A construction method for installing a recyclable steel silo greenhouse

By using H-shaped steel and bolt connection construction methods in the construction of silo greenhouses, the deficiencies in wind pressure resistance and construction efficiency of traditional silo greenhouses are solved, and a high turnover rate and low-risk construction effect is achieved, which is suitable for windy environments. construction below.

CN115822339BActive Publication Date: 2024-10-29CHINA RAILWAY 10 BUREAU GRP NO 7 ENG CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202211637201.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-16
Publication Date
2024-10-29
Estimated Expiration
2042-12-16

AI Technical Summary

Technical Problem

During the construction process of traditional silo greenhouses, there are problems such as low wind resistance, low compressive strength, non-recyclable materials, slow construction progress, high construction risks and large labor input.

Method used

The installation and construction method of the turnover-type steel silo greenhouse is adopted. H-shaped steel is used as the main structure, and bolted connections and pre-embedded anchor bolts are used to improve the plasticity and flexibility of the structure, achieve high turnover utilization of materials, and ensure that there is no need to worry. Construction is carried out under electrical conditions to reduce labor input and construction risks.

Benefits of technology

It improves the silo greenhouse's ability to withstand natural disasters, shortens the construction period, reduces construction risks and power consumption, improves material turnover utilization and construction efficiency, and meets the use requirements in most environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115822339B_ABST
    Figure CN115822339B_ABST
Patent Text Reader

Abstract

The present invention discloses a construction method and a method for using a recyclable steel silo shed installation, which belongs to the technical field of silo shed installation and construction of a mixing station; the method comprises the following steps: S1, preparation before construction; S2, foundation excavation; S3, pre-embedding of anchor bolts; S4, component processing and on-site entry; S5, steel beam hoisting; S6, installation correction; S7, high-strength bolt construction; S8, roof beam hoisting; S9, purlin installation; S10, roof and wall panel installation; S11, self-inspection and cleaning. The H-shaped steel provided by the present invention has good plasticity and flexibility, high structural stability, and can make the silo shed have greater resistance to natural disasters, so that such silo shed can meet the use requirements in most environments.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of installation and construction of a mixing station silo shed, and in particular to an installation and construction method of a revolving type steel silo shed. Background Art

[0002] At present, traditional silo greenhouses have problems such as low wind resistance and compressive strength, non-circulation of materials, slow construction progress, high construction risks, and large labor input. Therefore, there is an urgent need for a recyclable steel silo greenhouse installation and construction method with good plasticity and flexibility, high structural stability, high material turnover rate, and low labor input. Summary of the invention

[0003] In order to achieve the above object, the present invention adopts the following technical solutions:

[0004] A method for installing and constructing a recyclable steel silo greenhouse comprises the following steps:

[0005] S1, Preparation before construction

[0006] S11, leveling and rolling the mixing station site, and then carrying out stone throwing and gravel replacement;

[0007] S12, filling of mixing station is carried out in different areas;

[0008] S13, according to the construction organization plan, carry out protection of on-site buildings and set up obvious signs for overhead cables within the working range;

[0009] S2, foundation excavation

[0010] Use total station to lay out and set concrete independent foundation on the steel structure column of material shed;

[0011] S3, pre-embedded foundation bolts

[0012] Review the column foot positioning axis of foundation construction and bury the anchor bolts;

[0013] S4, component processing and delivery

[0014] The components are processed by the processing factory in units according to the installation sequence and then supplied as a complete set; the components are stacked in the designated location according to the site plan;

[0015] S5, steel beam hoisting;

[0016] S6, installation and calibration

[0017] Use a total station or plumb bob to check and calibrate the verticality of the steel column, and fix it immediately after calibration;

[0018] S7, high-strength bolt construction

[0019] All components are connected by bolts;

[0020] S8, roof beam hoisting

[0021] The installation process of roof beams is: ground assembly → inspection → aerial hoisting;

[0022] S9, purlin installation

[0023] Use the method of one hook and multiple hoists or hoisting in pieces to hoist the purlins, check and correct the straightness with a tie wire and steel ruler, and finally fix them with bolts;

[0024] S10, roof and wall panel installation

[0025] S101, on-site storage requirements;

[0026] S102, corrugated tile roof installation;

[0027] S103, Installation precautions;

[0028] S11, self-check and cleaning

[0029] After the construction of the silo greenhouse is completed, a comprehensive inspection of the silo greenhouse is carried out; after the installation work is completed, the debris is cleaned up to ensure dust-free.

[0030] Furthermore, the specific implementation steps of step S102 of installing the profiled tile roof are:

[0031] S1021, plate ribs overlapped in the back-to-wind direction;

[0032] S1022, the plates are connected by ribs, and the female ribs are buckled on the male buckles;

[0033] S1023, at the ridge and marked on the drawing, the steel plate needs to be bent 80 degrees to form a water retaining plate, and at the eaves and lower end, it needs to be arched 10 degrees to form a drip line;

[0034] S1024, leave a gap of about 100mm between the two slope steel plates at the ridge to facilitate the insertion of the bending tool, and extend the corrugated steel plate 100mm-200mm outside at the gutter;

[0035] S1025, the fixing screws should be perpendicular to the steel plate and purlin, and aligned with the center of the purlin. Hang the line before nailing to make the nail line straight.

[0036] Furthermore, the specific implementation steps of step S8 roof beam hoisting are:

[0037] S81, before ground assembly, check the friction surface between the components and the high-strength bolts; when assembling on the ground, use oil-free sleepers to pad the components, and use wooden bars to support the two sides of the components to form an assembly platform. The platform has at least 4 support points. Place the solid web beams on the platform and assemble them according to the drawing numbers. First, use high-strength bolts to connect and tighten them initially. After accurate inspection, use a force measuring wrench to tighten them finally; repeat the above steps to assemble all the rows, and then check the hanging points, alignment benchmarks and center lines;

[0038] S82, use high-strength bolts that meet the use requirements to connect, and the high-strength bolts can be freely inserted into the holes, and the insertion direction is consistent; the high-strength bolts are tightened from the center to the outside with a kilogram electric wrench, and the tightening is divided into initial tightening and final tightening. The initial tightening force should be 50% of the final tightening; when there is a gap on the contact surface of the high-strength bolt, it is not necessary to process the gap less than 1.0mm; for the gap of 1.0-3.0mm, grind the higher side into a 1:10 slope, and the grinding direction is perpendicular to the force direction; for the gap greater than 3.0mm, add a pad, and the pad treatment method is the same as the contact surface;

[0039] S83, single-beam hoisting is adopted, and two-point binding is adopted for the hoisting points, and the binding points are padded with soft materials; when hoisting, the steel beam is first lifted about 50cm from the ground, and the center of the steel beam is aligned with the center of the installation position, and then the steel beam is lifted above the top of the column, and then the steel beam is rotated with a slip rope to align it with the top of the column or the corbel, and the hook is slowly dropped, and the brake is immediately applied when the steel beam just touches the top of the column, and the bolts are inserted into the holes to align with the reserved bolt holes, and the bolts are temporarily tightened to fix them, and the verticality correction and final fixation are carried out at the same time.

[0040] The present invention has the following beneficial effects:

[0041] 1. Most of the construction sites of the present invention are located in the river valley between two mountains. Affected by the wind "narrow pipe effect", they are in a strong wind environment all year round. The impact of side wind and side pressure on the silo greenhouse is long-term and the pressure is high. The columns and beams use H-shaped steel as the main force-bearing structure of the silo greenhouse. The H-shaped steel has good plasticity and flexibility and high structural stability, which can make the silo greenhouse have greater resistance to natural disasters, so that this type of silo greenhouse can meet the use requirements in most environments;

[0042] 2. The connection between the columns and beams of the silo greenhouse of the present invention is bolted. When constructing the column foundation, the anchor bolts are pre-buried. The columns are connected to the foundation by anchor bolts. Before installing the columns, the length of the wall is calculated, and a layer of isolation oil is applied in advance, and a layer of 1mm thick plastic film is wrapped after anti-corrosion treatment to separate the surface of the columns from the concrete. When dismantling the silo greenhouse, the outer package concrete can be removed to allow the columns to be completely stripped. After anti-corrosion treatment again, the turnover utilization rate of the columns can be improved to more than 300%;

[0043] 3. The steel column and the crossbeam are connected by bolts in the present invention. The steel components are connected to the steel plates in advance in the factory. During construction, the bolts are reinforced by electric wrenches when hoisted to the corresponding positions. This can greatly improve the construction efficiency and shorten the construction period while reducing labor input.

[0044] 4. The silo shed of the present invention is constructed by bolt connection, which is not affected by power supply conditions and can be constructed normally without electricity. The whole process can be constructed without electricity. Compared with the original welding connection process, the probability of electric shock is almost reduced to zero, which greatly reduces the construction risk;

[0045] 5. The silo shed of the present invention is connected by bolts and does not require electricity supply, which greatly reduces power consumption and reduces costs while also achieving energy-saving and environmental protection effects. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] Figure 1 The present invention provides a process flow chart of a recyclable steel silo greenhouse installation and construction method. DETAILED DESCRIPTION

[0047] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0048] Example 1

[0049] Reference Figure 1 , in this embodiment, includes:

[0050] 1. The specific construction steps are as follows:

[0051] 1. Preparation before construction

[0052] 1) Before leveling and rolling the mixing station site, the surface vegetation and humus must be cleared, and then stone filling and gravel replacement should be carried out.

[0053] 2) The filling of the mixing station must be carried out in different areas. The width of each filling should be controlled at about 30m. First, fill the area from the access road to the foundation of the mixer to facilitate the entry of mechanical equipment for the next step of construction. Then carry out the filling operation of the silo range foundation. The filling operation should be carried out in layers. The layered filling height should be controlled within 30cm, and the total filling height should be controlled at about 50cm. During the filling construction, the fill material must be flattened by a bulldozer and then rolled. The mixing station site should be rolled by a roller for no less than 5 times, and the filling should be rolled for no less than 6 times. During construction, the filling construction quality should be strictly controlled, and the phenomenon of spring soil and potholes collecting water is strictly prohibited.

[0054] 3) According to the construction organization plan, do a good job of protecting the on-site buildings and set up obvious signs for the overhead cables within the operation range. Do a good job of the three connections and one leveling work on the site. Before installation, remove the concrete ash, set up the foundation positioning line, and use red paint to clearly mark the accurate "+" axis to ensure that it coincides with the steel column axis.

[0055] 2. Foundation excavation

[0056] The foundation construction is all carried out with a total station. The foundation of the steel structure column of the material shed is an independent C30 concrete foundation. The foundation size of the main beam column is 1.2m×1.4m×1.2m, and the foundation size of the wind-resistant column is 1m×1.2m×1.2m. The foundation is excavated manually. After the excavation is completed, the foundation bearing capacity is tested. The designed foundation bearing capacity is 180Kpa. If the foundation bearing capacity requirements are not met, the base should be replaced with stone.

[0057] 3. Pre-embedded anchor bolts

[0058] Check the column foot positioning axis of the foundation construction and bury the anchor bolts. To ensure the accurate positioning of the anchor bolts, the anchor bolts are positioned and fixed with steel template hole sleeves, and the concrete pouring construction can be carried out only after repeated verification. The part of the anchor bolt exposed to the ground is wrapped with plastic sheeting for protection.

[0059] 4. Component processing and delivery

[0060] The components are processed in units according to the installation sequence and then supplied as a complete set by the processing plant. When transporting the components, vehicles are selected according to the length and weight. The components must be leveled on the transport vehicle, and signs must be set for overlength. The tying must be firm. The length of both ends must be extended, the tying method must be used, and the pads between the components must be ensured to ensure that the components are not deformed during transportation and the coating is not damaged. During loading, unloading and hoisting, pads must be used between the wire rope and the components for protection.

[0061] According to the site plan, the components are stacked in the designated location. The component storage site must be flat and solid, without water accumulation. The bottom layer of the component stacking is padded with oil-free sleepers, and the fulcrums of each layer of steel components must be on the same vertical line to prevent the steel components from being crushed and deformed. After the components are stacked, there are obvious signs indicating the model, specification, and quantity of the components for installation. Two steel frames are a unit. The first unit should be installed near the gable with column support.

[0062] 5. Steel beam hoisting

[0063] Before hoisting, first determine the location of the component hanging point, determine the binding method, and take protective measures during hoisting; after the steel column is hoisted, when the column foot is about 30-40cm away from the anchor bolt, straighten it, align the installation hole of the column foot with the bolt, and slowly drop the hook into place; after the initial calibration, when the vertical deviation is within 20mm, tighten the bolt, temporarily fix it and unhook it. Before installing the steel column, calculate the length of the wall, brush it with oil in advance, wrap it with a 1mm thick plastic film, separate it from the concrete, and do anti-corrosion treatment for turnover and secondary use.

[0064] 6. Installation and calibration

[0065] The verticality correction of the steel column is checked with a total station or a plumb bob. When there is a deviation, a jack is used for correction. For elevation correction, the base is slightly raised with a jack, and then the thickness of the pad is increased or decreased. After the column foot is corrected, the anchor bolts are tightened immediately. After the overall correction of the steel column is correct, fine stone concrete is poured under the base plate of the column foot to fix it.

[0066] The axis and verticality of the steel beam are measured and corrected using a jack and a fall chain, and fixed immediately after correction.

[0067] 7. High-strength bolt construction

[0068] All components are connected by bolts. The following matters should be noted during construction:

[0069] 1) High-strength bolts must have a material certificate (quality assurance certificate) before construction and must be retested before use.

[0070] 2) High-strength bolts must be managed and properly kept by designated personnel and must not be thrown around or placed randomly. During the installation process, the bolts must not be damaged or contaminated by dirt to prevent changes in the torque coefficient.

[0071] 3) High-strength bolts must be moisture-proof and corrosion-resistant.

[0072] 4) When installing bolts, use a bald crowbar and punch to align the screw holes of the upper and lower (or front and back) connecting plates so that the bolts can be inserted freely.

[0073] 5) If the error of the screw hole of the connecting plate is large, it should be checked and analyzed and handled as appropriate. If adjusting the screw hole is ineffective or the remaining local screw holes are not in the correct position, an electric reamer or a manual reamer can be used to drill holes.

[0074] 6) On the same connection surface, high-strength bolts should be put in the same direction and should be tightened after installation.

[0075] 8. Hoisting of roof beams

[0076] The roof beam installation process is: ground assembly → inspection → aerial lifting.

[0077] 1) Before ground assembly, check the components. If the deformation or defects of the components exceed the allowable deviation, they must be processed. Also check the friction surface of the high-strength bolt connection. There must be no debris such as mud and sand. The friction surface must be flat and dry, and it is not allowed to work in the rain. When assembling on the ground, use oil-free sleepers to pad the components, and support the components on both sides with wooden bars to enhance stability. Before assembly, form an assembly platform with at least 4 support points. Place the solid web beams on the platform and splice them according to the drawing numbers. First, use high-strength bolts to connect and tighten them. After the inspection is accurate, use a force measuring wrench to tighten them. Similarly, assemble all the rows, and then check the hanging points, alignment benchmarks and center lines.

[0078] 2) The length and diameter of high-strength bolts used for connection must meet the requirements. High-strength bolts should be inserted into the hole freely, and must not be forcibly knocked or gas cut to expand the hole. The insertion direction must be consistent. High-strength bolts are tightened from the center to the outside with a kilogram electric wrench. The tightening is divided into initial tightening and final tightening. The initial tightening force should be 50% of the final tightening. When there is a gap on the contact surface of the high-strength bolt, the gap less than 1.0mm can be left untreated; for a gap of 1.0-3.0mm, the raised side is ground into a 1:10 bevel, and the grinding direction is perpendicular to the force direction; for a gap greater than 3.0mm, a pad is added, and the pad treatment method is the same as the contact surface.

[0079] 3) Single-beam hoisting is adopted for hoisting, and two-point binding is adopted for hoisting points. Soft material pads are used for binding points to prevent damage to steel components. When hoisting, first lift the steel beam about 50cm from the ground, align the center of the steel beam with the center of the installation position, then slowly lift the hook, lift the steel beam above the top of the column, and then use the slip rope to rotate the steel beam to align it with the top of the column or the bull leg, so that the hook is in place. When dropping the hook, it is done slowly, and the brake is immediately applied when the steel beam just touches the top of the column, align the reserved bolt hole, insert the bolt into the hole, and temporarily tighten it to fix it. At the same time, the verticality correction and final fixation are carried out. The verticality of the steel beam is checked with a hanging hammer. After the first steel beam is connected, two slip ropes are used to pull the steel beam from both sides. After that, each steel beam is hoisted and fixed with the secondary beam. After the steel beam is corrected, various supports can be installed, and the bolts are finally tightened to fix it.

[0080] 9.Purlin installation

[0081] The purlin has a small cross section and is light in weight. It is hoisted by one hook and multiple hoists or in pieces. The correction of the purlin is mainly the spacing size and its own straightness. The spacing check rod is moved back and forth between the purlin rods. If there is an error, loosen or tighten the bolts for correction. The straightness is checked and corrected with a wire and a steel ruler, and finally fixed with bolts.

[0082] 10.Roof and wall panel installation

[0083] 10.1 On-site storage requirements

[0084] 1) Corrugated tiles should be placed on sleepers or other pads for storage. It is not advisable to put the steel plate in direct contact with the ground. If placed outdoors, it must be covered with waterproof cloth.

[0085] 2) The stacking area of ​​corrugated tiles should be far away from other exposed steel materials, such as steel bars, so as to prevent the rust on these steel materials from falling onto the color steel plates and being difficult to remove, causing rust spots and penetrating the steel plates.

[0086] 3) When steel plates are stacked, no other heavy objects shall be placed on the steel plates, and people are strictly prohibited from stepping on them.

[0087] 4) When the corrugated tiles are transported to the surface and placed on the roof before installation, it is strictly forbidden to place them on the installed steel plates to avoid damage to the steel plates due to gravity concentration. The steel plates left on the roof that have not been installed on the same day must be stacked into bundles and tied up to avoid being blown away by strong winds.

[0088] 5) Screws, sealants and other spare parts must be placed in the warehouse to avoid loss.

[0089] 10.2 Installation of profiled tile roof

[0090] 1) When laying the boards, pay attention to the annual wind direction, and the overlap of the board ribs must be in the opposite direction of the annual wind direction.

[0091] 2) The connection between plates only overlaps one rib, and the female rib must be buckled on the male buckle.

[0092] 3) At the ridge and marked on the drawing, the steel plate needs to be bent upwards by about 80 degrees to form a water retaining plate, and arched downwards by about 10 degrees at the eaves and the lower end to form a drip line.

[0093] 4) A gap of at least 100mm should be left between the two slopes of the steel plates at the ridge to facilitate the insertion of the bending tool, and the corrugated steel plate should be extended 100mm-200mm at the gutter.

[0094] 5) The fixing screws should be perpendicular to the steel plate and purlin, and aligned with the center of the purlin. A line should be hung before nailing to make the nail line straight.

[0095] 6) After installing every 5-6 steel plates, check the flatness of both ends of the plate. If there is any error, make timely adjustments.

[0096] 10.3 Installation Notes

[0097] 1) Transportation: When transporting a single steel plate, 3-5 people are needed to carry it, depending on the length of the steel plate, so as not to deform the steel plate. When transporting, the plate should be placed on the roof in the installation direction to prevent the steel plate from turning around on the surface of the roof. When transporting, do not drag the steel plate on a rough surface, and do not drag the steel plates between each other to avoid damaging the topcoat.

[0098] 2) When walking on the corrugated tiles on the roof, you must wear soft shoes without nails and without textured soles. Your feet can only step on the grooved part of the steel plate. It is strictly forbidden to step on the pedal ribs, and it is forbidden to walk or stand on the gutters.

[0099] 3) The order of screw fixing must be the same as the direction of board laying. It is strictly forbidden to fix the screws in reverse.

[0100] 4) When cutting steel plates on site, try to do it on the ground and do not cut near other steel plates. If it must be done on the roof, do not do this operation on other steel plates. The front of the steel plate should face downward during cutting. After cutting, the remaining iron filings on the steel plate must be cleaned up, otherwise it will easily lead to early rust of the steel plate.

[0101] 5) Where sealant is required, it must be applied strictly according to the requirements to avoid water leakage.

[0102] 6) Gutters and openings are important parts of roof waterproofing. Construction workers must carry out the construction carefully and quality inspectors must focus on checking them. The next process cannot be carried out without passing the inspection.

[0103] 7) When drawing lines on steel plates, it is advisable to use watercolor pens, not pencils. It should not be used in contact with materials such as lead and copper, and paint should not be applied where there is silicone.

[0104] 11. Self-inspection and cleaning

[0105] After the construction of the silo greenhouse is completed, a comprehensive inspection of the silo greenhouse should be carried out to observe whether the various connection parts of the silo greenhouse are firmly connected, whether the waterproof effect meets the actual needs, and whether there is any water accumulation.

[0106] After the installation work is completed, the iron filings and debris left on the roof and walls that day must be cleaned up, the dirty places should be cleared of dust and dirt, and it is best to wipe them with a damp cloth to ensure that they are clean and dust-free.

[0107] 2. Materials and Equipment

[0108] 1. Main equipment configuration

[0109] Serial number Instrument Name unit quantity Remark 1 25t truck crane tower 2 2 50t jack tower 8 3 5t electric hoist tower 8 4 welder tower 2 5 Total Station tower 1 6 Level tower 1 7 50m steel measuring tape Bundle 2 8 10m steel measuring tape Bundle 4

[0110] 2. Major labor organizations

[0111] Four workers are assigned to be responsible for lifting and initial reinforcement, four workers are responsible for secondary reinforcement and connection construction, two management personnel are assigned, one is responsible for material supply, and one is responsible for quality control during the process.

[0112] 3. Quality Control

[0113] 1. Engineering quality control standards

[0114] 1) "Code for Construction and Quality Acceptance of Steel Structure Engineering" (GB50205-2001)

[0115] 2) "Concrete Structure Engineering Construction Quality Acceptance Code" (GB50204-2002)

[0116] 3) "Code for Acceptance of Construction Quality of Building Foundation Engineering" (GB50202-2002)

[0117] 4) Technical Specification for Cold-Formed Thin-Walled Steel Structures (GB50018-2002)

[0118] 5) "Design and Construction Specifications for Corrugated Metal Sheets" (YBJ216-88)

[0119] 6) Technical Code for Welding of Building Steel Structures (JGJ81-2002)

[0120] 7) Selection of steel: The columns and beams of the frame are mainly made of Q235B steel, and its quality standards should comply with the "Technical Conditions for Ordinary Carbon Structural Steel" (GB / T700) and "Low Alloy High Strength Structural Steel"

[0121] According to the provisions of (GB / T1591), the cold-bent steel used in the purlins of the wall beams must also pass the cold-bending test.

[0122] 8) The 10.9 grade hexagonal high-strength bolts used should comply with the current national standards "High-strength large hexagon head bolts for steel structures" (GB / T1228), "High-strength large hexagon head nuts for steel structures" (GB / T1229), "High-strength washers for steel structures" (GB / T1230) and "Technical conditions for high-strength large hexagon head bolts, large hexagon head nuts and washers for steel structures".

[0123] 2. Project quality assurance measures

[0124] 1) Strictly follow the material, layout, cutting, assembly and welding technical requirements specified in the "Steel Structure Engineering Construction and Quality Acceptance Code" GB50205-2001 to carry out steel structure manufacturing and hoisting.

[0125] 2) The friction contact surface of the component shall be constructed according to the sandblasting process. The friction surface of the component after treatment shall not be painted or stained. The friction coefficient test uses a bolt specimen, the friction treatment material of the specimen, the high-strength bolt and the friction surface of the component are the same, and the friction coefficient is ≥0.45.

[0126] 3) The bolt connection holes are punched with a steel plate punching machine and the pass rate is checked.

[0127] 4) When hoisting vertical long components such as steel columns, the hoisting point should be set at 2 / 3 of the column length. When hoisting components such as roof beams, the hoisting point should be set at an equal distance from the midpoint.

[0128] 5) When aligning and correcting the steel columns, pay attention to the influence of wind force, sunlight temperature and temperature difference. Do not correct when the wind force exceeds level 5. Immediately install the lateral beams or take reinforcement measures for the corrected columns. Correction work should be carried out in the morning or in a time and environment with low temperature under sunlight.

[0129] 6) Before installing the steel structure, the foundation needs to be re-measured to ensure that it meets the installation requirements. During the installation of the steel structure, measurements and corrections are carried out, and the error is controlled within the prescribed allowable range.

[0130] 7) Inspect the steel physically and in the warranty document. The warranty document mainly pays attention to data such as yield point, cold bending, room temperature impact toughness, carbon content, etc. If it does not meet the requirements, it cannot be used.

[0131] 8) During the steel structure production process, self-inspection and mutual inspection shall be carried out, and special inspection shall be carried out in strict accordance with the "Steel Structure Engineering Construction and Quality Acceptance Code" GB50205-2001.

[0132] 9) H-beam steel plates are butt welded and tested to meet the second-level weld quality standards.

[0133] 10) Steel structure engineering construction and acceptance specifications Pay attention to the protection of finished product paint and deformation during transportation. The components are tied firmly and rubber pads are used to protect the tying to avoid damage to the paint. And make matching transport racks according to the transport vehicle and component shape to prevent deformation.

[0134] 11) Before lifting, check the matching of the column foundation axis, column foot bolts and the bolt holes of the column base plate.

[0135] 12) After the steel columns are hoisted, the measuring tools are measured and calibrated in time to prepare for the hoisting of the roof beams.

[0136] IV. Safety Measures

[0137] 1. Safety matters during construction

[0138] 1) On-site workers should receive relevant professional and functional training.

[0139] 2) Personnel entering the site must wear safety helmets.

[0140] 3) The distribution box at the construction site must adopt the TN-S grounding protection system (i.e. three-phase five-wire system).

[0141] 4) Perform job operations strictly in accordance with job operating procedures to avoid safety accidents caused by violation of operating procedures.

[0142] 5) Job operators must strictly follow the operating procedures when performing their job operations. Those who fail to strictly follow the operating procedures will be severely punished once discovered.

[0143] 6) The installation of steel columns and steel beams is the main skeleton. The following principles of hoisting sequence should be followed during installation: first erect standard columns, then beams, then roof trusses (forming a flow operation); first connect on the ground, then put the whole into place; first steel columns, then beams, then roof trusses; first horizontal structures, then plane components.

[0144] 2. Notes on steel column installation:

[0145] 1) Before lifting, check the strength of the wire rope and lifting equipment and check for defects and safety hazards. A trial lift must be carried out. When the height of one end is 100-200 mm, stop the lift, check the firmness of the rigging, the stability of the crane, and the verticality of the steel column, and then command the crane to slowly descend.

[0146] 2) After the steel column is hoisted above the bolt, the operators should stand in a good position, hold the column foot firmly, align the reserved hole on the column foot plate with the bolt, insert it, stop falling into the ditch when the column is lowered to the adjusting nut, pry the column with a crowbar, align its center line with the center line of the foundation, and tighten the column foot nut. The hook can be removed only when it is safe.

[0147] 3) For single unstable structural columns, temporary protection measures such as wind cables must be added.

[0148] 3. Safety measures to prevent crane tipping

[0149] 1) The road at the hoisting site must be flat and solid, and the backfill soil and soft soil layers must be treated. If the soil is soft, a separate road should be paved. The crane shall not be parked on a slope for work, and it is not allowed for the two sides of the crane to be high and low.

[0150] 2) Overloading is strictly prohibited.

[0151] 3) Slanted lifting is prohibited. Slanted lifting will cause overload and wire rope out of the groove, and even cause rope breaking and rollover accidents. Slanted lifting will also cause the heavy object to swing rapidly after leaving the ground, which may injure people or other objects.

[0152] 4) The slings used to bind the components must be calculated. All lifting tools should be inspected regularly and any damaged ones should be identified. The binding method should be correct and firm to prevent the slings from breaking or slipping off the components during lifting, causing the crane to lose weight and tip over.

[0153] 5) Do not lift heavy components or equipment of unknown weight.

[0154] 6) It is prohibited to carry out lifting operations in wind conditions of level 6.

[0155] 7) Commanders should use unified command signals, which should be clear and accurate. Crane operators should obey the commands.

[0156] 4. Safety measures to prevent falling from heights

[0157] 1) Operators must use safety belts correctly when performing aerial work. Safety belts should generally be hung high and used low, that is, the hook at the end of the safety belt rope should be hung high, while the operator should operate at a low position.

[0158] 2) When using a pry bar at high altitude, the person should stand firmly. If there is a scaffold or installed components nearby, one should hold it with one hand and operate it with the other. The depth of the pry bar should be appropriate. If the prying distance is large, it should be pried gradually and it is not advisable to rush for success.

[0159] 3) The ladder used for climbing must be firm. It must be tied to the fixed structure with a rope when in use. The angle between the ladder and the ground is generally 65 to 70 degrees.

[0160] 4) Operators are not allowed to wear hard-soled leather shoes when working at heights.

[0161] 5. Safety measures to prevent injuries from falling objects from heights

[0162] 1) Tools, parts, etc. used by high-altitude operators should be placed in the tool bag they carry with them and should not be thrown down at will.

[0163] 2) Ground operators should try to avoid staying or passing directly under the aerial work surface, and should not stay or pass under the crane's boom or components being hoisted.

[0164] 3) After the components are installed, the connection quality must be checked. Only when the connection is safe and reliable can the hook be loosened or the fixing tools be used for removal.

[0165] 4) If the structure is not fixed, no hooks are allowed, and sleeves must be added at the corners during lifting.

[0166] 5) Temporary railings should be set up around the lifting site to prohibit non-staff from entering and outsiders from approaching.

[0167] 6. Other security measures

[0168] 1) Before construction, safety and technical briefings must be conducted group by group. The content of the briefings must be highly targeted, well-recorded, and the safety responsibility system must be clearly defined.

[0169] 2) Strengthen the feedback of safety information during construction, continuously eliminate potential safety hazards during the construction process, and ensure rapid feedback of safety information, which is an important aspect of preventing and controlling accidents.

[0170] 3) Personnel engaged in high-altitude work must undergo a physical examination. Those who suffer from high blood pressure, heart disease, epilepsy, fear of heights, or other conditions that are not suitable for high-altitude work are not allowed to engage in high-altitude work. High-altitude workers are strictly prohibited from working while sick or after drinking, and must take measures to prevent heatstroke and cool down.

[0171] 4) To do a good job of anti-theft, construction workers should not only install well, but also strengthen the security around them to prevent damage and random taking by outsiders. For important items such as steel pipes, machinery, parts, etc., a special room should be set up for locked storage, and registration should be done for receipt and storage.

[0172] 5) Various construction materials should be classified and stacked neatly in an orderly manner. Pay attention to regular recycling of leftover materials, timely clean up of waste materials, set up garbage bins at designated locations, and keep the construction site clean and tidy.

[0173] 6) Materials must be stacked in different categories when entering the warehouse, and safety inspections must be carried out, especially for gas cylinders, and registration records must be made. Eye-catching fire prevention signs must be erected around the dangerous goods warehouse area. Materials must be collected by a designated person, and they must not be distributed at will, and they must be registered. The distance between gas cylinders must not be less than 5 meters, and the distance from open flames must not be less than 10 meters, and there must be safety isolation measures around them.

[0174] 7) Do a good job of fire prevention, strictly abide by the relevant fire prevention regulations of the construction site, strengthen fire prevention facilities, and prevent fire accidents. When performing hot work such as welding or cutting at the construction site, pay attention to the danger of environmental pollution in the surrounding area in advance to prevent fire. There must be fire-fighting equipment such as fire extinguishers and fire hoses in both the work area and the living area, and strengthen the protection measures against strong winds. Before the strong wind comes, scattered items on the site should be gathered, construction materials and tools should be recycled in the room, construction waste should be concentrated in the temporary yard, and the nodes of the installed structural parts should be fixed. The overall structure must be reinforced and stable.

[0175] V. Environmental Protection Measures

[0176] 1) Discarded waste materials, spare parts, packaging bags, etc. in the production area should be promptly recycled and cleaned up, and the construction site should be kept clean to protect the surrounding landscape and environment from damage.

[0177] 2) Hazardous substances (such as fuel, oil, waste materials, garbage, etc.) generated in the production area are stored in a centralized manner, and after being processed, they are transported to designated locations for burial to prevent damage to the ecological environment.

[0178] 3) A sprinkler truck is installed in the station to regularly spray water and remove dust on the site to prevent construction dust from affecting the surrounding environment.

[0179] 4) Arrange working hours reasonably, arrange low-noise work in between, pay attention to mechanical maintenance, reduce noise levels, try to avoid vehicles entering and exiting at night, and do not arrange processing work with high noise at night.

[0180] 5) When mechanical transport vehicles pass through residential areas, they must slow down and are strictly prohibited from honking.

[0181] 6) The site should be cleaned up after each day’s construction, and various machines and tools on site should be collected and handled by a dedicated person. “The site should be cleaned up after people leave and materials should be cleared away after work is completed.”

[0182] 7) After use, the equipment should be rinsed clean, placed in the designated area according to the "standard storage specifications", and protected so as not to affect the surrounding environment.

[0183] 6. Resource Conservation

[0184] The present invention innovates the construction technology by studying the selection of silo greenhouse frame materials and the construction technology, and applies the construction method to construction practice, promotes the application of the new silo greenhouse bolt connection technology in engineering construction, effectively reduces the waste and loss of silo greenhouse materials, and reduces the investment in electricity costs; at the same time, the construction method adopts bolt connection, and with the same number of construction personnel, the work efficiency is improved by 17%, saving labor resources.

[0185] VII. Benefit Analysis

[0186] 1. Economic Benefits

[0187] 1) Installation and construction method of recyclable steel silo greenhouse: The silo frames are all connected by bolts, which improves the material turnover rate. 121.8 tons of steel are required to process a 30×120m silo greenhouse, of which 89.2 tons of steel can be turned over more than 3 times, including columns, beams and steel purlins. A single silo greenhouse can save 356,800 yuan in steel costs. There are 4 mixing stations in our section, which can save 1.427 million yuan in steel costs.

[0188] 2) Installation and construction method of recyclable steel silo greenhouse: The silo frame is connected by bolts to reduce electricity cost investment. According to the conventional silo frame welding connection process, at least 5 welding machines are required for simultaneous construction. It takes 1 month to install a silo greenhouse. According to the calculation of 3 hours of welding work per day by a single welding machine, 450 degrees of electricity are required per day. With bolt connection, each silo greenhouse can save 14,000 yuan in electricity cost. There are 4 mixing stations in my section, which can save 56,000 yuan in electricity cost.

[0189] 3) Construction method for installation of recyclable steel silo greenhouse: The silo frame is connected by bolts to save construction time and reduce labor cost. According to the conventional silo frame installation process, at least 10 workers are required to work at the same time, and it takes 1 month to install a silo greenhouse. The bolt connection construction can save 5 days of construction time for each silo greenhouse installation. According to the labor cost of 300 yuan per person per day, the daily labor cost investment is 3,000 yuan, and each silo greenhouse can save 15,000 yuan in labor costs. There are 4 mixing stations in my section, which can save 60,000 yuan in labor costs.

[0190] 4) Total savings = increased material turnover rate of 1.427 million yuan + electricity cost savings of 56,000 yuan + labor cost savings of 60,000 yuan = 1.543 million yuan, with significant economic benefits.

[0191] 2. Social Benefits

[0192] This method has been successfully applied in the SG5 section of Xizhao Expressway of China Railway Tenth Bureau Seventh Company. It adopts a recyclable steel silo greenhouse installation method composed of an H-shaped steel silo frame and bolt connection construction method to overcome the problems of traditional silo greenhouse installation technology such as non-recyclable materials, slow construction progress, high construction risks, and large labor input. It ensures the construction quality of the silo greenhouse, speeds up the construction progress, reduces material loss, reduces labor costs, and reduces construction risks. It provides a more advanced construction method for similar projects and has broad prospects for promotion and application.

[0193] 8. Project Examples

[0194] China Railway 10th Bureau Group Seventh Engineering Co., Ltd. Xizhao Expressway SG5 section, the total length of the section is 25.529km, the total amount of concrete is 1.418 million m 3 When planning the temporary construction project, in order to ensure the construction progress, it was planned to build 4 mixing stations. The temporary construction cost was extremely high. In order to reduce the temporary construction cost, the research team combined the actual situation on site, actively organized technical personnel to conduct research and innovation, and invited relevant experts to evaluate the site and the plan. H-shaped steel was used as the frame of the silo greenhouse, and a recyclable silo greenhouse installation method with bolt connection was adopted.

[0195] After the application of the recyclable steel silo greenhouse installation method in practice, through on-site observation, the mixing station has fully withstood the test of strong winds since the completion of the silo greenhouse, and meets the conditions for normal use in bad weather. And through comparative analysis of material consumption, environmental safety, construction progress, cost and other aspects, the use of this method greatly reduces human resource investment in the construction process, improves construction progress, reduces energy consumption, and has good social benefits, which is worthy of promotion and popularization.

[0196] The embodiments described above are only descriptions of the preferred modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims

1. A method for installing and constructing a recyclable steel silo greenhouse, characterized in that: include: S1, Preparation before construction S11, leveling and rolling the mixing station site, and then carrying out stone throwing and gravel replacement; S12, filling of mixing station is carried out in different areas; S13, according to the construction organization plan, carry out protection of on-site buildings and set up obvious signs for overhead cables within the working range; S2, foundation excavation Use total station to lay out and set up concrete independent foundation on the steel structure column of material shed; S3, pre-embedded foundation bolts Review the column foot positioning axis of foundation construction and bury the anchor bolts; S4, component processing and delivery The components are processed by the processing factory in units according to the installation sequence and then supplied as a complete set; the components are stacked in the designated location according to the site plan; S5, steel beam hoisting; S6, installation and calibration Use a total station or plumb bob to check and calibrate the verticality of the steel column, and fix it immediately after calibration; S7, high-strength bolt construction All components are connected by bolts; S8, roof beam hoisting The installation process of roof beams is: ground assembly → inspection → aerial hoisting; S9, purlin installation Use the method of one hook and multiple hoists or hoisting in pieces to hoist the purlins, check and correct the straightness with a tie wire and steel ruler, and finally fix them with bolts; S10, roof and wall panel installation S101, on-site storage requirements; S102, corrugated tile roof installation; S103, Installation precautions; S11, self-check and cleaning After the construction of the silo shed is completed, a comprehensive inspection of the silo shed is carried out; after the installation work is completed, the debris is cleaned up to ensure dust-free; Among them, the specific implementation steps of step S102 of installing the profiled tile roof are: S1021, plate ribs overlapped in the back-to-wind direction; S1022, the plates are connected by ribs, and the female ribs are buckled on the male buckles; S1023, at the ridge and marked on the drawing, the steel plate needs to be bent 80 degrees to form a water retaining plate, and at the eaves and lower end, it needs to be arched 10 degrees to form a drip line; S1024, leave a gap of about 100mm between the two slope steel plates at the ridge to facilitate the insertion of the bending tool, and extend the corrugated steel plate 100mm-200mm outside at the gutter; S1025, the fixing screws should be perpendicular to the steel plate and purlin, and aligned with the center of the purlin. Before nailing, hang the line to make the nail line straight; The specific implementation steps of step S8 roof beam hoisting are: S81, before ground assembly, check the friction surface between the components and the high-strength bolts; when assembling on the ground, use oil-free sleepers to pad the components, and use wooden bars to support the two sides of the components to form an assembly platform. The platform has at least 4 support points. Place the solid web beams on the platform and assemble them according to the drawing numbers. First, use high-strength bolts to connect and tighten them initially. After accurate inspection, use a force measuring wrench to tighten them finally; repeat the above steps to assemble all the rows, and then check the hanging points, alignment benchmarks and center lines; S82, use high-strength bolts that meet the use requirements to connect, and the high-strength bolts can be freely inserted into the holes in the same direction; the high-strength bolts are tightened from the center to the outside with a kilogram electric wrench, and the tightening is divided into initial tightening and final tightening. The initial tightening force should be 50% of the final tightening; when there is a gap on the contact surface of the high-strength bolt, the gap less than 1.0mm is not processed; for the gap of 1.0~3.0mm, the higher side is ground into a 1:10 bevel, and the grinding direction is perpendicular to the force direction; for the gap greater than 3.0mm, a pad is added, and the pad treatment method is the same as the contact surface; S83, single-beam hoisting is adopted, and two-point binding is adopted for the hoisting points, and the binding points are padded with soft materials; when hoisting, the steel beam is first lifted about 50cm from the ground, and the center of the steel beam is aligned with the center of the installation position, and then the steel beam is lifted above the top of the column, and then the steel beam is rotated with a slip rope to align it with the top of the column or the corbel, and the hook is slowly dropped, and the brake is immediately applied when the steel beam just touches the top of the column, and the bolts are inserted into the holes to align with the reserved bolt holes, and the bolts are temporarily tightened to fix them, and the verticality correction and final fixation are carried out at the same time.

Citation Information

Patent Citations

  • Construction method of multi-layer large-span assembled integral space steel grid box-type structure factory building

    CN105756380A

  • Installation and construction method of photovoltaic-technology-agriculture combined greenhouse photovoltaic power generation body

    CN108093979A