Sand blocking ditch dike with good sand blocking effect

By designing a sand barrier embankment, using the combined structure of wire fence, shrub, backpressure soil and sand barrier ditch, the problem of loss of sand barrier function caused by burying the railway sand barrier is solved, and a longer-term sand barrier effect and better Low risk of sand damage improves railway operation safety.

CN222065239UActive Publication Date: 2024-11-26CHINA RAILWAY FIRST SURVEY & DESIGN INST GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420629242.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-11-26
Estimated Expiration
2034-03-29

AI Technical Summary

Technical Problem

The existing railway sand barriers are buried by sand over time and lose their sand barrier function, resulting in wind and sand damage that seriously affects the safety of trains. The existing technology is difficult to effectively extend the service life of the sand barriers and reduce the damage to the roadbed.

Method used

设计一种挡沙沟堤,包括向铁路路基侧设置铁丝围栏、灌木、小乔木、防护栅栏,墙体背后设置反压土体和挡沙沟,墙体与基础连接,顶部设有凸缘和 The surface of the steel bar is covered with dry stone or egg gravel, and the sand-blocking dike is set on the outermost side of the sand prevention measures.

Benefits of technology

Effectively improves the sand blocking function and sand prevention effect, extends the service life of sand barriers, reduces the damage to the roadbed, and blocks and accumulates when wind and sand flow encounters walls, making it easy to clean, promotes the growth of surface vegetation, and enhances long-term sand prevention ability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222065239U_ABST
    Figure CN222065239U_ABST
Patent Text Reader

Abstract

The utility model discloses a sand blocking ditch dike with a good sand blocking effect. The sand barriers on the two sides of the railway can be buried by sand as time goes on and lose the sand blocking function. The utility model comprises a sand-blocking ditch embankment, wherein the sand-blocking ditch embankment is sequentially provided with an iron wire fence, shrubs, small trees and a railway protective fence towards the railway roadbed side; the sand blocking ditch dike comprises a wall, a back pressure soil body is arranged behind the wall, one side of the back pressure soil body makes contact with the wall, and the other side of the back pressure soil body is provided with an inclined face. A sand blocking ditch is formed in one side of the back pressure soil body slope; the inclined plane of the sand retaining ditch and the inclined plane of the back pressure soil body are coplanar; the wall body comprises a vertical wall panel and a top flange, and the top flange is arranged on the windward side; and the vertical wall panel is connected with the foundation. The sand-proof pressure of facilities between the sand-proof ditch dike and the railroad bed is reduced, the growth of surface vegetation is facilitated, the long-term sand-proof capability is improved, and the operation comfort of the railroad bed is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of wind and sand prevention, and in particular relates to a sand retaining ditch embankment with good sand retaining effect. Background Art

[0002] Wind and sand hazards have always been the main factor that plagues road construction and safe operation in sandy areas. China is the country with the longest distribution of railways in sandy areas in the world, with a total length of about 1.5×104km, mainly concentrated in the northwest region. With the acceleration of the construction of transportation trunk lines, the problem of railway wind and sand has become more prominent. The length of some sections affected by wind and sand hazards is as high as more than 30%, seriously affecting the safety of train driving. Especially for high-speed railways that pass through or are adjacent to desert environments, fast and high-standard wind and sand prevention and control projects are required to ensure the construction and safe operation of railway projects. In areas with strong wind and sand activities and abundant sand sources, a variety of sand barrier comprehensive measures are generally set up to improve the sand blocking effect. However, as time goes on, the sand barriers on both sides of the railway will be buried by sand and lose their sand blocking function. Utility Model Content

[0003] In order to make up for the deficiencies of the prior art, the utility model provides a sand retaining ditch embankment with good sand retaining effect, which improves the sand retaining function and sand prevention effect, prolongs the service life of sand barriers on both sides of the railway, and reduces sand damage to the roadbed.

[0004] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0005] A sand retaining ditch embankment with good sand retaining effect, characterized in that: it comprises a sand retaining ditch embankment, wherein the sand retaining ditch embankment is sequentially provided with wire fences, shrubs, small trees, and railway protection fences toward the railway roadbed;

[0006] The sand retaining ditch embankment comprises a wall, a counter-pressure soil body is arranged behind the wall, one side of the counter-pressure soil body is in contact with the wall, and the other side is provided with an inclined surface;

[0007] A sand retaining ditch is arranged on one side of the slope of the counter-pressure soil body. The sand retaining ditch is arranged below the ground and is in an inverted trapezoidal shape. The slope of the sand retaining ditch is coplanar with the slope of the counter-pressure soil body.

[0008] Furthermore, the wall includes a vertical wall panel and a top flange, and the top flange is arranged on the windward side; the vertical wall panel and the top flange are arranged vertically, and the cross-section of the top flange is rectangular; the vertical wall panel is connected to the foundation.

[0009] Furthermore, the cross-sectional area of ​​the foundation is larger than that of the wall.

[0010] Furthermore, reinforcement bars need to be provided at the joints between the wall and the foundation, the vertical wall panels and the top flange.

[0011] Furthermore, the cross-section of the counter-pressure soil body is a right-angled trapezoid.

[0012] Furthermore, the surface of the sand retaining ditch embankment is covered with dry-laid stone slabs or pebbles.

[0013] Furthermore, the sand retaining ditch embankment is arranged at the outermost side of the sand prevention measures.

[0014] Beneficial effects of the utility model:

[0015] 1) The sand retaining ditch embankment of the utility model is made of local materials, the wall is thin and relies on the soil for force, and the cost is low. A flange is provided on the top of the wall, and the wind and sand flow is blocked twice when it encounters the wall. The wind direction changes and vortex swirls. Most of the sand particles cannot pass over the wall and fall and accumulate outside the wall. The sand particles that pass over the wall will partially fall into the sand intercepting ditch after energy dissipation, and the sand accumulation is relatively easy to clean;

[0016] 2) The utility model reduces the sand control pressure of the facilities between the sand retaining ditch and the railway roadbed, which is conducive to the growth of surface vegetation, improves the long-term sand control capability, and ensures the operational comfort of the railway roadbed;

[0017] 3) The wall of the expanded foundation of the sand retaining embankment of the utility model has a wall back that closely fits the back-pressure compacted soil, and can still have good stability under the action of strong wind. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a front view schematic diagram of the sand retaining ditch embankment of the utility model;

[0019] Figure 2 It is a front view schematic diagram of a wind and sand protection belt formed by a sand retaining ditch embankment of the utility model;

[0020] In the figure: 1-sand retaining ditch embankment, 1-1. wall, 1-2. counter pressure soil, 1-3. sand retaining ditch, 1-4. foundation, 2. wire fence, 3. shrubs, 4. small trees, 5. railway protection fence. DETAILED DESCRIPTION

[0021] The present invention is described in detail below in conjunction with specific implementation methods.

[0022] The utility model has good stability and utilizes the wind movement principle to effectively reduce the wind and sand from passing over the structure body, thereby reducing the technical difficulty of sand prevention.

[0023] like Figure 1 , 2 As shown, the utility model comprises a sand retaining ditch embankment 1, the surface of which is covered with dry-laid slabs of stone or pebbles to improve the wind erosion resistance.

[0024] The sand retaining ditch 1 is provided with wire fence 2, shrubs 3, small trees 4, and railway protection fence 5 in sequence toward the railway embankment; the utility model is arranged on the windward side of the dominant wind direction and on both sides of the uncertain wind direction, and is generally arranged on the outermost side of the sand control measures, which is conducive to sand control and vegetation growth on both sides of the railway. The replanted shrubs 3 are selected from native plants, such as Caragana korshinskii, Caragana scabra, Amorpha fruticosa, etc., which have drought resistance, windproof and sand fixation effects, and wind resistance.

[0025] The sand retaining ditch 1 comprises a wall 1-1, which comprises a vertical wall panel and a top flange, wherein the top flange is arranged on the windward side; the vertical wall panel and the top flange are arranged vertically, and the cross section of the top flange is rectangular; the height of the wall 1-1 is preferably 1m to 1.5m, the length of the top flange is 0.2 to 0.3m, and the thickness is 0.2 to 0.3m. The wall height and the size of the top flange should be determined according to the wind force and the amount of sand carried.

[0026] The vertical wall panel is connected to the foundation 1-4, and the cross-sectional area of ​​the foundation 1-4 is larger than that of the wall 1-1. The foundation 1-4 adopts an enlarged foundation to increase the stability of the wall structure and avoid overturning due to wind. The wall 1-1 and the foundation 1-4 can be made of mortar-laid slabs or concrete, and the top flange is cast with concrete. The concrete wall should be cast as a whole, and construction joints should not be left in batches. There should be no horizontal joints in the staggered stacking of mortar-laid slabs.

[0027] Reinforcement bars need to be provided at the joints between the wall 1-1 and the foundation 1-4, the vertical wall panels and the top flange to increase the overall connectivity.

[0028] A counter-pressure soil body 1-2 is arranged behind the wall body 1-1, and the cross section of the counter-pressure soil body 1-2 is a right-angled trapezoid; one side of the counter-pressure soil body 1-2 contacts the wall 1-1, and the other side is provided with an inclined surface; the counter-pressure soil body 1-2 is filled after the strength of the foundation 1-4 and the wall 1-1 reaches the requirements, and is compacted and compacted closely with them. The counter-pressure soil body 1-2 can be made of local materials, and dry-laid stone or gravel is adopted on the surface to prevent wind erosion;

[0029] A sand retaining ditch 1-3 is set on one side of the slope of the counter-pressure soil body 1-2. The sand retaining ditch 1-3 is set below the ground and is in an inverted trapezoidal shape. The slope of the sand retaining ditch 1-3 is coplanar with the slope of the counter-pressure soil body 1-2. The sand retaining ditch has the same size as the wall. It is recommended that the ditch bottom or embankment top is 1.2 to 1.5 meters, and the ditch depth or embankment height is 1 to 1.5 meters, which is determined by the wind force and the amount of sand carried. The sand retaining ditch adopts a trapezoidal ditch to increase the amount of sand storage.

[0030] The sand retaining embankment in the utility model adopts a wall structure with a foundation. The wall is thin and relies on the back pressure soil behind the wall to bear the force, so it can still have good stability under the action of strong wind. A flange is arranged on the top of the wall, and steel bars are arranged at the joints of the flanges to increase the overall connectivity to prevent damage. When the wind and sand flow encounters the wall, it is blocked again at the flange, and the wind direction changes to generate vortex vortexes. Most of the sand particles cannot pass over the wall and fall and accumulate on the outside of the wall. After the sand particles that pass over the wall are dissipated, some of them fall into the sand retaining ditch faster. The sand retaining ditch has good integrity and is relatively convenient to repair and maintain.

[0031] In the description of the present invention, unless otherwise clearly specified and limited, the terms "set", "install", "connect", "connect", and "fix" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0032] The content of the utility model is not limited to the examples listed, and any equivalent changes made to the technical solution of the utility model by ordinary technicians in this field after reading the specification of the utility model are covered by the claims of the utility model.

Claims

1. A sand retaining ditch embankment with good sand retaining effect, characterized in that: It comprises a sand retaining ditch embankment (1), wherein the sand retaining ditch embankment (1) is provided with a wire fence (2), shrubs (3), small trees (4), and a railway protection fence (5) in sequence toward the railway roadbed side; The sand retaining ditch embankment (1) comprises a wall (1-1), a counter-pressure soil body (1-2) is arranged behind the wall (1-1), one side of the counter-pressure soil body (1-2) is in contact with the wall (1-1), and the other side is provided with an inclined surface; A sand retaining ditch (1-3) is arranged on one side of the slope of the counter-pressure soil body (1-2); the sand retaining ditch (1-3) is arranged below the ground and is in an inverted trapezoidal shape; the slope of the sand retaining ditch (1-3) is coplanar with the slope of the counter-pressure soil body (1-2).

2. A sand retaining ditch embankment with good sand retaining effect according to claim 1, characterized in that: The wall (1-1) comprises a vertical wall panel and a top flange, wherein the top flange is arranged on the windward side; the vertical wall panel and the top flange are arranged vertically, and the cross section of the top flange is rectangular; the vertical wall panel is connected to the foundation (1-4).

3. The sand-blocking ditch embankment with good sand-blocking effect according to claim 2 is characterized in that: The cross-sectional area of ​​the foundation (1-4) is larger than that of the wall (1-1).

4. The sand-blocking ditch embankment with good sand-blocking effect according to claim 3 is characterized in that: Steel bars need to be provided at the joints between the wall (1-1), the foundation (1-4), the vertical wall panels and the top flange.

5. The sand-blocking ditch embankment with good sand-blocking effect according to claim 4 is characterized in that: The cross section of the counter-pressure soil body (1-2) is a right-angle trapezoid.

6. The sand-blocking ditch embankment with good sand-blocking effect according to claim 5 is characterized by: The surface of the sand retaining ditch embankment (1) is covered with dry-laid stone slabs or pebbles.

7. The sand-blocking ditch embankment with good sand-blocking effect according to claim 6 is characterized by: The sand retaining ditch embankment (1) is arranged at the outermost side of the sand prevention measures.