Night concrete floor elevation control method

Through measures such as positioning and line laying, axis projection measurement, elevation measurement and verticality observation, the problems of axis displacement and elevation in the control of concrete floor slabs have been solved, and higher construction quality and progress have been achieved.

CN119041690AInactive Publication Date: 2024-11-29ZHEJIANG TONGAN CONSTRUCT CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411098982.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-12
Publication Date
2024-11-29
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During construction, the elevation control of concrete floor slabs at night has problems such as axis displacement, inaccurate elevation, and verticality deviation, which affects the construction quality and progress.

Method used

Adopt positioning, axis projection control, elevation measurement, verticality observation and engineering measurement control measures, including the use of laser reference points, leveling instruments, theodolites and steel rulers to ensure the axis and verticality through precise calibration and verification. and the accuracy of the elevation, implement the model-first construction method.

Benefits of technology

The accuracy and construction quality of concrete floor elevation measurement are improved, the qualification of each process is ensured, rework is reduced and construction efficiency is improved.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention discloses a night concrete floor elevation control method which comprises the following steps: S1, positioning and paying off; s2, an axis projection measurement control method; s3, height measurement; s4, observing the perpendicularity; s5, settlement observation; and S6, performing engineering measurement control measures. The engineering is carried out in advance through a template, the engineering must be actually measured during construction, and the engineering cannot enter the next process for construction if the engineering is not inspected to be qualified in the previous process. The project is ensured to be qualified, and the construction quality is ensured. And the surveying personnel accurately measures the paying-off positioning of the project, and draws a construction paying-off diagram and paying-off records. Measurement personnel should take various measures in operation, measurement precision is guaranteed, standardization, normalization and programming are achieved, and engineering services are better provided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a method for controlling the elevation of a concrete floor at night. Background Art

[0002] This project is a factory project with a large area and a long length. The "three-line" operation is difficult, and the axis displacement, inaccurate elevation, verticality deviation and other phenomena often occur. Therefore, the "three-line" construction quality control is an important factor affecting the progress of this project. How to make the elevation measurement more accurate. To solve this problem, we consider a method for controlling the elevation of concrete floor at night. Summary of the invention

[0003] The purpose of the present invention is to provide a method for controlling the elevation of a concrete floor at night to solve the problems raised in the above-mentioned background technology.

[0004] To achieve the above object, the present invention provides the following technical solution: a method for controlling the elevation of a concrete floor at night, comprising the following steps:

[0005] S1, positioning and laying out;

[0006] S2, axis projection control method;

[0007] S3, elevation measurement;

[0008] S4, verticality observation;

[0009] S5. Settlement observation;

[0010] S6. Engineering measurement control measures.

[0011] The specific steps of step S1 are:

[0012] S11. Basis for positioning and laying out:

[0013] Determine the plane control scheme and survey accuracy according to the general plan of the architectural design, and conduct survey of the on-site axis control network and elevation control points using the building red line piles, national elevation standard piles and on-site points designated by the planning department;

[0014] S12. Survey and design of plane control network:

[0015] S121. The plane control network should be considered from the overall perspective first, following the principle of overall first, then local, and high precision controlling low precision;

[0016] S122. Only by controlling the first-level grid can the construction requirements be met;

[0017] S123. According to the characteristics of the building's plane shape, the main control axis is determined using the given on-site points. When positioning and laying out the lines, the control axis network is accurately measured, and the stakes are set in a place that is easy to observe and not easily damaged to be fixed and protected;

[0018] S124. After determining the main axis control network, the other main axes of the building are encrypted using the rectangular coordinate positioning and layout method based on the basic plan. After the angle and distance are calibrated to meet the point position limit requirements, the building plane rectangular control network is laid out.

[0019] Preferably, the specific steps of step S2 are:

[0020] Calibration of S21 axis control piles:

[0021] During the foundation construction process, according to the calibration of the primary plane control network in the field, the axis control piles are re-measured every half month to prevent pile position displacement;

[0022] S22, axis projection method:

[0023] The axis projection adopts the internal control method, and the foundation construction below ±0.000 adopts the theodolite direction line intersection method to transfer the axis, and the error of the survey point should not exceed ±3mm, and the error between the axes should not exceed ±2m;

[0024] S23. After the foundation construction is completed, the laser base point is placed on the concrete slab surface, and the anchor hook is welded with a 200×200×10mm steel plate and set to the predetermined position. The axis of each level is projected and measured with a theodolite to determine the laser reference point as shown in the figure; a small circle center is chiseled on the steel plate as the laser control point; during construction control, the plumb line is placed on these laser reference points for centering and leveling; a receiving target is placed on the laser hole reserved on the slab surface, and then the laser is ignited and the light spot is displayed on the receiving target;

[0025] S24. Before vertical projection measurement, the reference point control network should be calibrated, and the calibration accuracy should not be lower than the accuracy of the building plane rectangular control network to ensure the vertical transmission accuracy of the axis;

[0026] S25. The verticality is controlled by the plane control axis. The axis is marked with a "red triangle" on the outer edge of the building. After the templates of each layer are calibrated, the theodolite is used to measure upward from ±0.000 to ensure that the verticality deviation of each layer is no more than 3mm, thereby checking the accuracy of the axis and ensuring that the verticality deviation is no more than 15mm within the total height range of the entire project. Professional measurement units should be asked to review the verticality at any time to ensure accuracy;

[0027] S26. When laying out the construction layer, the projection axis should be checked on the structural layer plane first, and then the detailed axis should be measured after closure.

[0028] Preferably, the specific steps of step S3 are:

[0029] S31. Survey and design of elevation control network:

[0030] S311. Based on the site leveling base points provided by the surveying and mapping management department, use a level to re-survey and check the provided leveling base points. After the calibration is qualified, a closed or leveling route is measured and set up, and the site plane control points are measured together, which is the primary condition for ensuring the vertical accuracy control of the construction;

[0031] S312. Based on the leveling base points provided by the surveying and mapping management department, bury semi-permanent elevation points, and then conduct joint survey to measure the elevation of the semi-permanent points in the field area;

[0032] S313. There should be at least three leveling points in the site, with a spacing of less than 1 km, a distance of more than 25 meters from buildings, and a distance of no less than 15 meters from the backfill edge;

[0033] S314. Level of elevation control network and observation technology requirements: The level of elevation control network is planned to be set at level three;

[0034] S32, Elevation Construction Measurement:

[0035] S321. When measuring the elevation inside the foundation pit, first measure the elevation control points to determine whether the level points in the field have been moved. Only after the joint measurement confirms that they are correct can the required elevation be measured inside the foundation pit.

[0036] S322. The elevation of the foundation is measured and set using a level, a tower ruler, and a long steel ruler. The elevation of the foundation is measured and set using the steel ruler transfer method.

[0037] S323. For vertical transfer of elevation, use a steel ruler to measure vertically from the starting elevation point of the first floor. When the transfer height exceeds the length of the steel ruler, another elevation starting line should be set. The steel ruler needs to be corrected by tension, ruler length, and temperature differences.

[0038] S324. Before leveling the construction layer, the three elevation points transferred from the first floor should be calibrated first. When the difference is less than 3mm, the horizontal line should be measured based on its average point. When leveling, the level should be placed in the center of the measuring point range as much as possible, and a precise leveling should be carried out. The allowable error of the horizontal line elevation is 3mm.

[0039] Preferably, the specific steps of step S4 are: vertical observation work, including observation of verticality deviation of each floor and observation of verticality deviation of total height. When the building is raised layer by layer, the vertical deviation of the building is caused by the force of the foundation or the verticality control deviation, so it is necessary to set a point to observe the verticality. This work is carried out together with the axis measurement point for observation and inspection. Once the axis deviation is found to be greater than 3mm and intersects with the sight line, it should be considered to be caused by deviation. When observing, the accurate bottom axis is used as the reference line, and the maximum deviation value is observed, and records are made for analysis of the situation. If any abnormality is found, it should be reported to the supervision company in time, and corresponding measures should be taken.

[0040] Preferably, the specific steps of step S5 are: marking the monitoring points according to the designed monitoring points, observing once for each additional layer of load, and keeping records.

[0041] Preferably, the specific steps of step S6 are:

[0042] S61. Control of verticality of building corners: After the axis projection inspection of each floor above ±0.000 meets the accuracy requirements, use the theodolite direction line method to project the building corners and the main axis to the facade of the wall or column and mark them with ink lines. The allowable axis deviation for each floor shall not exceed 2mm, and ensure that at least 3 axes are projected on each facade.

[0043] S62. Construction error control.

[0044] Preferably, the specific steps of step S62 are:

[0045] S621. Measurements must be made using qualified theodolites, levels, steel rulers, etc. The instruments should be strictly inspected according to regulations to prevent measurement errors caused by instrument errors themselves;

[0046] S622. Each time you take a measurement, the instrument should be placed firmly to ensure the accuracy of the instrument's operation and leveling. When taking a measurement, the measurement method of positive and negative mirrors should be used.

[0047] S623. The survey time should be selected on a windless, cloudy day, avoiding scorching sun and rainy days, to reduce the impact of natural conditions on survey accuracy;

[0048] S624. The surveying work shall be performed by fixed full-time surveyors from beginning to end. The important axis positioning and measurement shall be checked and reviewed by the project technical leader together with the professional foreman. The axis, verticality, elevation, etc. shall be checked before and after each concrete pouring. Any errors shall be corrected in time.

[0049] Compared with the prior art, the beneficial effects of the present invention are: this project implements the model first, and the project must be measured and measured during construction. The next process cannot be started without passing the previous process inspection. This project will ensure qualification and construction quality. The surveyor accurately measures the layout and positioning of this project, and draws the construction layout diagram and layout record. The surveyor should take various measures in the operation to ensure the measurement accuracy, standardize, normalize and proceduralize, and better serve the project. DETAILED DESCRIPTION

[0050] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0051] The present invention provides a technical solution: a method for controlling the elevation of a concrete floor at night, comprising the following steps:

[0052] S1, positioning and laying out;

[0053] S2, axis projection control method;

[0054] S3, elevation measurement;

[0055] S4, verticality observation;

[0056] S5. Settlement observation;

[0057] S6. Engineering measurement control measures.

[0058] Specifically, the specific steps of step S1 are:

[0059] S11. Basis for positioning and laying out:

[0060] Determine the plane control scheme and survey accuracy according to the general plan of the architectural design, and conduct survey of the on-site axis control network and elevation control points using the building red line piles, national elevation standard piles and on-site points designated by the planning department;

[0061] S12. Survey and design of plane control network:

[0062] S121. The plane control network should be considered from the overall perspective first, following the principle of overall first, then local, and high precision controlling low precision;

[0063] S122. Only by controlling the first-level grid can the construction requirements be met;

[0064] S123. According to the characteristics of the building's plane shape, the main control axis is determined using the given on-site points. When positioning and laying out the lines, the control axis network is accurately measured, and the stakes are set in a place that is easy to observe and not easily damaged to be fixed and protected;

[0065] S124. After determining the main axis control network, the other main axes of the building are encrypted using the rectangular coordinate positioning and layout method based on the basic plan. After the angle and distance are calibrated to meet the point position limit requirements, the building plane rectangular control network is laid out.

[0066] Specifically, the specific steps of step S2 are:

[0067] Calibration of S21 axis control piles:

[0068] During the foundation construction process, according to the calibration of the primary plane control network in the field, the axis control piles are re-measured every half month to prevent pile position displacement;

[0069] S22, axis projection method:

[0070] The axis projection adopts the internal control method, and the foundation construction below ±0.000 adopts the theodolite direction line intersection method to transfer the axis, and the error of the survey point should not exceed ±3mm, and the error between the axes should not exceed ±2m;

[0071] S23. After the foundation construction is completed, the laser base point is placed on the concrete slab surface, and the anchor hook is welded with a 200×200×10mm steel plate and set to the predetermined position. The axis of each level is projected and measured with a theodolite to determine the laser reference point as shown in the figure; a small circle center is chiseled on the steel plate as the laser control point; during construction control, the plumb line is placed on these laser reference points for centering and leveling; a receiving target is placed on the laser hole reserved on the slab surface, and then the laser is ignited and the light spot is displayed on the receiving target;

[0072] S24. Before vertical projection measurement, the reference point control network should be calibrated, and the calibration accuracy should not be lower than the accuracy of the building plane rectangular control network to ensure the vertical transmission accuracy of the axis;

[0073] S25. The verticality is controlled by the plane control axis. The axis is marked with a "red triangle" on the outer edge of the building. After the templates of each layer are calibrated, the theodolite is used to measure upward from ±0.000 to ensure that the verticality deviation of each layer is no more than 3mm, thereby checking the accuracy of the axis and ensuring that the verticality deviation is no more than 15mm within the total height range of the entire project. Professional measurement units should be asked to review the verticality at any time to ensure accuracy;

[0074] S26. When laying out the construction layer, the projection axis should be checked on the structural layer plane first, and then the detailed axis should be measured after closure.

[0075] Specifically, the specific steps of step S3 are:

[0076] S31. Survey and design of elevation control network:

[0077] S311. Based on the site leveling base points provided by the surveying and mapping management department, use a level to re-survey and check the provided leveling base points. After the calibration is qualified, a closed or leveling route is measured and set up, and the site plane control points are measured together, which is the primary condition for ensuring the vertical accuracy control of the construction;

[0078] S312. Based on the leveling base points provided by the surveying and mapping management department, bury semi-permanent elevation points, and then conduct joint survey to measure the elevation of the semi-permanent points in the field area;

[0079] S313. There should be at least three leveling points in the site, with a spacing of less than 1 km, a distance of more than 25 meters from buildings, and a distance of no less than 15 meters from the backfill edge;

[0080] S314. Level of elevation control network and observation technology requirements: The level of elevation control network is planned to be set at level three;

[0081] S32, Elevation Construction Measurement:

[0082] S321. When measuring the elevation inside the foundation pit, first measure the elevation control points to determine whether the level points in the field have been moved. Only after the joint measurement confirms that they are correct can the required elevation be measured inside the foundation pit.

[0083] S322. The elevation of the foundation is measured and set using a level, a tower ruler, and a long steel ruler. The elevation of the foundation is measured and set using the steel ruler transfer method.

[0084] In order to ensure the accuracy of vertical control, the elevation benchmark must be correctly measured and set. The elevation points measured on the same plane layer shall not be less than three, and they shall be checked against each other. After the check, the height difference of the three points shall not exceed 3mm, and the average value shall be taken as the elevation benchmark point for the plane construction. The benchmark is set at the stable position of the slope. Cement mortar can be used to form a vertical plane, marked with a red triangle, and the absolute elevation and relative elevation are marked for easy use in construction;

[0085] S323. For vertical transfer of elevation, use a steel ruler to measure vertically from the starting elevation point of the first floor. When the transfer height exceeds the length of the steel ruler, another elevation starting line should be set. The steel ruler needs to be corrected by tension, ruler length, and temperature differences.

[0086] S324. Before leveling the construction layer, the three elevation points transferred from the first floor should be calibrated first. When the difference is less than 3mm, the horizontal line should be measured based on its average point. When leveling, the level should be placed in the center of the measuring point range as much as possible, and a precise leveling should be carried out. The allowable error of the horizontal line elevation is 3mm.

[0087] 5. A nighttime concrete floor elevation control method according to claim 1, characterized in that: the specific steps of step S4 are: vertical observation work, including observation of verticality deviation of each layer and observation of verticality deviation of total height. When the building is gradually increased, due to the force of the foundation or the verticality control deviation, the vertical deviation of the building is caused, so it is necessary to set a point to observe the verticality. This work is carried out together with the axis measurement point projection for observation and inspection. Once the axis deviation is found to be greater than 3mm and intersects with the sight line, it should be considered to be caused by deviation. During observation, the accurate bottom axis is used as the reference line, and its maximum deviation value is observed, and records are made for analysis of the situation. If any abnormality is found, it should be reported to the supervision company in time, and corresponding measures should be taken.

[0088] Specifically, the specific steps of step S5 are: mark the monitoring points according to the designed monitoring points, observe once for each additional layer of load, and keep records.

[0089] Specifically, the specific steps of step S6 are:

[0090] S61. Control of verticality of building corners: After the axis projection inspection of each floor above ±0.000 meets the accuracy requirements, use the theodolite direction line method to project the building corners and the main axis to the facade of the wall or column and mark them with ink lines. The allowable axis deviation for each floor shall not exceed 2mm, and ensure that at least 3 axes are projected on each facade.

[0091] S62. Construction error control.

[0092] Specifically, the specific steps of step S62 are:

[0093] S621. Measurements must be made using qualified theodolites, levels, steel rulers, etc. The instruments should be strictly inspected according to regulations to prevent measurement errors caused by instrument errors themselves;

[0094] S622. Each time you take a measurement, the instrument should be placed firmly to ensure the accuracy of the instrument's operation and leveling. When taking a measurement, the measurement method of positive and negative mirrors should be used.

[0095] S623. The time for measurement should be chosen on a windless, cloudy day, avoiding scorching sun and rainy days, so as to reduce the impact of natural conditions on measurement accuracy;

[0096] S624. The surveying work shall be performed by fixed full-time surveyors from beginning to end. The important axis positioning and measurement shall be checked and reviewed by the project technical leader together with the professional foreman. The axis, verticality, elevation, etc. shall be checked before and after each concrete pouring. Any errors shall be corrected in time.

[0097] Construction coordination among related disciplines

[0098] 1. Coordinated construction measures between civil engineering and decoration engineering

[0099] Practice has proved that good coordination among related professional trades in decoration construction is a prerequisite for ensuring the smooth progress of the project, ensuring the quality of decoration and reducing rework waste. Therefore, the following interspersed coordination must be done in interior decoration construction.

[0100] (1) When civil engineering enters the decoration stage, a detailed monthly decoration plan should be drawn up and sent to relevant units or other trades for coordination.

[0101] (2) Civil engineering should provide the required horizontal control lines and axis control points for each floor for each type of professional work. (3) The construction sequence of interior decoration should be to first carry out wet work such as mortar leveling and plastering, and then carry out secondary decoration, ceiling cover panels, paint, coatings and other surface engineering construction.

[0102] (4) Coordination with door and window projects: Civil engineering should provide openings that conform to the structure in the drawings. Interior and exterior wall decoration can only be carried out after the door and window frames are installed.

[0103] (5) When cross-coordinating construction, it is also very important to pay attention to the protection of the finished products and semi-finished products of each other. Strict handover inspections should be carried out between the upper and lower processes, and records should be kept so that when problems arise, the responsible person and the cause can be traced back in time and the problems can be solved in a timely manner.

[0104] 2. Coordinated construction measures between civil engineering and water supply and drainage engineering

[0105] (1) Construction reservation and embedding should be carried out strictly in accordance with the requirements of the drawings of this profession and at the same time meet the requirements of professional drawings such as architecture and structure.

[0106] (2) The position of the casing buried in the cast-in-place reinforced concrete should be consistent with the position in the design drawings.

[0107] (3) The casing embedded in cast-in-place reinforced concrete should be firmly connected to the surrounding steel bars during installation to prevent displacement caused by concrete pouring and vibration.

[0108] (4) After the casing buried in the cast-in-place reinforced concrete is installed in place, polystyrene foam plastic (flame retardant) is used to fill the casing to prevent the casing from being blocked by concrete pouring.

[0109] (5) When one or both ends of the casing buried in cast-in-place reinforced concrete are on the inner side of the cast-in-place reinforced concrete formwork, a red paint mark should be applied on the inner side of the formwork at the end of the casing so that the casing can be found after the formwork is removed.

[0110] (6) The embedded iron parts and other embedded parts in the cast-in-place reinforced concrete shall be selected, manufactured and embedded in accordance with the design requirements. A red paint mark shall be painted on the side of the cast-in-place reinforced concrete formwork where they are installed so that they can be found after the formwork is removed.

[0111] (7) After the casing, embedded iron and other components are embedded and installed, and before concrete pouring, the team leader, foreman and quality inspector shall check the specifications, models and embedded positions according to the drawings one by one to see if they are correct. After checking, fill in the hidden acceptance data and submit it to the supervision engineer and other relevant personnel entrusted by the owner for on-site signature.

[0112] (8) For the holes where the pipeline passes through the floor slab, steel pipes are used as hole molds. Before using the hole molds, the dirt on the surface of the hole molds should be cleaned to prevent them from being stained by the poured concrete, causing slag inclusion in the floor slab concrete, which will cause leakage along the hole molds of the floor slab when it is put into use. The hole molds must be installed according to the position in the design drawing, and then a φ6 round steel is used as a stirrup on each side of the hole mold to clamp it to prevent it from shifting during the pouring of concrete. After the floor slab concrete has initially set, slowly rotate it to remove the hole mold.

[0113] (9) The holes and casings reserved for this specialty in the construction drawings and structure drawings shall be reviewed and proofread in accordance with the drawings of this specialty together with the civil construction personnel before concrete pouring.

[0114] (10) When pouring concrete, the installers should stay close to the casing, embedded iron parts and other embedded parts so that they can quickly handle and solve problems such as displacement that may be caused by concrete pouring and vibration.

[0115] (11) After the building formwork is removed, the casing, embedded iron parts and other embedded parts should be found in time, and the filling materials in the casing should be removed.

[0116] 3. Coordination measures between civil engineering and other installation projects

[0117] (1) The direction of the wiring pipes and brackets should be coordinated with other installation sections, ensuring that the ventilation ducts are installed first, followed by the water supply ducts and then the power pipelines.

[0118] (2) It is strictly forbidden to drill holes on the reinforced concrete beams and walls of this project. In order to ensure that no hole is missed and no wire pipe is misplaced, a special person is assigned on site to check the reserved holes of the civil engineering and verify the reserved and embedded work.

[0119] (3) When it is difficult for the reserved steel pipe to pass through the steel mesh and the steel bars need to be moved, the consent of the civil engineering department should be sought, and remedial measures should be taken for the surrounding steel bars after reservation.

[0120] (4) Steel pipes are connected by sleeves. The size of the sleeve should be between 1.5 and 3 times the outer diameter of the connecting pipe, and the connecting end of the connecting pipe should be at the center of the sleeve.

[0121] (5) Avoid crossing and overlapping of piping as much as possible.

[0122] (6) For reinforced concrete beams and wall panels that need to be penetrated by casing for secondary piping, steel casing should be reserved before pouring concrete. The casing should be buried accurately and firmly connected to the surrounding steel bars after being in place to avoid displacement due to vibration. The casing should be tightly packed with foam plastic to prevent concrete from pouring in during vibration.

[0123] (7) The knocking holes of the embedded boxes and junction boxes cannot be knocked off at will, and the embedded boxes should be installed with mouth guards and lock nuts.

[0124] (8) Steel pipes should be placed in the knock-out holes of boxes and boxes should not be used as jumper wires for pipelines.

[0125] (9) All steel surface-mounted or concealed boxes are connected by steel bars.

[0126] (10) After the installation of the through-the-wall magnetic pipe of the pipeline, it should be carefully checked to prevent omissions and coordinate misalignment, and marked.

[0127] (11) Equipment embedded parts and fixings should be fixed on a firm support. If the civil support is not strong enough, reinforcement should be carried out.

[0128] (12) After the building formwork is removed, find the embedded parts and embedded boxes in time, take out the fillings in the boxes and protect the pipe openings to prevent debris from falling into the pipes.

[0129] (13) When pouring concrete, the installers should cooperate on site and take remedial measures at any time if any problems are found.

[0130] Construction site layout principles

[0131] The layout of the construction site should take full account of various environmental factors and construction needs, noise nuisance, traffic organization, etc. The layout should be based on the following principles:

[0132] (I) The site plan is arranged and scheduled as the construction progresses. The stage plan layout needs to be adjusted separately to suit the construction focus of that period.

[0133] (2) In the plane layout, full consideration should be given to the optimization and reasonable arrangement of construction machinery and equipment, offices, roads, site entrances and exits, temporary storage areas, etc.

[0134] (III) The stacking of construction turnover materials should be located within the coverage of vertical transport machinery as far as possible, in order to reduce the occurrence of secondary handling.

[0135] (iv) Small and medium-sized machinery should be placed in a safe environment and out of the range of impact from high-altitude objects.

[0136] (V) Temporary power supplies and electrical wiring should be laid away from stairs and emergency exits with heavy traffic and areas easily hit by falling objects. Electrical wiring should be laid concealed in pipes as much as possible.

[0137] (VI) This project should focus on strengthening on-site safety management, environmental protection and civilized construction management, so that the project is always in a clean, sanitary, orderly and reasonable state, making the project a veritable green building in terms of environmental protection and energy conservation.

[0138] (VII) Control dust, sewage discharge, and waste disposal.

[0139] (8) Make full use of existing temporary facilities for construction and minimize unnecessary investment in temporary facilities.

[0140] (IX) Strict and effective measures shall be formulated for the storage and treatment of generated construction waste and garbage, and their timely transportation.

[0141] (10) Set up on-site roads that are convenient for transportation vehicles to pass through and ensure their reliability.

[0142] (11) Clean and maintain the roads you pass through.

[0143] Construction site layout

[0144] (I) Site enclosure

[0145] The construction site is separated from the surrounding roads and office and living areas by a lightweight fence with a height of 2.5 meters. Relevant public service advertisements and safety and civilized construction slogans are placed on the fence, and the fence is appropriately greened. The gate and fence of the construction site should be kept firm and neat, and obvious signs, slogans, eight signs and two pictures should be set up at the entrance and exit, with clear, standardized and beautiful writing; flushing facilities and return water trenches should be built at the gate according to standardization requirements.

[0146] (II) Vertical transportation machinery

[0147] 14 tower cranes and several material hoists are arranged on site to solve the problem of vertical and horizontal transportation of bulk materials. Special plans must be prepared for the foundation and installation of large equipment, which can only be implemented after approval, and the installation and use notification procedures must be completed before use.

[0148] (III) Layout of on-site production facilities

[0149] Carpentry shed and steel bar shed: Standardized assembled light steel movable sheds are used. Power distribution room: Special standardized color steel sheds are used, equipped with rat-proof nets, ventilation convection windows, sandboxes, fire extinguishers and other fire-fighting facilities. Cement barrels and dry-mixed mortar tanks: They are closed according to dust prevention requirements, public service advertisements and slogans are set up on the outside of the enclosure, and dust curtains are set up.

[0150] (IV) Arrangement of on-site office facilities

[0151] The office area is located on the southwest side of the east district. It is a two-story light steel mobile house with fences set up around it to separate it from the construction area. Parking spaces are set up in the office area and appropriate greening is carried out.

[0152] (V) Construction roads

[0153] Construction road method: 5-6m wide concrete road, replaced with 200mm thick pond slag and 150mm thick C30 commercial concrete, and the site is as connected as possible on all sides.

[0154] (VI) On-site drainage

[0155] Site drainage: Drainage ditches are set up along the road, connected to the sedimentation tank, and then discharged into the municipal rainwater system. Drainage ditch method: 240 thick brick open ditch, 100 thick C15 concrete cushion layer at the bottom of the ditch, 200 deep, 1:3 cement mortar plastering in the ditch, drainage slope 0.5%. Temporary drainage: Drainage ditches are set up around temporary facilities, and the method is the same as road drainage ditches.

[0156] (VII) General layout of construction

[0157] Temporary power supply for construction

[0158] The main line of temporary power supply for construction is laid underground from the substation designated by Party A to the main distribution cabinet, and then branched to the secondary distribution box; according to JGJ46-2005 "Technical Specifications for Temporary Power Safety at Construction Sites", the main cable line shall use three-phase five-wire armored cable, and rubber copper core cable shall be used for the conductors from the secondary distribution box to the tertiary distribution box to the construction machinery.

[0159] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A method for controlling the elevation of a concrete floor at night, characterized in that: The following steps are included: S1, positioning and laying out; S2, axis projection control method; S3, elevation measurement; S4, verticality observation; S5. Settlement observation; S6. Engineering measurement control measures.

2. A method for controlling the elevation of a concrete floor at night according to claim 1, characterized in that: The specific steps of step S1 are: S11. Basis for positioning and laying out: Determine the plane control scheme and survey accuracy according to the general plan of the architectural design, and conduct survey of the on-site axis control network and elevation control points using the building red line piles, national elevation standard piles and on-site points designated by the planning department; S12. Survey and design of plane control network: S121. The plane control network should be considered from the overall perspective first, following the principle of overall first, then local, and high precision controlling low precision; S122. Only by controlling the first-level grid can the construction requirements be met; S123. According to the characteristics of the building's plane shape, the main control axis is determined using the given on-site points. When positioning and laying out the lines, the control axis network is accurately measured, and the stakes are set in a place that is easy to observe and not easily damaged to be fixed and protected; S124. After determining the main axis control network, the other main axes of the building are encrypted using the rectangular coordinate positioning and layout method based on the basic plan. After the angle and distance are calibrated to meet the point position limit requirements, the building plane rectangular control network is laid out.

3. A method for controlling the elevation of a concrete floor at night according to claim 1, characterized in that: The specific steps of step S2 are: Calibration of S21 axis control piles: During the foundation construction process, according to the calibration of the primary plane control network in the field, the axis control piles are re-measured every half month to prevent pile position displacement; S22, axis projection method: The axis projection adopts the internal control method, and the foundation construction below ±0.000 adopts the theodolite direction line intersection method to transfer the axis, and the error of the survey point should not exceed ±3mm, and the error between the axes should not exceed ±2m; S23. After the foundation construction is completed, the laser base point is placed on the concrete slab surface, and the anchor hook is welded with a 200×200×10mm steel plate and set to the predetermined position. The axis of each level is projected and measured with a theodolite to determine the laser reference point as shown in the figure; a small circle center is chiseled on the steel plate as the laser control point; during construction control, the plumb line is placed on these laser reference points for centering and leveling; a receiving target is placed on the laser hole reserved on the slab surface, and then the laser is ignited and the light spot is displayed on the receiving target; S24. Before vertical projection measurement, the reference point control network should be calibrated, and the calibration accuracy should not be lower than the accuracy of the building plane rectangular control network to ensure the vertical transmission accuracy of the axis; S25. The verticality is controlled by the plane control axis. The axis is marked with a "red triangle" on the outer edge of the building. After the templates of each layer are calibrated, the theodolite is used to measure upward from ±0.000 to ensure that the verticality deviation of each layer is no more than 3mm, thereby checking the accuracy of the axis and ensuring that the verticality deviation is no more than 15mm within the total height range of the entire project. Professional measurement units should be asked to review the verticality at any time to ensure accuracy; S26. When laying out the construction layer, the projection axis should be checked on the structural layer plane first, and then the detailed axis should be measured after closure.

4. A method for controlling the elevation of a concrete floor at night according to claim 1, characterized in that: The specific steps of step S3 are: S31. Survey and design of elevation control network: S311. Based on the site leveling base points provided by the surveying and mapping management department, use a level to re-survey and check the provided leveling base points. After the calibration is qualified, a closed or leveling route is measured and set up, and the site plane control points are measured together, which is the primary condition for ensuring the vertical accuracy control of the construction; S312. Based on the leveling base points provided by the surveying and mapping management department, bury semi-permanent elevation points, and then conduct joint survey to measure the elevation of the semi-permanent points in the field area; S313. There should be at least three leveling points in the site, with a spacing of less than 1 km, a distance of more than 25 meters from buildings, and a distance of no less than 15 meters from the backfill edge; S314. Level of elevation control network and observation technology requirements: The level of elevation control network is planned to be set at level three; S32, Elevation Construction Measurement: S321. When measuring the elevation inside the foundation pit, first measure the elevation control points to determine whether the level points in the field have been moved. Only after the joint measurement confirms that they are correct can the required elevation be measured inside the foundation pit. S322. The elevation of the foundation is measured and set using a level, a tower ruler, and a long steel ruler. The elevation of the foundation is measured and set using the steel ruler transfer method. S323. For vertical transfer of elevation, use a steel ruler to measure vertically from the starting elevation point of the first floor. When the transfer height exceeds the length of the steel ruler, another elevation starting line should be set. The steel ruler needs to be corrected by tension, ruler length, and temperature differences. S324. Before leveling the construction layer, the three elevation points transferred from the first floor should be calibrated first. When the difference is less than 3mm, the horizontal line should be measured based on its average point. When leveling, the level should be placed in the center of the measuring point range as much as possible, and a precise leveling should be carried out. The allowable error of the horizontal line elevation is 3mm.

5. A method for controlling the elevation of a concrete floor at night according to claim 1, characterized in that: The specific steps of step S4 are: vertical observation work, including observation of verticality deviation of each floor and observation of verticality deviation of total height. When the building is raised layer by layer, the vertical deviation of the building is caused by the force of the foundation or the verticality control deviation, so it is necessary to set a point to observe the verticality. This work is carried out together with the axis measurement point for observation and inspection. Once the axis deviation is found to be greater than 3mm and intersects with the sight line, it should be considered to be caused by deviation. When observing, the accurate bottom axis is used as the reference line, and the maximum deviation value is observed, and records are made for analysis. If any abnormality is found, it should be reported to the supervision company in time, and corresponding measures should be taken.

6. A method for controlling the elevation of a concrete floor at night according to claim 1, characterized in that: The specific steps of step S5 are: marking the monitoring points according to the designed monitoring points, observing once for each additional layer of load, and keeping records.

7. A method for controlling the elevation of a concrete floor at night according to claim 1, characterized in that: The specific steps of step S6 are: S61. Control of verticality of building corners: After the axis projection inspection of each floor above ±0.000 meets the accuracy requirements, use the theodolite direction line method to project the building corners and the main axis to the facade of the wall or column and mark them with ink lines. The allowable axis deviation for each floor shall not exceed 2mm, and ensure that at least 3 axes are projected on each facade. S62. Construction error control.

8. A method for controlling the elevation of a concrete floor at night according to claim 7, characterized in that: The specific steps of step S62 are: S621. Measurements must be made using qualified theodolites, levels, steel rulers, etc. The instruments should be strictly inspected according to regulations to prevent measurement errors caused by instrument errors themselves; S622. Each time you take a measurement, the instrument should be placed firmly to ensure the accuracy of the instrument's operation and leveling. When taking a measurement, the measurement method of positive and negative mirrors should be used. S623. The survey time should be selected on a windless, cloudy day, avoiding scorching sun and rainy days, to reduce the impact of natural conditions on survey accuracy; S624. The surveying work shall be performed by fixed full-time surveyors from beginning to end. The important axis positioning and measurement shall be checked and reviewed by the project technical leader together with the professional foreman. The axis, verticality, elevation, etc. shall be checked before and after each concrete pouring. Any errors shall be corrected in time.

Citation Information

Patent Citations

  • Measurement and control method for bridge construction

    CN104457716A

  • Concrete night construction elevation control device and construction method thereof

    CN105484500A

  • Night concrete pouring elevation control method

    CN115045504A

  • Construction paying-off measuring method

    CN115451925A