Hard rock stratum cantilever bailey beam steel trestle supporting structure and construction method thereof

Through the support structure and construction method of the hard rock layer cantilevered Bere beam steel trench, the cooperation between temporary support pier steel pipes and structural pier steel pipes is solved, and the construction quality and efficiency are improved , and the scope of adaptation to the construction environment has been expanded.

CN119021088APending Publication Date: 2024-11-26WUXI COMM CONSTR ENG GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411057341.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

During the construction of the steel trest, the hard rock layer causes the steel pipe piles to be unable to sink to the soil depth through simple mechanical vibration, affecting the construction efficiency and quality.

Method used

The support structure of the hard rock formation cantilevered Bere beam steel trench, including temporary pier steel pipes and structural pier steel pipes, is realized through the cooperation of the support frame and stabilizer parts, and concrete piles are poured in the riverbed to improve the Construction quality and efficiency.

Benefits of technology

It improves the construction quality and efficiency of steel trests, expands the scope of construction environment adaptation, and enhances the stability of the structure and the stability of construction equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021088A_ABST
    Figure CN119021088A_ABST
Patent Text Reader

Abstract

The invention discloses a hard rock stratum cantilever bailey beam steel trestle supporting structure which comprises two temporary buttress steel pipes and a structural pier steel pipe, the bottom ends of the temporary buttress steel pipes are vertically provided with a plurality of inserting steel bars, and a supporting frame is arranged between the top ends of the two temporary buttress steel pipes. The structural pier steel pipe is arranged on one side of the temporary buttress steel pipe in parallel, a supporting assembly is arranged in the temporary buttress steel pipe and comprises supporting rods, a plurality of connecting inclined holes are formed in the pipe section of the structural pier steel pipe, and one supporting rod is arranged in each connecting inclined hole in a sliding mode. The construction method comprises the steps of bailey beam installation, temporary buttress steel pipe installation, structural pier steel pipe installation and concrete pouring. The construction method has the effects that the construction quality and the construction efficiency of the steel trestle are improved, and the construction environment application range of the steel trestle is expanded.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of steel trestle construction, and in particular to a hard rock stratum cantilever Bailey beam steel trestle support structure and a construction method thereof. Background Art

[0002] A trestle is a bridge structure that facilitates locomotives and vehicles to travel across the bridge, and is usually composed of piers, abutments, and steel beams. Steel trestles are large-scale temporary buildings that are indispensable in the construction process, and the construction of steel trestles adopts the "fishing method." The "fishing method" is a specific construction process, which involves the use of the total station three-dimensional coordinate method to set out and locate each steel pipe pile by setting temporary control points on the temporary bridge, followed by sinking, cutting piles, clamping piles, and drilling platform construction. At present, the characteristics of the "fishing method" construction are its accuracy and efficiency. Through precise measurement and positioning, it ensures the accurate placement of steel pipe piles and steel casings, thereby ensuring the structural stability and safety of the steel trestle. In addition, this method is also applicable to various environments and conditions, including deep water and complex geological conditions, and can still effectively complete the construction of the steel trestle.

[0003] With regard to the above-mentioned related technologies, the inventor believes that during the construction of the above-mentioned steel trestle, the steel pipe piles of the trestle, as the supporting structure of the steel trestle, usually need to be vertically hoisted to the riverbed, and a vibrating hammer is used to vibrate the steel pipe piles of the trestle and sink them into the riverbed soil. However, when there is a hard rock layer in the riverbed, the steel pipe piles of the steel trestle cannot sink to the depth of the soil through simple mechanical vibration, which affects the construction efficiency and quality of the steel trestle. Summary of the invention

[0004] In order to improve the construction quality and construction efficiency of the steel trestle and expand the construction environment adaptability range of the steel trestle, the present application provides a hard rock stratum cantilever Bailey beam steel trestle support structure and a construction method thereof.

[0005] The hard rock cantilever Bailey beam steel trestle support structure and its construction method provided in this application adopt the following technical solutions: A hard rock cantilever Bailey beam steel trestle support structure comprises a temporary pier steel pipe and a structural pier steel pipe, wherein two temporary pier steel pipes are vertically arranged, a plurality of plug-in steel bars are vertically arranged at the bottom of the temporary pier steel pipe, a support frame is arranged between the top ends of the two temporary pier steel pipes, the structural pier steel pipe is arranged in parallel on one side of the temporary pier steel pipe, a support assembly is arranged in the temporary pier steel pipe, the support assembly comprises a support rod, a plurality of connecting inclined holes are opened on the pipe section of the structural pier steel pipe, and one support rod is slidably arranged in each of the connecting inclined holes.

[0006] By adopting the above technical solution, after completing the installation of the Bailey beam of one span, the next span is connected to the end of the Bailey beam of the previous span, two temporary pier steel pipes are vertically installed below the Bailey beam of the next span, and the support frame is connected to the top of the two temporary pier steel pipes. The support frame supports the Bailey beam of the next span. The structural pier steel pipe is sunk to a suitable depth in the riverbed, holes are drilled in it and stones are cleared out, concrete is poured into it, and after forming, the concrete pile is connected to the Bailey beam, and the temporary pier steel pipe is removed. Through the mutual cooperation of the temporary pier steel pipe and the structural pier steel pipe, the construction quality and construction efficiency of the steel trestle are improved, and the construction environment adaptability range of the steel trestle is expanded.

[0007] Optionally, the supporting assembly includes a lifting block, a mounting plate, a sliding rod and a sliding block, the lifting block is slidably set in the temporary pier steel pipe, the lifting block is a cylindrical block, and the sliding rod is arranged along its radial direction below the lifting block, one mounting plate is connected to each end of the sliding rod, the mounting plate is connected to the bottom surface of the lifting block, one sliding block is slidably set on each sliding rod, several sliding blocks are arranged in a one-to-one correspondence with several support rods, the sliding blocks are connected to the corresponding support rods, and the extension lines of several support rods are concentrated at a point on the central axis of the temporary pier steel pipe.

[0008] By adopting the above technical solution, after the temporary pier steel pipe is placed on the riverbed, the lifting block is pressed down, and a number of support rods extend from the connecting inclined holes and support the riverbed, thereby achieving stable support for the temporary pier steel pipe and improving the stability of the device.

[0009] Optionally, the bottom end of the temporary pier steel pipe is closed, a connecting threaded pipe is connected to the temporary pier steel pipe, a connecting plate is arranged below the temporary pier steel pipe, an inner ring wall of the connecting plate is provided with an internal thread, an outer ring wall of the connecting threaded pipe is provided with an external thread, the connecting threaded pipe is threadedly connected to the connecting plate, and the plug-in steel bar is connected to the bottom surface of the connecting plate.

[0010] By adopting the above technical solution, since the inserted steel bars are threadedly connected to the connecting threaded pipe through the connecting plate, when dismantling the temporary pier steel pipe, it is only necessary to screw the temporary pier steel pipe to separate the connecting threaded pipe from the connecting plate, thereby reducing the resistance encountered when dismantling the temporary pier steel pipe.

[0011] Optionally, a pressure column is placed inside the temporary pier steel pipe, and the bottom end of the pressure column abuts against the top end of the lifting block.

[0012] By adopting the above technical solution, when the pressure column is lowered into the temporary pier steel pipe, the lifting block moves downward under the squeezing of the pressure column, thereby realizing the driving of the lifting block.

[0013] Optionally, the compression column is formed by connecting a first connecting column and a second connecting column, the first connecting column is arranged above the second connecting column, and the density of the second connecting column is greater than the density of the first connecting column.

[0014] By adopting the above technical solution, since the density of the first connecting column is smaller than that of the second connecting column, the center of gravity of the temporary pier steel pipe is lowered, thereby increasing the stability of the structure.

[0015] Optionally, a mounting groove is provided at the top of the temporary pier steel pipe, the support frame includes a supporting horizontal plate and a supporting vertical plate connected to the bottom surface thereof, the supporting vertical plate is inserted in the mounting groove, a reinforcing rib is connected between the supporting vertical plate and the supporting horizontal plate, a stabilizing member is provided on the temporary pier steel pipe, the stabilizing member includes a top support ring plate, a sleeve cylinder and a reinforcing support plate, the top support ring plate is connected to the top of the sleeve cylinder, the reinforcing support plate is connected between the outer ring wall of the sleeve cylinder and the bottom surface of the top support ring plate, a limiting ring is connected to the outer ring wall of the temporary pier steel pipe, the sleeve cylinder is sleeved on the outside of the temporary pier steel pipe, the bottom end of the sleeve cylinder abuts against the top end of the limiting ring, the top support ring plate remains flush with the bottom end of the mounting groove, and the top support ring plate is connected to the bottom surface of the support frame.

[0016] By adopting the above technical solution, the stabilizer is sleeved on the temporary pier steel pipe, and the support vertical plate is inserted into the installation groove of the temporary pier steel pipe, and the top support ring plate is connected with the bottom surface of the support vertical plate. The setting of the stabilizer increases the stability between the temporary pier steel pipe and the support frame, and the setting of the installation groove facilitates the installation of the support frame.

[0017] Optionally, the support frame is provided with several groups of fixing components, the fixing components include a fixing plate, a connecting screw and an abutment plate, two fixing plates are arranged in parallel in each group of the fixing components, the fixing plate is vertically arranged on the top surface of the supporting cross plate, the setting direction of the fixing plate is perpendicular to the length direction of the supporting cross plate, the two ends of the fixing plate in the length direction extend out above the supporting cross plate, one connecting screw is vertically arranged on the bottom surface of the two ends of the fixing plate in the length direction, the connecting bolts on the bottom surfaces of the two fixing plates are arranged one by one, an abutment plate is connected between the two corresponding connecting bolts, and the abutment plate abuts against the bottom surface of the supporting cross plate.

[0018] By adopting the above technical solution, the fixed plate is adjusted to a suitable position on the supporting cross plate, the supporting cross plate is clamped between the fixed plate and the abutment plate, and the Bailey beam is clamped between the corresponding two fixed plates, thereby achieving the fixation of the Bailey beam and reducing the possibility of the Bailey beam being skewed and shaken during the construction process.

[0019] The construction method of the cantilevered Bailey beam steel trestle in hard rock strata includes the following steps: S1: Bailey beam installation: After the installation of one span of Bailey beam is completed, the main beam of the Bailey beam of the next span is installed by hoisting and cantilevering, and a temporary pier steel pipe is hoisted at the front end of the Bailey beam of the next span to connect it to the riverbed: S2: Bailey beam support: A support frame for supporting the Bailey beam is installed between the tops of the two temporary pier steel pipes. The support frame supports the Bailey beam of the next span: S3: Installation of structural pier steel pipe: Install the structural pier steel pipe below the end of the next span Bailey beam, and make its bottom end penetrate into the riverbed soil at a suitable depth, and place the impact drill in the structural pier steel pipe to impact and form a hole; S4: Concrete pouring: pour concrete into the steel pipe of the structural pier. After the concrete is formed, the top of the poured concrete pile is connected to the Bailey beam to support the Bailey beam. S5: Temporary structure removal: Remove the support frame and temporary pier steel pipes and reuse them when installing the support for the next span of Bailey beam.

[0020] In summary, the present application includes at least one of the following beneficial technical effects: 1. Through the coordination of temporary pier steel pipes and structural pier steel pipes, the construction quality and efficiency of the steel trestle are improved, and the scope of application of the steel trestle construction environment is expanded; 2. The setting of the stabilizing parts increases the stability between the temporary pier steel pipe and the support frame, and the setting of the installation groove facilitates the installation of the support frame; 3. The density of the first connecting column is smaller than that of the second connecting column, so that the center of gravity of the temporary pier steel pipe is biased downward, increasing the stability of the structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a structural schematic diagram of an embodiment of the present application for reflecting a cantilevered Bailey beam steel trestle support structure for hard rock formations and its construction method.

[0022] Figure 2 It is a partial cross-sectional view used to reflect the internal structure of the temporary pier steel pipe in the embodiment of the present application.

[0023] Figure 3 yes Figure 2 Enlarged view of part A in the middle.

[0024] Figure 4 yes Figure 2 Enlarged view of part B in the middle.

[0025] Explanation of the reference numerals: 01, Bailey beam; 1, temporary pier steel pipe; 101, connecting inclined hole; 102, installation groove; 2, structural pier steel pipe; 21, steel cage; 3, support assembly; 31, support rod; 32, lifting block; 321, lifting blind groove; 322, lifting rod; 33, installation plate; 34, sliding rod; 35, sliding block; 4, fixing assembly; 41, fixing plate; 42, connecting screw; 43, fastening bolt; 44, abutment plate; 5, stabilizer; 51, top support ring plate; 52, sleeve cylinder; 53, reinforced support plate; 6, support frame; 61, support horizontal plate; 62, support vertical plate; 63, reinforced rib plate; 7, connecting threaded pipe; 8, connecting plate; 9, plug-in steel bar; 10, limit ring; 11, pressure column; 111, first connecting column; 112, second connecting column; 12, guide slope. DETAILED DESCRIPTION

[0026] The following is combined with Figure 1-4 The present application is further described in detail. The present application provides a hard rock stratum cantilever Bailey beam steel trestle support structure and a construction method thereof, which has the effect of improving the construction quality and efficiency of the steel trestle and expanding the construction environment adaptability range of the steel trestle.

[0027] Reference Figure 1-3 The supporting structure of the cantilevered Bailey beam steel trestle in hard rock formation includes a temporary pier steel pipe 1, a structural pier steel pipe 2, a supporting assembly 3, a fixing assembly 4, a stabilizing member 5, a steel cage 21 and a supporting frame 6. Two temporary pier steel pipes 1 are vertically arranged, and the bottom end of the temporary pier steel pipe 1 is closed and the top end is open. The supporting frame 6 is arranged on the top ends of the two temporary pier steel pipes 1.

[0028] Reference Figure 1 and Figure 2 The bottom end of the temporary pier steel pipe 1 is provided with a connecting threaded pipe 7, and a connecting plate 8 is provided below the temporary pier steel pipe 1. The connecting plate 8 is a cylindrical shape with an open top, and an internal thread is provided on the inner ring wall of the connecting plate 8. The connecting plate 8 is threadedly connected with the connecting threaded pipe 7. A plurality of plug-in steel bars 9 are vertically provided on the bottom surface of the connecting plate 8, and the bottom end of the plug-in steel bars 9 is provided with a pointed tip.

[0029] Reference Figure 1 and Figure 2The support assembly 3 is arranged in the temporary pier steel pipe 1, and the support assembly 3 includes a support rod 31, a lifting block 32, a mounting plate 33, a sliding rod 34 and a sliding block 35. The lifting block 32 is cylindrical, and the lifting block 32 is slidably arranged in the temporary pier steel pipe 1. A lifting blind groove 321 is provided on the top surface of the lifting block 32, and a lifting rod 322 is fixedly connected to the inner ring wall of the lifting blind groove 321 along the diameter direction. A plurality of sliding rods 34 are arranged below the lifting block 32 along its radial direction, and the planes where the plurality of sliding rods 34 are located are parallel to the bottom surface of the lifting block 32. A mounting plate 33 is fixedly connected to each end of the sliding rod 34, and the mounting plate 33 is connected to the bottom surface of the lifting block 32. A sliding block 35 is slidably connected to each sliding rod 34 , and a bottom surface of each sliding block 35 is fixedly connected to an inclined support rod 31 , and the extension lines of the support rod 31 intersect at the same point on the central axis of the temporary pier steel pipe 1 .

[0030] Reference Figure 1 and Figure 2 A plurality of connecting oblique holes 101 are provided on the ring wall of the temporary pier steel pipe 1 near the bottom end. The plurality of connecting oblique holes 101 are arranged one by one with the plurality of supporting rods 31, and the supporting rods 31 are slidably arranged in the corresponding connecting oblique rods. A pressure column 11 is arranged in the temporary pier steel pipe 1, and the pressure column 111 includes a first connecting column 111 and a second connecting column 112, and the first connecting column 111 is connected to the top end of the second connecting column 112. The density of the second connecting column 112 is greater than that of the first connecting column 111, and the bottom end of the second connecting column 112 abuts against the hoisting block 32.

[0031] Reference Figure 1 and Figure 3 The support frame 6 includes a horizontal support plate 61 and a vertical support plate 62 vertically connected to the bottom of the support plate 61. A plurality of reinforcing ribs 63 are vertically fixedly connected between the bottom of the support plate 61 and the side wall of the support plate 62. A mounting groove 102 is provided at the top of the temporary pier steel pipe 1, and the vertical support plate 62 is clamped in the mounting groove 102.

[0032] Reference Figure 1 and Figure 3, the stabilizing member 5 is arranged on the temporary pier steel pipe 1, and the stabilizing member 5 includes a top support ring plate 51, a sleeve cylinder 52 and a reinforcing support plate 53. The top support ring plate 51 is fixedly connected to the top end of the sleeve cylinder 52, and the inner diameter of the sleeve cylinder 52 is the same as the outer diameter of the temporary pier steel pipe 1. Several reinforcing support plates 53 are fixedly connected along the circumferential direction between the bottom surface of the top support ring plate 51 and the outer ring wall of the sleeve cylinder 52. A limiting ring 10 is connected to the outer ring wall of the temporary pier steel pipe 1. When the sleeve cylinder 52 is sleeved on the temporary pier steel pipe 1, the bottom end of the sleeve cylinder 52 abuts against the limiting ring 10, and the top surface of the top support ring plate 51 is kept flush with the bottom end of the mounting groove 102. The top support ring plate 51 is connected to the support vertical plate 62 by bolts.

[0033] Reference Figure 1 and Figure 3 , a plurality of groups of fixing components 4 are arranged on the support frame 6, and the fixing components 4 include fixing plates 41, connecting screws 42, fastening bolts 43 and abutting plates 44. Each group of fixing components 4 includes two fixing plates 41 arranged in parallel, and the fixing plates 41 are vertically placed on the top surface of the supporting transverse plate 61 and are perpendicular to the length direction of the supporting transverse plate 61. The top ends of the two fixing plates 41 close to each other are provided with guide inclined surfaces 12. The length of the fixing plates 41 is greater than the width of the supporting transverse plate 61, and a connecting screw 42 is vertically fixedly connected to the bottom surface of both ends of the length direction of the fixing plates 41. The two connecting screws 42 on the two fixing plates 41 are arranged one by one, and the two corresponding connecting screws 42 pass through the corresponding abutting plates 44 and are threadedly connected with the fastening bolts 43, and the supporting transverse plate 61 is sandwiched between the fixing plates 41 and the abutting plates 44.

[0034] Reference Figure 1 and Figure 2 During the construction of the steel trestle, the installation and erection of the upper span Bailey beam 01 is completed first, and two temporary pier steel pipes 1 are suspended and hoisted using a crawler crane, and the plug-in steel bars 9 set at the bottom of the temporary pier steel pipe 1 are inserted into the riverbed soil. The pressure column 11 is hoisted into the temporary pier steel pipe 1, and the pressure column 11 presses the lifting block 32 downward. The support rod 31 slides in the connecting inclined hole 101 under the drive of the lifting block 32 and the guidance of the connecting inclined hole 101, and the sliding block 35 moves along the sliding rod 34 toward the inner ring wall close to the temporary pier steel pipe 1. The support rod 31 extends out of the temporary pier steel pipe 1 and supports it on the riverbed, realizing the support of the temporary pier steel pipe 1 and improving the stability of the temporary pier steel pipe 1. Since the density of the first connecting column 111 is greater than the density of the second connecting column 112, the center of gravity of the temporary pier steel pipe 1 is lowered, further improving the overall stability of the structure.

[0035] Reference Figure 3 and Figure 1, put the stabilizing member 5 on the temporary pier steel pipe 1, then insert the supporting vertical plate 62 of the supporting frame 6 into the installation groove 102 of the temporary pier steel pipe 1, and connect the top support ring plate 51 and the supporting vertical plate 62 together. The setting of the stabilizing member 5 improves the connection strength and stability between the supporting frame 6 and the temporary pier steel pipe 1. Adjust the position of the fixing component 4 on the supporting horizontal plate 61, tighten the fastening bolts 43, and the abutment plate 44 and the fixing plate 41 together clamp the supporting horizontal plate 61. The fixing plate 41 clamps the two sides of the Bailey beam 01, realizes the fixed limit of the Bailey beam 01, and reduces the possibility of the Bailey beams 01 parallel to each other being skewed or shaken.

[0036] Reference Figure 1-3 After completing the above operations, the crawler hoists the upper and lower spans of the Bailey beam 01, and hoists the structural pier steel pipe 2 to the bottom of the Bailey beam 01. Use mechanical vibration to sink the structural pier steel pipe 2 to a suitable depth. Since the contact area between the structural pier steel pipe 2 and the riverbed is small, the pressure is large during sinking, and it is relatively convenient to sink to a suitable depth. Use an impact drill to impact and form a hole in the structural pier steel pipe 2, and clear the material in the structural pier steel pipe 2. Lower the steel cage 21 into the structural pier steel pipe 2, and pour concrete into it. After the concrete is formed, remove the support frame 6, and connect the formed concrete pile to the bottom end of the Bailey beam 01 to support the Bailey beam 01. After removing the pressure column 11 from the temporary pier steel pipe 1, hoist the hoisting block 32 upward through the hoisting column, and the support rod 31 is retracted into the temporary pier steel pipe 1 through the connecting inclined hole 101. The temporary pier steel pipe 1 is screwed, the connecting threaded pipe 7 is separated from the threaded disc, and the plug-in steel bar 9 is left in the riverbed. The temporary pier steel pipe 1 is removed for easy use in the construction of the next span of Bailey beam 01.

[0037] The implementation principle of the hard rock layer cantilever Bailey beam steel trestle support structure and its construction method in the embodiment of the present application is as follows: when constructing the steel trestle, first complete the installation and erection of the upper span Bailey beam 01, and insert the two temporary pier steel pipes 1 into the riverbed soil. The pressure column 11 is hoisted into the temporary pier steel pipe 1, and the support rod 31 extends out of the temporary pier steel pipe 1 and supports it on the riverbed, thereby supporting the temporary pier steel pipe 1. The stabilizer 5 is sleeved on the temporary pier steel pipe 1, and then the support vertical plate 62 of the support frame 6 is inserted into the installation groove 102 of the temporary pier steel pipe 1. The position of the fixing component 4 on the supporting horizontal plate 61 is adjusted, and the fixing plate 41 clamps the two sides of the Bailey beam 01, thereby fixing and limiting the Bailey beam 01.

[0038] After completing the above operations, the structural pier steel pipe 2 is hoisted under the Bailey beam 01 and sunk to a suitable depth. An impact drill is used to impact a hole in the structural pier steel pipe 2, and the material in the structural pier steel pipe 2 is cleared out, and concrete is poured into it. After the concrete is formed, the support frame 6 is removed, and the formed concrete pile is connected to the bottom end of the Bailey beam 01.

[0039] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. Hard rock cantilever Bailey beam steel trestle support structure, characterized by: It comprises a temporary pier steel pipe (1) and a structural pier steel pipe (2), wherein two temporary pier steel pipes (1) are vertically arranged, a plurality of plug-in steel bars (9) are vertically arranged at the bottom of the temporary pier steel pipe (1), a support frame (6) is arranged between the top ends of the two temporary pier steel pipes (1), the structural pier steel pipe (2) is arranged parallel to one side of the temporary pier steel pipe (1), a support assembly (3) is arranged in the temporary pier steel pipe (1), and the support assembly (3) comprises a support rod (31), a plurality of connecting inclined holes (101) are opened on the pipe section of the structural pier steel pipe (2), and one support rod (31) is slidably arranged in each of the connecting inclined holes (101).

2. The hard rock stratum cantilever Bailey beam steel trestle support structure according to claim 1 is characterized by: The support assembly (3) comprises a lifting block (32), a mounting plate (33), a sliding rod (34) and a sliding block (35). The lifting block (32) is slidably arranged in the temporary pier steel pipe (1). The lifting block (32) is a cylindrical block. A plurality of sliding rods (34) are arranged below the lifting block (32) along the radial direction thereof. One mounting plate (33) is connected to each end of the sliding rod (34). The mounting plate (33) is connected to the bottom surface of the lifting block (32). One sliding block (35) is slidably arranged on each sliding rod (34). A plurality of sliding blocks (35) are arranged in one-to-one correspondence with a plurality of supporting rods (31). The sliding blocks (35) are connected to the corresponding supporting rods (31). The extension lines of the plurality of supporting rods (31) are concentrated at a point on the central axis of the temporary pier steel pipe (1).

3. The hard rock cantilever Bailey beam steel trestle support structure according to claim 2 is characterized by: The bottom end of the temporary pier steel pipe (1) is closed, a connecting threaded pipe (7) is connected to the temporary pier steel pipe (1), a connecting plate (8) is arranged below the temporary pier steel pipe (1), an inner ring wall of the connecting plate (8) is provided with an internal thread, an outer ring wall of the connecting threaded pipe (7) is provided with an external thread, the connecting threaded pipe (7) is threadedly connected to the connecting plate (8), and the plug-in steel bar (9) is connected to the bottom surface of the connecting plate (8).

4. The hard rock stratum cantilever Bailey beam steel trestle support structure according to claim 2 is characterized by: A pressure column (11) is placed inside the temporary pier steel pipe (1), and the bottom end of the pressure column (11) abuts against the top end of the lifting block (32).

5. The hard rock stratum cantilever Bailey beam steel trestle support structure according to claim 4 is characterized in that: The compression column (11) is formed by connecting a first connecting column (111) and a second connecting column (112); the first connecting column (111) is arranged above the second connecting column (112); and the density of the second connecting column (112) is greater than the density of the first connecting column (111).

6. The hard rock stratum cantilever Bailey beam steel trestle support structure according to claim 5 is characterized by: The top of the temporary pier steel pipe (1) is provided with a mounting groove (102); the support frame (6) comprises a supporting transverse plate (61) and a supporting vertical plate (62) connected to the bottom surface thereof; the supporting vertical plate (62) is inserted into the mounting groove (102); a reinforcing rib plate (63) is connected between the supporting vertical plate (62) and the supporting transverse plate (61); a stabilizing member (5) is provided on the temporary pier steel pipe (1); the stabilizing member (5) comprises a top supporting ring plate (51), a sleeve cylinder (52) and a reinforcing supporting plate (53); the top supporting ring plate (51) is connected to the The top end of the sleeve cylinder (52), the reinforcing support plate (53) is connected between the outer ring wall of the sleeve cylinder (52) and the bottom surface of the top support ring plate (51), the outer ring wall of the temporary pier steel pipe (1) is connected with a limiting ring (10), the sleeve cylinder (52) is sleeved on the outside of the temporary pier steel pipe (1), the bottom end of the sleeve cylinder (52) abuts against the top end of the limiting ring (10), the top support ring plate (51) is kept flush with the bottom end of the mounting groove (102), and the top support ring plate (51) is connected to the bottom surface of the support frame (6).

7. The hard rock stratum cantilever Bailey beam steel trestle support structure according to claim 6 is characterized by: The support frame (6) is provided with a plurality of groups of fixing components (4), the fixing components (4) comprising a fixing plate (41), a connecting screw (42) and an abutting plate (44), two fixing plates (41) are arranged in parallel in each group of the fixing components (4), the fixing plates (41) are vertically arranged on the top surface of the supporting transverse plate (61), the setting direction of the fixing plates (41) is perpendicular to the length direction of the supporting transverse plate (61), the two ends of the fixing plates (41) in the length direction extend above the supporting transverse plate (61), one connecting screw (42) is vertically arranged on the bottom surface of the two ends of the fixing plates (41) in the length direction, the connecting bolts on the bottom surfaces of the two fixing plates (41) are arranged one by one, an abutting plate (44) is connected between the two corresponding connecting bolts, and the abutting plate (44) abuts against the bottom surface of the supporting transverse plate (61).

8. The construction method of the cantilever Bailey beam steel trestle in hard rock according to any one of claims 1 to 7, characterized in that: The following steps are involved: S1: Installation of Bailey beam (01): After the installation of one span of Bailey beam (01) is completed, the main beam of the Bailey beam (01) of the next span is installed by hoisting and cantilevering, and a temporary pier steel pipe (1) is hoisted at the front end of the Bailey beam (01) of the next span to connect it with the riverbed: S2: Bailey beam (01) support: A support frame (6) for supporting the Bailey beam (01) is installed between the top ends of the two temporary pier steel pipes (1). The support frame (6) supports the Bailey beam (01) of the next span: S3: Installation of the structural pier steel pipe (2): The structural pier steel pipe (2) is installed below the end of the next span Bailey beam (01), and its bottom end is inserted into the riverbed soil at a suitable depth, and an impact drill is placed in the structural pier steel pipe (2) to impact and form a hole; S4: Concrete pouring: pouring concrete into the structural pier steel pipe (2). After the concrete is formed, the top of the poured concrete pile is connected to the Bailey beam (01) to achieve support for the Bailey beam (01); S5: Temporary structure removal: The support frame (6) and the temporary pier steel pipe (1) are removed and reused when installing and supporting the next span of Bailey beam (01).