Method and device for online determining heat rate target during peak regulation of coal-fired unit

By determining the target value of the heat consumption rate online and optimizing and adjusting the heat consumption rate in coal-fired units is solved, the problem of rising heat consumption rate during low-load operation of coal-fired units is improved, energy efficiency and flexibility are improved, operating costs are reduced, and the power grid is ensured.

CN118970928APending Publication Date: 2024-11-15NORTH CHINA ELECTRICAL POWER RES INST +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411057331.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The heat consumption rate of coal-fired units increases when operating at low loads, affecting energy efficiency, and lacks flexibility and load response capabilities during peak shaving, resulting in an increase in coal consumption for power supply, affecting economics and grid stability.

Method used

By determining the target value of the heat consumption rate online, using real-time and historical operating data for cluster analysis, checking the measurement point and cylinder pressure efficiency, optimizing and adjusting to improve energy efficiency, the energy-saving potential of the excavator unit, and improving flexibility and load response capabilities.

Benefits of technology

The optimal target value determination of the heat consumption rate during low-load operation of coal-fired units is achieved, which reduces the heat consumption rate, improves the unit's energy efficiency and flexibility, reduces operating costs, and ensures the safety and stability of the power grid.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118970928A_ABST
    Figure CN118970928A_ABST
Patent Text Reader

Abstract

The invention provides a method and device for online determining a heat rate target during peak regulation of a coal-fired unit, and relates to the field of energy efficiency improvement, and the method comprises the steps: determining an optimal target value of a heat rate according to obtained real-time operation data and historical operation data; determining whether energy-saving potential exists or not according to the optimal target value of the heat consumption rate; and if yes, executing measuring point inspection and high, medium and low pressure cylinder efficiency inspection, and performing energy efficiency optimization adjustment based on an inspection result. According to the method, the optimal target value which the steam turbine heat rate should reach during low-load operation of deep peak regulation of the coal-fired unit can be rapidly determined on line, and the operation energy efficiency of the unit is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of energy efficiency improvement, and specifically to a method and device for online determining a heat rate target during peak load regulation of a coal-fired unit. Background Art

[0002] With the large-scale access of new energy power generation to the power grid, the healthy development of clean energy cannot be separated from the support of flexible regulation of coal-fired power. This has changed the role of coal-fired power generation units, from the original single power generation to the "ballast stone" of the power grid stability, and has also caused coal-fired units to operate under low load for a long time. Especially in recent years, in order to further improve the flexibility of thermal power operation and the ability to absorb new energy, the lower limit of unit output (minimum load rate) has been continuously refreshed. The operation of the unit deviates from the design value, the heat consumption increases, and the efficiency of the turbine subsystem decreases, resulting in a significant increase in coal consumption for power supply, affecting the economic efficiency of the unit operation.

[0003] At present, the power supply coal consumption value is usually used to measure the energy efficiency of the unit. When the coal-fired unit is running at low load, the power supply coal consumption increases significantly and the unit energy efficiency decreases. The heat rate of the steam turbine unit is one of the most important factors affecting the power supply coal consumption. On the one hand, the low load operation of the unit causes the heat rate of the steam turbine unit to increase, but "whether the increase is within a reasonable range", "whether the unit still has energy-saving potential", and "where is the key point of energy saving" are still issues that power generation companies need to study and solve in depth. On the other hand, during peak load regulation, how to improve the flexibility and rapid response load capacity of coal-fired units is another issue that power generation companies are most concerned about.

[0004] This section is intended to provide a background or context to the embodiments of the invention recited in the claims. No admission is made that the description herein is prior art by inclusion in this section. Summary of the invention

[0005] In response to the problems in the prior art, the present application provides a method and device for online determining the heat rate target and improving the energy efficiency during peak shaving of a coal-fired unit, which can realize online and rapid determination of the optimal target value that the steam turbine heat rate should reach when the coal-fired unit is operating at low load for deep peak shaving, thereby improving the unit's operating energy efficiency.

[0006] In order to solve the above technical problems, this application provides the following technical solutions:

[0007] In a first aspect, the present application provides a method for online determining a heat rate target during peak load regulation of a coal-fired unit, comprising:

[0008] Determine the optimal target value of heat rate based on the acquired real-time operation data and historical operation data;

[0009] determining whether there is energy saving potential according to the optimal target value of the heat rate;

[0010] If so, perform a measurement point check and a high, medium, and low pressure cylinder efficiency check, and make energy efficiency optimization adjustments based on the inspection results.

[0011] Furthermore, determining the optimal target value of heat rate according to the acquired real-time operation data and historical operation data includes:

[0012] Performing cluster analysis on the real-time operation data and historical operation data to determine normal operation data;

[0013] Calculate the heat rate of the steam turbine unit under the current load according to the normal operation data;

[0014] The optimal target value of the heat rate is determined according to the inherent value of the heat rate of the steam turbine unit under the current load and the heat rate of the steam turbine unit under the current load.

[0015] Furthermore, determining whether there is energy saving potential according to the optimal target value of the heat rate includes:

[0016] If the heat rate of the steam turbine unit under the current load is not greater than the optimal target value of the heat rate, it is determined that there is no energy saving potential;

[0017] If the heat rate of the steam turbine unit under the current load is greater than the optimal target value of the heat rate, it is determined to have energy-saving potential.

[0018] Furthermore, the execution of the measuring point inspection and the high, medium and low pressure cylinder efficiency inspection includes:

[0019] Determine whether the measuring point needs to be inspected and calibrated according to the measuring point value in the real-time operation data, the preset design value and the first threshold value;

[0020] If not, determine the design values ​​of high, medium and low pressure cylinder efficiencies under the peak load;

[0021] Whether the coal-fired unit components need to be overhauled is determined based on the actual efficiency value in the real-time operation data, the design values ​​of the high, medium and low pressure cylinder efficiencies under the peak load, and the second threshold.

[0022] In a second aspect, the present application provides a device for online determining a heat rate target during peak load regulation of a coal-fired unit, comprising:

[0023] An optimal target determination unit, used to determine an optimal target value of heat rate according to the acquired real-time operation data and historical operation data;

[0024] an energy-saving potential determination unit, used to determine whether there is energy-saving potential according to the optimal target value of the heat rate;

[0025] The energy efficiency optimization and adjustment unit is used to perform measurement point inspection and high, medium and low pressure cylinder efficiency inspection, and perform energy efficiency optimization and adjustment based on the inspection results.

[0026] Furthermore, the optimal target determination unit includes:

[0027] A normal data screening module, used to perform cluster analysis on the real-time operation data and historical operation data to determine normal operation data;

[0028] A unit heat rate calculation module, used to calculate the heat rate of the steam turbine unit under the current load according to the normal operation data;

[0029] The optimal target determination module is used to determine the optimal target value of the heat rate according to the inherent value of the heat rate of the steam turbine unit under the current load and the heat rate of the steam turbine unit under the current load.

[0030] Furthermore, the energy saving potential determination unit includes:

[0031] A first determination module is used to determine that there is no energy saving potential if the heat rate of the steam turbine unit under the current load is not greater than the optimal target value of the heat rate;

[0032] The second determination module is used to determine that the steam turbine unit has energy-saving potential if the heat rate of the steam turbine unit under the current load is greater than the optimal target value of the heat rate.

[0033] Furthermore, the energy efficiency optimization and adjustment unit includes:

[0034] A measuring point inspection module, used to determine whether the measuring point needs to be inspected and calibrated according to the measuring point value in the real-time operation data, the preset design value and the first threshold value;

[0035] The efficiency design determination module is used to determine the efficiency design values ​​of the high, medium and low pressure cylinders under the peak load if no;

[0036] The efficiency check module is used to determine whether the coal-fired unit components need to be repaired based on the actual efficiency value in the real-time operation data and the design values ​​of the high, medium and low pressure cylinder efficiencies under the peak load and the second threshold.

[0037] In a third aspect, the present application provides an electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the program, the method for online determining the heat rate target and improving energy efficiency during peak load regulation of the coal-fired unit is implemented.

[0038] In a fourth aspect, the present application provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of a method for online determining a heat rate target and improving energy efficiency during peak load regulation of the coal-fired unit.

[0039] In a fifth aspect, the present application provides a computer program product, including a computer program / instruction, which, when executed by a processor, implements the steps of a method for online determining a heat rate target and improving energy efficiency during peak load regulation of the coal-fired unit.

[0040] In response to the problems in the prior art, the method and device for online determining the heat rate target and improving energy efficiency during peak-shaving of coal-fired units provided in the present application can realize online rapid determination of the optimal target value that the steam turbine heat rate should reach when the coal-fired unit is operating at low load for deep peak-shaving, and then deeply analyze the reasons for the increase in heat rate and correspond the energy efficiency improvement to the specific work of energy-saving upgrading and optimization and transformation of the unit, further tap the energy-saving potential of the unit, and enhance the unit's ability to respond to grid load, which is of great significance for reducing operating costs, improving the economic efficiency of unit operation, and ensuring the safe and stable operation of the power grid. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0042] Figure 1 This is a flow chart of a method for online determining a heat rate target and improving energy efficiency during peak load regulation of a coal-fired unit in an embodiment of the present application;

[0043] Figure 2 A flow chart for determining an optimal target value of heat rate in an embodiment of the present application;

[0044] Figure 3 A flowchart for determining whether there is energy saving potential in an embodiment of the present application;

[0045] Figure 4 A flow chart showing the execution of the measurement point inspection and the high, medium and low pressure cylinder efficiency inspection in the embodiment of the present application;

[0046] Figure 5 This is a structural diagram of a device for online determining a heat rate target and improving energy efficiency during peak load regulation of a coal-fired unit in an embodiment of the present application;

[0047] Figure 6 This is a structural diagram of the optimal target determination unit in an embodiment of the present application;

[0048] Figure 7 This is a structural diagram of an energy-saving potential determination unit in an embodiment of the present application;

[0049] Figure 8 This is a structural diagram of the energy efficiency optimization and adjustment unit in the embodiment of the present application;

[0050] Fig. 9 It is a schematic diagram of the structure of an electronic device in an embodiment of the present application;

[0051] Fig.10 This is a schematic diagram of the overall process in the embodiment of the present application;

[0052] Fig.11 This is one of the load rate schematic diagrams in the embodiment of this application;

[0053] Fig.12 This is the second load rate schematic diagram in the embodiment of the present application;

[0054] Fig.13 This is the third load rate schematic diagram in the embodiment of the present application. DETAILED DESCRIPTION

[0055] To make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings. Here, the exemplary embodiments of the present invention and their descriptions are used to explain the present invention, but are not intended to limit the present invention.

[0056] The information collected in the technical solution of this application is information and data authorized by the user or fully authorized by all parties, and the collection, storage, use, processing, transmission, provision, disclosure and application of relevant data comply with the relevant laws, regulations and standards of relevant countries and regions, take necessary confidentiality measures, do not violate public order and good morals, and provide corresponding operation entrances for users to choose to authorize or refuse.

[0057] Provide users with corresponding operation entrances for them to choose to agree or reject the automated decision-making results; if the user chooses to reject, the expert decision-making process will be entered.

[0058] In one embodiment, see Figure 1 In order to quickly determine the optimal target value of the heat rate of the steam turbine that should be achieved when the coal-fired unit is in deep peak-shaving at low load, and improve the unit's operating energy efficiency, the present application provides a method for determining the heat rate target online during peak-shaving of a coal-fired unit, including:

[0059] S101: determining an optimal target value of heat rate according to the acquired real-time operation data and historical operation data;

[0060] S102: determining whether there is energy saving potential according to the optimal target value of the heat rate;

[0061] S103: If yes, perform a measurement point check and a high-, medium-, and low-pressure cylinder efficiency check, and perform energy efficiency optimization adjustment based on the inspection results.

[0062] It can be understood that the method provided in this application aims to solve the problems of "whether the increase in steam turbine heat rate is within a reasonable range", "whether the unit still has energy-saving potential" and "where are the key points of energy saving" during peak load regulation of coal-fired units, and analyze the reasons for the increase in steam turbine heat rate to correspond to the direction of energy-saving upgrades and optimization and transformation of the unit, further tap the energy-saving potential of the unit, improve the efficiency of unit operation, improve the flexibility of coal-fired units and the ability to quickly respond to loads, and ensure the safe and stable operation of the power grid.

[0063] The method provided in this application mainly comprises the following steps:

[0064] 1. Retrieve real-time operation data of units: retrieve real-time operation data of coal-fired power plant units;

[0065] 2. Retrieve historical operation data of the unit: retrieve historical data of the coal-fired power plant unit under the load for at least 1 hour;

[0066] 3. Abnormal data judgment: put the real-time running data in the historical data, and use the density-based cluster analysis method (BSCAN algorithm) to judge whether the real-time data is abnormal data; if the data is abnormal data, stop the calculation and display "Data abnormality alarm!"; if the data is normal, proceed to the next step;

[0067] 5. Determine the optimal target value of the heat rate of the steam turbine unit;

[0068] 6. Compare the optimal target value of the heat rate of the steam turbine unit with the current heat rate of the steam turbine unit, analyze the energy-saving potential and improve energy efficiency.

[0069] From the above description, it can be seen that the method for online determining the heat rate target and improving energy efficiency during peak-shaving of coal-fired units provided in this application can realize online rapid determination of the optimal target value that the steam turbine heat rate should reach when the coal-fired unit is operating at low load for deep peak-shaving, and then deeply analyze the reasons for the increase in heat rate and correspond the energy efficiency improvement to the specific work of energy-saving upgrading and optimization and transformation of the unit, further tapping the energy-saving potential of the unit and improving the unit's ability to respond to grid load, which is of great significance for reducing operating costs, improving the economic efficiency of unit operation, and ensuring the safe and stable operation of the power grid.

[0070] In one embodiment, see Figure 2 , the step of determining the optimal target value of heat rate according to the acquired real-time operation data and historical operation data includes:

[0071] S201: performing cluster analysis on the real-time operation data and the historical operation data to determine normal operation data;

[0072] S202: Calculating the heat rate of the steam turbine unit under the current load according to the normal operation data;

[0073] S203: Determine the optimal target value of the heat rate according to the inherent value of the heat rate of the steam turbine unit under the current load and the heat rate of the steam turbine unit under the current load.

[0074] It can be understood that the determination of the optimal target value of the heat rate of the steam turbine unit can be carried out according to the following steps:

[0075] The calculation formula is as follows:

[0076] q TB,x =q TB,pt +Δq TB (1)

[0077] in:

[0078] q TB,pt ——The inherent value of heat rate of the steam turbine unit under the current load. The method of obtaining it is: take the heat rate values ​​under at least three loads of the unit acceptance test before commissioning and input them into the system. Take the load r as the independent variable, and the inherent value of heat rate q TB,pt is the dependent variable, and the relationship between the two is q TB,pt =a+br+cr 2 , the system is based on q under three loads TB,pt The linear regression method can be used to obtain the regression coefficients a, b, and c, from which the formula for the change of the inherent value of the heat rate of the steam turbine unit with the load can be obtained, and the heat rate of the steam turbine unit under the current load can be calculated online:

[0079] Δq TB =Δq ACC +Δq cw +Δq SAH +Δq hs -Δq hp +Δq q (2)

[0080] in:

[0081] Δq ACC ——The impact of ambient temperature on the coal consumption of air-cooled steam turbine units (calculated according to the industry standard DL / T1929-2018, no further details). If the unit is a wet-cooled unit, this item is 0, kJ / kW·h;

[0082] Δq cw ——The impact of ambient temperature on the coal consumption of wet-cooled steam turbine units (calculated according to the industry standard DL / T1929-2018, no further details). If the unit is an air-cooled unit, this item is 0, kJ / kW·h;

[0083] Δq SAH——The impact of boiler air heater on the heat consumption of steam turbine generator set (calculated according to industry standard DL / T1929-2018, no further description). If the unit is equipped with air heater, this item is 0, kJ / kW·h;

[0084] Δq hs ——The impact of extraction steam on the heat consumption of the steam turbine generator set when it is used for factory heating (calculated according to the industry standard DL / T1929-2018, no further details), kJ / kW·h.

[0085] Δq hp ——The impact of external heat supply (steam) on the heat consumption of the steam turbine generator set (calculated according to the industry standard DL / T1929-2018, no further details), kJ / kW·h;

[0086] Δq q ——The impact of turbine aging on the heat consumption of the steam turbine generator set (calculated according to the ASME standard PTC6 of the Association of Mechanical Engineers, no further details), kJ / kW·h.

[0087] From the above description, it can be seen that the method provided in this application for online determining the heat rate target and improving energy efficiency during peak load regulation of coal-fired units can determine the optimal target value of the heat rate based on the acquired real-time operating data and historical operating data.

[0088] In one embodiment, see Figure 3 , the determining whether there is energy saving potential according to the optimal target value of the heat rate includes:

[0089] S301: If the heat rate of the steam turbine unit under the current load is not greater than the optimal target value of the heat rate, it is determined that there is no energy saving potential;

[0090] S302: If the heat rate of the steam turbine unit under the current load is greater than the optimal target value of the heat rate, it is determined to have energy-saving potential.

[0091] It is understandable that, based on the previous steps, it is necessary to compare the optimal target value of the heat rate of the steam turbine unit with the current heat rate of the steam turbine unit, analyze the energy-saving potential, and improve energy efficiency.

[0092] 1) If the current heat rate of the steam turbine unit is ≤ the optimal target value of the heat rate of the steam turbine unit, it is judged that there is no energy-saving potential and no further operation is required;

[0093] 2) If the current heat rate of the steam turbine unit is greater than the optimal target value of the heat rate of the steam turbine unit, it is judged that there is energy-saving potential and further operation is required.

[0094] From the above description, it can be seen that the method provided in this application for online determining the heat rate target and improving energy efficiency during peak load regulation of coal-fired units can determine whether there is energy-saving potential based on the optimal target value of the heat rate.

[0095] In one embodiment, see Figure 4 The execution of the measuring point inspection and the high, medium and low pressure cylinder efficiency inspection includes:

[0096] S401: Determine whether it is necessary to inspect and calibrate the measuring point according to the measuring point value in the real-time operation data, the preset design value and the first threshold value;

[0097] S402: If not, determine the design values ​​of high, medium and low pressure cylinder efficiencies under the peak load;

[0098] S403: Determine whether it is necessary to overhaul the coal-fired unit components according to the actual efficiency value in the real-time operation data, the design values ​​of the high, medium and low pressure cylinder efficiencies under the peak load, and the second threshold.

[0099] It can be understood that the measurement point inspection and the high, medium and low pressure cylinder efficiency inspection can be implemented according to the following steps.

[0100] a. Check the measuring points:

[0101] That is to check whether the measuring points are accurate. Specifically, compare the dial data (the actual measured value in the real-time operation data) with the design value. The measuring points include: feed water temperature measuring point, feed water flow measuring point, main steam temperature measuring point, main steam pressure measuring point, high-pressure heater inlet water temperature measuring point, high-pressure heater outlet water temperature measuring point, high-pressure heater drain temperature measuring point, high-pressure heater steam inlet pressure measuring point, cold section reheater steam pressure measuring point, cold section reheater steam temperature measuring point, reheater desuperheating water flow measuring point. See Fig.10 shown.

[0102] if Then proceed directly to the next step;

[0103] if It is judged that the measuring point is inaccurate and needs to be inspected and calibrated;

[0104] b. Compare the efficiency of high, medium and low pressure cylinders, and conduct maintenance and equipment optimization:

[0105] Take the design values ​​of high, medium and low pressure cylinder efficiency under at least three loads during the performance test, fit a curve according to the load, obtain the formula of the curve, and calculate the design values ​​of high, medium and low pressure cylinder efficiency under the peak load according to the formula;

[0106] If the actual efficiency value ≥ the design value, you can proceed directly to the next step;

[0107] If the actual efficiency value is less than the design value, the system interface will pop up an option module:

[0108] The pop-up message "Is there any leakage in the high, medium and low pressure cylinders of the steam turbine?" is displayed. If "Yes" is selected, the system will automatically pop up "Please check the high, medium and low pressure cylinders, partitions, blade tip radial clearances,

[0109] Make optimization adjustments to eliminate or reduce the leakage to the specified range of the inspection procedures". After completion, click "Finished" to proceed to the next selection interface; if you select "No", you will proceed to the next selection interface.

[0110] The question “Does the steam seal leakage exceed the requirements of the test procedure” will pop up. If you select “Yes”, the system will automatically pop up “Replace a new steam seal or optimize and adjust to eliminate or reduce the leakage to within the requirements of the test procedure”. After completion, click “Completed” to proceed to the next selection interface. If you select “No”, you will proceed to the next selection interface.

[0111] The system valve leakage exceeds the test procedure. If you select "Yes",

[0112] The system will automatically pop up "Replace a new valve or optimize and adjust to eliminate or reduce the leakage to the specified range of the inspection procedures". After completion, click "Completed" to proceed to the next selection interface; if you select "No", you will proceed to the next selection interface.

[0113] The question "Is there any salt or scale accumulation in the flow section?" will pop up. If you select "Yes," the system will automatically pop up "Cleaning to remove salt and scale accumulation." After completion, click "Finished" to proceed to the next selection interface. If you select "No," you will proceed to the next selection interface.

[0114] The question "Is the drain end difference of the heater higher than the design value?" pops up. If you select "Yes", the system will automatically pop up:

[0115] "Is the drain water level or the tube sheet at the drain inlet deformed?" If you select "Yes", the system will automatically pop up "Please repair". After completion, click "Completed" to proceed to the next selection interface; if you select "No", you will proceed to the next selection interface;

[0116] The system will automatically pop up the question "Is the drain pipe scaled?" if you select "Yes"

[0117] "Please clean up in time", click "Completed" after completion, and then proceed to the next selection interface;

[0118] If you select "No", proceed to the next selection interface;

[0119] A pop-up message "Is there any blockage in the water inlet pipe bundle of the heater?" If you select "Yes", the system will automatically pop up a message "Please clean it in time". After completion, click "Completed" to proceed to the next selection interface; if you select "No", a pop-up message "Please proceed to the next step" will appear.

[0120] c. Make operation optimization adjustments:

[0121] If the measurement points are accurate, there is no leakage in the high, medium and low pressure cylinders of the steam turbine or it does not exceed the provisions of the test regulations, the steam seal leakage does not exceed the provisions of the test regulations, the system valve leakage does not exceed the provisions of the test regulations, there is no salt accumulation in the flow part, and the drain end difference of the heater is not higher than the design value, then the operation optimization adjustment can be combined with the boiler combustion optimization:

[0122] Check the main steam temperature:

[0123] If the main steam temperature is ≥ the design value, the message “No optimization adjustment required” will pop up;

[0124] If the main steam temperature is less than the design value, a message will pop up saying “On the premise of ensuring that the heating surface does not overheat, increase the main steam temperature as much as possible to make it as close to the design value as possible”;

[0125] Check the main steam pressure:

[0126] Obtain the design value of main steam pressure: Take at least three design values ​​of main steam pressure under load and input them into the system. The system uses linear regression method to obtain the formula of main steam pressure changing with load. The design value of main steam pressure under the peak load can be obtained through the formula.

[0127] If the main steam pressure is ≥ the design value, the message “No optimization adjustment required” will pop up;

[0128] If the main steam pressure is lower than the design value, a message will pop up saying “On the premise of ensuring safe operation of the unit, increase the main steam pressure to make it as close to the design value as possible”;

[0129] Check the reheat steam temperature:

[0130] If the reheat steam temperature is ≥ the design value, the “No optimization adjustment required” pop-up message will appear;

[0131] If the reheat steam temperature is less than the design value, a message will pop up saying “On the premise of ensuring that the heating surface does not overheat, increase the reheat steam temperature as much as possible to make it as close to the design value as possible”;

[0132] Check the reheat steam pressure:

[0133] · Obtain the design value of reheat steam pressure: Take at least three design values ​​of reheat steam pressure under load and input them into the system. The system uses the linear regression method to obtain the formula of how reheat steam pressure changes with load, and obtains the design value of reheat steam pressure under the peak load according to the formula;

[0134] If the reheat steam pressure is ≥ the design value, the message “No optimization adjustment required” will pop up;

[0135] If the reheat steam pressure is less than the design value, a message will pop up saying “Reduce the reheat steam pressure to make it as close to the design value as possible while ensuring safe operation of the unit”;

[0136] From the above description, it can be seen that the method provided in this application for online determination of heat rate target and improvement of energy efficiency during peak load regulation of coal-fired units can perform measurement point inspection and high, medium and low pressure cylinder efficiency inspection.

[0137] The following is an explanation using an embodiment.

[0138] Taking a 1000MW supercritical wet-cooled coal-fired unit as an example, during peak load regulation, the unit load rate drops to 35%, at which time the unit heat rate is 8238.69 kJ / kW.h.

[0139] 1. Retrieve real-time data: retrieve real-time operation data of coal-fired power plant units;

[0140] 2. Retrieve historical data: retrieve the historical data of the coal-fired power plant units under the load within 1 hour;

[0141] 3. Abnormal data judgment: put the real-time operation data in the historical data, and use the density-based cluster analysis method (BSCAN algorithm) to determine whether the real-time data is abnormal data. If the data is normal, proceed to the next step;

[0142] 4. Determination of the optimal target value of the heat rate of the steam turbine unit:

[0143] 1) Determination of the inherent value of heat rate of the steam turbine unit under the current load: Check the acceptance test report before the unit is put into operation, and the heat rates at 100%, 75%, and 50% load are 7215.32 kJ / kW.h, 7300.25 kJ / kW.h, and 7678.6 kJ / kW.h, respectively. Fit the heat rate to a curve according to the load, and the formula of the curve is y=2347.36x 2 -4447.60x+9315.56. When the current peak load is 35%, the inherent value of the heat rate of the steam turbine unit is q TB,pt According to the formula, it is 8046.452 kJ / kW.h. Fig.11 shown.

[0144] According to formula (2) and industry standard DL / T1929-2018, we get:

[0145] Since the unit is a wet cooling unit, ΔqACC=0;

[0146] According to the calculation method of industry standard DL / T1929-2018, Δq cw =13.70kJ / kwh;

[0147] Because the unit is put into operation with a heater, Δq SAH =0;

[0148] According to the actual situation of the unit, no extraction steam is used for heating the plant, Δq hs =0;

[0149] According to the calculation method of industry standard DL / T1929-2018, Δq hp =36.23kJ / kwh;

[0150] According to the ASME standard PTC6, Δq q =5.23kJ / kwh.

[0151] According to formula (1), the optimal target value of the heat rate of the steam turbine unit under the current conditions is obtained:

[0152] q TB,x =8046.452+13.7+36.23+5.23=8101.612kJ / kwh

[0153] 5. Compare the optimal target value of the heat rate of the steam turbine unit with the current heat rate of the steam turbine unit, analyze the energy-saving potential and improve energy efficiency.

[0154] The current heat rate of the steam turbine unit is 8238.69 kJ / kW.h, which is 137.08 kJ / kW.h higher than the optimal target value of the heat rate of the steam turbine unit. This is the potential for energy saving. Further operations are as follows:

[0155] a. After checking the measuring points, it was found that the differences between the checked measuring points and the design values ​​were all less than 5%.

[0156] b. Compare the efficiency of high, medium and low pressure cylinders, and conduct maintenance and equipment optimization:

[0157] During the performance test, the efficiency of the high-pressure cylinder was 84.71% under 100% load, 82.01% under 75% load, and 79.32% under 50% load. The fitting curve is shown in Fig.12 shown.

[0158] The fitting principle of the intermediate pressure cylinder and the low pressure cylinder is the same as that of the high pressure cylinder, and will not be repeated. According to the formula, the efficiency of the intermediate pressure cylinder and the low pressure cylinder of the steam turbine under 35% load are both lower than the actual value, and there is no need to proceed to the next step.

[0159] According to the formula, the efficiency of the high-pressure cylinder of the steam turbine under 35% load is 77.71%, and the actual efficiency of the high-pressure cylinder is 75.4%. If the actual efficiency value is less than the obtained value, then:

[0160] ·Inspecting the turbine, it was found that the radial clearance of the blade tip was large and there was leakage. Through optimization and adjustment, the leakage was reduced to the specified range of the inspection regulations;

[0161] Check that the steam seal leakage does not exceed the requirements of the test procedures, and there is no need to replace the steam seal or optimize the adjustment;

[0162] The valve leakage does not exceed the requirements of the test procedures, so there is no need to replace the valve or optimize the adjustment;

[0163] Check if there is a small amount of salt and scale accumulation in the flow section, and remove the salt and scale accumulation by cleaning;

[0164] Check that the drain end difference of the heater is not higher than the design value.

[0165] c. Make operation optimization adjustments:

[0166] Check the main steam temperature:

[0167] The inspection revealed that the main steam temperature was 592°C, 8°C lower than the design value of 600°C. By optimizing the boiler combustion, the main steam temperature was raised to 599°C while ensuring that the heating surface did not overheat.

[0168] Check the main steam pressure:

[0169] Take at least three design values ​​of main steam pressure under load, fit a curve according to the load, and find the design value of main steam pressure under the peak load on the curve. Fig.13 shown.

[0170] According to the formula, the main steam pressure at 35% load is 9.04Mpa, and the current actual main steam pressure is 8.94Mpa. Under the premise of ensuring the safe operation of the unit, the main steam pressure is increased to make it as close to the design value as possible;

[0171] Check the reheat steam temperature:

[0172] If the reheat steam temperature is ≥ the design value, no further step is required;

[0173] Check the reheat steam pressure:

[0174] If the reheat steam pressure is ≥ the design value, no further step is required.

[0175] Through the above maintenance, adjustment and optimization, the heat rate of the steam turbine unit was reduced from 8238.69 kJ / kW.h to 8092.546 kJ / kW.h, which effectively reduced the heat rate and improved the energy efficiency of the unit.

[0176] Based on the same inventive concept, the embodiment of the present application also provides a device for online determining the heat rate target and improving the energy efficiency during the peak shaving of a coal-fired unit, which can be used to implement the method described in the above embodiment, as described in the following embodiment. Since the principle of solving the problem by the device for online determining the heat rate target and improving the energy efficiency during the peak shaving of a coal-fired unit is similar to the method for online determining the heat rate target and improving the energy efficiency during the peak shaving of a coal-fired unit, the implementation of the device for online determining the heat rate target and improving the energy efficiency during the peak shaving of a coal-fired unit can refer to the implementation of the method based on software performance benchmark determination, and the repetitions will not be repeated. As used below, the terms "unit" or "module" can be a combination of software and / or hardware that implements predetermined functions. Although the system described in the following embodiments is preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceived.

[0177] In one embodiment, see Figure 5 In order to realize online rapid determination of the optimal target value that the heat rate of the steam turbine should reach when the coal-fired unit is operating at low load for deep peak regulation, and to improve the unit's operating energy efficiency, the present application provides a device for online determination of the heat rate target and improvement of energy efficiency during peak regulation of a coal-fired unit, including: an optimal target determination unit 501, an energy-saving potential determination unit 502, and an energy efficiency optimization adjustment unit 503.

[0178] The optimal target determination unit 501 is used to determine the optimal target value of the heat rate according to the acquired real-time operation data and historical operation data;

[0179] An energy-saving potential determination unit 502 is used to determine whether there is energy-saving potential according to the optimal target value of the heat rate;

[0180] The energy efficiency optimization and adjustment unit 503 is used to perform a measurement point check and a high-, medium-, and low-pressure cylinder efficiency check, and perform energy efficiency optimization and adjustment based on the check results.

[0181] In one embodiment, see Figure 6 The optimal target determination unit 501 includes: a normal data screening module 601, a unit heat consumption calculation module 602 and an optimal target determination module 603.

[0182] A normal data screening module 601 is used to perform cluster analysis on the real-time operation data and the historical operation data to determine normal operation data;

[0183] The unit heat rate calculation module 602 is used to calculate the heat rate of the steam turbine unit under the current load according to the normal operation data;

[0184] The optimal target determination module 603 is used to determine the optimal target value of the heat rate according to the inherent value of the heat rate of the steam turbine unit under the current load and the heat rate of the steam turbine unit under the current load.

[0185] In one embodiment, see Figure 7 The energy saving potential determination unit 502 includes: a first determination module 701 and a second determination module 702.

[0186] The first determination module 701 is used to determine that there is no energy saving potential if the heat rate of the steam turbine unit under the current load is not greater than the optimal target value of the heat rate;

[0187] The second determination module 702 is used to determine that the steam turbine unit has energy-saving potential if the heat rate of the steam turbine unit under the current load is greater than the optimal target value of the heat rate.

[0188] In one embodiment, see Figure 8 The energy efficiency optimization and adjustment unit 503 includes: a measurement point inspection module 801, an efficiency design determination module 802 and an efficiency inspection module 803.

[0189] The measuring point checking module 801 is used to determine whether the measuring point needs to be inspected and calibrated according to the measuring point value in the real-time operation data, the preset design value and the first threshold value;

[0190] The efficiency design determination module 802 is used to determine the efficiency design values ​​of the high, medium and low pressure cylinders under the peak load if no;

[0191] The efficiency check module 803 is used to determine whether the coal-fired unit components need to be repaired based on the actual efficiency value in the real-time operation data and the design values ​​of the high, medium and low pressure cylinder efficiencies under the peak load and the second threshold.

[0192] From the hardware level, in order to realize online rapid determination of the optimal target value that the heat rate of the steam turbine should reach when the coal-fired unit is in deep peak-shaving low-load operation, and improve the unit's operating energy efficiency, the present application provides an embodiment of an electronic device for realizing all or part of the contents of the method for online determination of the heat rate target and improvement of energy efficiency during peak-shaving of the coal-fired unit, and the electronic device specifically includes the following contents:

[0193] Processor, memory, communication interface and bus; wherein the processor, memory and communication interface communicate with each other through the bus; the communication interface is used to realize the information transmission between the device for online determining the heat rate target and improving the energy efficiency during the peak load of the coal-fired unit and the core business system, user terminal and related database and other related equipment; the logic controller can be a desktop computer, a tablet computer and a mobile terminal, etc., and the present embodiment is not limited thereto. In the present embodiment, the logic controller can be implemented with reference to the embodiment of the method for online determining the heat rate target and improving the energy efficiency during the peak load of the coal-fired unit, and the embodiment of the device for online determining the heat rate target and improving the energy efficiency during the peak load of the coal-fired unit, and the contents thereof are incorporated herein, and the repeated parts are not repeated.

[0194] It is understandable that the user terminal may include a smart phone, a tablet electronic device, a network set-top box, a portable computer, a desktop computer, a personal digital assistant (PDA), a vehicle-mounted device, a smart wearable device, etc. Among them, the smart wearable device may include smart glasses, a smart watch, a smart bracelet, etc.

[0195] In practical applications, part of the method for online determination of the heat rate target and improvement of energy efficiency during peak load regulation of coal-fired units can be executed on the electronic device side as described above, or all operations can be completed in the client device. The selection can be made based on the processing capability of the client device and the limitations of the user's usage scenario. This application does not limit this. If all operations are completed in the client device, the client device may also include a processor.

[0196] The client device may have a communication module (i.e., a communication unit) that can communicate with a remote server to achieve data transmission with the server. The server may include a server on the task scheduling center side, and other implementation scenarios may also include a server on an intermediate platform, such as a server on a third-party server platform that has a communication link with the task scheduling center server. The server may include a single computer device, or a server cluster consisting of multiple servers, or a server structure of a distributed device.

[0197] Fig. 9 FIG. 9 is a schematic block diagram of the system structure of the electronic device 9600 according to an embodiment of the present application. Fig. 9 As shown, the electronic device 9600 may include a central processor 9100 and a memory 9140; the memory 9140 is coupled to the central processor 9100. It is worth noting that Fig. 9is exemplary; other types of structures may also be used to supplement or replace this structure to implement telecommunication functions or other functions.

[0198] In one embodiment, the method function of determining the heat rate target online and improving energy efficiency during peak load regulation of coal-fired units can be integrated into the central processor 9100. The central processor 9100 can be configured to perform the following control:

[0199] S101: determining an optimal target value of heat rate according to the acquired real-time operation data and historical operation data;

[0200] S102: determining whether there is energy saving potential according to the optimal target value of the heat rate;

[0201] S103: If yes, perform a measurement point check and a high-, medium-, and low-pressure cylinder efficiency check, and perform energy efficiency optimization adjustment based on the inspection results.

[0202] From the above description, it can be seen that the method for online determining the heat rate target and improving energy efficiency during peak-shaving of coal-fired units provided in this application can realize online rapid determination of the optimal target value that the steam turbine heat rate should reach when the coal-fired unit is operating at low load for deep peak-shaving, and then deeply analyze the reasons for the increase in heat rate and correspond the energy efficiency improvement to the specific work of energy-saving upgrading and optimization and transformation of the unit, further tapping the energy-saving potential of the unit and improving the unit's ability to respond to grid load, which is of great significance for reducing operating costs, improving the economic efficiency of unit operation, and ensuring the safe and stable operation of the power grid.

[0203] In another embodiment, the device for determining the heat rate target online and improving the energy efficiency when the coal-fired unit is peak-shaving can be configured separately from the central processor 9100. For example, the data composite transmission device for determining the heat rate target online and improving the energy efficiency when the coal-fired unit is peak-shaving can be configured as a chip connected to the central processor 9100, and the function of the method for determining the heat rate target online and improving the energy efficiency when the coal-fired unit is peak-shaving is realized through the control of the central processor.

[0204] like Fig. 9 As shown, the electronic device 9600 may also include: a communication module 9110, an input unit 9120, an audio processor 9130, a display 9160, and a power supply 9170. It is worth noting that the electronic device 9600 does not necessarily have to include Fig. 9 In addition, the electronic device 9600 may also include Fig. 9 For components not shown, reference may be made to the prior art.

[0205] like Fig. 9As shown, the central processing unit 9100 is sometimes also referred to as a controller or an operation control, and may include a microprocessor or other processor device and / or logic device. The central processing unit 9100 receives input and controls the operation of various components of the electronic device 9600.

[0206] The memory 9140 may be, for example, one or more of a cache, a flash memory, a hard drive, a removable medium, a volatile memory, a non-volatile memory or other suitable devices. The above-mentioned information related to the failure may be stored, and a program for executing the relevant information may also be stored. The CPU 9100 may execute the program stored in the memory 9140 to implement information storage or processing, etc.

[0207] The input unit 9120 provides input to the central processing unit 9100. The input unit 9120 is, for example, a key or a touch input device. The power supply 9170 is used to provide power to the electronic device 9600. The display 9160 is used to display display objects such as images and texts. The display may be, for example, an LCD display, but is not limited thereto.

[0208] The memory 9140 may be a solid-state memory, such as a read-only memory (ROM), a random access memory (RAM), a SIM card, etc. It may also be a memory that saves information even when the power is off, can be selectively erased, and is provided with more data, examples of which are sometimes referred to as EPROMs, etc. The memory 9140 may also be some other type of device. The memory 9140 includes a buffer memory 9141 (sometimes referred to as a buffer). The memory 9140 may include an application / function storage unit 9142, which is used to store application programs and function programs or processes for executing the operation of the electronic device 9600 through the central processor 9100.

[0209] The memory 9140 may also include a data storage unit 9143 for storing data, such as contacts, digital data, pictures, sounds, and / or any other data used by the electronic device. The driver storage unit 9144 of the memory 9140 may include various drivers for communication functions of the electronic device and / or for executing other functions of the electronic device (such as messaging applications, address book applications, etc.).

[0210] The communication module 9110 is a transmitter / receiver 9110 that sends and receives signals via an antenna 9111. The communication module (transmitter / receiver) 9110 is coupled to the central processor 9100 to provide input signals and receive output signals, which may be the same as the case of a conventional mobile communication terminal.

[0211] Based on different communication technologies, multiple communication modules 9110 may be provided in the same electronic device, such as a cellular network module, a Bluetooth module and / or a wireless LAN module. The communication module (transmitter / receiver) 9110 is also coupled to a speaker 9131 and a microphone 9132 via an audio processor 9130 to provide an audio output via the speaker 9131 and receive an audio input from the microphone 9132, thereby realizing a common telecommunication function. The audio processor 9130 may include any suitable buffer, decoder, amplifier, etc. In addition, the audio processor 9130 is also coupled to the central processor 9100, so that recording can be performed on the local machine through the microphone 9132, and the sound stored on the local machine can be played through the speaker 9131.

[0212] The embodiment of the present application also provides a computer-readable storage medium capable of implementing all the steps of the method for determining the heat rate target online and improving the energy efficiency when the coal-fired unit is peak-shaving and the execution subject is a server or a client in the above embodiment. The computer-readable storage medium stores a computer program. When the computer program is executed by a processor, all the steps of the method for determining the heat rate target online and improving the energy efficiency when the coal-fired unit is peak-shaving and the execution subject is a server or a client in the above embodiment are implemented. For example, when the processor executes the computer program, the following steps are implemented:

[0213] S101: determining an optimal target value of heat rate according to the acquired real-time operation data and historical operation data;

[0214] S102: determining whether there is energy saving potential according to the optimal target value of the heat rate;

[0215] S103: If yes, perform a measurement point check and a high-, medium-, and low-pressure cylinder efficiency check, and perform energy efficiency optimization adjustment based on the inspection results.

[0216] From the above description, it can be seen that the method for online determining the heat rate target and improving energy efficiency during peak-shaving of coal-fired units provided in this application can realize online rapid determination of the optimal target value that the steam turbine heat rate should reach when the coal-fired unit is operating at low load for deep peak-shaving, and then deeply analyze the reasons for the increase in heat rate and correspond the energy efficiency improvement to the specific work of energy-saving upgrading and optimization and transformation of the unit, further tapping the energy-saving potential of the unit and improving the unit's ability to respond to grid load, which is of great significance for reducing operating costs, improving the economic efficiency of unit operation, and ensuring the safe and stable operation of the power grid.

[0217] It will be appreciated by those skilled in the art that embodiments of the present invention may be provided as methods, devices, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0218] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (apparatus), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0219] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0220] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0221] The present invention uses specific embodiments to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea. At the same time, for those skilled in the art, according to the idea of ​​the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as a limitation on the present invention.

Claims

1. A method for determining a heat rate target online during peak load regulation of a coal-fired unit, characterized in that: include: Determine the optimal target value of heat rate based on the acquired real-time operation data and historical operation data; determining whether there is energy saving potential according to the optimal target value of the heat rate; If so, perform a measurement point check and a high, medium, and low pressure cylinder efficiency check, and make energy efficiency optimization adjustments based on the inspection results.

2. The method for determining the heat rate target online during peak load regulation of a coal-fired unit according to claim 1, characterized in that: Determining the optimal target value of heat rate according to the acquired real-time operation data and historical operation data includes: Performing cluster analysis on the real-time operation data and historical operation data to determine normal operation data; Calculate the heat rate of the steam turbine unit under the current load according to the normal operation data; The optimal target value of the heat rate is determined according to the inherent value of the heat rate of the steam turbine unit under the current load and the heat rate of the steam turbine unit under the current load.

3. The method for determining the heat rate target online during peak load regulation of a coal-fired unit according to claim 2, characterized in that: The determining whether there is energy saving potential according to the optimal target value of the heat rate includes: If the heat rate of the steam turbine unit under the current load is not greater than the optimal target value of the heat rate, it is determined that there is no energy saving potential; If the heat rate of the steam turbine unit under the current load is greater than the optimal target value of the heat rate, it is determined to have energy-saving potential.

4. The method for determining the heat rate target online during peak load regulation of a coal-fired unit according to claim 1, characterized in that: The execution of the measuring point inspection and the high, medium and low pressure cylinder efficiency inspection includes: Determine whether the measuring point needs to be inspected and calibrated according to the measuring point value in the real-time operation data, the preset design value and the first threshold value; If not, determine the design values ​​of high, medium and low pressure cylinder efficiencies under the peak load; Whether the coal-fired unit components need to be overhauled is determined based on the actual efficiency value in the real-time operation data, the design values ​​of the high, medium and low pressure cylinder efficiencies under the peak load, and the second threshold.

5. A device for determining the heat rate target online during peak load regulation of a coal-fired unit, characterized in that: include: An optimal target determination unit, used to determine an optimal target value of heat rate according to the acquired real-time operation data and historical operation data; an energy-saving potential determination unit, used to determine whether there is energy-saving potential according to the optimal target value of the heat rate; The energy efficiency optimization and adjustment unit is used to perform measurement point inspection and high, medium and low pressure cylinder efficiency inspection, and perform energy efficiency optimization and adjustment based on the inspection results.

6. The device for determining the heat rate target online during peak load regulation of a coal-fired unit according to claim 5, characterized in that: The optimal target determination unit comprises: A normal data screening module, used to perform cluster analysis on the real-time operation data and historical operation data to determine normal operation data; A unit heat rate calculation module, used to calculate the heat rate of the steam turbine unit under the current load according to the normal operation data; The optimal target determination module is used to determine the optimal target value of the heat rate according to the inherent value of the heat rate of the steam turbine unit under the current load and the heat rate of the steam turbine unit under the current load.

7. The device for determining the heat rate target online during peak load regulation of a coal-fired unit according to claim 6, characterized in that: The energy saving potential determination unit comprises: A first determination module is used to determine that there is no energy saving potential if the heat rate of the steam turbine unit under the current load is not greater than the optimal target value of the heat rate; The second determination module is used to determine that the steam turbine unit has energy-saving potential if the heat rate of the steam turbine unit under the current load is greater than the optimal target value of the heat rate.

8. The device for determining the heat rate target online during peak load regulation of a coal-fired unit according to claim 5, characterized in that: The energy efficiency optimization and adjustment unit comprises: A measuring point inspection module, used to determine whether the measuring point needs to be inspected and calibrated according to the measuring point value in the real-time operation data, the preset design value and the first threshold value; The efficiency design determination module is used to determine the efficiency design values ​​of the high, medium and low pressure cylinders under the peak load if no; The efficiency check module is used to determine whether the coal-fired unit components need to be repaired based on the actual efficiency value in the real-time operation data and the design values ​​of the high, medium and low pressure cylinder efficiencies under the peak load and the second threshold.

9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the steps of the method for online determining the heat rate target during peak load regulation of a coal-fired unit as described in any one of claims 1 to 4 are implemented.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method for online determining the heat rate target during peak load regulation of a coal-fired unit as described in any one of claims 1 to 4 are implemented.

11. A computer program product comprising a computer program / instructions, characterized in that When the computer program / instruction is executed by a processor, the steps of the method for online determining the heat rate target during peak load regulation of a coal-fired unit as described in any one of claims 1 to 4 are implemented.