase the strength of the roof support until the roof L a >L b , if L a >L b , then continue to arrange according to the design plan.

[0015] Compared with the prior art, the present invention has the following beneficial effects:

[0016] The method of anchor cable reinforcement support for the advanced section of the mining roadway proposed in the present invention obtains the distribution expression of the elastic-plastic tangential stress of the roof based on the different cohesion and thickness of the rock layer of the roadway roof, and obtains the development range of the plastic zone according to the condition of equal elastic-plastic tangential stress, which provides a new theoretical analysis method for the advanced support of the roadway. The adoption of this support design method can significantly improve the support efficiency of the advanced section of the mining roadway, effectively avoid the damage caused by repeated squeezing of the roadway roof, reduce the space occupancy rate of the mining roadway, improve the coal mining, transportation, pedestrian and ventilation capacity, and ensure the safe and stable service of the advanced section of the mining roadway. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is the mechanical structure model of the roof surrounding rock in the leading section of the rectangular mining tunnel. DETAILED DESCRIPTION

[0018] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0019] The present invention provides a method for designing anchor cable reinforcement support for the leading section of a mining tunnel, and the specific steps include:

[0020] (1) Through field measurements in the mine and theoretical analysis, the support range of the roof of the advanced section of the mining roadway is determined, providing a theoretical basis for the advanced support of the mining roadway and determining the preliminary design scheme for the advanced support of the mining roadway. It is divided into three steps: ① The stress concentration coefficient of the advanced section of the roof of the mining roadway is obtained through field measurements in the mine, and the maximum support pressure of the roof of the advanced section of the mining roadway is determined, providing basic parameters for subsequent theoretical analysis; ② Based on the elastic-plastic theory, the elastic-plastic tangential stress distribution characteristics of different rock layers in the roof are discussed, and the expression of the elastic-plastic tangential stress distribution of the roof under different roof thicknesses and cohesion is obtained; ③ The expression of tangential stress in the elastic-plastic zone is combined to solve the expression of the range distribution of the plastic zone of the roof under different roof rock layer thicknesses and cohesion conditions.

[0021] This example combines the actual measurement of the mine site and theoretical analysis to find that the stress on the top plate of the advanced section of the mining roadway is compared with that of the non-advanced section of the roadway, which is manifested as an increase in the original rock stress of the roadway top plate, that is, the stress of the advanced section of the mining roadway top plate is KγH. Among them, K is the stress concentration coefficient, γ is the bulk density of the surrounding rock of the roof plate (kN / m 3)、H is the maximum buried depth of the roadway (m), and the above parameters can all be obtained through on-site measurement. Therefore, the development range of the roof plastic zone can be determined by the elastic-plastic theory analysis of the goaf roadway support.

[0022] The following assumptions are made for the goaf roadway: ① The goaf roadway is equivalent to a circular roadway, and the equivalent circle radius is R0; ② The surrounding rock is an ideal elastic-plastic body; ③ The stress values at the boundaries of each rock layer are equal; ④ In the roadway section, the in-situ stresses in the horizontal and vertical directions are equal and do not change along the roadway length direction. As Figure 1 shown, a polar coordinate system is established based on the rectangular goaf roadway.

[0023] For Figure 1 the trapezoidal roadway analysis shown, at this time:

[0024]

[0025] L1, L2, and L3 are the lengths when the plastic zone extends in different rock layers respectively, and R0 is the equivalent circle radius. Their expressions are as follows:

[0026]

[0027]

[0028] According to the elastic-plastic theory, the expression of the tangential stress of the roadway surrounding rock plastic zone is:

[0029]

[0030] The distribution of the tangential stress of the plastic zone in different sections is:

[0031] When R0 < r < R0 + l1:

[0032]

[0033] When R0 + l1 < r < R0 + l1 + l2:

[0034]

[0035]

[0036] When R0 + l1 + l2 < r < R0 + l1 + l2 + l3:

[0037]

[0038]

[0039] Similarly, the expression of the tangential stress of the elastic zone is:

[0040]

[0041] The elastic tangential stress distribution in different sections is as follows:

[0042] When R0 < r < R0 + l1:

[0043]

[0044] When R0 + l1 < r < R0 + l1 + l2:

[0045]

[0046]

[0047] When R0 + l1 + l2 < r < R0 + l1 + l2 + l3:

[0048]

[0049]

[0050] Where: c is the cohesion of the surrounding rock, MPa; r is the polar radius in the polar coordinate system, m; θ is the polar angle in the polar coordinate system, °; H1, H2, H3 are the thicknesses of the roof rock layers, m; R0 is the equivalent circle radius, m; a is the width of the rectangular roadway, m; b2 is the height of the high side of the trapezoidal roadway, m.

[0051] Furthermore, when at this time, the corresponding r is the plastic zone range R p , for simplicity of calculation, substituting the friction angle

[0052] When R0 < r < R0 + l1, by combining Equation 1 and Equation 4, we can obtain:

[0053]

[0054] When R0 + l1 < r < R0 + l1 + l2, by combining Equation 2 and Equation 5, the radius of the plastic zone is:

[0055] R P = R Pa + l1 + R0

[0056]

[0057] Where:

[0058]

[0059]

[0060]

[0061]

[0062]

[0063]

[0064]

[0065]

[0066] When R0 + l1 + l2 < r < R0 + l1 + l2 + l3, by combining Equation 3 and Equation 6, the radius of the plastic zone can be obtained as follows:

[0067] R P = R Pb + l1 + l2 + R0

[0068]

[0069] Where:

[0070]

[0071]

[0072]

[0073]

[0074]

[0075]

[0076]

[0077] In the formula: c is the cohesion of the surrounding rock, MPa; r is the polar radius in the polar coordinate system, m; θ is the polar angle in the polar coordinate system, °; H1, H2, and H3 are the thicknesses of the roof rock layers, m; c1, c2, and c3 are the cohesions corresponding to the roof rock layers 1-3; R0 is the equivalent circle radius, m; a is the width of the rectangular roadway, m; b2 is the height of the high side of the trapezoidal roadway, m; H is the maximum buried depth of the roadway, m; θ is the angle between the plastic zone range in different directions and the horizontal direction, °; α is the coal seam dip angle, °.

[0078] Furthermore, based on the suspension theory, the support strength of the roof in the front advanced section is obtained, and a series of preliminary support design schemes that meet the support strength are determined. The design content includes the cable bolt layout method and installation angle of various support schemes.

[0079] (2) The accuracy of the theoretical analysis is further demonstrated through numerical simulation, the damage and failure characteristics of the tunnel roof in the preliminary design scheme are analyzed, and the final design scheme of the advanced support of the mining tunnel is determined.

[0080] In order to further demonstrate the accuracy of the theoretical analysis, numerical simulation is used to further demonstrate the theoretical analysis, and the damage and destruction characteristics of the tunnel roof of the preliminary design scheme are analyzed. 3D The development of the plastic zone of the leading section of the mining tunnel roof is simulated under theoretical assumptions to verify the accuracy of the theoretical analysis. Pre-design the roof damage safety threshold S a , the damage value S of the tunnel roof is obtained through simulation b , if S a b , readjust and optimize the relevant theoretical design support parameters until S a >S b , if S a >S b , then simulate each design scheme on this basis.

[0081] Under the condition of ensuring the support strength, the changes in the plastic zone of the roof of various support schemes are simulated, the simulation results are summarized, and the most economical scheme with a simulated roof plastic zone development range not exceeding the plastic zone radius of the theoretical simulation is selected as the final design scheme.

[0082] (3) Apply the final design scheme to the actual site and adjust the density of anchor cables according to the field test results until the support design requirements are met.

[0083] Apply the final layout plan to the actual site and set the actual crack development safety threshold L of the roof leading section a After the anchor cable is laid, a crack detector is arranged on the leading section of the mining roadway roof to record the on-site crack development monitoring data and detect the maximum value L of the crack development in the leading section of the roadway roof. b , if L a <L b , appropriately increase the anchor cable layout in this area to increase the roof support strength until the roof L a >L b , if L a >L b , then continue to arrange according to the design plan.​

Claims

1. A method for designing anchor cable reinforcement support for the leading section of a mining tunnel, characterized in that: The specific steps include: (1) Through on-site measurement and theoretical analysis, the range of roof support for the advanced section of the mining roadway is determined, providing a theoretical basis for the advanced support of the mining roadway and determining the preliminary design scheme for the advanced support of the mining roadway; In step (1), the stress concentration coefficient of the roof of the leading section of the mining roadway is determined by field measurement in the mine; the theoretical analysis adopts the elastic-plastic theory to obtain the distribution of elastic tangential stress and plastic tangential stress in rock layers with different cohesion and different thickness, and determines the development of the plastic zone of the roof of the leading section of the mining roadway; The plastic tangential stress is obtained from the elastic-plastic theory The expression is: Wherein, c is the cohesion of surrounding rock, in MPa; R0 is the equivalent circle radius, in m; r is the polar diameter in polar coordinate system, in m; Elastic tangential stress The expression is: Where K is the stress concentration factor; γ is the density of the surrounding rock of the roof, in kN / m 3 ; H is the maximum burial depth of the tunnel, in m; (2) Through numerical simulation, the accuracy of theoretical analysis is further demonstrated, the damage characteristics of the tunnel roof in the preliminary design are analyzed, and the final design scheme of the advanced support of the mining tunnel is determined; In step (2), the numerical simulation uses FLAC 3D Simulate and pre-design the roof damage safety threshold S a , the damage value S of the tunnel roof is obtained through simulation b , if S a b , then readjust and optimize the relevant theoretical design support parameters until S a >S b , if S a >S b , verify the correctness of the theoretical analysis, and on this basis simulate various design schemes, judge their damage and destruction characteristics, and determine the optimal design scheme;​ (3) Apply the final design scheme to the actual site and adjust the anchor cable arrangement density according to the field test results until the support design requirements are met; In step (3), when applied on site, the actual crack development safety threshold L of the roof leading section is set a After the anchor cable is laid, a crack detector is arranged on the front section of the mining roadway to detect the maximum value L of the crack development in the front section of the roadway roof. b , if L a <L b , then the anchor cables are appropriately arranged in this area to increase the strength of the roof support until the roof L a >L b , if L a >L b , then continue to arrange according to the design plan.

Citation Information

Patent Citations

  • Mining roadway frame style advanced support bracket

    CN104047627A

  • Method for ventilation-assisting roadway arrangement and surrounding rock stability control in later period of coal mining

    CN105134214A

  • Method for evaluating stability of grouting anchor cable forepoling stoping working face roadway

    CN110119527A