Direct-current electric arc furnace for waste catalyst treatment

By setting up a multi-stage cooling water circulation assembly and lifting frame in a DC arc furnace, the problems of insufficient liner thickness and cooling are solved, the cooling and service life of the liner are achieved, and the efficiency of precious metal recycling is improved.

CN119085305APending Publication Date: 2024-12-06ZHUZHOU FLASHLIGHT IND FURNACE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411402430.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing DC arc furnace has a large lining thickness and lacks water cooling function, which leads to high manufacturing cost and short service life, making it difficult to efficiently cool, affecting the efficiency of precious metal recycling.

Method used

The first, second and third cooling water circulation components are designed, including a top-down and independent multi-stage cooling water system. By setting cooling chambers and valve tubes on the side walls, top and bottom of the arc furnace body, the effective cooling of the furnace lining is achieved. , and adjust the electrode rod height and stirring teeth through the lifting frame and transmission assembly to improve the heating uniformity of the material.

Benefits of technology

It improves the cooling effect of the furnace lining, reduces the thickness of the furnace lining, extends the service life, and improves the uniformity of material stirring and the efficiency of precious metal recycling.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119085305A_ABST
    Figure CN119085305A_ABST
Patent Text Reader

Abstract

The invention discloses a waste catalyst treatment direct-current electric arc furnace which comprises an adjusting base and an electric arc furnace body arranged on the adjusting base, and the electric arc furnace body is composed of a furnace body and a furnace cover. Wherein the furnace body is composed of a furnace bottom, a furnace lining, a slag discharge port, a discharge port and a first cooling water circulation assembly, the slag discharge port and the discharge port are formed in the two sides of the lower portion of the furnace lining respectively, the first cooling water circulation assembly is arranged on the periphery of the furnace lining, and the first cooling water circulation assembly comprises multiple sections of independent cooling water systems from top to bottom; the furnace cover comprises a cover body, and a first feed port, a second feed port, a third feed port and an exhaust pipe which are arranged on the cover body, and further comprises a second cooling water circulation assembly arranged on the cover body. The electric arc furnace body is cooled through the first cooling water circulation assembly, the second cooling water circulation assembly and the third cooling water circulation assembly, the first cooling water circulation assembly comprises multiple sections of independent cooling water systems from top to bottom, the cooling effect of the furnace lining is improved through the design, the thickness of the furnace lining is reduced, and the service life of the furnace lining is prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of electric arc furnaces, in particular to a direct current electric arc furnace for treating waste catalysts. Background Art

[0002] A DC arc furnace is an arc furnace that uses direct current as energy. Like an AC arc furnace, it uses the arc generated between the electrode and the charge (or molten pool) to generate heat, thereby achieving the purpose of smelting.

[0003] Recover precious metals from waste catalysts containing precious metals to complete secondary recycling of precious metals. However, the lining of the existing DC arc furnace is made of a number of bricks stacked together. The brick stacking is thick and high, and there is no water cooling function. The lining has limited high temperature resistance, which leads to high manufacturing costs and short service life of the lining. Summary of the invention

[0004] The object of the present invention is to provide a DC arc furnace for treating waste catalysts. The present invention realizes cooling of the side walls and the top and bottom of the arc furnace body by setting up the first, second and third cooling water circulation components. This design ensures the cooling effect of the device. In addition, the first cooling water circulation component includes a top-down and independent multi-stage cooling water system. This design not only improves the cooling effect of the furnace lining, but also reduces the thickness of the furnace lining, thereby extending the service life of the furnace lining.

[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a waste catalyst treatment DC arc furnace, comprising: an adjusting base, an arc furnace body arranged on the adjusting base, the arc furnace body consisting of a furnace body and a furnace cover; wherein the furnace body consists of a furnace bottom, a furnace lining, a slag discharge port and a material discharge port respectively arranged on both sides of the lower part of the furnace lining, and a first cooling water circulation component arranged on the periphery of the furnace lining, the first cooling water circulation component comprising a top-down and independent multi-stage cooling water system; the furnace cover comprises a cover body, and a first feed port, a second feed port, a third feed port, and an exhaust pipe arranged on the cover body, and also comprises a second cooling water circulation component arranged on the cover body; a lifting frame body arranged on the outer wall of the furnace lining; and an electric pole rod assembly passing through the middle of the furnace cover; and also comprises a stirring assembly arranged on the furnace bottom, when the lifting frame body is in operation, it can drive the electric shock rod assembly to achieve height adjustment, and at the same time, the transmission assembly drives the stirring assembly to complete the stirring of the material in the furnace body.

[0006] Preferably, each group of the cooling water system includes a first cooling cavity arranged at the periphery of the furnace lining, and a first water inlet valve pipe and a first water outlet valve pipe respectively arranged at the upper and lower parts of the first cooling cavity.

[0007] Preferably, the second cooling water circulation component includes a second water inlet valve pipe installed on the top of the cover body and connected to the annular channel provided in the cover body, and a plurality of second drain valve pipes staggeredly installed on the surface of the cover body and connected to the annular channel, wherein one end of the plurality of second drain valve pipes away from the annular channel is placed below the second water inlet valve pipe.

[0008] Preferably, a third cooling water circulation component is also provided at the bottom of the furnace bottom, and the third cooling water circulation component includes a second cooling cavity provided at the furnace bottom, and a third water inlet valve pipe and a third water outlet valve pipe provided at the bottom of the furnace bottom and connected to the second cooling cavity.

[0009] Preferably, the lifting frame body includes an electric slide rail and an electric slider slidably installed inside the electric slide rail, and a support plate is fixed to the side wall of the electric slider; it also includes a bracket arranged on the end of the support plate away from the electric slider, and the electrode rod assembly is installed at the bottom end of the bracket.

[0010] Preferably, the electrode rod assembly includes a mounting plate fixed at the bottom end of the bracket, and a plurality of electric cylinders arranged in the middle of the mounting plate, the telescopic ends of the plurality of electric cylinders passing downward through a through hole opened in the middle of the cover body and extending toward the interior of the furnace body; and also includes an electrode rod body fixed at the telescopic end of each of the electric cylinders.

[0011] Preferably, the stirring assembly includes a plurality of pillars rotatably connected to the upper surface of the furnace bottom, the plurality of pillars are connected to the furnace bottom via torsion springs and correspond one-to-one to a plurality of electrode rod bodies; and stirring teeth arranged on the periphery of each of the pillars.

[0012] Preferably, the transmission assembly includes a connecting rod fixed at the lower part of each electrode rod body, and a wedge block arranged at the outer end of the connecting rod; it also includes a transmission column fixed at the upper part of each support, and the transmission column is in contact with the wedge surface where the corresponding wedge block is located.

[0013] Preferably, the adjustment base includes a support, and a rotating shaft arranged on one side of the support, the rotating shaft is placed below the discharge port and is fixed to the bottom of the furnace body through a first mounting frame arranged thereon; it also includes a transmission slide groove opened on the other side of the support, a transmission slider arranged in the transmission slide groove, a step platform is fixed on the top, a mounting piece is slidably mounted on the step surface where the step platform is located, and a second mounting frame rotatably mounted on the mounting piece, the second mounting frame is fixed to a side of the furnace body away from the first mounting frame; it also includes a plurality of electric push rods installed at the bottom of the support, the plurality of electric push rods are fixedly connected to the step platform through connecting blocks fixed at their telescopic ends and serve as a driving source for movement of the step platform.

[0014] Preferably, a temperature sensor is also provided on the furnace cover.

[0015] Compared with the prior art, the present invention has the following beneficial effects:

[0016] 1. The present invention realizes cooling of the side walls and the top and bottom of the arc furnace body by setting up the first, second and third cooling water circulation components. This design ensures the cooling effect of the device. In addition, the first cooling water circulation component includes a top-down and independent multi-stage cooling water system. This design not only improves the cooling effect of the furnace lining, but also reduces the thickness of the furnace lining, thereby extending the service life of the furnace lining.

[0017] 2. As other embodiments of the present invention, when the electric push rod is driven to extend, the platform can move in the direction away from the rotating shaft. When it moves to the right, the mounting member moves to the left relative to the platform, so that the position of the first mounting frame is higher than the second mounting frame. The furnace body as a whole is offset toward the slag discharge port to facilitate slag discharge at the slag discharge port. When the electric push rod is shortened, the first mounting frame is lower than the second mounting frame, and the device as a whole is deflected toward the discharge port to facilitate discharge of materials at the discharge port.

[0018] 3. The electrode rod assembly of the present invention is designed to achieve height adjustment through a lifting frame, and the electrode rod body is further moved longitudinally through an electric cylinder. The electrode rod body is further lifted and lowered to achieve the rotation of the support. When the height of the electrode rod body is adjusted, the stirring teeth complete the stirring process, thereby increasing the uniformity of heating of the material. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the three-dimensional structure from a first viewing angle of the present invention;

[0020] Figure 2 is a schematic diagram of a second viewing angle stereoscopic structure of the present invention;

[0021] Figure 3 It is a schematic diagram of the third perspective of the present invention;

[0022] Figure 4 is a schematic diagram of a third perspective structure of the present invention;

[0023] Figure 5 It is a front view structural schematic diagram of the present invention;

[0024] Figure 6 It is a schematic diagram of the cross-sectional structure of the present invention;

[0025] Figure 7 It is a schematic diagram of the enlarged structure of the electrode rod assembly and the stirring assembly;

[0026] Figure 8 for Figure 7 Another perspective structural diagram of .

[0027] In the figure: 1. Adjustment base; 101. Support; 102. Rotating shaft; 103. Transmission slide; 104. Transmission slide block; 105. Electric push rod; 106. First mounting frame; 107. Second mounting frame; 108. Ladder; 109. Mounting piece; 2. Furnace body; 3. Furnace cover; 4. Slag discharge port; 5. Discharge port; 6. First cooling water circulation assembly; 601. First cooling chamber; 602. First water inlet valve pipe; 603. First water outlet valve pipe; 7. Second cooling water circulation assembly; 701. Second Inlet valve pipe; 702, second drain valve pipe; 8, lifting frame; 801, electric slide rail; 802, electric slider; 803, support plate; 804, bracket; 9, electrode rod assembly; 901, mounting plate; 902, electric cylinder; 903, electrode rod body; 904, connecting rod; 905, wedge block; 906, support column; 907, transmission column; 908, stirring teeth; 10, first feed port; 11, second feed port; 12, third feed port; 13, exhaust pipe; 14, temperature sensor. DETAILED DESCRIPTION

[0028] In the description of the present invention, it should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as limiting the present invention. The following describes various embodiments of the present invention in detail in conjunction with the drawings.

[0029] Example 1

[0030] See also Figures 1 to 8 The present invention preferably provides a technical solution: a waste catalyst treatment DC arc furnace, comprising: an adjusting base 1, an arc furnace body arranged on the adjusting base 1, the arc furnace body consisting of a furnace body 2 and a furnace cover 3; wherein the furnace body 2 is composed of a furnace bottom, a furnace lining, a slag discharge port 4 and a discharge port 5 respectively arranged on both sides of the lower part of the furnace lining, and a first cooling water circulation component 6 arranged on the periphery of the furnace lining, and the first cooling water circulation component 6 includes a top-down and independent multi-stage cooling water system; the furnace cover 3 includes a cover body, and a first feed port 10, a second feed port 11, a third feed port 12, and an exhaust pipe 13 arranged on the cover body, and also includes a second cooling water circulation component 7 arranged on the cover body; a lifting frame 8 arranged on the outer wall of the furnace lining; and an electric pole rod assembly 9 that runs through the middle of the furnace cover 3; and also includes a stirring component arranged at the furnace bottom, when the lifting frame 8 is in operation, it can drive the electric shock rod assembly to achieve height adjustment, and at the same time, the transmission assembly drives the stirring assembly to complete the stirring of the material in the furnace body 2.

[0031] As is known, the purpose of a DC electric arc furnace is to recover precious metals from waste catalysts containing precious metals and complete the secondary recycling of precious metals. Specifically, the materials required include precious metal secondary resource materials, waste catalysts containing precious metals, collectors and auxiliary materials, which are fed in proportion. Here, the first feed port 10, the second feed port 11 and the third feed port 12 where the furnace cover 3 is located are used for feeding materials, and the slag discharge port 4 and the discharge port 5 where the furnace body 2 is located are used for discharging waste slag and precious metals, respectively. Figure 1 , 3 As shown in Figures 4 and 6, the operation mode of the electric arc furnace is as follows: after the material is added into the DC electric arc furnace, the material adding amount is 3-5t per furnace, the material is melted under the condition of 1500-1700℃ in the electric arc furnace, the precious metal enters the collector, the slag is discharged into the slag bag from the slag discharge port 4, the next batch of material is added, after multiple captures, the total amount of precious metals in the collector reaches a certain content, and the precious metal alloy is discharged from the discharge port 5 to form an ingot;

[0032] The design highlights of the present invention are as follows: the furnace body 2 and the furnace cover 3 are made of high-temperature resistant materials and are integrally cast, which effectively reduces the manufacturing cost, and the first cooling water circulation component 6 and the second cooling water circulation component 7 are respectively arranged on the outer surfaces of the furnace lining and the furnace cover 3, which can realize the cooling process of the two independently controlled. This design ensures the cooling effect of the device. In addition, the first cooling water circulation component 6 includes a top-down and independent multi-stage cooling water system. This design not only improves the cooling effect of the furnace lining, but also reduces the thickness of the furnace lining, thereby extending the service life of the furnace lining.

[0033] Furthermore, each cooling water system includes a first cooling cavity 601 arranged at the periphery of the furnace lining, and a first water inlet valve pipe 602 and a first water outlet valve pipe 603 respectively arranged at the upper and lower parts of the first cooling cavity 601 .

[0034] Combination Figure 3 , 4 As shown in FIG. 6 , the first cooling chamber 601 here surrounds the furnace lining to achieve a local cooling process of the furnace lining.

[0035] Furthermore, the second cooling water circulation component 7 includes a second water inlet valve pipe 701 installed on the top of the cover body and connected to the annular channel provided in the cover body, and a plurality of second drain valve pipes 702 staggeredly installed on the surface of the cover body and connected to the annular channel, wherein one end of the plurality of second drain valve pipes 702 away from the annular channel is placed below the second water inlet valve pipe 701.

[0036] Combination Figure 7 As shown, the second water inlet valve pipe 701 and the second drain valve pipe 702 are arranged on one side of the cover body to facilitate the water filling and draining process.

[0037] Furthermore, a third cooling water circulation assembly is also provided at the bottom of the furnace, and the third cooling water circulation assembly includes a second cooling cavity provided at the bottom of the furnace, and a third water inlet valve pipe and a third water outlet valve pipe provided at the bottom of the furnace and connected to the second cooling cavity.

[0038] This design further realizes the cooling of the bottom of the arc furnace, combined with Figure 5 As shown, under the action of the first, second and third cooling water circulation components, the device can realize the cooling process of the side walls, top and bottom of the electric arc furnace to improve the cooling effect of the electric arc furnace body.

[0039] Example 2

[0040] As another embodiment of the present invention, the lifting frame body 8 includes an electric slide rail 801, and an electric slider 802 slidably installed inside the electric slide rail 801, and a support plate 803 is fixed to the side wall of the electric slider 802; it also includes a bracket 804 arranged on the end of the support plate 803 away from the electric slider 802, and the electrode rod assembly 9 is installed at the bottom end of the bracket 804.

[0041] Here, the electrode rod assembly is connected to the electric slider 802 through the bracket 804 and the support plate 803. Therefore, when the electric slider 802 is driven to move longitudinally inside the electric slide rail 801, the height of the electrode rod assembly can be adjusted. Figure 3 As shown, the setting of the arc length is achieved by playing.

[0042] Furthermore, the electrode rod assembly 9 includes a mounting plate 901 fixed at the bottom end of the bracket 804, and a plurality of electric cylinders 902 arranged in the middle of the mounting plate 901, and the telescopic ends of the plurality of electric cylinders 902 pass downward through the through hole opened in the middle of the cover body and extend toward the inside of the furnace body 2; it also includes an electrode rod body 903 fixed at the telescopic end of each electric cylinder 902, further, the stirring assembly includes a plurality of pillars 906 rotatably connected to the upper surface of the furnace bottom, the plurality of pillars 906 are connected to the furnace bottom with torsion springs and correspond one-to-one to the plurality of electrode rod bodies 903; and stirring teeth 908 arranged on the periphery of each pillar 906, further, the transmission assembly includes a connecting rod 904 fixed at the lower part of each electrode rod body 903, and a wedge block 905 arranged at the outer end of the connecting rod 904; it also includes a transmission column 907 fixed at the upper part of each pillar 906, and the transmission column 907 is in contact with the wedge surface where the corresponding wedge block 905 is located.

[0043] Combination Figure 3 , 7As shown in FIG. 8 , the electrode rod assembly and the stirring assembly are connected via a transmission assembly, and the electrode rod body 903 where the electrode rod assembly is located is connected at its top to the corresponding electric cylinder 902, and its lower part is connected to a wedge 905 via a connecting rod 904, and the wedge 905 is in contact with a transmission column 907 at the upper part of the support 906. Here, the electrode rod assembly as a whole is height-adjusted via a lifting frame 8, and the electrode rod body 903 is further longitudinally moved via the electric cylinder 902, and the electrode rod body 903 is further lifted to realize the rotation of the support 906, so that when the height of the electrode rod body 903 is adjusted, the stirring teeth 908 complete the stirring process, thereby increasing the uniformity of material mixing.

[0044] Example 3

[0045] As other embodiments of the present invention, the adjusting base 1 includes a support 101, and a rotating shaft 102 arranged on one side of the support 101, the rotating shaft 102 is placed below the discharge port 5 and is fixed to the bottom of the furnace body 2 through a first mounting frame 106 arranged thereon; it also includes a transmission slide 103 opened on the other side of the support 101, a transmission slider 104 arranged in the transmission slide 103, a step platform 108 is fixed on the top of the transmission slide 103, a mounting member 109 is slidably mounted on the step surface where the step platform 108 is located, and a second mounting frame 107 rotatably mounted on the mounting member 109, the second mounting frame 107 is fixed to a side of the furnace body 2 away from the first mounting frame 106; it also includes a plurality of electric push rods 105 installed at the bottom of the support 101, the plurality of electric push rods 105 are fixedly connected to the step platform 108 through connecting blocks fixed at their telescopic ends and serve as a driving source for the movement of the step platform 108.

[0046] Combination Figure 1 , 2 5, a rotating shaft 102 and a step 108 are respectively installed on both sides of the support 101, and the rotating shaft 102 is fixed to one side of the bottom of the furnace body 2 through a first mounting frame 106 arranged thereon, and the step 108 slides on the support 101 at its bottom through a transmission slider 104 and a transmission slide groove 103, and its top is connected to the other side of the bottom of the furnace body 2 through a mounting piece 109 and a second mounting frame 107. It is worth noting that the discharge port 5 and the slag discharge port 4 are arranged on both sides of the furnace lining and correspond to the positions of the first mounting frame 106 and the second mounting frame 107. Figure 5 When the electric push rod 105 is driven to extend, the platform 108 can move away from the rotating shaft 102, that is, it moves to the right. At the same time, the mounting member 109 moves to the left relative to the platform 108, so that the first mounting frame 106 is higher than the second mounting frame 107, and the furnace body as a whole is offset toward the slag discharge port 4 to facilitate slag discharge at the slag discharge port 4. When the electric push rod 105 is shortened, the first mounting frame 106 is lower than the second mounting frame 107, and the device as a whole is deflected toward the discharge port 5 to facilitate the discharge of materials at the discharge port 5.

[0047] Furthermore, a temperature sensor 14 is also provided on the furnace cover 3. Figure 3 As shown, the temperature sensor 14 can be used to detect the temperature of the arc furnace body in real time, and control the circulating cooling water cooling to control the furnace lining temperature within a corresponding stable range.

[0048] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. There are many ways of detachable installation, for example, it can be through the method of plug-in and snap-on matching, and for example, through the method of bolt connection, etc.

[0049] The above clearly and completely describes the concept, specific structure and technical effects of the present invention in combination with the embodiments and drawings, so as to fully understand the purpose, characteristics and effects of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, other embodiments obtained by technicians in this field without creative work are all within the scope of protection of the present invention. In addition, all the connection / connection relationships mentioned in the text do not refer to the direct connection of components, but refer to the fact that a better connection structure can be formed by adding or reducing connection accessories according to the specific implementation situation.

[0050] The specific description of the present invention in the above embodiments is only used to further illustrate the present invention and cannot be understood as limiting the scope of protection of the present invention. Technical engineers in this field may make some non-essential improvements and adjustments to the present invention based on the contents of the above invention, which fall within the scope of protection of the present invention.

Claims

1. A DC arc furnace for treating spent catalyst, It is characterized in that include: An adjusting base (1), an arc furnace body arranged on the adjusting base (1), the arc furnace body consisting of a furnace body (2) and a furnace cover (3); The furnace body (2) is composed of a furnace bottom, a furnace lining, a slag discharge port (4) and a material discharge port (5) respectively arranged on both sides of the lower part of the furnace lining, and a first cooling water circulation component (6) arranged on the periphery of the furnace lining, and the first cooling water circulation component (6) includes a multi-stage cooling water system that is independent from top to bottom; The furnace cover (3) comprises a cover body, and a first feed port (10), a second feed port (11), a third feed port (12), and an exhaust pipe (13) arranged on the cover body, and also comprises a second cooling water circulation component (7) arranged on the cover body; A lifting frame (8) arranged on the outer wall of the furnace lining; and an electrode rod assembly (9) penetrating the middle of the furnace cover (3); It also includes a stirring assembly arranged at the bottom of the furnace. When the lifting frame (8) is in operation, it can drive the electric shock rod assembly to achieve height adjustment. At the same time, the transmission assembly drives the stirring assembly to complete the stirring of the materials in the furnace body (2).

2. A DC arc furnace for treating spent catalyst according to claim 1, Features: Each group of the cooling water system comprises a first cooling cavity (601) arranged on the periphery of the furnace lining, and a first water inlet valve pipe (602) and a first water outlet valve pipe (603) respectively arranged at the upper and lower parts of the first cooling cavity (601).

3. A DC arc furnace for treating spent catalyst according to claim 1, Features: The second cooling water circulation component (7) comprises a second water inlet valve pipe (701) installed on the top of the cover body and connected to the annular channel provided in the cover body, and a plurality of second water discharge valve pipes (702) staggeredly installed on the surface of the cover body and connected to the annular channel, wherein one end of the plurality of second water discharge valve pipes (702) away from the annular channel is placed below the second water inlet valve pipe (701).

4. A DC arc furnace for treating spent catalyst according to claim 1, Features: A third cooling water circulation assembly is also provided at the bottom of the furnace bottom, and the third cooling water circulation assembly includes a second cooling cavity provided at the furnace bottom, and a third water inlet valve pipe and a third water outlet valve pipe provided at the bottom of the furnace bottom and connected to the second cooling cavity.

5. A DC electric arc furnace for treating spent catalyst according to claim 1, Features: The lifting frame (8) comprises an electric slide rail (801) and an electric slider (802) slidably mounted inside the electric slide rail (801), and a support plate (803) is fixed to the side wall of the electric slider (802); It also includes a bracket (804) arranged at the end of the support plate (803) away from the electric slider (802), and the electrode rod assembly (9) is installed at the bottom end of the bracket (804).

6. A DC electric arc furnace for treating spent catalyst according to claim 5, Features: The electrode rod assembly (9) comprises a mounting plate (901) fixed at the bottom end of the bracket (804), and a plurality of electric cylinders (902) arranged in the middle of the mounting plate (901), and the telescopic ends of the plurality of electric cylinders (902) pass downward through a through hole opened in the middle of the cover body and extend toward the inside of the furnace body (2); It also includes an electrode rod body (903) fixed to the telescopic end of each electric cylinder (902).

7. A DC electric arc furnace for treating spent catalyst according to claim 1, Features: The stirring assembly comprises a plurality of pillars (906) rotatably connected to the upper surface of the furnace bottom, the plurality of pillars (906) being connected to the furnace bottom via torsion springs and corresponding one to one with the plurality of electrode rod bodies (903); And stirring teeth (908) are arranged on the periphery of each of the pillars (906).

8. A DC arc furnace for treating spent catalyst according to claim 7, Features: The transmission assembly includes a connecting rod (904) fixed at the lower part of each electrode rod body (903), and a wedge block (905) arranged at the outer end of the connecting rod (904); and also includes a transmission column (907) fixed at the upper part of each support (906), and the transmission column (907) is in contact with the wedge surface of the corresponding wedge block (905).

9. A DC electric arc furnace for treating spent catalyst according to claim 1, Features: The adjusting base (1) comprises a support (101) and a rotating shaft (102) arranged on one side of the support (101); the rotating shaft (102) is placed below the discharge port (5) and is fixed to the bottom of the furnace body (2) via a first mounting frame (106) arranged thereon; It also includes a transmission slide groove (103) provided on the other side of the support (101), a transmission slider (104) provided in the transmission slide groove (103), a ladder platform (108) fixed on the top thereof, a mounting member (109) slidably mounted on the ladder surface where the ladder platform (108) is located, and a second mounting frame (107) rotatably mounted on the mounting member (109), the second mounting frame (107) being fixed to a side of the furnace body (2) away from the first mounting frame (106); It also includes a plurality of electric push rods (105) installed at the bottom of the support (101), wherein the plurality of electric push rods (105) are fixedly connected to the ladder platform (108) through connecting blocks fixed at their telescopic ends and serve as a driving source for the movement of the ladder platform (108).