Steel wire rope production scheduling method and scheduling system

Through improved teaching and learning algorithms and scheduling models, the wire rope production process is optimized, solving the low production efficiency and delay problems caused by traditional manual scheduling, and achieving more efficient multi-batch and small-batch production management.

CN118735197AInactive Publication Date: 2024-10-01LIAONING POLYTECHNIC VOCATIONAL COLLEGE
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410864853.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-28
Publication Date
2024-10-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional wire rope production scheduling methods rely on manual planning, resulting in delayed delivery of production orders and low efficiency, and cannot effectively respond to changes in multi-batch and small-batch production needs.

Method used

An improved teaching and learning algorithm is used to construct a wire rope production scheduling model. By decomposing production tasks, setting constraints, and using improved local search and teaching strategies, the production process is optimized to minimize and maximize completion time.

Benefits of technology

It improves the efficiency of multi-batch and small-batch production, can be adjusted from time to time according to abnormal conditions in the production process, has strong applicability, reduces production delays and improves overall efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735197A_ABST
    Figure CN118735197A_ABST
Patent Text Reader

Abstract

The invention discloses a steel wire rope production scheduling method and scheduling system, and belongs to the technical field of production scheduling, and the scheduling method comprises the steps: obtaining a steel wire rope production order, and dividing steel wire ropes into different task groups according to production tasks; setting completion targets according to different task groups of the steel wire ropes, determining constraint conditions of a steel wire rope production process according to the completion targets, and constructing a steel wire rope production scheduling model; and solving the steel wire rope production scheduling model by adopting an improved teaching and learning algorithm to obtain an optimal production process. By adopting the method and the system, the constructed steel wire rope production scheduling model is solved by using the improved teaching and learning algorithm, real-time adjustment can be carried out according to abnormal conditions generated in the production process, the production efficiency is improved, and the applicability is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steel wire rope production scheduling, and in particular to a production scheduling method and a scheduling system. Background Art

[0002] In the 21st century, the competition in the manufacturing industry is becoming increasingly fierce. While enterprises have gained great development space, they are also under threats and challenges. The factors that determine the core competitiveness of enterprises are reflected in the products they provide. Products are required to be high quality, low price, short delivery time, and able to continuously adapt to the changing market and personalized customer needs. This puts higher requirements on the production operation planning and balanced production of the enterprise's manufacturing workshop.

[0003] my country's wire rope market is developing very rapidly, and the demand for wire rope is also increasing. Customers' demand for products is also becoming more and more complicated. Production is gradually showing a trend of mass production and customization. In production orders, single-digit products account for a large proportion of production orders. The production process shows the problem of multiple batches and small batches. Therefore, how to reasonably schedule production during the processing process is more important. At present, the traditional solution is to manually plan the production tasks of the workshop. When problems occur in production, the plan is adjusted according to manual experience, but this method often causes delayed delivery of production orders, low production efficiency, and is not conducive to enterprise development. Summary of the invention

[0004] The object of the present invention is to provide a steel wire rope production scheduling method and scheduling system to solve the problems mentioned in the above background.

[0005] To achieve the above object, the present invention provides a steel wire rope production scheduling method, comprising the steps of:

[0006] S1. Obtain the steel wire rope production order and divide the steel wire rope into different task groups according to the production tasks;

[0007] S2. According to different wire rope task groups, set completion targets, determine the constraints of the wire rope production process according to the completion targets, and build a wire rope production scheduling model;

[0008] S3. Use the improved teaching and learning algorithm to solve the wire rope production scheduling model and obtain the optimal production process.

[0009] Preferably, in step S2, the goal is to minimize the maximum completion time of all workpieces, and the objective function is:

[0010] minC max

[0011] In the formula, C max Represents the maximum completion time of all artifacts.

[0012] Preferably, in step S2, the constraints of the steel wire rope production process include:

[0013] Constraint 1: Each machine can only process one part at a time, and once a task is started, it cannot be interrupted;

[0014] Constraint 2: Only one processing task group can be selected for the same processing task;

[0015] Constraint three: a task group can only be processed on the same machine;

[0016] Constraint condition 4: The processing task group processed on the same machine can only have one front processing task group and one back processing task group, and the front processing task group and the back processing task group cannot be the same processing task group;

[0017] Constraint five: The processing tasks of the same processing task group can only have one pre-processing and post-processing group, and the pre-processing group and post-processing group cannot be the same processing task group;

[0018] Constraint six: the number of wire drawing reels on the machine must be greater than the number of drawing passes of all tasks in the processing task group;

[0019] Constraint seven: the start time of the processing task group on the same machine is after the previous processing task group is completed and the corresponding die chain is replaced;

[0020] Constraint eight: The start time of the processing task of the same processing task group is after the previous processing task is completed and the corresponding mold chain is replaced.

[0021] Preferably, the process of solving the steel wire rope production scheduling model using the improved teaching and learning algorithm in step S3 includes:

[0022] S31, coding, determining the processing tasks and the number of processing machines, and coding according to the processing task information, the coding includes A code and B code, A code represents the processing group machine and the processing sequence on each machine, B code represents the internal processing sequence of the processing group and the composition of the processing task group;

[0023] S32, generating initial solutions of A code and B code;

[0024] S33, initializing the population according to the generated initial solution;

[0025] S34. Solve the objective function based on the improved teaching and learning algorithm to obtain the optimal production process.

[0026] The step S34 specifically includes:

[0027] S341, judging whether the iteration reaches the maximum number of generations set by the algorithm, randomly generating student individuals from the population with a probability of α% to enter the diligent group of students, all diligent group students perform local search, and the remaining student individuals are the lazy group, which mutates with a probability of β%;

[0028] S342. The individual with the best fitness among all individuals in the population is selected as the teacher, and the remaining individuals are selected as students. The teacher's feasible solution uses the teaching strategy to teach the student's feasible solution;

[0029] S343, dividing the taught population into multiple learning groups, wherein the individual with the best fitness is the group leader, who can independently perform neighborhood search, and the other students complete the neighborhood search with the help of the group leader, and the group leader uses the learning strategy to teach the other individuals, and the learning strategy is the same as the teaching strategy;

[0030] S344, forming a new generation population, and returning to step S341 to determine the number of iterations. If the number of iterations is not met, repeat the steps; if the number of iterations is met, output the optimal production process result.

[0031] Preferably, the local search strategy of the diligent group of students and the variation strategy of the lazy group of students in step S341 include:

[0032] Diligent group local search strategy

[0033] In the two parts of encoding, A encoding and B encoding, the initial position and the ending position were randomly selected in the diligent group;

[0034] In A coding, the processing task group between the selected initial position and the end position is machine-flipped, changing the original solution machine allocation and the processing order on each machine;

[0035] In B coding, the processing tasks between the selected starting position and the ending position and the corresponding grouping information are flipped;

[0036] Generate the processing order of the processing tasks in each task group according to the relative order of the processing tasks in the B code;

[0037] Lazy group student mutation strategy

[0038] Two positions were randomly selected in each of the two parts of coding, A coding and B coding, for the diligent group of students;

[0039] In A coding, the processing task groups of the two selected positions are interchanged;

[0040] In B coding, the processing tasks and corresponding grouping information of the two selected positions are exchanged;

[0041] Generate the processing order of the processing tasks in each task group according to the order in which the processing tasks appear in the B code;

[0042] The processing order of the processing tasks in each task group is generated according to the relative order in which the processing tasks appear in the B code.

[0043] Preferably, the teaching strategy in step S342 includes:

[0044] The teacher's feasible solution teaches the two parts of the student's feasible solution separately, and selects the gene fragments in the A coding and B coding parts of the teacher's feasible solution and the student's feasible solution respectively, where the gene lengths are the same;

[0045] Replace the gene fragments selected in the two-part coding of the student's feasible solution with the corresponding gene fragments of the teacher's feasible solution; if there are identical task groups or identical tasks in the student's feasible solution, delete the repeated genes outside the gene fragments learned from the teacher's feasible solution, and complete the missing genes according to the order of the teacher's feasible solution.

[0046] A scheduling system for a wire rope production scheduling method includes a basic data management module, a data analysis module and a production operation module. The basic data management module is used to manage the existing total production resources, equipment information and order information. The data analysis module analyzes the order information according to the existing total production resource data and equipment information to generate an initial production task information table. The production operation module receives the initial production task information table generated by the data analysis module and generates an optimal scheduling plan according to abnormal problems generated during the production process.

[0047] Preferably, the basic data management module includes a raw material management module, an equipment management module and an order module; the raw material management module is used to record the quantity and inventory information of existing raw materials; the equipment management module is used to record the number of equipment and equipment processing module chain information; the order module is used to manage the production quantity and processing diameter information in the order;

[0048] The data analysis module includes a data grouping module, a resource calculation module and an allocation module. The data grouping module groups the data according to the processing diameter information of the order. The resource calculation module calculates whether the quantity of raw materials in the existing inventory is sufficient according to the production quantity of the order. The allocation module allocates the grouped data according to the equipment, machine and mold chain information, and generates an initial production task information table according to the allocation result.

[0049] The production operation module includes a constraint formation module and a production scheduling module. The constraint formation module sets production constraint conditions according to the completion target; the production scheduling module uses a teaching and learning algorithm to handle abnormal problems generated in the production process based on the initial production task information table and the set constraint conditions, and generates an optimal scheduling plan based on the completion target.

[0050] Therefore, the present invention adopts the above-mentioned steel wire rope production scheduling method and scheduling system, which has the following

[0051] Beneficial effects:

[0052] (1) Grouping wire ropes according to different production orders using their diameter specifications eliminates repeated preparation work for similar wire ropes and improves production efficiency for multiple and small batches;

[0053] (2) The constructed wire rope production scheduling model is solved using the improved teaching and learning algorithm, which can be adjusted in real time according to abnormal situations generated during the production process, thereby improving production efficiency and having strong applicability.

[0054] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0055] Figure 1 A method flow chart of an embodiment of a steel wire rope production scheduling method of the present invention;

[0056] Figure 2 A schematic diagram of a local search strategy for an embodiment of a steel wire rope production scheduling method of the present invention;

[0057] Figure 3 A schematic diagram of a variation strategy of an embodiment of a steel wire rope production scheduling method of the present invention;

[0058] Figure 4 A schematic diagram of a teacher strategy for an embodiment of a steel wire rope production scheduling method of the present invention;

[0059] Figure 5 It is a framework diagram of an embodiment of a steel wire rope production scheduling system of the present invention. DETAILED DESCRIPTION

[0060] Example

[0061] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.

[0062] Reference Figure 5 , a wire rope production scheduling system, including a basic data management module, a data analysis module and a production operation module.

[0063] Basic data management module: used to manage the total amount of existing production resources, equipment information and order information.

[0064] The basic data management module includes the raw material management module, the equipment management module and the order module; the raw material management module is used to record the quantity and inventory information of existing raw materials; the equipment management module is used to record the number of equipment and equipment processing module chain information; the order module is used to manage the production quantity and processing diameter information in the order.

[0065] Data analysis module: Analyze order information based on existing production resource total data and equipment information to generate an initial production task information table.

[0066] The data analysis module includes a data grouping module, a resource calculation module and an allocation module. The data grouping module groups the data according to the processing diameter information of the order. The resource calculation module calculates whether the quantity of raw materials in the existing inventory is sufficient according to the order production quantity. The allocation module allocates the grouped data according to the equipment, machine and mold chain information, and generates an initial production task information table based on the allocation results.

[0067] The production operation module receives the initial production task information table generated by the data analysis module, and generates the optimal scheduling plan based on the abnormal problems generated during the production process.

[0068] The production operation module includes a constraint formation module and a production scheduling module. The constraint formation module sets production constraints according to the completion target; the production scheduling module uses a teaching and learning algorithm to handle abnormal problems arising in the production process based on the initial production task information table and the set constraints, and generates the optimal scheduling plan based on the completion target.

[0069] Reference Figure 1 , a wire rope production scheduling system method, the steps comprising:

[0070] S1. Obtain the wire rope production order and divide the wire rope into different task groups according to the production tasks. In the same processing task group, the basic mold chain used is the same.

[0071] S2. According to different wire rope task groups, set completion targets, determine the constraints of the wire rope production process based on the completion targets, and build a wire rope production scheduling model.

[0072] Specifically, the goal is to minimize the maximum completion time of all workpieces, and the objective function is:

[0073] minC max

[0074] In the formula, C max The goal is to maximize the completion time of all artifacts.

[0075] The constraints of the wire rope production process include:

[0076] Constraint one: each machine can only process one part at a time, and once a task starts processing, it cannot be interrupted.

[0077] Constraint 2: Only one processing task group can be selected for the same processing task. The formula is:

[0078]

[0079] In the formula, J represents the processing task set, X j,g Indicates whether processing task j is processed within processing task g, X j,g ∈{0,1}.

[0080] Constraint three: a task group can only be processed on the same machine, and its formula is:

[0081]

[0082] In the formula, G represents the set of processing task groups, x g,h Indicates whether the processing task group g is assigned to machine h for processing, x g,h ∈{0,1}.

[0083] Constraint condition 4: The processing task group processed on the same machine can only have one front processing task group and one back processing task group, and the front processing task group and the back processing task group cannot be the same processing task group. The formula is:

[0084]

[0085] B j +T j =E j ,j∈J

[0086] In the formula, B j represents the start time of processing task j, T j represents the processing time of processing task j, E j represents the completion time of processing task j, h g,g' Indicates whether the processing task group g assigned to machine h is prioritized and the adjacent processing task group g' is processed. The first processing task group of machine h is represented as h 0,g =1,h g,g' ∈{0,1}.

[0087] Constraint five: The processing task of the same processing task group can only have one pre-processing and post-processing group, and the pre-processing group and post-processing group cannot be the same processing task group. The formula is

[0088]

[0089] In the formula, gj,j' Indicates whether the processing task j of the processing task group g is prioritized and the adjacent processing task j' is processed. The first processing task in the processing task group g is represented by g 0,j =1, g j,j' ∈{0,1},Bt g Indicates the start time of processing task group g, Et g represents the completion time of processing task group h, Stg j,j' It represents the intra-group preparation time of processing task j and processing task j' in the g-th group.

[0090] Constraint six: The number of wire drawing reels on the machine must be greater than the number of drawing passes of all tasks in the processing task group. The formula is:

[0091] maxL j <ml,j∈g

[0092] In the formula, ml represents the maximum value of the machine's installed mold chain, L j Indicates the number of processing mold chains used by processing task g.

[0093] Constraint seven: The start time of the processing task group on the same machine is after the previous processing task group is completed and the corresponding mold chain is replaced. The formula is:

[0094] Bt g -Et g-1 -Sth g,g-1 ≥0,x g,h =1,x g-1,h =1,h g,g-1 =1

[0095] Where Sth g,g-1 It represents the inter-group preparation time for switching from processing task group g to processing task g-1 on machine h.

[0096] Constraint condition eight: The start time of the processing task of the same processing task group is after the previous processing task is completed and the corresponding mold chain is replaced. The formula is:

[0097] B j -E j-1 -Stg j,j-1 ≥0,j-1,j∈g,g j,j' =1.

[0098] S3. Use the improved teaching and learning algorithm to solve the wire rope production scheduling model and obtain the optimal production process.

[0099] Preferably, the process of solving the steel wire rope production scheduling model using the improved teaching and learning algorithm in step S3 includes:

[0100] S31. Coding: determine the processing tasks and the number of processing machines. Coding is performed according to the processing task information. The coding includes A coding and B coding. A coding represents the processing group machines and the processing sequence on each machine. B coding represents the internal processing sequence of the processing group and the composition of the processing task group.

[0101] Take 10 processing tasks and two processing machines for illustration. The processing task information table is shown in Table 1.

[0102] Table 1 Processing task information table

[0103]

[0104] According to the above, each task group corresponds to a corresponding basic module chain, and the above generated feasible decoding is shown in Table 2.

[0105] Table 2 Coding

[0106]

[0107] The left side is A code, and the right side is B code. B code is divided into two lines. The first line indicates the processing task sequence number, and the second line indicates the processing task group to which the corresponding processing task is assigned.

[0108] S32: Generate initial solutions of A code and B code.

[0109] A-coded initial solution generation

[0110] Randomly sort the serial numbers of the processing task groups, then assign machines according to the sorted order, traverse in order, assign the traversed array according to the rule of minimum completion time, and generate the initial A code, such as 4, 1, a, 3, 2.

[0111] B-coded initial solution generation

[0112] Randomly sort the order of the processing tasks, select the processing task group to which the processing task is assigned according to the basic mold chain, and modify the order of the processing tasks in the group using the LDC rule based on the fact that the preparation time in the group is shorter when changing from a long mold chain to a short mold chain than when changing from a short mold chain to a long mold chain. In the same group of tasks, the processing tasks with longer drawing passes are processed first. For example, processing task 7 is arranged first in group 3.

[0113] S33. Initialize the population according to the generated initial solution.

[0114] S34. Solve the objective function based on the improved teaching and learning algorithm to obtain the optimal production process.

[0115] The step S34 specifically includes:

[0116] S341. Determine whether the iteration has reached the maximum number of generations set by the algorithm, randomly generate student individuals from the population with a probability of α% and enter the diligent group of students. All diligent group students conduct local search, and the remaining student individuals are the lazy group and mutate with a probability of β%.

[0117] Diligent group local search strategy

[0118] like Figure 2 As shown, in the two-part encoding of the diligent group, the initial position and the end position are randomly selected in the A encoding and the B encoding. In the A encoding, the processing task group between the selected initial position and the end position is flipped by the machine, changing the original machine allocation and the processing order on each machine. In the B encoding, the processing tasks between the selected starting position and the end position and the corresponding grouping information are flipped. The processing order of the processing tasks in each task group is generated according to the relative order of the processing tasks in the B encoding.

[0119] Lazy group student mutation strategy

[0120] like Figure 3 As shown, two positions are randomly selected in the two parts of the coding of the diligent group of students, A coding and B coding. In A coding, the processing task groups of the two selected positions are interchanged. In B coding, the processing tasks and corresponding grouping information of the two selected positions are interchanged. The processing order of the processing tasks in each task group is generated according to the order in which the processing tasks appear in B coding. The processing order of the processing tasks in each task group is generated according to the relative order in which the processing tasks appear in B coding.

[0121] S342. The individual with the best fitness among all individuals in the population is selected as the teacher, and the remaining individuals are selected as students. The teacher's feasible solution uses the teaching strategy to teach the student's feasible solution.

[0122] Teaching strategies include:

[0123] The teacher's feasible solution teaches the two parts of the student's feasible solution separately, and selects the gene fragments in the A coding and B coding parts of the teacher's feasible solution and the student's feasible solution respectively, where the gene lengths are the same;

[0124] Replace the gene fragments selected in the two-part coding of the student's feasible solution with the corresponding gene fragments of the teacher's feasible solution; if there are identical task groups or identical tasks in the student's feasible solution, delete the repeated genes outside the gene fragments learned from the teacher's feasible solution, and complete the missing genes according to the order of the teacher's feasible solution.

[0125] In the feasibility of the teaching strategy, it may happen that the machine cannot process the task group, and the feasible solution is repaired.

[0126] The repair process is: traverse all processing task groups, find the processing tasks that do not meet the processing range, then traverse the machines, find the machine set of the machine's processing task group, remove the processing tasks that do not meet the processing range from the processing machine, and move the other processing tasks in sequence, and put the processing task group at the end of the machine that can process the task, and finally the machine with the shortest completion time. Repeat the above process until all processing task groups meet the requirements, such as Figure 4 shown.

[0127] S343, dividing the taught population into multiple learning groups, wherein the individual with the best fitness is the group leader, who can independently perform neighborhood search, and the other students complete the neighborhood search with the help of the group leader, and the group leader uses the learning strategy to teach the other individuals, and the learning strategy is the same as the teaching strategy;

[0128] S344, forming a new generation population, and returning to step S341 for iterative judgment, if the iterative structure is not satisfied, repeat the steps; if the iterative result is satisfied, output the optimal production process result.

[0129] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.

Claims

1. A method for scheduling the production of steel wire ropes, characterized in that the steps include: S1. Obtain the steel wire rope production order and divide the steel wire rope into different task groups according to the production tasks; S2. According to different wire rope task groups, set completion targets, determine the constraints of the wire rope production process according to the completion targets, and build a wire rope production scheduling model; S3. Use the improved teaching and learning algorithm to solve the wire rope production scheduling model and obtain the optimal production process.

2. A steel wire rope production scheduling method according to claim 1, characterized in that: In step S2, the goal is to minimize the maximum completion time of all workpieces, and the objective function is: minC max In the formula, C max Represents the maximum completion time of all artifacts.

3. A steel wire rope production scheduling method according to claim 2, characterized in that: In step S2, the constraints of the wire rope production process include: Constraint 1: Each machine can only process one part at a time, and once a task is started, it cannot be interrupted; Constraint 2: Only one processing task group can be selected for the same processing task; Constraint three: a task group can only be processed on the same machine; Constraint condition 4: The processing task group processed on the same machine can only have one front processing task group and one back processing task group, and the front processing task group and the back processing task group cannot be the same processing task group; Constraint five: The processing tasks of the same processing task group can only have one pre-processing and post-processing group, and the pre-processing group and post-processing group cannot be the same processing task group; Constraint six: the number of wire drawing reels on the machine must be greater than the number of drawing passes of all tasks in the processing task group; Constraint seven: the start time of the processing task group on the same machine is after the previous processing task group is completed and the corresponding die chain is replaced; Constraint eight: The start time of the processing task of the same processing task group is after the previous processing task is completed and the corresponding mold chain is replaced.

4. A steel wire rope production scheduling method according to claim 3, characterized in that: The process of solving the steel wire rope production scheduling model using the improved teaching and learning algorithm in step S3 includes: S31, coding, determining the processing tasks and the number of processing machines, and coding according to the processing task information, the coding includes A code and B code, A code represents the processing group machine and the processing sequence on each machine, B code represents the internal processing sequence of the processing group and the composition of the processing task group; S32, generating initial solutions of A code and B code; S33, initializing the population according to the generated initial solution; S34. Solve the objective function based on the improved teaching and learning algorithm to obtain the optimal production process.

5. A steel wire rope production scheduling method according to claim 4, characterized in that: The step S34 specifically includes: S341, judging whether the iteration reaches the maximum number of generations set by the algorithm, randomly generating student individuals from the population with a probability of α% to enter the diligent group of students, all diligent group students perform local search, and the remaining student individuals are the lazy group, which mutates with a probability of β%; S342. The individual with the best fitness among all individuals in the population is selected as the teacher, and the remaining individuals are selected as students. The teacher's feasible solution uses the teaching strategy to teach the student's feasible solution; S343, dividing the taught population into multiple learning groups, wherein the individual with the best fitness is the group leader, who can independently perform neighborhood search, and the other students complete the neighborhood search with the help of the group leader, and the group leader uses the learning strategy to teach the other individuals, and the learning strategy is the same as the teaching strategy; S344, forming a new generation population, and returning to step S341 to determine the number of iterations. If the number of iterations is not met, repeat the steps; if the number of iterations is met, output the optimal production process result.

6. A steel wire rope production scheduling method according to claim 5, characterized in that: The local search strategy of the diligent group of students and the variation strategy of the lazy group of students in step S341 include: Diligent group local search strategy In the two parts of encoding, A encoding and B encoding, the initial position and the ending position were randomly selected in the diligent group; In A coding, the processing task group between the selected initial position and the end position is machine-flipped, changing the original solution machine allocation and the processing order on each machine; In B coding, the processing tasks between the selected starting position and the ending position and the corresponding grouping information are flipped; Generate the processing order of the processing tasks in each task group according to the relative order of the processing tasks in the B code; Lazy group student mutation strategy Two positions were randomly selected in each of the two parts of coding, A coding and B coding, for the diligent group of students; In A coding, the processing task groups of the two selected positions are interchanged; In B coding, the processing tasks and corresponding grouping information of the two selected positions are exchanged; Generate the processing order of the processing tasks in each task group according to the order in which the processing tasks appear in the B code; The processing order of the processing tasks in each task group is generated according to the relative order in which the processing tasks appear in the B code.

7. A steel wire rope production scheduling method according to claim 5, characterized in that: The teaching strategy in step S342 includes: The teacher's feasible solution teaches the two parts of the student's feasible solution separately, and selects the gene fragments in the A coding and B coding parts of the teacher's feasible solution and the student's feasible solution respectively, where the gene lengths are the same; Replace the gene fragments selected in the two-part coding of the student's feasible solution with the corresponding gene fragments of the teacher's feasible solution; if there are identical task groups or identical tasks in the student's feasible solution, delete the repeated genes outside the gene fragments learned from the teacher's feasible solution, and complete the missing genes according to the order of the teacher's feasible solution.

8. A scheduling system for a steel wire rope production scheduling method according to any one of claims 1 to 7, characterized in that: It includes a basic data management module, a data analysis module and a production operation module. The basic data management module is used to manage the existing total production resources, equipment information and order information. The data analysis module analyzes the order information according to the existing total production resource data and equipment information to generate an initial production task information table. The production operation module receives the initial production task information table generated by the data analysis module and generates an optimal scheduling plan according to abnormal problems generated during the production process.

9. The scheduling system of the steel wire rope production scheduling method according to claim 8, characterized in that: The basic data management module includes a raw material management module, an equipment management module and an order module; the raw material management module is used to record the quantity and inventory information of existing raw materials; the equipment management module is used to record the number of equipment and equipment processing module chain information; the order module is used to manage the production quantity and processing diameter information in the order; The data analysis module includes a data grouping module, a resource calculation module and an allocation module. The data grouping module groups the data according to the processing diameter information of the order. The resource calculation module calculates whether the quantity of raw materials in the existing inventory is sufficient according to the production quantity of the order. The allocation module allocates the grouped data according to the equipment, machine and mold chain information, and generates an initial production task information table according to the allocation result. The production operation module includes a constraint formation module and a production scheduling module. The constraint formation module sets production constraint conditions according to the completion target; the production scheduling module uses a teaching and learning algorithm to handle abnormal problems generated in the production process based on the initial production task information table and the set constraint conditions, and generates an optimal scheduling plan based on the completion target.