Medical intelligent sterilization gas filling system and method

By designing a medical intelligent sterilization gas filling system, and utilizing remote control valves and nitrogen replacement technology, the risk of oxygen contact during ethylene oxide filling was solved, achieving an automated and safe filling process and reducing the safety hazards of manual operation.

CN118912366AActive Publication Date: 2024-11-08SICHUAN XINTU FLUID CONTROL TECHNOLOGY CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202410885632.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-03
Publication Date
2024-11-08
Estimated Expiration
2044-07-03

AI Technical Summary

Technical Problem

Existing technologies pose a risk of oxygen exposure during ethylene oxide filling, leading to potential hazards and corrosiveness, and require manual operation, which also presents safety risks.

Method used

A medical intelligent sterilization gas filling system was designed. The system remotely controls the valves through the control system, combines gas and liquid phase channels, uses nitrogen replacement and vacuum technology to ensure an oxygen-free environment, and uses RFID to identify gas cylinder information to achieve automated filling.

Benefits of technology

It improves filling safety, reduces the risk of valve leakage, reduces manual operation, enhances the system's fault tolerance, and ensures the reliability and safety of the filling process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118912366A_ABST
    Figure CN118912366A_ABST
Patent Text Reader

Abstract

The invention discloses a medical intelligent sterilization gas filling system and method.The medical intelligent sterilization gas filling system comprises a control system and a filling pipeline, the filling pipeline comprises a gas phase channel and a liquid phase channel, and the gas phase channel is used for adjusting the gas pressure of the pipeline, discharging oxygen in the pipeline and recycling redundant filling gas; control valves remotely controlled by the control system are mounted on the gas-phase channel and the liquid-phase channel, the gas-phase channel is sequentially connected with a gas-phase conveying pipeline, a gas-phase filling hose, a gas return valve and a first cylinder valve and then connected into a gas cylinder, and pressure monitoring equipment in communication connection with the control system is further mounted on the gas-phase channel and used for monitoring the pressure condition of the pipeline; the liquid-phase channel is used for filling a gas cylinder with sterilization gas EO, the liquid-phase channel is sequentially connected with a liquid-phase filling hose, a liquid inlet valve and a second cylinder valve and then is connected to the gas cylinder, and valves of all pipelines are intelligently controlled, so that the filling safety is guaranteed, the error-tolerant rate is increased, and the risk caused by valve leakage to a human body is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of industrial gas filling, and in particular to a medical intelligent sterilization gas filling system and method. Background Art

[0002] Ethylene oxide (EO) is an important organic chemical raw material and an important raw material for the production of surfactants, lubricants, resins, adhesives and other products. Its chemical formula is C2H4O and it is a colorless transparent liquid. In the field of medical and health care, ethylene oxide is used as a sterilizing gas and can often be used to sterilize instruments and surgical instruments. However, ethylene oxide has a low boiling point and is toxic, corrosive and flammable. It will react violently when in contact with oxygen and cause harm to the human body. Therefore, it is necessary to select appropriate materials and methods during the preparation, production and filling process to avoid the risk of ethylene oxide contacting with oxygen. Ethylene oxide leakage will have an impact on the human body. Therefore, it is necessary to reduce manual operations. Therefore, a medical sterilizing gas intelligent filling system that can intelligently fill ethylene oxide is needed. Summary of the invention

[0003] The purpose of the present invention is to provide a medical intelligent sterile gas filling system and filling method, to keep the pipeline of the filling system oxygen-free, to ensure the filling safety, to improve the fault tolerance rate and to reduce the risk of valve leakage to the human body by intelligently controlling the valves of each pipeline.

[0004] To achieve the above objectives, this application provides the following solutions: On the one hand, the present application provides a medical intelligent sterilizing gas filling system, including a control system and a filling pipeline, the filling pipeline including a gas phase channel and a liquid phase channel, the gas phase channel is used to adjust the pipeline air pressure, discharge oxygen in the pipeline and recover excess filling gas, the gas phase channel and the liquid phase channel are both equipped with control valves remotely controlled by the control system, the gas phase channel is connected to the gas phase delivery pipeline, the gas phase filling hose, the return valve and the first bottle valve in sequence, and then connected to the gas cylinder, the gas phase channel is also equipped with a pressure monitoring device that is communicatively connected to the control system and is used to monitor the pressure of the pipeline; the liquid phase channel is used to fill the sterilizing gas EO into the gas cylinder, and the liquid phase channel is connected to the liquid phase filling hose, the liquid inlet valve and the second bottle valve in sequence, and then connected to the gas cylinder.

[0005] In some specific embodiments, the gas phase channel includes a gas phase vacuum pipeline, a gas phase venting pipeline, a nitrogen pressurizing pipeline and a mixed gas large bottle filling-return pipeline that are all connected to the gas phase transport pipeline. Each pipeline is installed with a control valve remotely controlled by the control system to control the connection between the pipeline and the gas phase transport pipeline. The gas phase transport pipeline is connected to the gas phase filling hose, the return valve and the first bottle valve in sequence and then connected to the gas cylinder. A pressure monitoring device is installed on the nitrogen pressurizing pipeline.

[0006] In some specific embodiments, one end of the gas-phase vacuum pumping pipeline is connected to the gas-phase vacuum pumping equipment, and the other end is connected to the gas-phase vacuum automatic control valve and then connected to the gas-phase delivery pipeline; one end of the gas-phase venting pipeline is connected to the gas-phase venting equipment, and the other end is connected to the first one-way valve and the gas-phase venting automatic control valve in sequence and then connected to the gas-phase delivery pipeline; one end of the mixed gas bottle filling-return air pipeline is connected to the return air equipment, and the other end is connected to the second one-way valve and the return air automatic control valve in sequence and then connected to the gas-phase delivery pipeline; an oxygen content analyzer that is communicatively connected to the control system is installed on the mixed gas bottle filling-return air pipeline; one end of the nitrogen boosting pipeline is connected to the gas-phase N2 supply system, and the other end is connected to the gas-phase nitrogen automatic control valve and the third one-way valve in sequence and then connected to the gas-phase delivery pipeline, and the pressure monitoring equipment is arranged on the pipeline at the output end of the third one-way valve.

[0007] In some specific embodiments, the liquid phase channel includes a liquid phase vacuum pipeline, a liquid phase venting pipeline, a nitrogen supply pipeline and an EO filling pipeline which are all connected to the liquid phase delivery pipeline. A control valve remotely controlled by the control system is installed on each pipeline to control the connection between the pipeline and the liquid phase delivery pipeline. The liquid phase delivery pipeline is connected to the liquid phase filling hose, the liquid inlet valve and the second bottle valve in sequence and then connected to the gas cylinder.

[0008] In some specific embodiments, one end of the nitrogen supply pipeline is connected to the liquid phase N2 supply system, and the other end is connected to the liquid phase nitrogen automatic control valve and the fourth one-way valve in sequence and then connected to the liquid phase delivery pipeline; one end of the EO filling pipeline is connected to the EO filling equipment, and the other end is connected to the EO filling automatic control valve and the fifth one-way valve in sequence and then connected to the liquid phase delivery pipeline; one end of the liquid phase vacuum pumping pipeline is connected to the liquid phase vacuum pumping equipment, and the other end is connected to the liquid phase vacuum automatic control valve in sequence and then connected to the liquid phase delivery pipeline; one end of the liquid phase venting pipeline is connected to the liquid phase venting equipment, and the other end is connected to the sixth one-way valve and the liquid phase venting automatic control valve in sequence and then connected to the liquid phase delivery pipeline.

[0009] In a second aspect, the present application provides a medical intelligent sterilization gas filling method, the filling process comprising the following steps: S1. Control all valves in the filling pipeline to keep them closed through the control system, put the gas cylinder into the work station, and verify the safety of the gas cylinder; S2. After the safety verification is passed, the gas phase transmission pipeline is vented and vacuumed; S3, venting and vacuuming the liquid phase delivery pipeline; S4, control the gas phase nitrogen automatic control valve to open, so that the gas phase N2 supply system replaces nitrogen with the filling device in the gas phase channel, and then vents and vacuumizes again; S5, control the liquid phase N2 supply system to replace nitrogen with the filling device in the liquid phase channel and then vent it, and vacuum the inside of the gas cylinder; S6, control the EO filling automatic control valve to open, and at the same time control the return air automatic control valve to open, close the valves on other pipelines, and start automatically filling the gas cylinder until it is filled to the target weight; S7, control the EO filling automatic control valve and the return air automatic control valve to close, control the liquid nitrogen automatic control valve and the gas nitrogen automatic control valve to open, and send the remaining liquid and gas pressure inside the pipeline to the gas cylinder.

[0010] In some specific implementations, the process of verifying the safety of the gas cylinder in step S1 is as follows: After the gas cylinder is placed at the workstation, the gas cylinder number uploaded by scanning the RFID code is received; Query the filling parameters of the gas cylinder corresponding to the gas cylinder number, including the type of gas last filled in the gas cylinder and the number of times the gas cylinder has been used; Determine whether the gas type last filled is the same as the gas type this time and whether the number of times the gas cylinder has been used has reached the threshold. If they are the same and have not reached the filling threshold, pass the safety verification and update the filling parameters of the gas cylinder.

[0011] In some specific implementations, the specific steps of step S2 include: S21, control the gas phase venting automatic control valve to open, vent the gas phase transmission pipeline through the gas phase venting equipment, and close the gas phase venting automatic control valve after venting to the venting target pressure; S32, control the gas phase vacuum automatic control valve to open, and use the gas phase vacuum pumping equipment to vacuum the gas phase conveying pipeline until the target vacuum target pressure is reached and then close the gas phase vacuum automatic control valve.

[0012] In some specific implementations, the specific process of step S3 is: S31, control the liquid phase venting automatic control valve to open, vent the liquid phase delivery pipeline through the liquid phase venting equipment, and close the liquid phase venting automatic control valve after venting to the venting target pressure for 10 seconds; S32, control the liquid phase vacuum automatic control valve to open, and use the liquid phase vacuum pumping equipment to vacuum the liquid phase delivery pipeline until the target vacuum target pressure is reached, and then close the liquid phase vacuum automatic control valve.

[0013] In some specific implementations, the specific process of step S4 is: S41, control the gas phase nitrogen automatic control valve to open, so that the gas phase N2 supply system replaces nitrogen with the filling device in the gas phase channel, and control the gas phase nitrogen automatic control valve to close after the replacement nitrogen filling reaches the target pressure; S42, control the gas phase venting automatic control valve to open, vent the gas phase transmission pipeline through the gas phase venting equipment, and close the gas phase venting automatic control valve after venting to the venting target pressure; S43, vacuuming the gas phase conveying pipeline, controlling the gas phase vacuum automatic control valve to open, vacuuming the gas phase conveying pipeline by gas phase vacuum pumping equipment, and closing the gas phase vacuum automatic control valve after reaching the target vacuum target pressure.

[0014] The present invention has the beneficial effects: This application uses RFID identification to match the information of the gas cylinder with the data on the cloud to monitor the safety of the gas cylinder, and vacuum equipment and nitrogen supply pipelines are installed in the liquid phase channel and the gas phase pipeline. Vacuuming can speed up gas filling; nitrogen circulation is used to cool the pump area, reduce liquid vaporization, and reduce damage to the pipeline; In this application, a remote pneumatic valve is used in the pipeline, and the opening and closing of the valve and the pressure in the pipeline can be remotely controlled through the control system. No manual operation is required during the filling process, which improves the fault tolerance rate and reduces potential risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 A schematic diagram of the pipeline connection of the medical intelligent sterilizing gas filling system provided by an embodiment of the present invention; Figure 2 A flow chart of the medical intelligent sterilizing gas filling method provided in an embodiment of the present invention.

[0016] Description of reference numerals: 1-gas phase vacuum equipment, 2-gas phase venting equipment, 3-return gas equipment, 4-gas phase N2 supply system, 5-liquid phase N2 supply system, 6-EO filling equipment, 7-liquid phase vacuum equipment, 8-liquid phase venting equipment, 9-gas phase vacuum automatic control valve, 10-gas phase venting automatic control valve, 11-first check valve, 12-return gas automatic control valve, 13-second check valve, 14-gas phase nitrogen automatic control valve, 15-third check valve, 16-liquid nitrogen automatic control valve, 17-the fourth one-way valve, 18-EO filling automatic control valve, 19-the fifth one-way valve, 20-liquid vacuum automatic control valve, 21-the sixth one-way valve, 22-liquid venting automatic control valve, 23-pressure monitoring equipment, 24-liquid filling hose, 25-gas filling hose, 26-return valve, 27-liquid supply valve, 28-the first bottle valve, 29-the second bottle valve, 30-gas cylinder, 31-weighing equipment. DETAILED DESCRIPTION

[0017] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. The following description of at least one exemplary embodiment is actually only illustrative and is by no means intended to limit the present invention and its application or use. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0018] The relative arrangement of components and steps, the numerical expressions and numerical values ​​set forth in these embodiments do not limit the scope of the present invention unless specifically stated otherwise.

[0019] At the same time, it should be understood that for the convenience of description, the sizes of the various parts shown in the drawings are not drawn according to the actual proportional relationship.

[0020] Additionally, descriptions of well-known structures, functions, and configurations may be omitted for clarity and conciseness.One of ordinary skill in the art will recognize that various changes and modifications may be made to the examples described herein without departing from the spirit and scope of the present disclosure.

[0021] Technologies, methods, and apparatus known to ordinary technicians in the relevant field may not be discussed in detail, but where appropriate, such technologies, methods, and apparatus should be considered part of the authorization specification.

[0022] In all examples shown and discussed herein, any specific values ​​should be interpreted as merely exemplary and not as limiting. Therefore, other examples of the exemplary embodiments may have different values.

[0023] Example 1 like Figure 1 As shown, this embodiment provides a medical intelligent sterilizing gas filling system, including a control system and a filling pipeline, the filling pipeline including a gas phase channel and a liquid phase channel, the gas phase channel is used to adjust the pipeline air pressure, discharge oxygen in the pipeline and recover excess filling gas, the gas phase channel and the liquid phase channel are both equipped with control valves remotely controlled by the control system, the gas phase channel is connected to the gas phase delivery pipeline, the gas phase filling hose 25, the return valve 26 and the first bottle valve 28 in sequence, and then connected to the gas cylinder 30, the gas phase channel is also equipped with a pressure monitoring device 23 that is communicatively connected to the control system, and is used to monitor the pressure of the pipeline; the liquid phase channel is used to fill the sterilizing gas EO into the gas cylinder 30, and the liquid phase channel is connected to the liquid phase filling hose 24, the liquid inlet valve and the second bottle valve 29 in sequence, and then connected to the gas cylinder 30.

[0024] Specifically, the gas phase channel includes a gas phase vacuum pipeline, a gas phase venting pipeline, a nitrogen boosting pipeline and a mixed gas large bottle filling-return pipeline that are all connected to the gas phase conveying pipeline. Each pipeline is installed with a control valve remotely controlled by the control system to control the connection between the pipeline and the gas phase conveying pipeline. The gas phase conveying pipeline is connected to the gas phase filling hose 25, the return valve 26 and the first bottle valve 28 in sequence and then connected to the gas cylinder 30. A pressure monitoring device 23 is installed on the nitrogen boosting pipeline.

[0025] Among them, one end of the gas phase vacuum pumping pipeline is connected to the gas phase vacuum pumping equipment 1, and the other end is connected to the gas phase vacuum automatic control valve 9 and then connected to the gas phase conveying pipeline; one end of the gas phase venting pipeline is connected to the gas phase venting equipment 2, and the other end is connected to the first one-way valve 11 and the gas phase venting automatic control valve 10 in sequence and then connected to the gas phase conveying pipeline; one end of the mixed gas bottle filling-return air pipeline is connected to the return air equipment 3, and the other end is connected to the second one-way valve 13 and the return air automatic control valve 12 in sequence and then connected to the gas phase conveying pipeline. An oxygen content analyzer that is communicated with the control system is installed on the mixed gas bottle filling-return air pipeline; one end of the nitrogen boosting pipeline is connected to the gas phase N2 supply system 4, and the other end is connected to the gas phase nitrogen automatic control valve 14 and the third one-way valve 15 in sequence and then connected to the gas phase conveying pipeline, and the pressure monitoring equipment 23 is arranged on the pipeline at the output end of the third one-way valve 15.

[0026] Specifically, the liquid phase channel includes a liquid phase vacuum pipeline, a liquid phase venting pipeline, a nitrogen supply pipeline and an EO filling pipeline which are all connected to the liquid phase conveying pipeline. A control valve which is remotely controlled by the control system is installed on each pipeline to control the connection between the pipeline and the liquid phase conveying pipeline. The liquid phase conveying pipeline is connected to the liquid phase filling hose 24, the liquid inlet valve and the second bottle valve 29 in sequence and then connected to the gas cylinder 30.

[0027] Among them, one end of the nitrogen supply pipeline is connected to the liquid phase N2 supply system 5, and the other end is connected to the liquid phase nitrogen automatic control valve 16 and the fourth one-way valve 17 in sequence and then connected to the liquid phase delivery pipeline; one end of the EO filling pipeline is connected to the EO filling equipment 6, and the other end is connected to the EO filling automatic control valve 18 and the fifth one-way valve 19 in sequence and then connected to the liquid phase delivery pipeline, one end of the liquid phase vacuum pipeline is connected to the liquid phase vacuum equipment 7, and the other end is connected to the liquid phase vacuum automatic control valve 20 in sequence and then connected to the liquid phase delivery pipeline, one end of the liquid phase venting pipeline is connected to the liquid phase venting equipment 8, and the other end is connected to the sixth one-way valve 21 and the liquid phase venting automatic control valve 22 in sequence and then connected to the liquid phase delivery pipeline.

[0028] Based on the above-mentioned medical intelligent sterilization gas filling system, its filling process can be summarized as: preliminary preparation work (checking the initial state, connecting the hose, selecting the formula, opening the bottle valve) → venting the gas phase channel to the target pressure → vacuuming the gas phase channel to the target pressure → venting the liquid phase channel to the target pressure → vacuuming the liquid phase channel to the target pressure → nitrogen replacement (filling device replaces nitrogen to the target pressure state → venting the nitrogen gas phase to the target pressure → vacuuming the nitrogen gas phase pipeline to the target pressure) → filling (EO liquid inlet and gas return at the same time → EO liquid inlet reaches the target weight → nitrogen purge in the liquid phase pipeline reaches a delay of 5s → nitrogen in the gas phase pipeline is pressurized to the target pressure) → filling end work (closing the bottle valve → confirming that the venting is to the target pressure → removing the hose → end), each specific step is: (1) Preliminary preparation: S1. All valves in the filling pipeline are controlled to remain closed by the control system, the gas cylinder 30 is placed in the work station, and the safety of the gas cylinder 30 is verified. The process of safety verification is as follows; S11, after the gas cylinder 30 is placed at the workstation, the gas cylinder 30 is scanned by RFID technology, and the number of the gas cylinder 30 obtained by the RFID scanning is uploaded to the control system; S12, query the filling parameters of the gas cylinder 30 corresponding to the number of the gas cylinder 30, the filling parameters include the type of gas last filled in the gas cylinder 30 and the number of times the gas cylinder 30 has been used; the control system confirms the gas last filled in the gas cylinder 30 through cloud data and checks the service life of the gas cylinder 30. When the filling parameters are confirmed to be valid, the filling personnel are started to ensure the stable performance of the filling; S13, determine whether the gas type of the last filling is the same as the gas type of the current filling and whether the number of times the gas cylinder 30 has been used has reached a threshold; if they are the same and have not reached the filling threshold, pass the safety verification and update the filling parameters of the gas cylinder 30.

[0029] S2. After the safety verification is passed, connect the hose and start to detect the system status. S21. Follow the prompts to confirm that the liquid return valve, the liquid supply valve 27, the first bottle valve 28 and the second bottle valve 29 are closed, and connect the gas phase filling hose 25 and the liquid phase filling hose 24.

[0030] S22, then open the liquid return valve, liquid supply valve 27, first bottle valve 28 and second bottle valve 29, obtain the oxygen content uploaded by the oxygen content analyzer and the pressure state in the system through the control program, and judge whether there is oxygen in the gas phase channel and the liquid phase channel; if there is oxygen, it is necessary to deoxygenate the system to ensure an oxygen-free environment in the system.

[0031] (2) Venting and vacuuming of the gas phase channel S3, venting and vacuuming the gas phase transmission pipeline, and receiving the pressure status in the transmission pipeline in real time; S31, venting the gas phase transport pipeline, controlling the gas phase venting automatic control valve 10 to open, venting the gas phase transport pipeline through the gas phase venting equipment 2, and closing the gas phase venting automatic control valve 10 after venting to the venting target pressure; S32, vacuuming the gas phase delivery pipeline, controlling the gas phase vacuum automatic control valve 9 to open, vacuuming the gas phase delivery pipeline by the gas phase vacuum pumping device 1, and closing the gas phase vacuum automatic control valve 9 after reaching the target vacuum target pressure; (3) Venting and vacuuming the liquid phase channel S4, venting and vacuuming the liquid phase delivery pipeline, and receiving the pressure status in the delivery pipeline in real time; S41, venting the liquid phase delivery pipeline, controlling the liquid phase venting automatic control valve 22 to open, venting the liquid phase delivery pipeline through the liquid phase venting device 8, and venting to the venting target pressure, delaying 10 seconds to close the liquid phase venting automatic control valve 22; S42, vacuuming the liquid phase delivery pipeline, controlling the liquid phase vacuum automatic control valve 20 to open, vacuuming the liquid phase delivery pipeline by the liquid phase vacuum pumping device 7, and closing the liquid phase vacuum automatic control valve 20 after reaching the target vacuum target pressure; (4) Nitrogen is replaced in the liquid phase channel and the gas phase channel to ensure an oxygen-free environment in the system; S5. Fill the gas phase transmission pipeline with nitrogen to replace the nitrogen S51, control the gas phase nitrogen automatic control valve 14 to open, so that the gas phase N2 supply system 4 replaces nitrogen with the filling device in the gas phase channel, and after the replacement nitrogen filling reaches the target pressure, control the gas phase nitrogen automatic control valve 14 to close; S52, control the gas phase venting automatic control valve 10 to open, vent the gas phase transmission pipeline through the gas phase venting equipment 2, and close the gas phase venting automatic control valve 10 after venting to the venting target pressure; S53, vacuumizing the gas phase delivery pipeline, controlling the gas phase vacuum automatic control valve 9 to open, vacuumizing the gas phase delivery pipeline by the gas phase vacuum pumping device 1, and closing the gas phase vacuum automatic control valve 9 after reaching the target vacuum target pressure; S6. Fill the liquid phase delivery pipeline with nitrogen and simultaneously evacuate the interior of the gas cylinder; S61, control the liquid nitrogen automatic control valve 16 to open, so that the liquid N2 supply system 5 replaces nitrogen with the filling device in the liquid phase channel, and after the replacement nitrogen filling reaches the target pressure, control the gas nitrogen automatic control valve 14 to close; S62, control the liquid phase venting automatic control valve 22 to open, and vent the liquid phase delivery pipeline and the gas inside the gas cylinder 30 through the liquid phase venting device 8, and vent to the venting target pressure and close the liquid phase venting automatic control valve 22; S63, vacuuming the liquid phase delivery pipeline, controlling the liquid phase vacuum automatic control valve 20 to open, vacuuming the liquid phase delivery pipeline by the liquid phase vacuum pumping device 7 until the target vacuum target pressure (lower than -0.5Mpa) is reached, and then the liquid phase vacuum automatic control valve 20 is closed; (5) Fill the system with medical sterilizing gas EO S7, open the control valve on the liquid phase pipeline EO filling pipeline and open the liquid phase nitrogen supply pipeline and the gas phase return pipeline at the same time, perform nitrogen purge and return gas treatment on the EO filling pipeline, close the valves on other pipelines, and start automatic filling until the target weight is filled; S71, control the EO filling automatic control valve 18 to open, so that the EO filling device 6 inputs EO into the liquid phase delivery pipeline; S72, while EO is being fed into the gas phase pipeline, the gas phase pipeline is being returned, and the gas return automatic control valve 12 on the mixed gas bottle filling-gas return pipeline is controlled to open so that the gas return device 3 can return gas to the pipeline; S73, real-time detection of whether the EO filled in the gas cylinder has reached the target weight, and after reaching the target weight, the EO filling automatic control valve 18 is controlled to close and stop filling (the gas phase flows back into the gas cylinder during the filling process, and the starting weight is when the gas cylinder is completely evacuated); S8. Treat the residual liquid and residual gas in the system with nitrogen, and pressurize the residual liquid and residual gas inside the gas phase channel and the liquid phase channel into the gas cylinder. Since EO has low pressure and low density, after filling to the target weight, there is still residual EO in the liquid phase delivery pipeline of the system. Therefore, it is necessary to purge the liquid phase delivery pipeline with nitrogen and fill the gas phase pipeline with nitrogen to increase the pressure, and push the gasified EO gas into the pipeline; S81, after reaching the target weight, control the EO filling automatic control valve 18 and the return air automatic control valve 12 to close, and then control the liquid nitrogen automatic control valve 16 to open, so that the liquid N2 supply system 5 purges nitrogen into the liquid phase channel, and sweeps the internal residual liquid back into the gas cylinder. After continuing to purge nitrogen for 5 seconds, delay for 5 seconds, and control the liquid nitrogen automatic control valve 16 to close; S82, control the gas-phase nitrogen automatic control valve 14 to open, so that the gas-phase N2 supply system 4 fills the gas-phase channel with nitrogen for pressurization, and sends the remaining gas pressure inside the pipeline to the gas cylinder 30, until the nitrogen in the gas-phase pipeline is pressurized to the target pressure, and then control the gas-phase nitrogen automatic control valve 14 to close.

[0032] S83, close the air return valve 26, the liquid supply valve 27, the first bottle valve 28, and the second bottle valve 29; (6) Dismantle the system after filling S9. Confirm that all valves in the system are closed, confirm that the remaining gas and liquid in the system are vented, and the venting target pressure has been reached, remove the hose, and the filling is completed.

[0033] During the filling process, the filling material is vaporized due to the long-term operation of the pump, so nitrogen is used to cool the pump. In addition, since EO gas has low pressure and low density, it is inconvenient to detect the pressure. Therefore, the gas phase channel and the liquid phase channel of the present application are both provided with nitrogen pipelines. The nitrogen booster pipeline of the gas phase channel is used for boosting, so that during the EO gas filling process, the pressure in the pipeline is increased, and the EO gas can be completely pressed into the gas cylinder 30, while the nitrogen supply pipeline of the liquid phase channel can back-sweep the residual gas in the liquid phase delivery pipeline, and the residual EO liquid gas in the pipeline is pushed into the gas cylinder 30 by the high pressure of nitrogen. The gas cylinder 30 is placed on the weighing device 31, and the target weight is observed. If it is reached, the filling is stopped.

[0034] It is understandable that, since EO liquid cannot directly contact oxygen during filling, it is necessary to ensure that the system is in an oxygen-free environment and protected by nitrogen. If oxygen is detected in the filling system, nitrogen is automatically blown into the system, pumped into the pipeline through the pump area, pressurized to 0.5Mpa, left to stand for 3 hours, and then vented to normal pressure through the program-controlled valve. In this way, the oxygen and nitrogen in the pipeline are replaced. When the oxygen and nitrogen in the system pipeline are replaced, the gas inside the cylinder is vented and the initial pressure inside the cylinder is detected. If the initial pressure is higher than -0.5Mpa, the cylinder is vacuumed to reduce the internal pressure of the cylinder to -0.5Mpa. After the treatment, the cylinder can be automatically filled, and the return air pipeline is opened until it is filled to the target weight. In order to avoid residual EO liquid when the system pipeline is subsequently disassembled, the residual liquid and residual gas pressure inside the pipeline are sent to the cylinder by refilling nitrogen.

Claims

1. A medical intelligent sterilization gas filling system, characterized in that: The invention comprises a control system and a filling pipeline, wherein the filling pipeline comprises a gas phase channel and a liquid phase channel, wherein the gas phase channel is used to adjust the gas pressure of the pipeline, discharge oxygen in the pipeline and recover excess filling gas, and control valves which are remotely controlled by the control system are installed on the gas phase channel and the liquid phase channel, and the gas phase channel is connected to a gas phase delivery pipeline, a gas phase filling hose (25), a gas return valve (26) and a first bottle valve (28) in sequence, and then connected to a gas cylinder (30), and a pressure monitoring device (23) which is communicatively connected to the control system is also installed on the gas phase channel and is used to monitor the pressure of the pipeline; the liquid phase channel is used to fill the sterilizing gas EO into the gas cylinder (30), and the liquid phase channel is connected to a liquid phase filling hose (24), a liquid inlet valve and a second bottle valve (29) in sequence, and then connected to the gas cylinder (30).

2. A medical intelligent sterilization gas filling system according to claim 1, characterized in that: The gas phase channel comprises a gas phase vacuum pipeline, a gas phase venting pipeline, a nitrogen boosting pipeline and a mixed gas large bottle filling-returning pipeline which are all connected to the gas phase conveying pipeline. A control valve which is remotely controlled by the control system is installed on each pipeline to control the connection between the pipeline and the gas phase conveying pipeline. The gas phase conveying pipeline is connected to the gas phase filling hose (25), the return valve (26) and the first bottle valve (28) in sequence and then connected to the gas cylinder (30). A pressure monitoring device (23) is installed on the nitrogen boosting pipeline.

3. A medical intelligent sterilization gas filling system according to claim 2, characterized in that: One end of the gas phase vacuum pumping pipeline is connected to the gas phase vacuum pumping device (1), and the other end is connected to the gas phase vacuum automatic control valve (9) and then communicated with the gas phase conveying pipeline. One end of the gas phase venting pipeline is connected to the gas phase venting device (2), and the other end is connected to the first check valve (11) and the gas phase venting automatic control valve (10) in sequence and then communicated with the gas phase conveying pipeline. One end of the mixed gas bottle filling-returning pipeline is connected to the return equipment (3), and the other end is connected to the second check valve (13) and the return gas automatic control valve (12) in sequence and then communicated with the gas phase conveying pipeline. An oxygen content analyzer connected to the control system is installed on the mixed gas bottle filling-returning pipeline. One end of the nitrogen boosting pipeline is connected to the gas phase N2 supply system (4), and the other end is connected to the gas phase nitrogen automatic control valve (14) and the third check valve (15) in sequence and then communicated with the gas phase conveying pipeline. The pressure monitoring device (23) is arranged on the pipeline at the output end of the third check valve (15).

4. A medical intelligent sterilization gas filling system according to claim 3, characterized in that: The liquid phase channel comprises a liquid phase vacuum pipeline, a liquid phase venting pipeline, a nitrogen gas supply pipeline and an EO filling pipeline which are all connected to the liquid phase delivery pipeline. A control valve which is remotely controlled by the control system is installed on each pipeline to control the connection between the pipeline and the liquid phase delivery pipeline. The liquid phase delivery pipeline is connected to the liquid phase filling hose (24), the liquid inlet valve and the second bottle valve (29) in sequence and then connected to the gas cylinder (30).

5. A medical intelligent sterilization gas filling system according to claim 4, characterized in that: One end of the nitrogen supply pipeline is connected to the liquid phase N2 supply system (5), and the other end is connected to the liquid phase nitrogen automatic control valve (16) and the fourth one-way valve (17) in sequence, and then connected to the liquid phase delivery pipeline; one end of the EO filling pipeline is connected to the EO filling equipment (6), and the other end is connected to the EO filling automatic control valve (18) and the fifth one-way valve (19) in sequence, and then connected to the liquid phase delivery pipeline; one end of the liquid phase vacuum pumping pipeline is connected to the liquid phase vacuum pumping equipment (7), and the other end is connected to the liquid phase vacuum automatic control valve (20) in sequence, and then connected to the liquid phase delivery pipeline; one end of the liquid phase venting pipeline is connected to the liquid phase venting equipment (8), and the other end is connected to the sixth one-way valve (21) and the liquid phase venting automatic control valve (22) in sequence, and then connected to the liquid phase delivery pipeline.

6. A medical intelligent sterilization gas filling method, characterized in that: The filling process includes the following steps: S1. Control all valves in the filling pipeline to remain closed through a control system, place the gas cylinder (30) in a work station, and perform safety verification on the gas cylinder (30); S2. After the safety verification is passed, the gas phase transmission pipeline is vented and vacuumed; S3, venting and vacuuming the liquid phase delivery pipeline; S4, control the gas phase nitrogen automatic control valve (14) to open, so that the gas phase N2 supply system (4) replaces the nitrogen with the filling device in the gas phase channel, and then vents and vacuumizes again; S5, controlling the liquid phase N2 supply system (5) to replace nitrogen with the filling device in the liquid phase channel and then venting it, and evacuating the inside of the gas cylinder; S6, control the EO filling automatic control valve (18) to open, and at the same time control the return air automatic control valve (12) to open, close the valves on other pipelines, and start automatically filling the gas cylinder until the target weight is reached; S7, control the EO filling automatic control valve (18) and the return air automatic control valve (12) to close, control the liquid nitrogen automatic control valve (16) and the gas nitrogen automatic control valve (14) to open, and send the residual liquid and residual gas in the pipeline to the gas cylinder (30) under pressure.

7. A medical intelligent sterilization gas filling method according to claim 6, characterized in that: The process of verifying the safety of the gas cylinder (30) in step S1 is as follows: After the gas cylinder (30) is placed at the workstation, the gas cylinder (30) number uploaded by scanning the RFID code is received; Querying the filling parameters of the gas cylinder (30) corresponding to the number of the gas cylinder (30), the filling parameters including the type of gas last filled into the gas cylinder (30) and the number of times the gas cylinder (30) was used; It is determined whether the type of gas filled last time is the same as the type of gas filled this time and whether the number of times the gas cylinder (30) has been used has reached a threshold; if they are the same and have not reached the filling threshold, the safety verification is passed and the filling parameters of the gas cylinder (30) are updated.

8. A medical intelligent sterilization gas filling method according to claim 6, characterized in that: The specific steps of step S2 include: S21, control the gas phase venting automatic control valve (10) to open, vent the gas phase transmission pipeline through the gas phase venting equipment (2), and close the gas phase venting automatic control valve (10) after venting to the venting target pressure; S32, control the gas phase vacuum automatic control valve (9) to open, and use the gas phase vacuum pumping equipment (1) to evacuate the gas phase conveying pipeline until the target vacuum target pressure is reached, and then close the gas phase vacuum automatic control valve (9).

9. A medical intelligent sterilization gas filling method according to claim 6, characterized in that: The specific process of step S3 is: S31, control the liquid phase venting automatic control valve (22) to open, vent the liquid phase delivery pipeline through the liquid phase venting device (8), and after venting to the venting target pressure, delay 10 seconds to close the liquid phase venting automatic control valve (22); S32, control the liquid phase vacuum automatic control valve (20) to open, and use the liquid phase vacuum pumping equipment (7) to evacuate the liquid phase delivery pipeline until the target vacuum target pressure is reached, and then close the liquid phase vacuum automatic control valve (20).

10. A medical intelligent sterilization gas filling method according to claim 6, characterized in that: The specific process of step S4 is: S41, controlling the gas phase nitrogen automatic control valve (14) to open, so that the gas phase N2 supply system (4) replaces nitrogen with the filling device in the gas phase channel, and controlling the gas phase nitrogen automatic control valve (14) to close after the replacement nitrogen filling reaches the target pressure; S42, control the gas phase venting automatic control valve (10) to open, vent the gas phase transmission pipeline through the gas phase venting equipment (2), and close the gas phase venting automatic control valve (10) after venting to the venting target pressure; S43, vacuuming the gas phase conveying pipeline, controlling the gas phase vacuum automatic control valve (9) to open, vacuuming the gas phase conveying pipeline through the gas phase vacuum pumping equipment (1), and closing the gas phase vacuum automatic control valve (9) after reaching the target vacuum target pressure.

Citation Information

Patent Citations

  • Device for flammable and explosive poisonous and harmful gas recovery process

    CN111594752A

  • Improved freeze concentration type ethylene oxide recycling system

    CN113509744A

  • Production device and method of ethylene oxide and carbon dioxide mixed sterilization gas

    CN115717685A

  • Purging device and purging method

    CN117859004A

  • A storage system for ethylene oxide

    CN207094187U