Gob-side entry driving method, construction method and system for advanced pre-injection consolidation of waste rock in goaf
Through the method of consolidating the tunnel along the goaf area with pre-injection and consolidation of the tunnel along the sky, the problems of coal recovery rate and tunnel stability under deep mining were solved, and efficient and safe zero-coal column tunnels were achieved, which improved the coal recovery rate and The excavation efficiency enhances the stability of the surrounding rock in the tunnel.
Patent Information
- Application Number
- CN202410763007.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-13
- Publication Date
- 2024-11-29
AI Technical Summary
In the existing coal mine tunnel excavation technology, it is impossible to effectively balance the coal recovery rate, technical process difficulty and tunnel surrounding rock stability, especially the increase in the width of the coal column under deep mining, resulting in a decrease in coal yield rate and difficulty in tunnel maintenance.
The method of consolidating the consolidation along the tunnel in the goaf is adopted. By obtaining the mine site data, the height, volume and weight of the consolidation area are determined, and the proportion of components and flow radius of the consolidation high-strength consolidation agent are designed, and the composition ratio and flow radius of the consolidation agent are combined. Injection hole parameters realize advanced pre-injection consolidation during tunnel excavation, forming high-strength consolidation bodies, and realizing zero-coal columns digging along the air tunnels while burning.
It improves coal recovery rate and excavation efficiency, enhances the stability of the tunnel surrounding rock, reduces the cost of anchor cable support, simplifies the construction process, realizes green and efficient gangue backfill, and makes up for the shortcomings of the existing technology.
Smart Images

Figure CN119041914A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of coal mine tunneling, and in particular to a tunneling method, construction method and system for tunneling along the goaf by pre-injecting and consolidating loose gangue in goaf areas. Background Art
[0002] The stability of the surrounding rock of the roadway is of great significance to the production of the mine. The layout and support method of the mining roadway are closely related to the stability of the surrounding rock of the roadway. Among the newly excavated roadways in my country's coal mines, about 80% of the coal roadways are affected by mining. For a long time, in order to cope with the impact of mining on the mining face, the lower section roadway is generally arranged outside a certain range of the working face. However, with the continuous increase in mining depth, the width of the coal pillar protecting the roadway is getting larger and larger, resulting in a decrease in coal recovery rate and difficulty in roadway maintenance.
[0003] Therefore, there is an urgent need for a coal-pillar-free tunnel protection method that can balance the coal recovery rate, technical process difficulty and tunnel surrounding rock stability. Summary of the invention
[0004] The present application provides a method, construction method and system for tunneling along the goaf with advance pre-injection and consolidation of loose gangue in goaf areas, which are used to solve the problem of a coal-pillar-free tunnel protection method that cannot achieve a balanced coal recovery rate, technical process difficulty and tunnel surrounding rock stability.
[0005] The first aspect of the present application provides a method for pre-injection consolidation of loose gangue in goaf area along the goaf, the method comprising:
[0006] Obtaining production data and basic data of rock collapse at the mine site, wherein the basic data includes lithology parameters of coal seam roof, coal seam mining height, tunnel excavation size and tunnel excavation speed;
[0007] According to the basic data, the height of the pre-injected consolidation area, the volume of the consolidation area and the weight of the gangue in the consolidation area are obtained;
[0008] Determine the composition ratio of the loose gangue rapid-setting high-strength consolidating agent based on the gangue block size, gradation size l, and the preset design requirements for the compressive strength of the formed cementing body;
[0009] Determine the proportion of each component in the consolidated body according to the strength requirement of the loose gangue consolidated body adapted to the mine site, wherein the consolidated body includes the loose gangue rapid-setting high-strength consolidating agent and the loose gangue;
[0010] According to the length of the pre-injected consolidation area, the flow radius of the loose gangue rapid setting high strength consolidating agent is determined;
[0011] Determine the parameters of the injection hole according to the mining height of the tunnel, the length of the advance injection area, and the minimum interval distance of the advance injection during tunnel excavation, wherein the parameters of the injection hole include the depth and inclination angle parameters of the injection hole;
[0012] The mine site application is carried out according to the consolidated body, the minimum spacing distance of the advance pre-injection and the injection hole parameters.
[0013] In some practicable ways, the step of obtaining the height, volume and weight of waste rock in the pre-injected consolidation area according to the basic data includes:
[0014] According to the lithology data of the coal seam roof, the expansion coefficient of the coal seam roof collapse gangue is obtained; wherein the expansion coefficient K P Calculation formula:
[0015]
[0016] Among them, K P is the coefficient of expansion; V1 is the volume of the rock in a loose state after crushing; V2 is the volume of the rock in an integral state before crushing;
[0017] Determine the height of the consolidation area for advance injection according to the expansion coefficient and the coal seam mining height;
[0018] Determine the volume of the consolidation area of the advance pre-injection according to the height of the consolidation area of the advance pre-injection and the length of the consolidation area of the advance pre-injection, wherein the length of the consolidation area of the advance pre-injection represents the length obtained by evaluating the degree of the mine pressure manifestation of the working face in the mine;
[0019] The weight of the gangue in the pre-injection consolidation area is determined according to the volume of the pre-injection consolidation area, the crushing expansion coefficient and the apparent density of the gangue before crushing; wherein,
[0020]
[0021] Among them, h g h is the height of the pre-injected consolidation area; m is the mining height of the tunnel; L is the length of the consolidation area of the advance injection; V g is the volume of the pre-injected consolidation area; ρ1 is the apparent density of the gangue before crushing; M g It is the weight of the waste rock in the consolidation area of the advance injection.
[0022] In some practicable methods, the step of determining the composition ratio of the loose gangue rapid-setting high-strength consolidating agent based on the preset design requirements for the compressive strength of the shaped cementitious body and the basic data includes:
[0023] According to the gangue block size, the gradation size, and the design requirements of the compressive strength of the preset shaped cementitious body, the injection pressure, initial setting time, final setting time, and the strength of the preset number of days are obtained;
[0024] The component ratio of the loose gangue rapid-setting high-strength consolidating agent is determined according to the injection pressure, the initial setting time, the final setting time and the strength in the preset number of days, wherein the loose gangue rapid-setting high-strength consolidating agent includes a strong dispersant, an initial setting accelerator and a high-efficiency water reducing agent.
[0025] In some practicable methods, the step of determining the proportion of each component in the consolidated body according to the strength requirement of the loose gangue consolidated body adapted to the mine site includes:
[0026] Determine the adaptive strength of the consolidation body according to the stress demand corresponding to the mine site, and the environmental factors affecting the stress caused by the mining height, burial depth and geological structure of the coal seam;
[0027] Determining the proportion of each component in the consolidated body according to the adaptability strength of the consolidated body;
[0028] According to the proportion of loose gangue quick-setting high-strength consolidating agent and loose gangue included in the consolidated body, the dosage volume of the loose gangue quick-setting high-strength consolidating agent is obtained; wherein,
[0029] The dosage volume of the loose gangue rapid setting high strength consolidating agent is V c Calculation formula:
[0030]
[0031] Among them, V c is the dosage volume of the loose gangue rapid setting high strength consolidating agent; n c is the proportion of the loose gangue rapid-setting high-strength consolidating agent in the consolidated body; n g is the proportion of the loose gangue in the consolidated body; ρ c It is the density of the loose gangue rapid-setting high-strength consolidating agent.
[0032] In some practicable methods, the step of determining the flow radius of the loose gangue rapid-setting high-strength consolidating agent according to the length of the pre-injected consolidation area includes:
[0033] According to the length of the pre-injected consolidation area, the flow radius of the loose gangue rapid setting high-strength consolidating agent is determined; wherein the flow radius r c Calculation formula:
[0034]
[0035] Among them, r c is the flow radius; L is the length of the pre-injected consolidation area.
[0036] In some practicable methods, the mining height of the tunnel, the length of the advance pre-injection area, and the minimum spacing distance of the advance pre-injection during tunnel excavation determine the parameters of the injection hole, and the parameters of the injection hole include the depth and inclination angle parameters of the injection hole, including:
[0037] According to the final setting time of the loose gangue quick-setting high-strength consolidating agent, the tunnel excavation speed, and the flow rate of the loose gangue quick-setting high-strength consolidating agent, the minimum spacing distance of the advance pre-injection during the tunnel excavation is determined; wherein the minimum spacing distance l of the advance pre-injection during the tunnel excavation s The calculation formula is:
[0038]
[0039] Among them, l s The minimum interval distance for advance injection; v j is the tunnel excavation speed; v l is the flow rate of the loose gangue rapid-setting high-strength consolidating agent; t3 is the time taken for the loose gangue rapid-setting high-strength consolidating agent to fill the advance pre-injection consolidation area; r is the radius of the injection pipe.
[0040] In some practicable methods, the step of determining the parameters of the injection hole according to the mining height of the tunnel, the length of the advance pre-injection area, and the minimum spacing distance of the advance pre-injection during tunnel excavation, wherein the parameters of the injection hole include the depth and inclination angle parameters of the injection hole, comprises:
[0041] The drilling depth and inclination angle of the injection pipe are determined according to the mining height of the tunnel, the length of the advance injection area, and the minimum interval distance of the advance injection during the tunnel excavation; wherein,
[0042]
[0043] Wherein, l1 is the drilling depth of the injection pipe; h m h is the mining height of the tunnel; g is the height of the pre-injected consolidation area; α is the inclination angle of the injection pipe drilling; l m is the distance between the injection pipe and the injection side roadway; L is the length of the consolidation area of the advance pre-injection; l s The minimum interval distance for advance injection.
[0044] The second aspect of the present application provides a method for pre-injection consolidation of loose gangue in goaf area along the goaf roadway construction, which is applied to the aforementioned method for pre-injection consolidation of loose gangue in goaf area along the goaf roadway construction, comprising:
[0045] Before the tunnel excavation work begins, according to the injection hole parameters, the gangue in the goaf is collapsed, injection holes are drilled, and injection pipes are laid to carry out injection operations; wherein the slurry used in the injection operation is a consolidated body.
[0046] After the final setting time of the loose gangue rapid setting high-strength consolidating agent in the consolidation body has passed, excavation operations are carried out along the cementing surface between the consolidation body and the coal body to form the tunnel section;
[0047] After the tunnel section is formed, anchor cable support operation is carried out, wherein the anchor cable includes an anchor rod and an anchor cable;
[0048] The tunnel face excavation operation and material injection operation are carried out simultaneously;
[0049] When the distance between the excavation face and the boundary of the injection consolidation area reaches the minimum distance for advance pre-injection, while the working face continues to excavate, the injection holes are constructed according to the designed drilling, and the injection operation is carried out in the injection holes; wherein, during the grouting operation, the grouting pressure is continuously increased without exceeding the limit value until the calculated required amount of slurry is used up, and the injection operation is stopped;
[0050] When the working face is excavated to the boundary of the next injection consolidation area, which is at the minimum interval distance of the advance pre-injection, while the working face continues to excavate, the injection hole is constructed according to the designed drilling, and the injection operation of the injection hole is carried out;
[0051] If they are at the minimum interval distance for advance pre-injection, the injection holes are constructed according to the designed drilling while the working face continues to be excavated, and the injection operation is carried out on the injection holes until the tunnel excavation is completed.
[0052] The third aspect of the present application provides a goaf area loose gangue advance pre-injection consolidation goaf-side roadway driving system, which is applied to the goaf area loose gangue advance pre-injection consolidation goaf-side roadway driving method mentioned above, comprising:
[0053] An acquisition module is used to acquire production data and basic data of collapsed gangue at the mine site, wherein the basic data includes lithology parameters of coal seam roof, coal seam mining height, tunnel excavation size and tunnel excavation speed;
[0054] An execution module is used to obtain the height, volume and weight of waste rock in the pre-injected consolidation area according to the basic data;
[0055] The proportioning module is used to determine the composition ratio of the loose gangue rapid-setting high-strength consolidating agent according to the gangue block size, gradation size l, and the preset design requirements of the compressive strength of the formed cementing body;
[0056] The proportioning module is also used to determine the proportion of each component in the consolidated body according to the strength requirement of the loose gangue consolidated body adapted to the mine site, wherein the consolidated body includes the loose gangue rapid-setting high-strength consolidating agent and the loose gangue;
[0057] A judgment module is used to determine the flow radius of the loose gangue rapid-setting high-strength consolidating agent according to the length of the pre-injected consolidation area;
[0058] The judgment module is further used to determine the parameters of the injection hole according to the mining height of the tunnel, the length of the advance pre-injection area, and the minimum interval distance of the advance pre-injection during tunnel excavation, wherein the parameters of the injection hole include the depth and inclination angle parameters of the injection hole;
[0059] The output module is used to carry out the application on the mine site according to the consolidation body, the minimum spacing distance of the advance pre-injection and the injection hole parameters.
[0060] A fourth aspect of the present application provides a computer-readable storage medium storing computer instructions for causing the computer to execute the aforementioned method for pre-injection and consolidation of loose gangue in goaf along the goaf.
[0061] Beneficial effects of this application:
[0062] A method for pre-injecting and consolidating loose gangue in goaf areas for goaf-side tunneling, firstly, obtaining production data of the mine site and basic data of collapsed gangue, wherein the basic data include lithology parameters of coal seam roof, coal seam mining height, tunnel excavation size and tunnel excavation speed; next, obtaining the height of the pre-injected consolidation area, the volume of the consolidation area and the weight of the gangue in the consolidation area according to the basic data; then, determining the component ratio of the loose gangue rapid-setting high-strength consolidating agent according to the gangue block size, gradation size l, and the design requirements of the compressive strength of the preset formed cementing body; determining the proportion of each component in the consolidation body according to the corresponding stress demand of the mine site; ratio, wherein the consolidation body includes the loose gangue quick-setting high-strength consolidating agent and loose gangue; the minimum spacing distance of the advance pre-injection is determined according to the final setting time of the loose gangue consolidation of the consolidation body, the tunnel excavation speed, and the flow rate of the cementitious consolidation material; the flow radius of the loose gangue quick-setting high-strength consolidating agent is determined according to the length of the consolidation area of the advance pre-injection, and then the tunnel mining height, the length of the advance pre-injection area, and the minimum spacing distance of the advance pre-injection during tunnel excavation are combined to further determine the parameters such as the injection hole depth and the inclination angle; finally, the mine site application is carried out according to the consolidation body, the minimum spacing distance of the advance pre-injection and the injection hole parameters. Through the above method, it is possible to pre-inject loose gangue fast-setting high-strength consolidating agent into the goaf of the mine in advance, so that the loose gangue and the consolidating agent in the pre-injection area form a high-strength consolidation body. While the tunnel is excavated along the bonding surface between the consolidation body and the coal body, advance pre-injection of the next consolidation area can be carried out, realizing zero-coal-pillar goaf excavation with high recovery rate and high excavation efficiency while injecting and excavating, thereby making up for the shortcomings of existing tunnel excavation technology. BRIEF DESCRIPTION OF THE DRAWINGS
[0063] In order to more clearly illustrate the specific implementation methods of the present application or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0064] Figure 1 This is a flow chart of a method for pre-injection consolidation of loose gangue in goaf areas;
[0065] Figure 2 This is a schematic diagram of determining the flow radius of the loose gangue quick-setting high-strength consolidating agent and the injection hole parameters of a method for pre-injecting loose gangue in goaf area to consolidate the goaf-side roadway in this application;
[0066] Figure 3 A schematic diagram of the side structure of a mine shaft for a method of pre-injection consolidation of loose gangue in goaf areas in this application;
[0067] Figure 4A schematic diagram of a mine structure top view of a method for pre-injection consolidation of loose gangue in goaf areas in this application;
[0068] Figure 5 The present invention discloses a flow chart of a method for constructing a tunnel along the goaf for pre-injection consolidation of loose gangue in goaf areas.
[0069] Description of reference numerals:
[0070] 1. Injection hole; 2. Anchor cable; 3. Anchor rod; 4. Solid coal; 5. Zero coal pillar tunneling along the goaf; 6. Bonding surface between consolidation body and coal body; 7. Injection consolidation area; 8. Advance injection and consolidation area; 9. Collapsed gangue in goaf; 10. Injection consolidation area boundary; 11. Minimum interval distance for advance pre-injection. DETAILED DESCRIPTION
[0071] The technical solution of the present application will be described clearly and completely below in conjunction with the embodiments. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0072] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0073] In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "multiple" is two or more, unless otherwise clearly and specifically defined. In addition, the terms "installed", "connected", and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, and it can be the internal connection of two elements. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0074] Some terms involved in this application are explained below to facilitate understanding of this application:
[0075] Core Logging: Core Logging refers to the process of observing, describing and recording the physical properties of the core, rock structure, boundaries between rock layers, changes in rock layers, etc. after core sampling.
[0076] Loose Circle Test: Loose Circle Test is a quantitative test method used to evaluate the stability of formations, usually used to evaluate the stability of soft soil foundations or rock formations.
[0077] The stability of the surrounding rock of the roadway is of great significance to mine production. The layout and support method of the mining roadway are closely related to the stability of the surrounding rock of the roadway. Since the lower section roadway is generally arranged outside a certain range of the working face, as the mining depth continues to increase, the width of the coal pillar protecting the roadway becomes larger and larger, resulting in a decrease in coal recovery rate and difficulty in roadway maintenance. The technology of non-pillar roadway protection has emerged. It is mainly divided into two methods: gob-side roadway excavation and gob-side roadway retention. The former refers to excavating the roadway along the stress reduction zone after the stress redistribution caused by mining tends to be stable, and the latter is to strengthen the support of the upper section roadway and reapply it to the lower section working face. Gob-side roadway excavation and gob-side roadway retention technology have improved the coal recovery rate to a certain extent, but they still have problems that need to be improved. For example, the existing gob-side roadway excavation technology still needs to leave a small coal pillar, which is difficult to achieve true non-pillar mining, and the stability of the coal pillar is difficult to guarantee. The technology of gob-side roadway retention is relatively complex and the roadway reuse rate is low, and it still requires a lot of labor and support costs.
[0078] Related non-pillar tunnel protection technologies:
[0079] (1) Gob-side tunneling: refers to the tunneling arrangement along the edge of the goaf after the mining stress of the upper working face is stable. It is mainly divided into complete gob-side tunneling technology, small coal pillar gob-side tunneling technology and gob-side tunneling with side filling. 1. Complete gob-side tunneling technology refers to the tunneling close to the goaf of the upper section after the overburden structure of the goaf is stable; 2. Gob-side tunneling technology with small coal pillars refers to the reservation of a 5-8m small coal pillar between the tunneling tunnel and the goaf of the upper section; 3. Gob-side tunneling with side filling refers to the pre-placement of concrete filling walls in the transport tunnel in front of the previous working face, close to the coal wall of the next working face. The width of the filling wall is reserved by wide-face tunneling or wall expansion of existing tunnels.
[0080] The problem is:
[0081] Disadvantages of the complete goaf-side tunneling technology: Since the tunnel is arranged completely close to the goaf, the stress environment of the surrounding rock is relatively poor, and the stability of the surrounding rock is difficult to ensure. At the same time, the communication between the tunnel and the goaf will cause risks such as fire in the goaf, gas outburst in the goaf, and water gushing.
[0082] Disadvantages of the small coal pillar roadway excavation technology along the goaf: Since there is still a coal pillar between the roadway and the goaf in this method, it is not a true pillar-free mining, so its coal recovery rate is relatively low. At the same time, the bearing capacity of the small coal pillar is relatively weak, and plastic damage is prone to occur. The roadway control is difficult and the maintenance cost is high.
[0083] Disadvantages of tunnel excavation with side filling and leaving tunnels along the empty space: Since the space for the concrete filling wall is reserved by wide-face tunneling or wall expansion of existing tunnels, the increase in tunnel cross-section will lead to an increase in the bending moment of its roof, causing further deterioration of the surrounding rock environment, which is not conducive to the stability of the surrounding rock. Wall expansion consumes additional construction and labor costs, reducing production efficiency.
[0084] (2) Gob-side lane retention: a certain support method is adopted behind the coal mining face to retain the mining lane along the edge of the gob area to serve the next working face. It is mainly divided into gob-side lane retention without laneside support and gob-side lane retention with laneside support. The laneside support is further divided into traditional laneside support and integral filling laneside support. Traditional laneside support includes wood pile support, dense pillar support, gangue belt support and concrete block support. The integral filling laneside support is divided into low-water material laneside filling and high-water material laneside filling.
[0085] The problem is:
[0086] After experiencing the stress disturbance of mining, the surrounding rock of the tunnel is damaged to varying degrees. Especially in the absence of tunnel side support, the surrounding rock of the tunnel is severely deformed, resulting in a low reuse rate of the retained tunnel, requiring multiple expansion and renovation, making tunnel control difficult, and the construction and support costs high. The technical process of tunnel side support is complex, the tunnel maintenance time is long, and the tunnel side filling body occupies the original tunnel space, resulting in a reduction in the tunnel cross-section, affecting the secondary use of the tunnel.
[0087] In view of this, the present application proposes a method for pre-injecting and consolidating loose gangue in the goaf and driving the goaf along the roadway. By pre-injecting loose gangue rapid-setting high-strength consolidating agent into the goaf in advance, the loose gangue and the loose gangue rapid-setting high-strength consolidating agent in the pre-injected area form a high-strength consolidated body. While the roadway is excavated along the bonding surface of the loose gangue rapid-setting high-strength consolidation body and the coal body, pre-injection of the next consolidation area is carried out, thereby realizing zero-coal-pillar roadway excavation along the goaf with high recovery rate and high excavation efficiency while injecting and excavating, thereby making up for the shortcomings of the existing roadway excavation technology.
[0088] like Figure 1 As shown, the first aspect of the present application proposes a method for pre-injection consolidation of loose gangue in goaf area along the goaf, the method comprising:
[0089] S100, obtain the production data and basic data of rock collapse at the mine site.
[0090] Among them, the basic data include coal seam roof lithology parameters, coal seam mining height, tunnel excavation size and tunnel excavation speed.
[0091] Specifically, the actual production of the mine is investigated to obtain on-site data such as coal seam roof lithology parameters, coal seam mining height, tunnel excavation size, tunnel excavation speed, etc. For example, coal seam roof lithology parameters such as rock density, strength, hardness, toughness, compressive strength, tensile strength, etc. Coal seam mining height, tunnel excavation size, and tunnel excavation speed can be determined according to the actual needs of the mine site.
[0092] These parameters can be used to form the conditions for advance pre-injection so as to better perform advance pre-injection.
[0093] S200, obtaining the height, volume and weight of waste rock in the pre-injected consolidation area according to the basic data.
[0094] Specifically, obtaining the height, volume and weight of the gangue in the pre-injected consolidation area includes the following steps:
[0095] According to the lithology data of the coal seam roof, the expansion coefficient of the coal seam roof collapse gangue is obtained; among them, the expansion coefficient K P Calculation formula:
[0096]
[0097] Among them, K P is the crushing expansion coefficient; V1 is the volume of the rock in a loose state after crushing, m 3 ; V2 is the volume of the rock in its entirety before it is crushed, m 3 ;
[0098] According to the expansion coefficient and the mining height of the coal seam, the height of the consolidation area for advance injection is determined;
[0099] The volume of the pre-injection consolidation area is determined according to the height of the pre-injection consolidation area and the length of the pre-injection consolidation area.
[0100] Among them, the length of the consolidation area of the advance injection refers to the length obtained by the mine's actual assessment of the degree of pressure manifestation on the working face;
[0101] The weight of the gangue in the pre-injection consolidation area is determined according to the volume of the pre-injection consolidation area, the crushing expansion coefficient and the apparent density of the gangue before crushing;
[0102]
[0103] Among them, h g is the height of the pre-injected consolidation area, m; h mis the mining height of the tunnel, m; L is the length of the consolidation area of the advance injection, m; V g is the volume of the consolidation area for advance injection, m 3 ; ρ1 is the apparent density of gangue before crushing, t / m 3 ;M g is the weight of waste rock in the consolidation area for advance injection, t.
[0104] It should be noted that after obtaining the field data such as the lithology parameters of the coal seam roof, the coal seam mining height, the tunnel excavation size, and the tunnel excavation speed, the height of the pre-injection consolidation body can be calculated according to the expansion coefficient of the roof collapse gangue (1), and the degree of pressure manifestation of the working face can be evaluated according to the actual situation of the mine, and the length of the pre-injection consolidation body can be comprehensively determined. Among them, the length of the pre-injection consolidation body can be determined according to different mines, using borehole peek test and loose circle test to obtain the depth of development and damage of the surrounding rock cracks, and then combined with the mining height and burial depth factors, multiplied by the safety factor (which can be the soil bearing capacity safety factor, the ratio between the actual soil bearing capacity and the design required bearing capacity) to determine the length L.
[0105] Next, the volume of the pre-injected consolidation area V is calculated according to formula (2): g , and the weight of the waste rock in the pre-injection consolidation area M g Then, we collected the collapsed gangue from the goaf on site, classified and counted the gangue particle size and weight, selected the gangue of suitable size to prepare standard specimens, and conducted laboratory experiments such as uniaxial compressive strength, triaxial compressive strength, tensile and shear strength tests, so as to fully understand the gangue strength parameter K P .
[0106] S300, determine the composition ratio of the loose gangue rapid-setting high-strength consolidating agent based on the gangue block size, gradation size l, and the preset design requirements for the compressive strength of the formed cementing body.
[0107] Specifically, determining the component ratio of the loose gangue rapid-setting high-strength consolidating agent includes the following steps:
[0108] According to the size of gangue blocks, gradation size, and the design requirements of the compressive strength of the preset shaped cementitious body, the injection pressure, initial setting time, final setting time, and strength in the preset number of days are obtained.
[0109] The component ratio of the loose gangue rapid-setting high-strength consolidating agent is determined according to the injection pressure, initial setting time, final setting time and the strength after a preset number of days; wherein, the loose gangue rapid-setting high-strength consolidating agent includes a strong dispersant, an initial setting accelerator and a high-efficiency water reducing agent.
[0110] It should be noted that step S300 is used to select the proportion of the components of the loose gangue rapid-setting high-strength consolidating agent, wherein the gangue block size refers to the size and distribution of the gangue block particles; the gradation size refers to the distribution range of the gangue particle size; the compressive strength of the formed binder refers to the ability of the binder (loose gangue rapid-setting high-strength consolidating agent and gangue) to withstand the maximum pressure without being damaged when subjected to a compressive load. Specifically, the strong dispersant, initial setting accelerator and high-efficiency water reducer are matched and adjusted according to the block size and gradation size l of the gangue, the compressive strength σ of the formed cementing body, the designed injection pressure p, the initial setting time t1, the final setting time t2 and the strength σ1 of 1 day (preset number of days) so as to meet the design requirements. That is to say, according to the parameters of the block size and gradation size of the gangue and the compressive strength of the formed cementing body as the target, the adjustment materials (strong dispersant (to avoid failure of high-pressure anti-bleeding delamination), initial setting accelerator and high-efficiency water reducer) are made, and the proportion of added components is equal. The mechanical properties test of loose gangue rapid-setting high-strength consolidator under different raw material component proportions is carried out. Combined with the parameter judgment criteria of the gangue sampled on site, the raw material component proportion scheme is preliminarily selected, and the proportion of p, t1, t2, σ1 of the loose gangue rapid-setting high-strength consolidator and the added components such as strong dispersant, initial setting accelerator and high-efficiency water reducer are preliminarily determined.
[0111] S400, determines the proportion of each component in the consolidated body according to the strength requirements of the loose gangue consolidated body adapted to the mine site.
[0112] The consolidating body includes loose gangue rapid-setting high-strength consolidating agent and loose gangue.
[0113] Specifically, determining the proportion of each component in the solid body includes the following steps:
[0114] Determine the adaptive strength of the consolidation body based on the corresponding stress requirements at the mine site, as well as the environmental factors affecting stress caused by the mining height, burial depth and geological structure of the coal seam;
[0115] According to the adaptive strength of the consolidated body, determine the proportion of each component in the consolidated body;
[0116] According to the proportion of loose gangue quick-setting high-strength consolidating agent and loose gangue included in the consolidated body, the dosage volume of the loose gangue quick-setting high-strength consolidating agent is obtained; wherein, the dosage volume of the loose gangue quick-setting high-strength consolidating agent V c Calculation formula:
[0117]
[0118] Among them, V c is the volume of loose gangue rapid setting high strength consolidating agent, m 3 ;n c is the proportion of loose gangue rapid-setting high-strength consolidating agent in the consolidated body; n g is the proportion of loose gangue in the consolidated body; ρ cis the density of the loose gangue rapid setting high strength consolidating agent, t / m 3 .
[0119] It should be noted that the mine site needs to form a technical solution for tunneling along the goaf, which puts forward corresponding requirements for the stress of the mine site. In other words, if tunneling along the goaf is to be achieved, the consolidation body needs to have corresponding adaptive strength. In this way, the loose gangue rapid-setting high-strength consolidating agent is fully combined with the loose gangue to form a consolidation body, and the two materials are integrally loaded to improve the load-bearing strength of a single component.
[0120] Furthermore, according to the actual needs of the mine site, combined with the factors affecting the stress environment such as mining height, burial depth, and geological structure, the adaptive strength of the two-component consolidation body is determined, and the proportion of each component in the consolidation body is obtained. In other words, the proportions of loose gangue rapid-setting high-strength consolidating agent and gangue are different, and the strength of the final consolidation body is different, so it is necessary to determine their proportions based on the strength of the consolidation body. The role of burial depth in the factors affecting the stress environment is that the original rock stress can be estimated through the formula; the role of mining height is that the stress concentration coefficient of the tunnel surrounding rock corresponding to different mining heights is different; in addition, multiple factors such as geological structure and filling range will cause stress concentration, that is, multiple factors affect the stress concentration caused respectively, and the change of each factor will affect the stress. In this way, when each factor forms a coefficient, the original rock stress is multiplied by these concentration coefficients to finally obtain the strength of the consolidation body. Among them, the corresponding relationship between the strength of the consolidation body and the proportion of each component of the consolidation body is obtained through a large number of experiments to obtain the original data.
[0121] For example, when the stress at the mine site needs to be 40 MPa, the strength of gangue, broken stone blocks, etc. is 10 MPa. In this case, it is necessary to use loose gangue rapid setting high-strength consolidating agent to increase the strength, thereby increasing the strength of the consolidated body to 40 MPa, and the amount of loose gangue rapid setting high-strength consolidating agent added can be obtained based on a limited number of experiments, in which the strength of gangue and the stress requirements at the mine site are only illustrated by way of example. In other words, when the strength of gangue is fixed, the strength is adjusted by adding the amount of loose gangue rapid setting high-strength consolidating agent.
[0122] After obtaining the stress demand at the mine site, the ratio of loose gangue quick-setting high-strength consolidating agent to loose gangue can be obtained. Next, according to the volume of the advance pre-injection area, the dosage volume V of the loose gangue quick-setting high-strength consolidating agent is calculated by formula (3): c .
[0123] S500, determining the flow radius of the loose gangue rapid-setting high-strength consolidating agent according to the length of the pre-injected consolidation area.
[0124] According to the length of the pre-injected consolidation area, the flow radius of the loose gangue rapid setting high-strength consolidating agent is determined; where the flow radius r c Calculation formula:
[0125]
[0126] Among them, r c is the flow radius, m; L is the length of the pre-injection consolidation zone, m.
[0127] S600, determining the parameters of the injection hole according to the mining height of the tunnel, the length of the advance pre-injection area, and the minimum interval distance of the advance pre-injection during tunnel excavation.
[0128] The parameters of the injection hole include injection hole depth and inclination angle parameters.
[0129] Specifically, determining the minimum interval distance for advance pre-injection includes the following steps:
[0130] The minimum interval distance for advance injection during tunnel excavation is determined based on the final setting time of the loose gangue quick-setting high-strength consolidating agent, the tunnel excavation speed, and the flow rate of the loose gangue quick-setting high-strength consolidating agent.
[0131] Among them, the minimum interval distance l for advance injection during tunnel excavation is s The calculation formula is:
[0132]
[0133] Among them, l s is the minimum interval distance for advance injection, m; v j is the tunnel excavation speed, m / h; v l is the flow rate of the loose gangue rapid-setting high-strength consolidating agent, m / h; t3 is the time taken for the loose gangue rapid-setting high-strength consolidating agent to fill the advance pre-injection consolidation area, h; r is the radius of the injection pipe, m.
[0134] It should be noted that in order to ensure that the adjacent gangue has been solidified and has sufficient strength during tunnel excavation, the final setting time of the loose gangue, the tunnel excavation speed, the flow rate of the cementing material, etc. are obtained according to the aforementioned consolidation body and the proportion of the loose gangue rapid-setting high-strength consolidating agent that forms the consolidation body, and the minimum interval distance of advance pre-injection during tunnel excavation is determined, as calculated in formula (4).
[0135] Formula (4) is used to obtain the minimum interval distance. That is, after completing the advance pre-injection at a certain position in the goaf of the mine, the advance pre-injection is performed again at the minimum interval distance, and this process is repeated until the tunnel excavation is completed.
[0136] It should also be noted that the obtained flow rate can not only help ensure that the various components in the loose gangue rapid-setting high-strength consolidating agent are fully mixed, thereby improving the uniformity and stability of the slurry, but also ensure the reaction rate and achieve efficient consolidation. A flow rate that is too fast or too slow may affect the reaction rate, thereby affecting the final consolidation effect. In addition, the flow rate also affects production efficiency, helps reduce energy consumption, improves production efficiency, and thus reduces production costs.
[0137] like Figure 2 Specifically, determining the injection hole parameters includes the following steps:
[0138] The drilling depth and inclination angle of the injection pipe are determined based on the mining height of the tunnel, the length of the advance pre-injection area, and the minimum interval distance of advance pre-injection during tunnel excavation.
[0139] The tunnel excavation dimensions include the tunnel mining height and width.
[0140] in,
[0141]
[0142] Where, l1 is the drilling depth of the injection pipe, m; h m is the mining height of the tunnel, m; h g is the height of the pre-injected consolidation area 8, m; α is the inclination angle of the injection pipe drilling, °; l m is the distance between the injection pipe and the injection side roadway, m; L is the length of the consolidation area of the advance pre-injection, m; l s The minimum interval distance for advance injection, m.
[0143] The flow radius of the high-strength fast-setting consolidating agent for loose gangue in formula (5) can be used to limit the length L of the advance pre-injection area; the parameters of injection hole 1 can be obtained by designing the injection pipe drilling depth and the injection pipe drilling inclination angle according to the cross-sectional height of the tunnel and the length of the advance pre-injection area using formula (6). The parameters of injection hole 5 can help control the injection speed and pressure. Figure 2 An injection hole 1 for feeding material through an injection pipe is formed on the zero-coal pillar tunneling tunnel 5 on one side of the injection consolidation area 7.
[0144] S700 is applied on-site in mines according to the consolidation body, the minimum spacing distance of advance pre-injection and the injection hole parameters.
[0145] Among them, according to the consolidated body, the minimum spacing distance of advance pre-injection and the injection hole parameters obtained in the above steps, it can be applied on-site in the mine to realize the advance pre-injection of loose gangue in the goaf.
[0146] In summary, the present application provides a method for pre-injecting and consolidating scattered gangue in goafs to excavate lanes along the goaf. During the tunnel excavation process, a self-compacting rapid-setting consolidating agent is pre-injected into a hole in the goaf on one side of the excavation section. The consolidating agent is fully combined with the scattered gangue in the goaf to form a high-strength bearing consolidation body. The lane is excavated along the cementing surface of the consolidation body and the coal body, and the stress environment of the surrounding rock of the lane excavation is greatly improved. According to the rapid-setting and early-solidifying characteristics of the high-strength consolidating agent for scattered gangue and the collapsed gangue, it is possible to excavate while injecting without stopping mining and waiting for the solidification process, which greatly improves the excavation efficiency and safety factor of the lane, and realizes green and efficient gangue backfilling and zero coal pillar lane excavation along the goaf. Compared with the existing goaf-side tunneling and goaf-side tunneling technologies, the zero-coal-pillar goaf-side tunneling technology can truly achieve zero coal pillar width and increase coal recovery rate. The high-strength consolidation body formed by loose gangue-cementitious materials greatly improves the stability of the surrounding rock of the excavated tunnel, and the side of the consolidation body does not need to be supported, reducing the construction and time cost of anchor cable support. The existing tunneling technology has a low tunnel reuse rate and requires repeated expansion and renovation. After adopting this method, the tunnel can be formed in one time, with a simple process, safety and efficiency. It can realize the effective recycling of gangue, alleviate the gangue pollution phenomenon in the mining area, and is in line with the concept of green mining.
[0147] like Figure 3 and Figure 4 The second aspect of the present application provides a method for pre-injection consolidation of loose gangue in goaf area along the goaf roadway construction, which is applied to the aforementioned method for pre-injection consolidation of loose gangue in goaf area along the goaf roadway construction, and the construction method comprises:
[0148] Before the tunnel excavation work begins, according to the parameters of the injection hole 1, the gangue 9 in the goaf is drilled, and the injection pipe is laid to carry out the injection operation; wherein the slurry used in the injection operation is a consolidated body.
[0149] In the area 8 to be consolidated after the final setting time of the consolidated body, excavation work is carried out along the cementing surface 6 between the consolidated body and the coal body to form the tunnel section;
[0150] After the tunnel section is formed, the anchor cable support operation is carried out, wherein the anchor cable includes anchor rod 3 and anchor cable 4;
[0151] The tunnel face excavation operation and material injection operation are carried out simultaneously;
[0152] When the distance between the excavation face and the boundary 10 of the injection consolidation area reaches the minimum distance 11 for advance pre-injection, while the working face continues to excavate, the injection hole 1 is constructed according to the designed drilling, and the injection operation of the injection hole 1 is carried out; wherein, during the grouting operation, the grouting pressure is continuously increased without exceeding the limit value until the calculated required amount of slurry is used up, and the injection operation is stopped;
[0153] When the working face is excavated to the boundary with the next injection consolidation area 7, and the distance from the advance pre-injection minimum interval 11, while the working face continues to excavate, the injection hole 1 is constructed according to the designed drilling, and the injection operation of the injection hole 1 is carried out;
[0154] If the minimum interval distance for advance pre-injection is 11, while the working face continues to advance, the injection hole 1 is constructed according to the designed drilling, and the injection operation of the injection hole 1 is carried out until the tunnel excavation is completed, forming a zero coal pillar tunnel 5 along the air.
[0155] In addition, the complex calculation and judgment processes such as the proportion of each component of the loose gangue rapid-setting high-strength consolidating agent, the proportion of each group in the consolidated body and the key parameter design of the injection hole are formed into a database (for example, a NoSQL database, a database for storage and query of large-scale data), for example, written into code and developed into software. Due to the complex and changeable geological conditions of mines, the tunnel dimensions and surrounding rock properties are also different. According to the on-site investigation of the coal seam overburden lithology parameters and the apparent strength of mine pressure, the length of the advance consolidation body is comprehensively determined. For example, the tunnel dimensions and surrounding rock properties are also different. According to the on-site investigation of the coal seam overburden lithology parameters and the apparent strength of mine pressure, etc., they are used as parameters and input into the software. The database in the software is used to directly output the proportion of each component of the loose gangue rapid-setting high-strength consolidating agent, the proportion of each component in the consolidation body and the key parameters of the injection hole, and the data such as the strength parameters of the gangue in the goaf and the tunnel excavation height are brought in. In other words, the corresponding proportion of each component of the loose gangue rapid-setting high-strength consolidating agent, the proportion of each component in the consolidation body and the key parameters of the injection hole are automatically called according to the parameters through the database of the software, and the corresponding on-site implementation plan is obtained to ensure the safe and efficient implementation of zero-coal-pillar goaf excavation while injecting and digging.
[0156] The third aspect of the present application provides a goaf area loose gangue advance pre-injection consolidation goaf-side roadway driving system, which is applied to the goaf area loose gangue advance pre-injection consolidation goaf-side roadway driving method mentioned above, comprising:
[0157] The acquisition module is used to obtain the production data of the mine site and the basic data of the collapsed gangue, wherein the basic data includes the lithology parameters of the coal seam roof, the coal seam mining height, the tunnel excavation size and the tunnel excavation speed;
[0158] An execution module is used to obtain the height of the pre-injected consolidation area, the volume of the consolidation area and the weight of the gangue in the consolidation area according to the basic data;
[0159] The proportioning module is used to determine the composition ratio of the loose gangue rapid-setting high-strength consolidating agent according to the gangue block size, gradation size l, and the preset design requirements of the compressive strength of the formed cementing body;
[0160] The proportioning module is also used to determine the proportion of each component in the consolidation body according to the strength requirements of the loose gangue consolidation body adapted to the mine site, wherein the consolidation body includes the loose gangue rapid-setting high-strength consolidating agent and the loose gangue;
[0161] A judgment module is used to determine the flow radius of the loose gangue rapid-setting high-strength consolidating agent according to the length of the pre-injected consolidation area;
[0162] The judgment module is also used to determine the parameters of the injection hole according to the mining height of the tunnel, the length of the advance pre-injection area, and the minimum interval distance of the advance pre-injection during tunnel excavation, and the parameters of the injection hole include the depth and inclination angle parameters of the injection hole;
[0163] Output module for mine site application based on consolidation body, minimum spacing distance for advance pre-injection and injection hole parameters.
[0164] A fourth aspect of the present application provides a computer-readable storage medium storing computer instructions for causing a computer to execute the aforementioned method for pre-injection and consolidation of loose gangue in goaf areas along the goaf.
[0165] In a fifth aspect of the present application, an electronic device is provided, comprising: at least one processor; and a memory connected to the at least one processor in communication; wherein the memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor executes the aforementioned method of pre-injection and consolidation of loose gangue in goaf area along the goaf.
[0166] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present application.
Claims
1. A method for pre-injection consolidation of loose gangue in goaf area along goaf roadway driving, characterized in that: include: Obtaining production data and basic data of rock collapse at the mine site, wherein the basic data includes lithology parameters of coal seam roof, coal seam mining height, tunnel excavation size and tunnel excavation speed; According to the basic data, the height of the pre-injected consolidation area, the volume of the consolidation area and the weight of the gangue in the consolidation area are obtained; Determine the composition ratio of the loose gangue rapid-setting high-strength consolidating agent based on the gangue block size, gradation size l, and the preset design requirements for the compressive strength of the formed cementing body; Determine the proportion of each component in the consolidated body according to the strength requirement of the loose gangue consolidated body adapted to the mine site, wherein the consolidated body includes the loose gangue rapid-setting high-strength consolidating agent and the loose gangue; According to the length of the pre-injected consolidation area, the flow radius of the loose gangue rapid-setting high-strength consolidating agent is determined; Determine the parameters of the injection hole according to the mining height of the tunnel, the length of the advance injection area, and the minimum interval distance of the advance injection during tunnel excavation, wherein the parameters of the injection hole include the depth and inclination angle parameters of the injection hole; The mine site application is carried out according to the consolidated body, the minimum spacing distance of the advance pre-injection and the injection hole parameters.
2. The method for pre-injection consolidation of loose gangue in goaf according to claim 1 is characterized in that: The step of obtaining the height, volume and weight of the gangue in the pre-injected consolidation area according to the basic data comprises: According to the lithology data of the coal seam roof, the expansion coefficient of the coal seam roof collapse gangue is obtained; wherein the expansion coefficient K P Calculation formula: Among them, K P is the coefficient of expansion; V1 is the volume of the rock in a loose state after crushing; V2 is the volume of the rock in an integral state before crushing; Determine the height of the consolidation area for advance injection according to the expansion coefficient and the coal seam mining height; Determine the volume of the consolidation area of the advance pre-injection according to the height of the consolidation area of the advance pre-injection and the length of the consolidation area of the advance pre-injection, wherein the length of the consolidation area of the advance pre-injection represents the length obtained by evaluating the degree of the mine pressure manifestation of the working face in the mine; The weight of the gangue in the pre-injection consolidation area is determined according to the volume of the pre-injection consolidation area, the crushing expansion coefficient and the apparent density of the gangue before crushing; wherein, Among them, h g h is the height of the pre-injected consolidation area; m is the mining height of the tunnel; L is the length of the consolidation area of the advance pre-injection; V g is the volume of the pre-injected consolidation area; ρ1 is the apparent density of the gangue before crushing; M g It is the weight of the waste rock in the consolidation area of the advance injection.
3. The method for pre-injection consolidation of loose gangue in goaf according to claim 2 is characterized in that: The step of determining the component ratio of the loose gangue rapid-setting high-strength consolidating agent based on the preset design requirements for the compressive strength of the formed cementitious body and the basic data comprises: According to the gangue block size, the gradation size, and the design requirements of the compressive strength of the preset shaped cementitious body, the injection pressure, initial setting time, final setting time, and the strength of the preset number of days are obtained; The component ratio of the loose gangue rapid-setting high-strength consolidating agent is determined according to the injection pressure, the initial setting time, the final setting time and the strength in the preset number of days, wherein the loose gangue rapid-setting high-strength consolidating agent includes a strong dispersant, an initial setting accelerator and a high-efficiency water reducing agent.
4. The method for pre-injection consolidation of loose gangue in goaf according to claim 1 is characterized in that: The step of determining the proportion of each component in the consolidated body according to the strength requirement of the loose gangue consolidated body adapted to the mine site includes: Determine the adaptive strength of the consolidation body according to the stress demand corresponding to the mine site, and the environmental factors affecting the stress caused by the mining height, burial depth and geological structure of the coal seam; Determining the proportion of each component in the consolidated body according to the adaptability strength of the consolidated body; According to the proportion of loose gangue quick-setting high-strength consolidating agent and loose gangue included in the consolidated body, the dosage volume of the loose gangue quick-setting high-strength consolidating agent is obtained; wherein, The dosage volume of the loose gangue rapid setting high strength consolidating agent is V c Calculation formula: Among them, V c is the dosage volume of the loose gangue rapid setting high strength consolidating agent; n c is the proportion of the loose gangue rapid-setting high-strength consolidating agent in the consolidated body; n g is the proportion of the loose gangue in the consolidated body; ρ c It is the density of the loose gangue rapid-setting high-strength consolidating agent.
5. The method for pre-injection consolidation of loose gangue in goaf according to claim 4 is characterized in that: The step of determining the flow radius of the loose gangue rapid-setting high-strength consolidating agent according to the length of the pre-injected consolidation area comprises: According to the length of the pre-injected consolidation area, the flow radius of the loose gangue rapid setting high-strength consolidating agent is determined; wherein the flow radius r c Calculation formula: Among them, r c is the flow radius; L is the length of the pre-injected consolidation area.
6. The method for pre-injection consolidation of loose gangue in goaf according to claim 3 is characterized in that: The step of determining the parameters of the injection hole based on the mining height of the tunnel, the length of the advance injection area, and the minimum spacing distance of the advance injection during tunnel excavation, wherein the parameters of the injection hole include the depth and inclination angle parameters of the injection hole, comprises: According to the final setting time of the loose gangue quick-setting high-strength consolidating agent, the tunnel excavation speed, and the flow rate of the loose gangue quick-setting high-strength consolidating agent, the minimum spacing distance of the advance pre-injection during the tunnel excavation is determined; wherein the minimum spacing distance l of the advance pre-injection during the tunnel excavation s The calculation formula is: Among them, l s The minimum interval distance for advance injection; v j is the tunnel excavation speed; v l is the flow rate of the loose gangue rapid-setting high-strength consolidating agent; t3 is the time taken for the loose gangue rapid-setting high-strength consolidating agent to fill the advance pre-injection consolidation area; r is the radius of the injection pipe.
7. The method for pre-injection consolidation of loose gangue in goaf according to claim 5 is characterized in that: The step of determining the parameters of the injection hole according to the mining height of the tunnel, the length of the advance pre-injection area, and the minimum spacing distance of the advance pre-injection during tunnel excavation, wherein the parameters of the injection hole include the depth and inclination angle parameters of the injection hole, comprises: The drilling depth and inclination angle of the injection pipe are determined according to the mining height of the tunnel, the length of the advance injection area, and the minimum interval distance of the advance injection during the tunnel excavation; wherein, Wherein, l1 is the drilling depth of the injection pipe; h m h is the mining height of the tunnel; g is the height of the pre-injected consolidation area; α is the inclination angle of the injection pipe drilling; l m is the distance between the injection pipe and the injection side roadway; L is the length of the consolidation area of the advance pre-injection; l s The minimum interval distance for advance injection.
8. A method for pre-injection consolidation of loose gangue in goaf area, characterized in that: The method for pre-injection consolidation of loose gangue in goaf area according to any one of claims 1 to 7 comprises: Before the tunnel excavation work begins, according to the injection hole parameters, the gangue in the goaf is collapsed, injection holes are drilled, and injection pipes are laid to carry out injection operations; wherein the slurry used in the injection operation is a consolidated body. After the final setting time of the loose gangue rapid setting high-strength consolidating agent in the consolidation body has passed, excavation operations are carried out along the cementing surface between the consolidation body and the coal body to form the tunnel section; After the tunnel section is formed, anchor cable support operation is carried out, wherein the anchor cable includes an anchor rod and an anchor cable; The tunnel face excavation operation and material injection operation are carried out simultaneously; When the distance between the excavation face and the boundary of the injection consolidation area reaches the minimum distance for advance pre-injection, while the working face continues to excavate, the injection holes are constructed according to the designed drilling, and the injection operation is carried out in the injection holes; wherein, during the grouting operation, the grouting pressure is continuously increased without exceeding the limit value until the calculated required amount of slurry is used up, and the injection operation is stopped; When the working face is excavated to the boundary of the next injection consolidation area, which is at the minimum interval distance of the advance pre-injection, while the working face continues to excavate, the injection hole is constructed according to the designed drilling, and the injection operation of the injection hole is carried out; If they are at the minimum interval distance for advance pre-injection, the injection holes are constructed according to the designed drilling while the working face continues to be excavated, and the injection operation is carried out on the injection holes until the tunnel excavation is completed.
9. A goaf-side tunneling system for pre-injection consolidation of loose gangue in goaf, characterized in that: The method for pre-injection consolidation of loose gangue in goaf area according to any one of claims 1 to 7 comprises: An acquisition module is used to acquire production data and basic data of collapsed gangue at the mine site, wherein the basic data includes lithology parameters of coal seam roof, coal seam mining height, tunnel excavation size and tunnel excavation speed; An execution module is used to obtain the height, volume and weight of waste rock in the pre-injected consolidation area according to the basic data; The proportioning module is used to determine the composition ratio of the loose gangue rapid-setting high-strength consolidating agent according to the gangue block size, gradation size l, and the preset design requirements of the compressive strength of the formed cementing body; The proportioning module is also used to determine the proportion of each component in the consolidated body according to the strength requirement of the loose gangue consolidated body adapted to the mine site, wherein the consolidated body includes the loose gangue rapid-setting high-strength consolidating agent and the loose gangue; A judgment module is used to determine the flow radius of the loose gangue rapid-setting high-strength consolidating agent according to the length of the pre-injected consolidation area; The judgment module is further used to determine the parameters of the injection hole according to the mining height of the tunnel, the length of the advance pre-injection area, and the minimum interval distance of the advance pre-injection during tunnel excavation, wherein the parameters of the injection hole include the depth and inclination angle parameters of the injection hole; The output module is used to carry out the application on the mine site according to the consolidation body, the minimum spacing distance of the advance pre-injection and the injection hole parameters.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable the computer to execute the method for advance pre-injection and consolidation of loose gangue in goaf along the goaf as described in any one of claims 1-7.