Earth excavation construction method for staggered deep and large pits in pits under complex overtown beach geology

The method addresses the challenges of constructing deep pits in complex floodplain geology by optimizing dewatering and using high-pressure jet grouting piles and 3D modeling, enhancing safety and efficiency in pit-in-pit excavation.

CN119083446APending Publication Date: 2024-12-06THE THIRD CONSTR OF CHINA CONSTR EIGHTH ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411174727.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The construction of deep and large pits in complex floodplain geology, particularly under soft soil and high groundwater conditions, faces challenges such as foundation collapse, pipe bursts, quicksand, and difficulty in understanding conventional two-dimensional drawings, leading to errors and increased construction time.

Method used

A method involving precipitation testing, high-pressure jet grouting piles, 3D modeling, and expanded clay board formwork to optimize excavation, ensuring accurate and efficient construction in staggered pits.

Benefits of technology

The method reduces construction difficulty, minimizes errors, speeds up the process, and enhances safety by optimizing dewatering operations, using high-pressure jet grouting piles and intuitive 3D modeling, and facilitates quick assembly and removal of formwork.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083446A_ABST
    Figure CN119083446A_ABST
Patent Text Reader

Abstract

The invention provides a staggered deep and large pit-in-pit earth excavation construction method under complex overtown beach geology. The method comprises the steps that a precipitation test and pit-in-pit precipitation scheme optimization are carried out; constructing a high-pressure jet grouting pile; establishing a pit-in-pit earthwork model and exposing a 3D printing material object; carrying out layered excavation on pit-in-pit earthwork; and mounting the ceramsite plate side mold of the foundation pit. The arrangement and the number of the precipitation wells are optimized, and unnecessary precipitation operation is saved; the high-pressure jet grouting piles are arranged close to the edge of the pit, so that the workload of slope excavation and the later concrete consumption of the side wall of the foundation pit are reduced; compared with traditional two-dimensional plane drawing construction disclosure, 3D model disclosure is more visual and easy to understand, the difficulty of paying-off positioning is lowered, and rework caused by errors in the excavation process is avoided; the ceramsite plate side mold can achieve the effects of rapid assembly, time saving and labor saving, plastering is not needed, mold removal can be avoided after pouring is completed, the strength and rigidity of the plate are higher than those of a traditional brick molding bed, and cracks and collapse are not prone to occurring when earthwork around the bearing platform is backfilled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building construction, and in particular relates to an earthwork excavation construction method for deep and large pits in a staggered arrangement under complex floodplain geology. Background Art

[0002] In recent years, large-scale deep foundation pit projects in urban construction have increased, and the form of foundation pits has become increasingly complex. Various staggered pits have become the key and difficult points of foundation pit construction. Especially under some complex floodplain geological conditions, the soil is soft and the groundwater is abundant, which makes the construction of pits in pits more difficult. Under the floodplain geological conditions along the Yangtze River, soft soil layers such as silty soil, silty clay, and silty sand are generally exposed within the scope of foundation pit excavation, and the bearing capacity of the foundation is low. If the foundation around the pit in the pit is not reinforced, accidents such as foundation pit collapse are prone to occur during the excavation process. In addition, due to the proximity to the main stream of the Yangtze River, the groundwater is hydraulically connected with the water of the Yangtze River. The water content of the strata under such geological conditions is generally high, and the groundwater level fluctuates significantly due to the seasonal changes in the water level of the Yangtze River. Therefore, precipitation work during the excavation process is particularly important. If precipitation is not timely, accidents such as pipe bursts and quick sand may occur. At the same time, the principle of fast excavation and fast support should be followed during the construction process, and the time interval between excavation and support should be shortened as much as possible. Due to the complex structure of the pit-in-pit and the overlapping excavation lines, the conventional two-dimensional plane drawings are often difficult to understand when conducting technical briefings, and workers are prone to make mistakes during construction. In order to solve the above technical problems, the present invention designs an earthwork excavation construction method for deep and large pits in staggered arrangements under complex floodplain geology. Summary of the invention

[0003] In view of the shortcomings of the prior art, the present invention provides a method for excavating earthwork in deep and large pits in a staggered arrangement under complex floodplain geology, which improves and optimizes the conventional pit-in-pit excavation construction method, significantly reduces the construction difficulty, speeds up the construction progress, and realizes accurate, fast, safe and efficient pit-in-pit excavation construction.

[0004] The present invention achieves the above technical objectives through the following technical means.

[0005] A method for excavating deep and large pits in a staggered arrangement under complex floodplain geology, comprising the following steps: Step 1: Precipitation test and optimization of pit-in-pit precipitation scheme; Step 2: High-pressure jet grouting pile construction; Step 3: Establish the earthwork model of the pit in the pit and hand over the 3D printing object; Step 4: Layered excavation of the pit within the pit; Step 5: Install the side formwork of the foundation pit expanded clay board.

[0006] Furthermore, the specific process of step 1 is as follows: Step 1.1: Analyze the actual water output of single wells and groups of wells under the operation of water pumps with different powers according to the measured data, and compare it with the rated water output. Determine the water pumps configured for the pumping wells and the maximum water output capacity of a single well through the change data of water output and water level drop. When officially lowering the water level, consider the interference effect of the group of wells and stagger the configuration of water pumps of different models. Step 1.2: Establish a geological model for simulation and calculation; organize the test data, set up pumping wells and observation wells in the three-dimensional model, substitute the parameters of the pumping wells including filter length, layer position, pumping volume, and water inflow into the three-dimensional numerical model, simulate and calculate the pumping test, compare the calculation results with the measured water level changes in the observation wells, repeatedly adjust and invert the relevant hydrogeological parameters, so that the model calculation curve coincides with the measured curve, and finally calculate the permeability coefficient of the regional confined aquifer and the maximum impact radius of the pumping test process; Step 1.3: Based on the data analysis of the above test wells, the pumping capacity of single and group wells, the permeability coefficient of the confined aquifer, and the parameters of the impact range are obtained. The number, distance, and pump power of the precipitation wells in the pit-in-pit area are optimized, so that the groundwater level can be reduced to below the designed excavation elevation before excavation of the pit-in-pit, ensuring the safety of excavation.

[0007] Furthermore, the mud hole diameter of the precipitation well is 650mm, the well pipe is a steel pipe with a diameter of 273mm and a wall thickness of 4mm, the filter pipe is a bridge-type filter pipe, and the filter material is medium-coarse sand, which is backfilled above the top of the filter pipe; the well in the pit is sealed with on-site clay, and the well outside the pit is sealed with clay balls + grouting.

[0008] Furthermore, the specific process of step 2 is as follows: Step 2.1: After the construction of surrounding engineering piles, retaining piles, and water-blocking curtains is completed and reaches 80% of the design strength, high-pressure jet grouting piles shall be constructed; before construction, the control points of the jet grouting piles shall be determined with a total station or GPS and marked. After the retest line is qualified, the pile positions shall be arranged and marked on site with a steel ruler and a measuring line to ensure that the displacement deviation of the pile hole center meets the requirements; Step 2.2: The sewage and mortar mixing system are built synchronously with the pile hole positioning, and then the mortar is mixed. After the slurry is mixed, it is sent to the slurry suction bucket and filtered by a screen with a sieve hole smaller than 1 / 2 of the nozzle diameter; Step 2.3: Before the drilling rig is constructed, test spraying is first carried out on the ground. After the drilling machine is tested and operated normally, the pilot hole drilling is started; the number of drill rod sections is recorded during the drilling process to ensure the accuracy of the drilling depth. To ensure the length of the high-pressure jet grouting pile, control measures are taken for the top and bottom elevations of the high-pressure jet grouting pile. By calculating the corresponding elevation and pile length, the pile bottom elevation and pile top elevation control marks are set to ensure the length of the high-pressure jet grouting pile; Step 2.4: After the drilling is completed, rotary grouting is carried out. First, high-pressure water is sent, then cement slurry and compressed air are sent. After rotating and spraying at the bottom of the pile for a period of time, it is rotated, lifted and sprayed again. When spraying, first reach the predetermined spraying pressure and spraying volume and then gradually lift the grouting pipe. If a fault occurs in the middle, stop lifting and rotary grouting to prevent the pile from being interrupted, and immediately check to eliminate the fault. If it is found that the slurry is not sprayed enough, affecting the designed diameter of the pile body, recheck; stop rotary grouting when it is lifted to the designed pile top elevation, lift the drill outlet, clean the grouting pump and delivery pipeline, and move the drilling rig.

[0009] Furthermore, the high-pressure jet grouting pile has a diameter of 800 mm, uses PO 42.5 grade ordinary Portland cement, uses 600 kg / m³ of cement, and has a water-cement ratio of 0.8. During construction, the speed is increased by 15 cm / min and the rotation speed is 20 r / min.

[0010] Furthermore, the specific process of step 3 is as follows: Step 3.1: For complex areas with interlaced pits, export the BIM model created by the BIM software into a 3D model in .obj format according to the foundation cap design drawing, then import it into the slicing software for slicing and export it into a .Gcode format file; then import the generated .Gcode format file into the printing platform software to realize 3D printing of the model; Step 3.2: Before excavation, the workers are given a physical briefing to let them intuitively understand the layout of the complex and staggered pits and the excavation deployment of earthworks at various elevations; during the excavation process, the management personnel will synchronously check and compare the on-site excavation situation with the model, on the one hand to guide the on-site excavation work, on the other hand to check and verify the positioning, elevation and size of the excavated earthwork.

[0011] Furthermore, the specific process of step 4 is as follows: After the construction of the drainage wells and high-pressure rotary jet grouting piles around the deep pit area is completed, the large-scale foundation pit excavation will be carried out. The pit-in-pit soil will be excavated after it has been excavated to the large-surface bottom plate elevation. Since there are many foundation pit elevations in the deep pit area and different foundation pit caps are staggered, the excavation principle is to excavate the earth at the lowest elevation first, then build the slope to the upper elevation, and excavate the earth layer by layer from low to high.

[0012] Furthermore, the specific process of step 5 is as follows: Two people will straighten the side form of the ceramsite board into place, one person will hold a pry bar, and after it is in place, one person will push on one side to align it accurately, and one person will pry up the wall panel with a pry bar, prying and squeezing at the same time, and move the side form of the ceramsite board into the line through the movement of the pry bar, and use adhesive mortar to evenly fill the joints. After installing the first board, temporary fixation will be adopted, and the second and third boards will continue to be installed. Special adhesive or mortar will be applied between the boards; after the installation of the side form of the ceramsite board is completed, the board joints and under the board will be filled with the prepared cement mortar. Before filling the cement mortar under the board, remove the debris under the board; Among them, when the side formwork of the expanded clay board is temporarily fixed, short steel bars or wooden planks are used to support the side formwork of the expanded clay board to prevent collapse. The temporary support is removed after the adhesive or mortar solidifies. In the area outside the deep pit with high-pressure rotary jet reinforcement, vertical excavation is used instead of slope excavation. The side formwork of the expanded clay board is installed in time during the excavation process to reduce the workload of slope excavation and the amount of concrete used in the side walls of the foundation pit in the later stage.

[0013] Furthermore, the expanded clay board side formwork is a 10 cm thick RLC board, which is used as a pit-in-pit side wall formwork in a deep pit area and is installed in two ways: oblique and vertical according to the side wall excavation form.

[0014] The present invention has the following beneficial effects: (1) The arrangement and number of dewatering wells were optimized, saving unnecessary dewatering operations; (2) High-pressure jet grouting piles were set near the center and edge of the pit, reducing the workload of slope excavation and the amount of concrete used for the side walls of the foundation pit in the later stage; (3) Compared with the traditional two-dimensional plane drawing construction briefing, the 3D model briefing method is more intuitive and easy to understand, which reduces the difficulty of line positioning and avoids rework caused by errors during excavation; (4) The expanded clay board side formwork can be assembled quickly, saving time and effort, without the need for plastering, and can be removed after pouring. The strength and rigidity of the board are higher than those of the traditional brick formwork, and cracks and collapse are not likely to occur when backfilling the soil around the pedestal. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a partial plan layout diagram of the pit-in-pit earthwork excavation structure of the present invention; Figure 2 for Figure 1 Typical cross-section of a pit with slope excavation; Figure 3 for Figure 1 Typical cross-section of a straight-wall excavation in a middle pit.

[0016] In the figure: 1. Pit within a pit (including elevator foundation pit, cap, water collection well, etc.); 2. Drainage well; 3. High-pressure jet grouting pile; 4. Ceramsite board side formwork; DETAILED DESCRIPTION

[0017] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments, but the protection scope of the present invention is not limited thereto.

[0018] The present invention discloses a method for excavating earthwork in deep and large pits arranged in a staggered manner under complex floodplain geology, comprising the following steps: Step 1: Dewatering test and optimization of dewatering scheme for pit 1: Arrange test wells before overall earthwork excavation to conduct verification and reference pumping tests.

[0019] Step 1.1: According to the measured data analysis, the actual water output of single wells and group wells under the operation of pumps with different powers is obtained, and compared with the rated water output. Through the change data of water output and water level drop, it is inferred that the pumping well is equipped with a 2.2kw water pump. The measured water output is 228~254.4m3 / d, and the water level drop of the pumping well is 4.51~5.17m. The maximum single well water output capacity is inferred to be 760.7~942.7m3 / d; during the formal precipitation, considering the interference of the group of wells, 2.2kw and 7.5kw water pumps are staggered.

[0020] Step 1.2: Based on the existing drilling data, geotechnical engineering investigation report, engineering geology, hydrogeological conditions and retaining structure design and other related data, a geological model is established with the help of Visual MODFlow software for simulation and calculation; according to the pumping test data, the test data are sorted out, and pumping wells and observation wells are set up in the three-dimensional model. The parameters such as the pumping well filter length, layer position, pumping volume, and water inflow are substituted into the three-dimensional numerical model, and the pumping test is simulated and calculated. The calculation results are compared with the measured water level changes in the observation wells, and the relevant hydrogeological parameters are repeatedly adjusted and inverted to make the model calculation curve match the measured curve as much as possible. Finally, the permeability coefficient K of the regional confined aquifer is calculated to be 8.6m / d; the maximum impact radius of the pumping test process is 230m.

[0021] Step 1.3: Based on the data analysis of the above test wells, the single and group well pumping volume, the permeability coefficient of the confined aquifer, and the parameters of the impact range are obtained, and the number, distance, and pump power of the dewatering wells 2 in the pit-in-pit 1 area are rationally arranged and optimized, so that the groundwater level can be reduced to below the designed excavation elevation before the excavation of the pit-in-pit 1, ensuring the safety of the excavation; Among them, the mud hole diameter of precipitation well 2 is 650mm, the well pipe is a steel pipe with a diameter of 273mm and a wall thickness of 4mm, the filter pipe is a bridge filter pipe, and the filter material is medium-coarse sand, which is backfilled above the top of the filter pipe; the wells in the pit are sealed with on-site clay, and the wells outside the pit are sealed with clay balls + grouting.

[0022] Step 2: Reference Figure 1 , 3 , High-pressure jet grouting pile 3 construction: Step 2.1: After the construction of surrounding engineering piles, retaining piles and waterproof curtains is completed and reaches 80% of the design strength, high-pressure jet grouting piles 3 shall be constructed; before construction, the control points of the jet grouting piles shall be determined with a total station or GPS and marked. After the retest line is qualified, the pile positions shall be arranged on site with a steel ruler and a measuring line, and marked to ensure that the displacement deviation of the pile hole center is less than 50mm.

[0023] Step 2.2: When the pile hole is positioned, the sewage and mortar mixing system are constructed simultaneously, and then the mortar is mixed; when making the slurry, the water-cement ratio must be strictly controlled according to the design and must not be changed at will; during the rotary spraying process, the mud should be prevented from settling and the concentration should not be reduced; damp or expired cement must not be used; when the slurry is sent to the suction bucket after mixing, it should be filtered with a screen, and the filter screen hole should be smaller than 1 / 2 of the nozzle diameter.

[0024] Step 2.3: Before the drilling rig is constructed, a test spraying should be carried out on the ground first. After the drilling machine is tested and operated normally, the hole drilling can be started. During the drilling process, the number of drill rod sections should be recorded in detail to ensure the accuracy of the drilling depth. In order to ensure the length of the high-pressure rotary jet pile 3, control measures should be taken for the pile top and pile bottom elevations of the high-pressure rotary jet pile 3 respectively. By calculating the corresponding elevation and pile length, the pile bottom elevation and pile top elevation control marks are set respectively to ensure the length of the rotary jet pile.

[0025] Step 2.4: After the drilling is completed, the rotary jet grouting is carried out. At the beginning, high-pressure water is sent first, and then cement slurry and compressed air are sent. Under normal circumstances, the compressed air can be sent 30 seconds later. After rotating and spraying at the bottom of the pile for 1 minute, the rotation, lifting and spraying are carried out again. When spraying, the predetermined spraying pressure and spraying volume should be reached first, and then the grouting pipe should be gradually lifted. If a fault occurs in the middle, the lifting and rotary jetting should be stopped to prevent the pile from being interrupted. At the same time, an inspection should be carried out immediately to eliminate the fault. If insufficient slurry injection is found, which affects the designed diameter of the pile body, a review should be carried out. When the rotary jet is lifted to the designed pile top elevation, the rotary jetting is stopped, the drill bit outlet is lifted, the grouting pump and the delivery pipeline are cleaned, and then the drilling rig is moved. Among them, the diameter of the high-pressure jet grouting pile 3 is 800mm, and it uses PO 42.5 grade ordinary Portland cement, the cement dosage is 600kg / m³, the water-cement ratio of the cement slurry is determined to be 0.8, the speed during construction is increased by 15cm / min, and the rotation speed is 20r / min.

[0026] Step 3: Establishment of earthwork model of pit in pit and physical presentation of 3D printing: Step 3.1: For complex areas where pits are intertwined, such as foundation pit caps, elevator foundation pits, and water collection wells, export the BIM model created by BIM software (such as Revit) as a 3D model in .obj format according to the foundation pit cap design drawings, and then import it into slicing software (such as Cura) for slicing and export it as a .Gcode format file; then, import the generated .Gcode format file into the printing platform software to realize 3D printing of the model. During the process, set the printing speed of the 3D printer as needed, and keep the printer in a stable state and stable power supply during printing.

[0027] Step 3.2: Before excavation, the workers are given a physical briefing to let them intuitively understand the layout of the complex and staggered pit-in-pit 1 and the excavation deployment of earthworks at various elevations; during the excavation process, the management personnel will synchronously check and compare the on-site excavation situation with the model, on the one hand to guide the on-site excavation work, on the other hand to check and verify the positioning, elevation and size of the excavated earthwork.

[0028] Step 4: Layered excavation of pit 1: After the construction of the dewatering wells 2 and high-pressure rotary jet piles 3 around the deep pit area is completed, the large-scale foundation pit excavation is carried out. The soil of the pit 1 in the pit is excavated after it reaches the large-scale bottom plate surface elevation. Since there are many foundation pit elevations in the deep pit area and different foundation pit caps are staggered, the excavation principle is to excavate the earth at the lowest elevation first, then build the slope to the upper elevation, and excavate the earth layer by layer from low to high.

[0029] Step 5: Reference Figure 2 , 3 ( Figure 2 , 3 In the figure, the numbers 5 and 6 represent the cushion layer and the reinforcement of the side wall of the pit in the pit respectively); the installation of the expanded clay board side formwork 4 for the foundation pit: during the layered excavation of the pit in the pit 1, the expanded clay board side formwork 4 of the side wall of the foundation pit at the corresponding elevation is installed and supported in time; among them, the expanded clay board side formwork 4 is a 10 cm thick RLC plate, which is used as the side wall formwork of the pit in the pit such as the pedestal, sump, elevator foundation pit in the deep pit area, and is divided into two installation methods: oblique and vertical according to the excavation form of the side wall.

[0030] Step 5.1: The fixing and installation of RLC wall panels can utilize the remaining waste materials on site, short wood and short steel bars in the construction waste pool, so that the construction waste can be reused.

[0031] Step 5.2: Wall panel installation: Two people will straighten the wall panel into place, one person will hold the pry bar; after it is in place, one person will push it from one side to align it accurately; one person will pry up the wall panel with the pry bar, prying and squeezing it at the same time, and move the wall panel into the line by moving the pry bar, so that the adhesive mortar can evenly fill the joint (it is better to squeeze out the mortar). After installing the first board, temporarily fix it and continue to install the second and third boards. Apply special adhesive or mortar between the boards.

[0032] Step 5.3: Temporary fixation of wall panels: Before the strength of the adhesive or mortar is sufficient, short steel bars or wooden planks are used to support the RLC wall panels to prevent them from collapsing. The temporary support can be removed only after the adhesive or mortar solidifies, which usually takes 1 to 2 days.

[0033] Step 5.4: In the area outside the deep pit where high-pressure rotary grouting is reinforced, vertical excavation is used instead of slope excavation. During the excavation process, the expanded clay board side formwork 4 is installed in time to reduce the workload of slope excavation and the amount of concrete used for the side walls of the foundation pit in the later stage.

[0034] Step 5.5: After the wall panels are installed, use the prepared cement mortar to fill the board joints and under the boards. Before filling the cement mortar under the boards, remove the debris under the boards.

[0035] The embodiments are preferred implementations of the present invention, but the present invention is not limited to the above-mentioned implementations. Any obvious improvements, substitutions or modifications that can be made by those skilled in the art without departing from the essential content of the present invention belong to the protection scope of the present invention.

Claims

1. A method for excavating deep and large pits in a staggered arrangement under complex floodplain geology. It is characterized in that The process includes the following: Step 1: Precipitation test and pit-in-pit (1) Optimization of precipitation scheme; Step 2: Construction of high pressure jet grouting piles (3); Step 3: Establish the earthwork model of the pit in the pit and hand over the 3D printing object; Step 4: Pit within a pit (1) Excavation of earthwork in layers; Step 5: Install the side formwork (4) of the foundation pit expanded clay board.

2. The earthwork excavation construction method for deep and large pits arranged in a staggered manner under complex floodplain geology according to claim 1, It is characterized in that The specific process of step 1 is as follows: Step 1.1: Analyze the actual water output of single wells and groups of wells under the operation of water pumps with different powers according to the measured data, and compare it with the rated water output. Determine the water pumps configured for the pumping wells and the maximum water output capacity of a single well through the change data of water output and water level drop. When officially lowering the water level, consider the interference effect of the group of wells and stagger the configuration of water pumps of different models. Step 1.2: Set up pumping wells and observation wells in the three-dimensional model, substitute the parameters of the pumping wells including filter length, layer position, pumping volume, and water inflow into the three-dimensional numerical model, simulate the pumping test, compare the calculation results with the measured water level changes in the observation wells, repeatedly adjust and invert the relevant hydrogeological parameters, so that the model calculation curve coincides with the measured curve, and finally calculate the permeability coefficient of the regional confined aquifer and the maximum impact radius of the pumping test process; Step 1.3: Based on the data analysis of the above test wells, the pumping volume of single and group wells, the permeability coefficient of the confined aquifer, and the parameters of the impact range are obtained to optimize the layout of the number, distance, and pump power of the precipitation wells (2) in the pit-in-pit (1) area.

3. The earthwork excavation construction method for deep and large pits arranged in a staggered manner under complex floodplain geology according to claim 2, It is characterized in that The mud hole diameter of the precipitation well (2) is 650 mm, the well pipe is a steel pipe with a pipe diameter of 273 mm and a wall thickness of 4 mm, the filter pipe is a bridge filter pipe, and the filter material is medium-coarse sand, which is backfilled to above the top of the filter pipe; the well in the pit is sealed with site clay, and the well outside the pit is sealed with clay balls + grouting.

4. The earthwork excavation construction method for deep and large pits in a complex floodplain geology arranged in a staggered manner according to claim 1, It is characterized in that The specific process of step 2 is as follows: Step 2.1: After the construction of surrounding engineering piles, retaining piles, and water-blocking curtains is completed and reaches 80% of the design strength, high-pressure jet grouting piles (3) shall be constructed. Before construction, the control points of the jet grouting piles shall be measured with a total station or GPS and marked. After the retest line is qualified, the pile positions shall be arranged on site with a steel ruler and a measuring line and marked. Step 2.2: The sewage and mortar mixing system are built synchronously with the pile hole positioning, and then the mortar is mixed. After the slurry is mixed, it is sent to the slurry suction bucket and filtered with a screen; Step 2.3: First, test grouting on the ground, and after the drilling machine is tested and running normally, start the pilot hole drilling; during the drilling process, record the number of drill rod sections, and take control measures for the pile top and pile bottom elevations of the high-pressure rotary grouting pile (3), respectively, and set the pile bottom elevation and pile top elevation control marks by calculating the corresponding elevation and pile length, so as to ensure the pile length of the high-pressure rotary grouting pile (3); Step 2.4: After the drilling is completed, rotary jet grouting is carried out. First, high-pressure water is sent, then cement slurry and compressed air are sent. After rotating and spraying at the bottom of the pile for a period of time, it is rotated, lifted and sprayed again. When spraying, first reach the predetermined spraying pressure and spraying volume and then gradually lift the grouting pipe. When the rotary jet is lifted to the designed pile top elevation, stop the rotary jet, lift the drill outlet, clean the grouting pump and delivery pipeline, and move the drilling rig.

5. The earthwork excavation construction method for deep and large pits in a staggered arrangement under complex floodplain geology according to claim 4, It is characterized in that The high-pressure jet grouting pile (3) has a diameter of 800 mm and uses PO 42.5 grade ordinary Portland cement, with a cement dosage of 600 kg / m³ and a water-cement ratio of the cement slurry of 0.

8. The speed during construction is increased by 15 cm / min and the rotation speed is 20 r / min.

6. The earthwork excavation construction method for deep and large pits in a staggered arrangement under complex floodplain geology according to claim 1, It is characterized in that The specific process of step 3 is as follows: Step 3.1: For the complex area of ​​pit-in-pit (1), export the BIM model created by the BIM software into a 3D model in .obj format according to the foundation foundation design drawing, then import it into the slicing software for slicing and export it into a .Gcode format file. Then import the file into the printing platform software to realize 3D printing of the model; Step 3.2: Before excavation, the workers are given a physical briefing to let them know the layout of the pit within the pit (1) and the excavation deployment of the earthwork at each elevation. During the excavation process, the management personnel will simultaneously check and compare the on-site excavation situation with the model to guide the on-site excavation work and check and verify the positioning, elevation and size of the excavated earthwork.

7. The earthwork excavation construction method of deep and large pits in a complex floodplain geology arranged in a staggered manner according to claim 1, It is characterized in that The specific process of step 4 is as follows: After the construction of the drainage wells (2) and high-pressure jet grouting piles (3) around the deep pit area is completed, the large-scale foundation pit is excavated. The soil of the pit-in-pit (1) is excavated after it reaches the elevation of the large-scale bottom plate surface. The excavation principle is to first excavate the soil at the lowest elevation, then build the slope to the upper level, and then excavate the soil layer by layer from low to high.

8. The earthwork excavation construction method for deep and large pits in a staggered arrangement under complex floodplain geology according to claim 1, It is characterized in that The specific process of step 5 is as follows: Two persons straighten the side formwork (4) of the ceramsite board into position, one person holds a pry bar, and after it is in position, one person pushes on one side to accurately align the line, and one person pries up the side formwork (4) of the ceramsite board with a pry bar, prying and squeezing at the same time, and moves the side formwork (4) of the ceramsite board into the line by moving the pry bar, and uses adhesive mortar to evenly fill the joints, and after the first board is installed, it is temporarily fixed, and other boards are installed continuously, and special adhesive or mortar is applied between the boards; after the installation of the side formwork (4) of the ceramsite board is completed, cement mortar is used to fill the board joints and under the board; When the ceramsite board side formwork (4) is temporarily fixed, short steel bars or wooden planks are used to support the ceramsite board side formwork (4) to prevent collapse, and the temporary support is removed after the adhesive or mortar solidifies; in the area outside the deep pit where high-pressure rotary jet reinforcement is applied, vertical excavation is used instead of slope excavation, and the ceramsite board side formwork (4) is installed in time during the excavation process, thereby reducing the workload of slope excavation and the amount of concrete used for the side wall of the foundation pit in the later stage.

9. The earthwork excavation construction method for deep and large pits arranged in a staggered manner under complex floodplain geology according to claim 8, It is characterized in that The ceramsite board side formwork (4) is a 10 cm thick RLC board, which is used as a pit-in-pit sidewall formwork in a deep pit area. It is installed in two ways: oblique and vertical according to the sidewall excavation form.