Small-section rectangular steel pipe structure facilitating pouring of high-strength self-compacting concrete
By opening pouring holes and ventilation holes in the small-section rectangular steel tube structure of high-strength self-compacting concrete, and using a special pouring mechanism, the problem that traditional pouring methods cannot achieve high strength is solved, and the one-time pouring of concrete and the high structure are achieved. The strength ensures the stable connection of steel pipes and the smooth exhaust of concrete.
Patent Information
- Application Number
- CN202323098873.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-16
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-11-16
AI Technical Summary
In the existing technology, the small-section rectangular steel tube structure of high-strength self-compacting concrete cannot adopt the traditional top-down pouring method due to its flat structure, resulting in the inability to achieve high-strength effects.
A structure including a pouring mechanism, a flat steel pipe and a base is designed. By opening pouring holes and ventilation holes on the sides of the flat steel pipe, combined with components such as the delivery pump, the first pump pipe, hoses, connectors and ground pumps, Realize the one-time pouring of concrete and the connection of multiple steel pipes to ensure the high strength and structural integrity of the concrete.
It realizes one-time pouring of concrete, avoids joints between concrete layers, improves the integrity and strength of the structure, and ensures the stable connection of steel pipes and smooth concrete connection through the setting of components such as connectors and wear-resistant sheets. Exhaust air improves the efficiency and stability of the pouring process.
Smart Images

Figure CN221799199U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of concrete pouring, in particular to a small-section rectangular steel pipe structure which is convenient for pouring high-strength self-compacting concrete. Background Art
[0002] Concrete technology is a discipline about the preparation, construction and performance optimization of concrete materials. Concrete is a composite material composed of cement, aggregate, water and admixture (mixed in a certain proportion. It is often used in the construction of buildings, foundations, roads, bridges and other structures. Steel pipe structures are required in the pouring process of self-compacting concrete. In the prior art, for the small-section rectangular steel pipe structure of high-strength self-compacting concrete, a flat rectangular structure is used for a cross-sectional area that is too small to adopt the traditional top-down pouring method. Because the cross-section is relatively flat, the pouring pipe cannot be extended into the end of the steel pipe, so the current high-strength self-compacting effect cannot be achieved. Therefore, a small-section rectangular steel pipe structure that is convenient for pouring high-strength self-compacting concrete is now proposed. Utility Model Content
[0003] In order to improve the small-section rectangular steel pipe structure for high-strength self-compacting concrete, a flat rectangular structure is used. The cross-sectional area is too small to adopt the traditional top-down pouring method. Because the cross-section is relatively flat, the pouring pipe cannot be extended into the end of the steel pipe, and thus the current high-strength self-compacting effect cannot be achieved. The utility model provides a small-section rectangular steel pipe structure that is convenient for pouring high-strength self-compacting concrete.
[0004] The utility model provides a small-section rectangular steel pipe structure that is convenient for pouring high-strength self-compacting concrete, and adopts the following technical solutions:
[0005] A small-section rectangular steel pipe structure convenient for pouring high-strength self-compacting concrete, comprising a pouring mechanism, a flat steel pipe and a base, wherein the pouring mechanism includes a delivery pump, a first pump pipe, a hose and a connector;
[0006] The delivery pump is fixedly installed on the top of the base, the first pump pipe is fixedly connected to one side of the delivery pump, the hose sleeve is connected to the end of the first pump pipe, and the connector sleeve is connected to the end of the hose;
[0007] A casting hole is provided on one side of the flat steel pipe, and a ventilation hole is provided on the surface of the flat steel pipe and at the bottom of the casting hole. The cross-sectional diameters of the hose and the first pump pipe are both 80 mm.
[0008] By adopting the above technical solution, by opening a pouring hole on the side of the flat steel pipe, concrete can be easily injected into the flat steel pipe. This design can realize one-time pouring of concrete, avoid the joints between concrete layers, and improve the integrity and strength of the structure. By setting air holes, the inside of the flat steel pipe can be connected to the external air to ensure that the gas in the concrete can be discharged smoothly.
[0009] Optionally, a first connecting piece is fixedly mounted on one end of the flat steel tube, and a second connecting piece is movably mounted on the bottom of the first connecting piece.
[0010] By adopting the above technical solution, a plurality of flat steel tubes can be easily connected by providing a first connecting member and a second connecting member.
[0011] Optionally, wear-resistant sheets are movably mounted on both sides of the surface of the first connecting member, and threaded holes are formed on the surfaces of the wear-resistant sheets.
[0012] By adopting the above technical solution and providing the wear-resistant sheet, it is possible to effectively prevent the locking screw from causing wear to the surface of the first connecting member after installation.
[0013] Optionally, the threaded hole passes through the inner wall of the second connecting member, and a locking screw is threadedly installed in the inner cavity of the threaded hole.
[0014] By adopting the above technical solution, the user can fix the first connecting member and the second connecting member conveniently through the provision of the locking screw and the threaded hole.
[0015] Optionally, a reinforcement piece is fixedly mounted on the inner side of the wear-resistant plate, and limiting plates are fixedly mounted on both sides of the wear-resistant plate.
[0016] By adopting the above technical solution, the user can reinforce the wear-resistant sheet by setting the reinforcement piece, and the user can limit the wear-resistant sheet by setting the limiting plate.
[0017] Optionally, a second pump pipe is fixedly connected to the other side of the delivery pump, and a ground pump is fixedly connected to the end of the second pump pipe.
[0018] By adopting the above technical solution, the high-strength self-compacting concrete inside the concrete truck can be effectively pumped to the second pump pipe through the operation of the ground pump, and finally poured into the flat steel pipe through the connecting head.
[0019] Optionally, a concrete truck is fixedly installed at the bottom of the ground pump, and a supporting structure is fixedly installed on one side of the concrete truck.
[0020] By adopting the above technical solution and providing a support structure, the stability of the ground pump during the concrete extraction process can be improved.
[0021] Optionally, control valves are provided on the surfaces of the delivery pump and the ground pump, and a sealing gasket is provided on the inner wall of the casting hole.
[0022] By adopting the above technical solution and setting a control valve, it is convenient for the user to control the amount of concrete during the pouring process.
[0023] In summary, the utility model has the following beneficial effects:
[0024] 1. The utility model can conveniently inject concrete into the flat steel pipe by opening a pouring hole on the side of the flat steel pipe. This design can realize one-time pouring of concrete, avoid the joints between concrete layers, and improve the integrity and strength of the structure. By setting the air holes, the inside of the flat steel pipe can be connected to the external air to ensure that the gas in the concrete can be discharged smoothly;
[0025] 2. The utility model facilitates the connection between multiple flat steel pipes by providing a first connecting piece and a second connecting piece. The wear-resistant sheet can effectively prevent the locking screw from causing wear to the surface of the first connecting piece after installation. The locking screw and the threaded hole can facilitate the user to fix the first connecting piece and the second connecting piece. The reinforcement piece can facilitate the user to reinforce the wear-resistant sheet. The limit plate can facilitate the user to limit the wear-resistant sheet. The high-strength self-compacting concrete inside the concrete truck can be effectively pumped to the second pump pipe through the operation of the ground pump, and finally poured into the flat steel pipe through the connecting head. The support structure can facilitate the improvement of the stability of the ground pump during the concrete extraction process. The control valve can facilitate the user to control the amount of concrete during the pouring process. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the structure of the utility model.
[0027] Figure 2 It is a side view of the flat steel tube structure of the utility model.
[0028] Figure 3 It is a top view of the first connecting piece structure of the utility model.
[0029] Description of reference numerals:
[0030] 1. Casting mechanism; 101. Delivery pump; 102. First pump pipe; 103. Hose; 104. Connector; 2. Flat steel pipe; 3. Base; 4. Casting hole; 5. Air vent; 6. First connecting piece; 7. Second connecting piece; 8. Wear-resistant sheet; 9. Threaded hole; 10. Locking screw; 11. Reinforcement piece; 12. Limiting plate; 13. Second pump pipe; 14. Ground pump; 15. Concrete truck; 16. Support structure; 17. Control valve; 18. Sealing gasket. DETAILED DESCRIPTION
[0031] The following is combined with Figures 1 to 3 This application is described in further detail.
[0032] Please refer to Figure 1-2 , a small-section rectangular steel pipe structure convenient for pouring high-strength self-compacting concrete, including a pouring mechanism 1, a flat steel pipe 2 and a base 3, wherein the pouring mechanism 1 includes a delivery pump 101, a first pump pipe 102, a hose 103 and a connector 104;
[0033] The delivery pump 101 is fixedly installed on the top of the base 3, the first pump tube 102 is fixedly connected to one side of the delivery pump 101, the hose 103 is sleeved and connected to the end of the first pump tube 102, and the connector 104 is sleeved and connected to the end of the hose 103;
[0034] A casting hole 4 is provided on one side of the flat steel pipe 2, and a vent hole 5 is provided on the surface of the flat steel pipe 2 and at the bottom of the casting hole 4. The cross-sectional diameters of the hose 103 and the first pump pipe 102 are both 80 mm.
[0035] By opening a pouring hole 4 on the side of the flat steel tube 2, concrete can be easily injected into the flat steel tube 2. This design can realize a one-time pouring of concrete, avoid the joints between concrete layers, and improve the integrity and strength of the structure. By setting the air vent 5, the inside of the flat steel tube 2 can be connected to the external air to ensure that the gas in the concrete can be discharged smoothly.
[0036] Reference Figure 2 and Figure 3 A first connecting piece 6 is fixedly installed at one end of the flat steel tube 2, and a second connecting piece 7 is movably installed at the bottom of the first connecting piece 6. By setting the first connecting piece 6 and the second connecting piece 7, it is convenient to connect multiple flat steel tubes 2. Wear-resistant sheets 8 are movably installed on both sides of the surface of the first connecting piece 6. A threaded hole 9 is opened on the surface of the wear-resistant sheet 8. By setting the wear-resistant sheet 8, it is effective to prevent the locking screw 10 from causing wear to the surface of the first connecting piece 6 after installation. The threaded hole 9 passes through the inner wall of the second connecting piece 7, and the inner cavity of the threaded hole 9 is threadedly installed with a locking screw 10. The setting of the locking screw 10 and the threaded hole 9 can facilitate the user to fix the first connecting piece 6 and the second connecting piece 7. A reinforcement piece 11 is fixedly installed on the inner side of the wear-resistant sheet 8, and a limiting plate 12 is fixedly installed on both sides of the wear-resistant sheet 8. The setting of the reinforcement piece 11 facilitates the user to reinforce the wear-resistant sheet 8, and the setting of the limiting plate 12 facilitates the user to limit the wear-resistant sheet 8.
[0037] Reference Figure 1 and Figure 2The other side of the delivery pump 101 is fixedly connected with a second pump pipe 13, and the end of the second pump pipe 13 is fixedly connected with a ground pump 14. The high-strength self-compacting concrete inside the concrete truck 15 can be effectively pumped to the second pump pipe 13 through the operation of the ground pump 14, and finally poured into the flat steel pipe 2 by the connector 104. The bottom of the ground pump 14 is fixedly installed with a concrete truck 15, and one side of the concrete truck 15 is fixedly installed with a support structure 16, and the support structure 16 includes a hydraulic rod fixedly set on the concrete truck 15. The support structure 16 is provided to facilitate the stability of the ground pump 14 in the process of extracting concrete. The surfaces of the delivery pump 101 and the ground pump 14 are both provided with a control valve 17, and the inner wall of the casting hole 4 is provided with a sealing gasket 18. The control valve 17 is provided to facilitate the user to control the amount of concrete during the casting process.
[0038] The implementation principle of the utility model is: the high-strength self-compacting concrete inside the concrete truck 15 is pumped to the second pump pipe 13 by the operation of the ground pump 14, and the delivery pump 101 can be operated to extract concrete from the connecting head 104 and poured into the flat steel pipe 2, and by opening a pouring hole 4 on the side of the flat steel pipe 2, the concrete can be directly injected into the flat steel pipe 2, which can realize one-time pouring of concrete, avoid the joints between concrete layers, and improve the integrity and strength of the structure.
[0039] The above are all preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any equivalent changes made based on the structure, shape, and principle of the present utility model should be included in the protection scope of the present utility model.
Claims
1. A small-section rectangular steel pipe structure for facilitating the pouring of high-strength self-compacting concrete, comprising a pouring mechanism (1), a flat steel pipe (2) and a base (3), Features: The pouring mechanism (1) comprises a delivery pump (101), a first pump pipe (102), a hose (103) and a connector (104); The delivery pump (101) is fixedly mounted on the top of the base (3); the first pump tube (102) is fixedly connected to one side of the delivery pump (101); the hose (103) is sleeved and connected to the end of the first pump tube (102); and the connector (104) is sleeved and connected to the end of the hose (103); A casting hole (4) is provided on one side of the flat steel pipe (2), and a vent hole (5) is provided on the surface of the flat steel pipe (2) and at the bottom of the casting hole (4). The cross-sectional diameters of the hose (103) and the first pump pipe (102) are both 80 mm.
2. A small-section rectangular steel pipe structure for pouring high-strength self-compacting concrete according to claim 1, Features: A first connecting piece (6) is fixedly mounted on one end of the flat steel tube (2), and a second connecting piece (7) is movably mounted on the bottom of the first connecting piece (6).
3. A small-section rectangular steel pipe structure for pouring high-strength self-compacting concrete according to claim 2, Features: Wear-resistant sheets (8) are movably mounted on both sides of the surface of the first connecting member (6), and threaded holes (9) are provided on the surfaces of the wear-resistant sheets (8).
4. A small-section rectangular steel pipe structure for pouring high-strength self-compacting concrete according to claim 3, Features: The threaded hole (9) passes through the inner wall of the second connecting member (7), and a locking screw (10) is threadedly mounted in the inner cavity of the threaded hole (9).
5. A small-section rectangular steel pipe structure for pouring high-strength self-compacting concrete according to claim 3, Features: A reinforcing piece (11) is fixedly mounted on the inner side of the wear-resistant plate (8), and limiting plates (12) are fixedly mounted on both sides of the wear-resistant plate (8).
6. A small-section rectangular steel pipe structure for pouring high-strength self-compacting concrete according to claim 1, Features: The other side of the delivery pump (101) is fixedly connected to a second pump pipe (13), and the end of the second pump pipe (13) is fixedly connected to a ground pump (14).
7. A small-section rectangular steel pipe structure for pouring high-strength self-compacting concrete according to claim 6, Features: A concrete truck (15) is fixedly mounted on the bottom of the ground pump (14), and a support structure (16) is fixedly mounted on one side of the concrete truck (15).
8. A small-section rectangular steel pipe structure for pouring high-strength self-compacting concrete according to claim 1, Features: The surfaces of the delivery pump (101) and the ground pump (14) are both provided with control valves (17), and the inner wall of the casting hole (4) is provided with a sealing gasket (18).