Energy pile and construction method thereof

By designing the insulation section and heat exchange section in the energy pile, adding graphite and iron filings to the cement soil pile, combined with the introduction device, the structural stability problem caused by temperature changes in traditional energy piles is solved, and more efficient replacement is achieved Thermal and construction efficiency ensure the safety and stability of the building.

CN118979491APending Publication Date: 2024-11-19ZHONGYUAN ENGINEERING COLLEGE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411195715.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

During operation, temperature changes in traditional energy piles lead to additional temperature stress, pile body deformation, pile foundation settlement and bearing capacity reduction, affecting the stability of the superstructure.

Method used

An energy pile including an insulating section and a heat exchange section is designed. The heat exchange section is arranged below the heat insulation section, and a U-shaped heat exchange pipe and prefabricated pipe pile are built-in. Graphite and iron filings are added to the cement soil pile to improve the Thermal conductivity coefficient is used, and an introduction device is used to prevent the heat exchange pipe from falling off and rotating. During the construction process, the prefabricated pipe piles are first sunk into the heat exchange device and then into the heat exchange device to improve efficiency.

Benefits of technology

It effectively reduces the impact of pile body bearing characteristics, improves the safety and stability of the building, and improves the heat exchange efficiency of energy piles, making the construction process simple and efficient.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979491A_ABST
    Figure CN118979491A_ABST
Patent Text Reader

Abstract

The invention discloses an energy pile and a construction method thereof, and relates to the technical field of ground source heat pumps. A prefabricated pipe pile is arranged in the heat insulation section; the heat exchange section is arranged below the heat insulation section; u-shaped heat exchange pipes are arranged in the heat insulation section and the heat exchange section, and inlets and outlets of the U-shaped heat exchange pipes are located in the top of the heat insulation section. A first filler is arranged outside the prefabricated pipe pile; and a second filler is arranged in the heat exchange section. According to the energy pile and the construction method thereof, the heat exchange section is placed on the cement soil pile section on the lower portion of the root planting pile, due to the fact that the cement soil pile section has the small elastic modulus, under the same temperature variation, the additional temperature stress of a pile body during working can be effectively reduced, and then the influence on the bearing characteristic of the pile body is effectively reduced; therefore, safety and stability of the upper building are guaranteed. In the pile forming process of the heat exchange section cement soil pile, the heat conductivity coefficient is increased by adding materials into cement paste, and the heat exchange efficiency of the energy pile is improved; construction is convenient, and construction efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of ground source heat pumps, and in particular to an energy pile and a construction method thereof. Background Art

[0002] Shallow geothermal energy is renewable, clean, environmentally friendly and widely distributed. The use of shallow geothermal energy has been strongly supported in my country in recent years. Energy piles (also known as ground source heat pump piles or ground source energy piles) are a technology that combines ground source heat pump technology with building foundation piles, mainly used to provide heating and cooling for buildings. The temperature changes of traditional energy piles during operation will produce additional temperature stress, pile deformation, pile foundation settlement, and reduced bearing capacity, which will affect the stability of the upper structure. Summary of the invention

[0003] The purpose of the present invention is to provide an energy pile and a construction method thereof, so as to solve the problems existing in the above-mentioned prior art, reduce the impact on the bearing characteristics of the pile foundation, and thus ensure the safety of the building.

[0004] To achieve the above object, the present invention provides the following solutions:

[0005] The present invention provides an energy pile, comprising a heat insulation section and a heat exchange section; a prefabricated pipe pile is arranged in the heat insulation section; the heat exchange section is arranged below the heat insulation section; U-shaped heat exchange tubes are arranged in the heat insulation section and the heat exchange section, and the inlet and outlet of the U-shaped heat exchange tube are located at the top of the heat insulation section; a first filler is arranged outside the prefabricated pipe pile; and a second filler is arranged in the heat exchange section.

[0006] Optionally, a heat exchange tube fixing device is provided in the prefabricated pipe pile, and the heat exchange tube fixing device includes a center clamp, an intermediate clamp is provided on both sides of the center clamp, and an outer clamp is provided on the side of the intermediate clamp away from the center clamp; the center clamp, the intermediate clamp and the outer clamp are connected by a connecting rod; the interior of the center clamp is used to pass a rotating rod; steel bars are provided in the intermediate clamp; and a heat exchange tube is provided in the outer clamp.

[0007] Optionally, a heat exchange tube introduction device is provided at the bottom of the rotating rod, and the heat exchange tube introduction device includes an anti-falling structure, an anti-falling seat, an anti-falling hook and an elastic member arranged at the bottom of the inner wall of the rotating rod; the outer diameter of the anti-falling seat is the same as the outer diameter of the rotating rod, the anti-falling seat is arranged at the bottom of the rotating rod, the middle part of the anti-falling hook is rotatably connected to the bottom of the anti-falling seat through a rotating shaft, the hook body at the upper part of the anti-falling hook matches the anti-falling structure, and the elastic member is arranged between the lower part of the anti-falling hook; a limiting ring is provided at the bottom of the anti-falling seat, the limiting ring is used to install the heat exchange tube, and the heat exchange tube passes through the lower part of the anti-falling hook.

[0008] Optionally, an anti-rotation structure is provided between the anti-falling seat and the rotating rod.

[0009] Optionally, the anti-falling structure is a protrusion on the inner wall of the rotating rod, and the protrusion is connected to the hook body of the anti-falling hook.

[0010] Optionally, the first filler is cement soil.

[0011] Optionally, the second filler is mixed cement soil, and the mixed cement soil is cement soil added with graphite and / or iron filings.

[0012] The present invention also discloses a construction method based on the above energy pile, comprising the following steps:

[0013] The first step is to make cement soil piles;

[0014] After the cement soil pile driver is positioned, the hole is rotated according to the pile foundation layout position, and then cement slurry is injected from the pile end to the pile top. During the drilling process, the drilling speed and drill bit speed are controlled to ensure that the cement slurry and the in-situ soil are evenly mixed into cement soil; materials are added to the cement slurry used for the cement soil pile in the heat exchange section to increase the thermal conductivity and form mixed cement soil;

[0015] The second step is to plant the stakes;

[0016] The prefabricated pipe pile is hoisted to the top of the pile planting position, and after positioning, the prefabricated pipe pile is placed vertically into the cement soil pile, so that the prefabricated pipe pile sinks into the cement soil by its own weight;

[0017] The third step is to use an introduction device to introduce the heat exchange tube into the root pile;

[0018] (1) Use a cement soil pile driver to introduce the heat exchange tube, remove the drill bit of the pile driver, replace the drill rod with the heat exchange tube introduction device grouting pipe, or directly use the cement soil pile driver drill rod with a suitable diameter as the grouting pipe; (2) Combine the heat exchange tube and the introduction device head into one, and connect the introduction device grouting pipe and the introduction device head; (3) After positioning, place the U-shaped heat exchange tube into the prefabricated pipe pile that has been placed in place through the heat exchange tube introduction device, and while the heat exchange tube sinks with the introduction device, install the heat exchange tube fixing device and its vertical connecting steel bars in sequence, and finally sink the heat exchange tube into the cement soil through the introduction device;

[0019] The fourth step is to sink the heat exchange tube into the cement soil through the introduction device, and start grouting after reaching the predetermined elevation; then grouting is carried out while pulling out the tube until all the grouting tubes are pulled out and the construction of rooted energy piles is completed.

[0020] Compared with the prior art, the present invention has achieved the following technical effects:

[0021] The energy pile and its construction method of the present invention place the heat exchange section in the cement soil pile section at the bottom of the rooted pile (its elastic modulus is about 1 / 100 of the elastic modulus of concrete). Since the cement soil pile section has a smaller elastic modulus, under the same temperature change, it can effectively reduce the additional temperature stress of the pile body during operation, and then effectively reduce the impact on the bearing characteristics of the pile body, thereby ensuring the safety and stability of the upper building. During the pile formation process of the heat exchange section cement soil pile, the thermal conductivity of the heat exchange section cement soil pile is increased by adding materials such as graphite and iron filings to the cement slurry, thereby improving the heat exchange efficiency of the energy pile. The head of the introduction device has the characteristics of anti-rotation and anti-falling during the introduction of the heat exchange tube, and can automatically fall off when the grouting and pulling of the tube are completed after the introduction of the heat exchange tube, so the construction is convenient. During the construction process, it is more convenient to sink the prefabricated pipe pile and the heat exchange device into the cement soil pile. By first sinking the prefabricated pipe pile and then sinking the heat exchange device, the construction process of the two does not cross, which can improve the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 It is a schematic diagram of the structure of the energy pile in the present invention;

[0024] Figure 2 It is a structural schematic diagram of the heat exchange tube fixing device in the energy pile of the present invention;

[0025] Figure 3 It is a structural schematic diagram of the connection between the head device of the introduction device and the heat exchange tube in the energy pile of the present invention;

[0026] Figure 4 It is a schematic structural diagram of the head device of the energy pile introduction device in the present invention;

[0027] Figure 5 It is a structural schematic diagram of the head device of the introduction device in the energy pile of the present invention in a detached state;

[0028] Figure 6 It is a schematic diagram of the cement soil pile structure of the energy pile construction method of the present invention;

[0029] Figure 7 This is a schematic diagram of the structure of placing prefabricated pipe piles in the energy pile construction method of the present invention;

[0030] Figure 8 This is a schematic diagram of the structure of the U-shaped heat exchange tube introduced into the energy pile construction method of the present invention;

[0031] Fig. 9 It is a schematic diagram of the grouting and pipe pulling structure of the energy pile construction method in the present invention.

[0032] Description of reference numerals:

[0033] L1, insulation section; L2, heat exchange section;

[0034] 1. Cement soil; 2. Mixed cement soil; 3. Energy pile; 4. U-shaped heat exchange tube; 5. Heat exchange tube introduction device; 6. Heat exchange tube fixing device; 7. Prefabricated pipe pile; 8. Steel bar; 9. Grouting pipe; 10. Heat exchange tube; 11. Anti-falling structure; 12. Spring; 13. Turn rod; 14. Nut; 15. Rotating shaft; 16. Anti-rotation structure. DETAILED DESCRIPTION

[0035] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0036] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0037] Embodiment 1:

[0038] like Figures 1 to 5 As shown, this embodiment provides an energy pile, including an insulating section L1 and a heat exchange section L2; a prefabricated pipe pile 7 is arranged in the insulating section L1; the heat exchange section L2 is arranged below the insulating section L1; U-shaped heat exchange tubes 4 are arranged in the insulating section L1 and the heat exchange section L2, and a layer of insulation material is wrapped on the outside of the heat exchange tubes in the insulating section L1 to achieve a heat insulation effect; the inlet and outlet of the U-shaped heat exchange tube 4 are located at the top of the insulating section L1; a first filler is arranged on the outside of the prefabricated pipe pile 7; and a second filler is arranged in the heat exchange section L2.

[0039] In this specific embodiment, a heat exchange tube fixing device 6 is provided in the prefabricated pipe pile 7, and the heat exchange tube fixing device 6 includes a central clamp, and an intermediate clamp is provided on both sides of the central clamp, and an outer clamp is provided on the side of the intermediate clamp away from the central clamp; the central clamp, the intermediate clamp and the outer clamp are connected by a connecting rod; the interior of the central clamp is used to pass the rotating rod 13; the intermediate clamp is provided with a steel bar 8; and the outer clamp is provided with a heat exchange tube 10. The heat exchange tube 10 in the outer clamp is a vertical section on both sides of the U-shaped heat exchange tube 4. In a more specific embodiment, the central clamp, the intermediate clamp and the outer clamp are all circular parts with one side open, and the circular parts include two semicircular parts, one end of the two semicircular parts is rotatably connected by a rotating shaft 15, and the other end of the two semicircular parts is connected by a bolt and a nut 14, and the diameters of the central clamp, the intermediate clamp and the outer clamp are selected according to actual needs. One end of the connecting rod is fixedly connected to the outer wall of a semicircular part, and the other end of the connecting rod is connected to the semicircular part in the adjacent clamp by bolts, thereby connecting the heat exchange tube 10, the steel bar 8 and the heat exchange tube introduction device 5 together, and the steel bar 8 is used to withstand the vertical tensile force to prevent the heat exchange tube 10 from being damaged.

[0040] A heat exchange tube introduction device 5 is arranged at the bottom of the rotating rod 13, and the heat exchange tube introduction device 5 includes an anti-falling structure 11, an anti-falling seat, an anti-falling hook and an elastic member arranged at the bottom of the inner wall of the rotating rod 13; the outer diameter of the anti-falling seat is the same as the outer diameter of the rotating rod 13, the anti-falling seat is arranged at the bottom of the rotating rod 13, the middle part of the anti-falling hook is rotatably connected with the bottom of the anti-falling seat through the rotating shaft 15, the hook body at the upper part of the anti-falling hook matches the anti-falling structure 11, and the elastic member is arranged between the lower part of the anti-falling hook; a limiting ring is arranged at the bottom of the anti-falling seat, and the limiting ring is used to install the heat exchange tube 10, and the heat exchange tube 10 passes through the lower part of the anti-falling hook. More specifically, the elastic member is a coil spring 12, and the anti-drop structure 11 is a protrusion on the inner wall of the rotating rod 13, which is connected to the hook body of the anti-drop hook. Under the action of the spring 12, the bottom of the two anti-drop hooks remain closed, and the hook body of the anti-drop hook contacts the top of the protrusion, so that the heat exchange tube introduction device 5 is hung on the bottom of the rotating rod 13 to prevent it from dropping. The heat exchange tube 10 is sunk into the cement soil 1, and grouting begins after reaching a predetermined elevation. Due to the pressure generated by the grouting, the two anti-drop hooks will overcome the pulling force of the spring 12 and separate outward, and the heat exchange tube introduction device 5 will automatically drop and separate.

[0041] An anti-rotation structure 16 is provided between the anti-drop seat and the rotating rod 13. Specifically, the anti-rotation structure 16 includes a groove at the end of the bottom side wall of the rotating rod 13, and a limit convex block is provided on the top surface of the anti-drop seat, and the limit convex block extends into the groove, so as to achieve the technical effect of preventing the rotating rod 13 and the anti-drop seat from rotating relative to each other.

[0042] The first filler is cement soil 1. The second filler is mixed cement soil 2, and the mixed cement soil 2 is cement soil added with graphite and / or iron filings.

[0043] Embodiment 2:

[0044] like Figures 6 to 9 As shown, the present invention also discloses a construction method of the energy pile based on the first embodiment, comprising the following steps:

[0045] The first step is to form cement soil piles;

[0046] After the cement soil pile driver is positioned, the hole is rotated according to the pile foundation layout position, and then cement slurry is injected from the pile end to the pile top. During the drilling process, the drilling speed and drill bit speed are controlled to ensure that the cement slurry and the in-situ soil are evenly mixed into cement soil; materials are added to the cement slurry used for the cement soil 1 pile in the heat exchange section L2 to increase the thermal conductivity, forming mixed cement soil 2;

[0047] The second step is to plant the stakes;

[0048] The prefabricated pipe pile 7 is hoisted to the top of the pile planting position, and after positioning, the prefabricated pipe pile 7 is vertically placed into the cement soil pile 1, so that the prefabricated pipe pile 7 sinks into the cement soil 1 by its own weight;

[0049] The third step is to use an introduction device to introduce the heat exchange tube 10 into the root pile;

[0050] (1) Use a cement soil pile driver to introduce the heat exchange tube 10, remove the drill bit of the pile driver, replace the drill rod with the heat exchange tube introduction device 5 grouting pipe 9, or directly use the cement soil 1 pile driver drill rod with a suitable diameter as the grouting pipe 9; (2) Combine the heat exchange tube 10 and the introduction device head into one, and connect the introduction device grouting pipe 9 and the introduction device head; (3) After positioning, use the heat exchange tube introduction device 5 to place the U-shaped heat exchange tube 4 into the prefabricated pipe pile 7 that has been placed in place, and while the heat exchange tube 10 sinks with the introduction device, install the heat exchange tube fixing device 6 and its vertical connecting steel bars 8 in sequence, and finally sink the heat exchange tube 10 into the cement soil 1 through the introduction device;

[0051] The fourth step is to sink the heat exchange tube 10 into the cement soil 1 through the introduction device, and start grouting after reaching the predetermined elevation; then grouting is performed while pulling out the tube until all the grouting tubes 9 are pulled out and the construction of rooting the energy pile 3 is completed.

[0052] It should be noted that it is obvious to those skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention, and any figure mark in the claims should not be regarded as limiting the claims involved.

[0053] The present specification uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core idea of ​​the present invention. At the same time, for those skilled in the art, according to the idea of ​​the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.

Claims

1. An energy pile, characterized in that: It comprises a heat insulation section and a heat exchange section; a prefabricated pipe pile is arranged in the heat insulation section; the heat exchange section is arranged below the heat insulation section; U-shaped heat exchange tubes are arranged in the heat insulation section and the heat exchange section, and the inlet and outlet of the U-shaped heat exchange tube are located at the top of the heat insulation section; a first filler is arranged outside the prefabricated pipe pile; and a second filler is arranged in the heat exchange section.

2. The energy pile according to claim 1, characterized in that: A heat exchange tube fixing device is arranged in the prefabricated pipe pile, and the heat exchange tube fixing device includes a center clamp, and an intermediate clamp is arranged on both sides of the center clamp respectively, and an outer clamp is arranged on the side of the intermediate clamp away from the center clamp; the center clamp, the intermediate clamp and the outer clamp are connected by a connecting rod; the interior of the center clamp is used to pass a rotating rod; steel bars are arranged in the intermediate clamp; and a heat exchange tube is arranged in the outer clamp.

3. The energy pile according to claim 2, characterized in that: A heat exchange tube introduction device is provided at the bottom of the rotating rod, and the heat exchange tube introduction device includes an anti-falling structure, an anti-falling seat, an anti-falling hook and an elastic member arranged at the bottom of the inner wall of the rotating rod; the outer diameter of the anti-falling seat is the same as the outer diameter of the rotating rod, and the anti-falling seat is arranged at the bottom of the rotating rod, and the middle part of the anti-falling hook is rotatably connected to the bottom of the anti-falling seat through a rotating shaft, the hook body at the upper part of the anti-falling hook matches the anti-falling structure, and the elastic member is arranged between the lower part of the anti-falling hook; a limiting ring is provided at the bottom of the anti-falling seat, and the limiting ring is used to install the heat exchange tube, and the heat exchange tube passes through the lower part of the anti-falling hook.

4. The energy pile according to claim 2, characterized in that: An anti-rotation structure is arranged between the anti-falling seat and the rotating rod.

5. The energy pile according to claim 2, characterized in that: The anti-falling structure is a protrusion on the inner wall of the rotating rod, and the protrusion is connected to the hook body of the anti-falling hook.

6. The energy pile according to claim 1, characterized in that: The first filler is cement soil.

7. The energy pile according to claim 1, characterized in that: The second filler is mixed cement soil, and the mixed cement soil is cement soil added with graphite and / or iron filings.

8. The energy pile construction method according to any one of claims 1 to 7, characterized in that: The following steps are involved: The first step is to make cement soil piles; After the cement soil pile driver is positioned, the hole is rotated according to the pile foundation layout position, and then cement slurry is injected from the pile end to the pile top. During the drilling process, the drilling speed and drill bit speed are controlled to ensure that the cement slurry and the in-situ soil are evenly mixed into cement soil; materials are added to the cement slurry used for the cement soil pile in the heat exchange section to increase the thermal conductivity and form mixed cement soil; The second step is to plant the stakes; The prefabricated pipe pile is hoisted to the top of the pile planting position, and after positioning, the prefabricated pipe pile is placed vertically into the cement soil pile, so that the prefabricated pipe pile sinks into the cement soil by its own weight; The third step is to use an introduction device to introduce the heat exchange tube into the root pile; (1) Use a cement soil pile driver to introduce the heat exchange tube, remove the drill bit of the pile driver, replace the drill rod with the heat exchange tube introduction device grouting pipe, or directly use the cement soil pile driver drill rod with a suitable diameter as the grouting pipe; (2) Combine the heat exchange tube and the introduction device head into one, and connect the introduction device grouting pipe and the introduction device head; (3) After positioning, place the U-shaped heat exchange tube into the prefabricated pipe pile that has been placed in place through the heat exchange tube introduction device, and while the heat exchange tube sinks with the introduction device, install the heat exchange tube fixing device and its vertical connecting steel bars in sequence, and finally sink the heat exchange tube into the cement soil through the introduction device; The fourth step is to sink the heat exchange tube into the cement soil through the introduction device, and start grouting after reaching the predetermined elevation; then grouting is carried out while pulling out the tube until all the grouting tubes are pulled out and the construction of rooted energy piles is completed.