Concrete diaphragm wall cofferdam body heightening device
By designing a heightening device for the cofferdam body of the concrete cutoff wall and utilizing the sliding and threaded transmission system of the installation plate and formwork, the problem of low construction efficiency of the traditional cutoff wall cofferdam body heightening has been solved, achieving high efficiency and safety. heightening process and promotes the reuse of formwork.
Patent Information
- Application Number
- CN202411081046.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The construction efficiency of the traditional cutoff wall cofferdam body is low when it is raised, and the long length requires frequent dismantling and erection of formwork, making the construction difficult.
A device for heightening the cofferdam body of a concrete anti-seepage wall is designed, which uses a mounting plate, a moving trough, a main formwork, a side formwork and a motor-driven mechanical system to achieve flexible movement and reuse of the formwork through sliding and thread transmission. , simplifying the concrete pouring process.
The construction efficiency and safety of the heightening of the cutoff wall and cofferdam body are improved, the construction difficulty is reduced, the formwork can be reused, and the overall construction efficiency is improved.
Smart Images

Figure CN118727792A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of construction equipment, and in particular to a device for raising the cofferdam body of a concrete anti-seepage wall. Background Art
[0002] In the fields of water conservancy, civil engineering and environmental protection, soil permeability is a long-standing challenge. Soil permeability threatens water sources, foundations and buildings, and may lead to geological disasters and environmental pollution. Therefore, in order to effectively prevent soil permeation, anti-seepage wall cofferdams are widely used in various engineering projects. Traditional anti-seepage wall cofferdams are usually made of materials such as concrete and polymer membranes. Their main function is to prevent the penetration of water and chemicals through physical barriers.
[0003] After the construction of the anti-seepage wall is completed, due to changes in project requirements or construction environment, it is necessary to increase the height of the anti-seepage wall cofferdam. The traditional method of increasing the height is usually to pour concrete on the top of the original anti-seepage wall. However, due to the long length of the anti-seepage wall, the formwork needs to be constantly dismantled and rebuilt, which makes the construction difficult and the construction efficiency low. Summary of the invention
[0004] In order to improve the problem of low construction efficiency when raising the anti-seepage wall, the present application provides a device for raising the cofferdam body of a concrete anti-seepage wall.
[0005] The present application provides a device for raising the concrete anti-seepage wall cofferdam body, which adopts the following technical solution: A device for raising the cofferdam body of a concrete anti-seepage wall comprises a mounting plate, a movable wheel is arranged at the bottom of the mounting plate, a movable groove is arranged on the top surface of the mounting plate, a movable plate is mounted on the mounting plate through the movable groove for vertical sliding, a fixed frame is mounted on the top surface of the movable plate, two mutually parallel main templates are mounted on the fixed frame, a first bidirectional screw rod is penetrated at the top and bottom of the two main templates, the main templates are threadedly matched with the first bidirectional screw rod, two clearance grooves are arranged on the side of the main template, a side template is penetrated in the clearance groove, and the side template is slidably matched with the main template along the thickness direction of the main template through the clearance groove.
[0006] By adopting the above technical scheme, the movable plate is placed on the existing wall, so that the two main templates are respectively located on both sides of the wall, and then the first bidirectional screw is rotated to make the main template fit the wall, and then the movable plate is moved downward, and the movable plate drives the main template and the side template to move downward through the fixed frame, so that the bottom surface of the side template is abutted against the top surface of the wall, and then concrete is poured between the main template and the side template, so as to realize the heightening of part of the wall; after completing the processing of part of the wall, the side template away from the mounting plate is moved along the thickness direction of the main template, so that the side template is separated from the clearance groove, and the mounting plate drives the main template to move a distance and then stops. At this time, the two main templates, one side template and the cast part of the heightened wall form a fence, and concrete is poured into the formed fence, thereby realizing the heightening of the wall, the template can be reused, the construction difficulty is small and the construction efficiency is high.
[0007] Preferably, a counterweight block is installed in the mounting plate, and a vertically arranged first screw and a first guide rod are rotatably installed in the mounting plate. The movable plate is sleeved on the outer periphery of the first screw and the first guide rod, and the movable plate cooperates with the first screw in threaded transmission. A first motor is installed at the bottom of the mounting plate, and the output end of the first motor is fixedly connected to the bottom end of the first screw.
[0008] By adopting the above technical solution, the first motor is started, and the first motor drives the fixing frame to move vertically, so that the bottom surface of the side formwork fits with the top surface of the wall, thereby facilitating the subsequent pouring of concrete.
[0009] Preferably, a connecting block is fixed to the outer side surface of one of the main templates, a second screw rod horizontally arranged is rotatably installed in the connecting block, a connecting plate is sleeved on the outer periphery of the second screw rod, the connecting plate and the second screw rod are threadedly matched, the connecting plate is fixedly connected to the side template away from the mounting plate, a gear 1 is sleeved and fixed on the outer periphery of the second screw rod, a rotating rod is rotatably installed in the connecting block, a gear 2 meshing with the gear 1 is sleeved and fixed on the outer periphery of the rotating rod, a second motor is mounted on the connecting block, and an output end of the second motor is fixedly connected to an end of the rotating rod.
[0010] By adopting the above technical solution, after completing the construction of the first part of the heightened wall, the second motor is started, the second motor drives the rotating rod to rotate, the rotating rod drives the second screw to rotate synchronously through gear one and gear two, and the second screw drives the side template to move in the direction away from the main template through the connecting plate, so that the side template is disengaged from the clearance groove, so that the installation plate can drive the main template to continue to move along the length direction of the wall.
[0011] Preferably, the fixed frame includes a vertically arranged fixed plate, a horizontal plate is fixed on the top of the fixed plate, a bearing plate is fixed on the side of the fixed plate, the bearing plate is fixedly connected to the side template close to the fixed plate, a vertically arranged worm is rotatably installed on the bearing plate, a worm wheel is fixedly mounted on the outer periphery of the first bidirectional screw and meshed with the worm, a third motor is installed on the top surface of the horizontal plate, and the output end of the third motor is fixedly connected to the top end of the worm.
[0012] By adopting the above technical solution, the mounting plate is placed on the top surface of the wall, and the two main templates are respectively located on both sides of the wall. The third motor is started, and the third motor drives the worm to rotate. The worm drives the two worm wheels to rotate, and the worm wheels drive the first bidirectional screw to rotate. The first bidirectional screw drives the two main templates to move toward the direction close to the wall, so that the two main templates are tightly fitted to the wall.
[0013] Preferably, a sprocket one is sleeved and fixed on the outer circumference of the worm one, a worm two is passed through the end of the horizontal plate away from the worm one, the worm two is rotatably connected to the horizontal plate, a second bidirectional screw is passed through the side of the main template away from the mounting plate, the main template is threadedly matched with the second bidirectional screw, a worm wheel two is sleeved and fixed on the outer circumference of the second bidirectional screw, the worm wheel two and the worm two are meshed with each other, a sprocket two is sleeved and fixed on the outer circumference of the worm two, and a chain is wound around the outer circumferences of the sprocket one and the sprocket two.
[0014] By adopting the above technical solution, worm one drives worm two to rotate through sprocket one, sprocket two and chain, and worm two drives the second bidirectional screw to rotate through worm two, thereby realizing synchronous rotation of the first bidirectional screw and the second bidirectional screw, and improving the stability of the main template.
[0015] Preferably, two second guide rods moving vertically are penetrated in the horizontal plate, and a conveying pipe is fixed to the bottom end of the two second guide rods. A plurality of nozzles 1 are provided on the side of the conveying pipe close to the main template, and the plurality of nozzles 1 are arranged at equal intervals along the length direction of the conveying pipe. Connecting pipes are provided at both ends of the conveying pipe, and a plurality of nozzles 2 are provided on the side of the connecting pipe close to the side template, and the plurality of nozzles 2 are arranged at equal intervals along the length direction of the connecting pipe. A storage box is installed on the top surface of the movable plate, and a pump body is installed on the horizontal plate. A feeding pipe is connected between the storage box and the pump body, and a discharge hose is connected between the pump body and the conveying pipe.
[0016] By adopting the above technical solution, the pump body is started, and the release agent in the storage box is transported through the feeding pipe and the discharging hose. The release agent in the delivery pipe is sprayed onto the surface of the main formwork through nozzle 1, and the release agent in the connecting pipe is sprayed onto the surface of the side formwork through nozzle 2, so that it is easy to demould after the subsequent concrete solidifies.
[0017] Preferably, a vertically arranged threaded sleeve is rotatably mounted on the top surface of the horizontal plate, a vertically arranged third screw is fixed on the outer peripheral surface of the conveying pipe, the third screw passes through the threaded sleeve, the third screw and the threaded sleeve are threadedly matched, a gear three is fixed on the outer peripheral sleeve of the threaded sleeve, a driving rod is rotatably mounted on the horizontal plate, a gear four meshing with the gear three is fixed on the outer peripheral sleeve of the driving rod, a fourth motor is mounted on the horizontal plate, and the output end of the fourth motor is fixedly connected to the end of the driving rod.
[0018] By adopting the above technical solution, the fourth motor is started, and the fourth motor drives the driving rod to rotate. The driving rod drives the threaded sleeve to rotate through gear three and gear four. The threaded rod moves vertically under the drive of the threaded sleeve, and then drives the conveying pipe and the connecting pipe to move vertically, so that the nozzle can spray the release agent on the surface of the main template and the side template.
[0019] Preferably, a dovetail groove is provided on the top surface of the horizontal plate, and a dovetail block is installed on the horizontal plate through the dovetail groove so as to be slidably mounted along its own length direction. A storage rod is fixed to the top surface of the dovetail block, and one end of the discharge hose away from the pump body passes around the storage rod, and a moving rope is fixed to the side of the dovetail block away from the pump body, and the other end of the moving rope passes through the top end of the adjacent second guide rod and is fixedly connected to the top surface of the horizontal plate.
[0020] By adopting the above technical solution, when the connecting tube drives the discharge hose to move downward, the second guide rod moves downward synchronously, and the discharge hose drives the dovetail block to move in the direction away from the second guide rod through the storage rod. When the connecting tube moves upward, the second guide rod moves upward, and the moving rope drives the dovetail block to move in the direction close to the second guide rod. The storage rod drives the discharge hose to move, thereby realizing the storage of the discharge hose and preventing it from being entangled.
[0021] In summary, the present application includes at least one of the following beneficial technical effects: 1. Place the movable plate on the existing wall so that the two main templates are located on both sides of the wall respectively, then rotate the first bidirectional screw rod to make the main template fit the wall, and then move the movable plate downward. The movable plate drives the main template and the side template to move downward through the fixed frame so that the bottom surface of the side template abuts against the top surface of the wall, and then pour concrete between the main template and the side template, so as to realize the heightening of part of the wall; after completing the processing of part of the wall, move the side template away from the installation plate along the thickness direction of the main template so that the side template is separated from the clearance groove, and the installation plate drives the main template to move a distance and then stop. At this time, the two main templates, one side template and the poured part of the heightened wall form a fence, and pour concrete into the formed fence, so as to realize the heightening of the wall. The template can be reused, the construction difficulty is small and the construction efficiency is high; 2. After the construction of the first part of the heightened wall is completed, the second motor is started, and the second motor drives the rotating rod to rotate. The rotating rod drives the second screw to rotate synchronously through gears 1 and 2. The second screw drives the side template to move away from the main template through the connecting plate, so that the side template is separated from the clearance groove, so that the installation plate drives the main template to continue to move along the length direction of the wall; 3. Start the pump body, and the release agent in the storage box is transported through the feeding pipe and the discharging hose. The release agent in the delivery pipe is sprayed onto the surface of the main formwork through nozzle 1, and the release agent in the connecting pipe is sprayed onto the surface of the side formwork through nozzle 2, so that it is easy to demould after the subsequent concrete solidifies. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the overall structure of a device for raising the concrete anti-seepage wall cofferdam body according to an embodiment of the present application.
[0023] Figure 2 It is a structural schematic diagram of a mounting plate and a fixing frame in a device for raising a concrete anti-seepage wall cofferdam body according to an embodiment of the present application.
[0024] Figure 3 It is a cross-sectional view of the mounting plate and the horizontal plate in the concrete anti-seepage wall cofferdam body heightening device according to an embodiment of the present application.
[0025] Figure 4 It is a cross-sectional view of a horizontal plate in a device for raising a concrete anti-seepage wall cofferdam body according to an embodiment of the present application.
[0026] Figure 5 It is a cross-sectional view of a connecting block in a device for raising a concrete anti-seepage wall cofferdam body according to an embodiment of the present application.
[0027] Figure numerals: 1, mounting plate; 11, moving wheel; 12, moving groove; 13, moving plate; 14, counterweight; 15, first screw; 16, first guide rod; 17, first motor; 2, fixed frame; 21, main template; 22, first bidirectional screw; 23, make way slot; 24, side template; 25, fixed plate; 26, horizontal plate; 27, bearing plate; 3, connecting block; 31, second screw; 32, connecting plate; 33, gear one; 34, gear two; 35, second motor; 36, rotating rod; 4, worm one; 41, worm wheel one; 42, The third motor; 43. Worm two; 44. Worm wheel two; 45. Sprocket one; 46. Sprocket two; 47. Chain; 48. Second bidirectional screw; 5. Delivery pipe; 51. Nozzle one; 52. Connecting pipe; 53. Nozzle two; 54. Storage box; 55. Feed pipe; 56. Pump body; 57. Discharge hose; 58. Valve; 6. Threaded sleeve; 61. Third screw; 62. Second guide rod; 63. Drive rod; 64. Gear three; 65. Gear four; 66. Fourth motor; 7. Dovetail block; 71. Dovetail groove; 72. Storage rod; 73. Moving rope. DETAILED DESCRIPTION
[0028] The following is combined with Figure 1-5 This application is described in further detail.
[0029] The present application embodiment discloses a device for raising the cofferdam body of a concrete anti-seepage wall. Figure 1 and Figure 2 The device for raising the cofferdam body of concrete anti-seepage wall includes a mounting plate 1, and moving wheels 11 are respectively installed at the bottom corners of the mounting plate 1, and a counterweight block 14 is installed in the mounting plate 1. A moving groove 12 is opened on the top surface of the mounting plate 1, and a moving plate 13 is installed on the mounting plate 1 through the moving groove 12 to slide vertically. A vertically arranged first screw 15 and a first guide rod 16 are rotatably installed in the mounting plate 1, and the first screw 15 and the first guide rod 16 pass through the moving plate 13, and the moving plate 13 and the first screw 15 are threadedly matched. A first motor 17 is installed at the bottom of the mounting plate 1, and the output end of the first motor 17 is fixedly connected to the bottom end of the first screw 15. Start the first motor 17, and the first motor 17 drives the fixed frame 2 to move downward, so that the bottom surface of the side formwork 24 fits with the top surface of the wall, Reference Figure 2 and Figure 3The top surface of the movable plate 13 is provided with a fixing frame 2, which includes a vertically arranged fixing plate 25, and a horizontally arranged horizontal plate 26 is fixed on the top of the fixing rod. Two mutually parallel main templates 21 are installed on the side of the fixing plate 25 away from the mounting plate 1, and two clearance grooves 23 are provided on the side of the main template 21, and side templates 24 are penetrated in the clearance grooves 23. The side templates 24 slide and cooperate with the main template 21 along the thickness direction of the main template 21 through the clearance grooves 23. Two bearing plates 27 are fixed on the side of the fixing plate 25 away from the mounting plate 1, and the bearing plates 27 are fixedly connected to the side templates 24 close to the mounting plate 1.
[0030] Reference Figure 4 and Figure 5 , the top and bottom of the two main templates 21 are penetrated with a first bidirectional screw 22, and the main template 21 is threadedly matched with the first bidirectional screw 22. A vertically arranged worm 4 is rotatably mounted on the bearing plate 27, and a worm wheel 41 meshing with the worm 4 is sleeved and fixed on the outer periphery of the first bidirectional screw 22. A third motor 42 is installed on the top surface of the horizontal plate 26, and the output end of the third motor 42 is fixedly connected to the top of the worm 4. A second bidirectional screw 48 is penetrated on the side of the main template 21 away from the mounting plate 1, and the main template 21 is threadedly matched with the second bidirectional screw 48. A worm 2 43 is penetrated on the end of the horizontal plate 26 away from the worm 4, and the worm 2 43 is rotatably connected to the horizontal plate 26. A worm wheel 2 44 is sleeved and fixed on the outer periphery of the second bidirectional screw 48, and the worm wheel 2 44 meshes with the worm 2 43. A sprocket 1 45 is sleeved and fixed on the outer circumference of the worm 1 4 , a sprocket 2 46 is sleeved and fixed on the outer circumference of the worm 2 43 , and a chain 47 is wound around the outer circumferences of the sprocket 1 45 and the sprocket 2 46 .
[0031] The mounting plate 1 is placed on the top surface of the wall, and the two main templates 21 are respectively located on both sides of the wall, and the third motor 42 is started. The third motor 42 drives the worm 4 to rotate, and the worm 4 drives the two worm wheels 41 to rotate. The worm wheel 41 drives the first bidirectional screw 22 to rotate, and the worm 4 drives the worm 2 43 to rotate through the sprocket 1 45, the sprocket 2 46 and the chain 47. The worm 2 43 drives the second bidirectional screw 48 to rotate through the worm 2, thereby realizing the synchronous rotation of the first bidirectional screw 22 and the second bidirectional screw 48. The first bidirectional screw 22 and the second bidirectional screw 48 drive the two main templates 21 to move toward the direction close to the wall, so that the two main templates 21 are tightly fitted to the wall. Reference Figure 3 and Figure 5, a connecting block 3 is fixed on the outer side of one of the main templates 21, and a horizontally arranged second screw 31 is rotatably installed in the connecting block 3. A connecting plate 32 is sleeved on the outer periphery of the second screw 31, and the connecting plate 32 is threadedly matched with the second screw 31, and the connecting plate 32 is fixedly connected to the side template 24 away from the mounting plate 1. A gear 1 33 is sleeved and fixed on the outer periphery of the second screw 31, and a rotating rod 36 is rotatably installed in the connecting block 3, and a gear 2 34 meshing with the gear 1 33 is sleeved and fixed on the outer periphery of the rotating rod 36. A second motor 35 is installed on the connecting block 3, and the output end of the second motor 35 is fixedly connected to the end of the rotating rod 36.
[0032] After the construction of the first part of the heightening wall is completed, the second motor 35 is started, and the second motor 35 drives the rotating rod 36 to rotate. The rotating rod 36 drives the second screw 31 to rotate synchronously through the gear 1 33 and the gear 2 34. The second screw 31 drives the side template 24 to move away from the main template 21 through the connecting plate 32, so that the side template 24 is separated from the clearance groove 23, so that the installation plate 1 drives the main template 21 to continue to move along the length direction of the wall. Reference Figure 3 and Figure 4 , two second guide rods 62 moving vertically are inserted into the horizontal plate 26, and the bottom ends of the two second guide rods 62 are fixed with a delivery pipe 5. A vertically arranged threaded sleeve 6 is rotatably installed on the top surface of the horizontal plate 26, and a vertically arranged third screw 61 is fixed on the outer circumference of the delivery pipe 5. The third screw 61 passes through the threaded sleeve 6, and the third screw 61 is threadedly matched with the threaded sleeve 6. A gear 3 64 is fixedly sleeved on the outer circumference of the threaded sleeve 6, and a driving rod 63 is rotatably installed on the horizontal plate 26, and a gear 4 65 meshing with the gear 3 64 is fixedly sleeved on the outer circumference of the driving rod 63. A fourth motor 66 is installed on the horizontal plate 26, and the output end of the fourth motor 66 is fixedly connected to the end of the driving rod 63. A plurality of nozzles 51 are arranged on the side of the delivery pipe 5 close to the main template 21, and the plurality of nozzles 51 are arranged at equal intervals along the length direction of the delivery pipe 5. Connecting pipes 52 are respectively arranged at both ends of the delivery pipe 5, and a valve 58 is arranged at the end of the delivery pipe 5 away from the mounting plate 1. A plurality of nozzles 53 are arranged on one side of the connecting pipe 52 close to the side template 24, and the plurality of nozzles 53 are arranged at equal intervals along the length direction of the connecting pipe 52. A storage box 54 for storing the release agent is installed on the top surface of the movable plate 13, a pump body 56 is installed on the horizontal plate 26, a feeding pipe 55 is connected between the storage box 54 and the pump body 56, and a discharge hose 57 is connected between the pump body 56 and the delivery pipe 5.
[0033] The pump body 56 is started, and the demoulding agent in the storage box 54 is transported through the feeding pipe 55 and the discharging hose 57. At the same time, the fourth motor 66 is started, and the fourth motor 66 drives the driving rod 63 to rotate. The driving rod 63 drives the threaded sleeve 6 to rotate through the gear three 64 and the gear four 65. The threaded rod moves vertically under the drive of the threaded sleeve 6, and then drives the conveying pipe 5 and the connecting pipe 52 to move vertically. The demoulding agent in the conveying pipe 5 is sprayed onto the surface of the main formwork 21 through the nozzle one 51, and the demoulding agent in the connecting pipe 52 is sprayed onto the surface of the side formwork 24 through the nozzle two 53, so that it is convenient to demould after the subsequent concrete solidifies.
[0034] Reference Figure 3 and Figure 4 The top surface of the horizontal plate 26 is provided with a dovetail groove 71, and the horizontal plate 26 is slidably mounted with a dovetail block 7 through the dovetail groove 71 along its length direction. A storage rod 72 is fixed to the top surface of the dovetail block 7, and one end of the discharge hose 57 away from the pump body 56 passes around the storage rod 72. A moving rope 73 is fixed to the side of the dovetail block 7 away from the pump body 56, and the other end of the moving rope 73 passes through the top end of the adjacent second guide rod 62 and is fixedly connected to the top surface of the horizontal plate 26.
[0035] When the connecting tube 52 drives the discharge hose 57 to move downward, the guide rod moves downward synchronously, and the discharge hose 57 drives the dovetail block 7 to move in a direction away from the second guide rod 62 through the storage rod 72. When the connecting tube 52 moves upward, the second guide rod 62 moves upward, and the moving rope 73 drives the dovetail block 7 to move in a direction close to the second guide rod 62. The storage rod 72 drives the discharge hose 57 to move, thereby realizing the storage of the discharge hose 57, so that it is not easy to be entangled. The implementation principle of the device for raising the cofferdam of a concrete anti-seepage wall according to the embodiment of the present application is as follows: placing the movable plate 13 on the existing wall so that the two main templates 21 are respectively located on both sides of the wall, then rotating the first bidirectional screw rod 22 so that the main template 21 fits the wall, and then moving the movable plate 13 downward, and the movable plate 13 drives the main template 21 and the side template 24 to move downward through the fixed frame 2, so that the bottom surface of the side template 24 abuts against the top surface of the wall, and then pouring concrete between the main template 21 and the side template 24, so as to achieve the heightening of part of the wall; after completing the processing of part of the wall, the side template 24 away from the mounting plate 1 is moved along the thickness direction of the main template 21, so that the side template 24 is separated from the clearance groove 23, and the mounting plate 1 drives the main template 21 to move a distance and then stops, at this time, the two main templates 21, one side template 24 and the cast completed heightening wall form a fence, and concrete is poured into the formed fence, so as to achieve the heightening of the wall, the template can be reused, the construction difficulty is small and the construction efficiency is high.
[0036] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A device for raising the cofferdam body of a concrete anti-seepage wall, characterized in that: The invention comprises a mounting plate (1), wherein a moving wheel (11) is arranged at the bottom of the mounting plate (1), a moving groove (12) is provided on the top surface of the mounting plate (1), a moving plate (13) is installed on the mounting plate (1) through the moving groove (12) for vertical sliding movement, a fixing frame (2) is installed on the top surface of the moving plate (13), two mutually parallel main templates (21) are installed on the fixing frame (2), a first bidirectional screw rod (22) is penetrated through the top and bottom of the two main templates (21), the main templates (21) and the first bidirectional screw rod (22) are threadedly matched, two clearance grooves (23) are provided on the side surface of the main template (21), a side template (24) is penetrated in the clearance groove (23), and the side template (24) is slidably matched with the main template (21) along the thickness direction of the main template (21) through the clearance groove (23).
2. The device for raising the concrete anti-seepage wall cofferdam according to claim 1, characterized in that: A counterweight (14) is installed in the mounting plate (1), and a vertically arranged first screw rod (15) and a first guide rod (16) are rotatably installed in the mounting plate (1). The movable plate (13) is sleeved on the outer periphery of the first screw rod (15) and the first guide rod (16), and the movable plate (13) and the first screw rod (15) are threadedly matched. A first motor (17) is installed at the bottom of the mounting plate (1), and the output end of the first motor (17) is fixedly connected to the bottom end of the first screw rod (15).
3. The device for raising the concrete anti-seepage wall cofferdam according to claim 1, characterized in that: A connecting block (3) is fixed to the outer side surface of one of the main templates (21), a second screw rod (31) arranged horizontally is rotatably mounted in the connecting block (3), a connecting plate (32) is sleeved on the outer periphery of the second screw rod (31), the connecting plate (32) and the second screw rod (31) are threadedly matched, the connecting plate (32) is fixedly connected to the side template (24) away from the mounting plate (1), a gear 1 (33) is sleeved and fixed on the outer periphery of the second screw rod (31), a rotating rod (36) is rotatably mounted in the connecting block (3), a gear 2 (34) meshing with the gear 1 (33) is sleeved and fixed on the outer periphery of the rotating rod (36), a second motor (35) is mounted on the connecting block (3), and an output end of the second motor (35) is fixedly connected to an end of the rotating rod (36).
4. The device for raising the concrete anti-seepage wall cofferdam according to claim 3 is characterized in that: The fixing frame (2) comprises a vertically arranged fixing plate (25), a horizontally arranged horizontal plate (26) is fixed on the top of the fixing plate (25), a bearing plate (27) is fixed on the side of the fixing plate (25), the bearing plate (27) is fixedly connected to the side template (24) close to the fixing plate (25), a vertically arranged worm gear (4) is rotatably mounted on the bearing plate (27), a worm wheel (41) meshing with the worm gear (4) is fixedly sleeved on the outer periphery of the first bidirectional screw (22), and a third motor (42) is mounted on the top surface of the horizontal plate (26), and an output end of the third motor (42) is fixedly connected to the top end of the worm gear (4).
5. The device for raising the concrete anti-seepage wall cofferdam according to claim 4, characterized in that: A sprocket wheel 1 (45) is sleeved and fixed on the outer circumference of the worm gear 1 (4); a worm gear 2 (43) is inserted through the end of the horizontal plate (26) away from the worm gear 1 (4); the worm gear 2 (43) is rotatably connected to the horizontal plate (26); a second bidirectional screw rod (48) is inserted through the side of the main template (21) away from the mounting plate (1); the main template (21) and the second bidirectional screw rod (48) are threadedly matched; a worm wheel 2 (44) is sleeved and fixed on the outer circumference of the second bidirectional screw rod (48); the worm wheel 2 (44) and the worm gear 2 (43) are meshed with each other; a sprocket wheel 2 (46) is sleeved and fixed on the outer circumference of the worm gear 2 (43); a chain (47) is wound around the outer circumferences of the sprocket wheel 1 (45) and the sprocket wheel 2 (46).
6. The device for raising the concrete anti-seepage wall cofferdam according to claim 4, characterized in that: Two second guide rods (62) movable vertically are provided in the horizontal plate (26), and a delivery pipe (5) is fixed at the bottom end of the two second guide rods (62). A plurality of nozzles (51) are provided on the side of the delivery pipe (5) close to the main template (21), and the plurality of nozzles (51) are arranged at equal intervals along the length direction of the delivery pipe (5). Connecting pipes (52) are provided at both ends of the delivery pipe (5), and the connecting pipes (52) are close to the main template (21). A plurality of nozzles (53) are arranged on one side of the side template (24), and the plurality of nozzles (53) are arranged at equal intervals along the length direction of the connecting pipe (52). A storage box (54) is installed on the top surface of the movable plate (13), a pump body (56) is installed on the horizontal plate (26), a feeding pipe (55) is connected between the storage box (54) and the pump body (56), and a discharge hose (57) is connected between the pump body (56) and the conveying pipe (5).
7. The device for raising the concrete anti-seepage wall cofferdam according to claim 6, characterized in that: A vertically arranged threaded sleeve (6) is rotatably mounted on the top surface of the horizontal plate (26); a vertically arranged third screw rod (61) is fixed on the outer peripheral surface of the conveying pipe (5); the third screw rod (61) passes through the threaded sleeve (6); the third screw rod (61) and the threaded sleeve (6) are threadedly matched; a gear three (64) is sleeved and fixed on the outer periphery of the threaded sleeve (6); a driving rod (63) is rotatably mounted on the horizontal plate (26); a gear four (65) meshing with the gear three (64) is sleeved and fixed on the outer periphery of the driving rod (63); a fourth motor (66) is mounted on the horizontal plate (26); an output end of the fourth motor (66) is fixedly connected to the end of the driving rod (63).
8. The device for raising the concrete anti-seepage wall cofferdam according to claim 7, characterized in that: A dovetail groove (71) is provided on the top surface of the horizontal plate (26), and a dovetail block (7) is slidably installed on the horizontal plate (26) along its own length direction through the dovetail groove (71), and a storage rod (72) is fixed on the top surface of the dovetail block (7), and one end of the discharge hose (57) away from the pump body (56) passes around the storage rod (72), and a moving rope (73) is fixed on the side of the dovetail block (7) away from the pump body (56), and the other end of the moving rope (73) passes through the top end of the adjacent second guide rod (62) and is fixedly connected to the top surface of the horizontal plate (26).