Building electromechanical pipeline support hanger

By adopting a combined structure of a U-shaped frame with a slider, a support plate and a support rod in the pipeline support hanger, the direct installation of the pipeline is realized, and the problem of low erection efficiency caused by the complex connection of pipeline weight and equipment in the prior art is solved. Improves the efficiency and safety of pipeline layout.

CN222163827UInactive Publication Date: 2024-12-13CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420855732.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-24
Publication Date
2024-12-13
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

When laying pipelines, the pipeline weight is large and the equipment connection is complicated, making the pipeline inconvenient to pass through multiple suspension booms, affecting the erection efficiency.

Method used

A construction mechanical and electrical pipeline support hanger is designed, using a combined structure of a U-shaped frame, a skateboard, a support plate and a support rod. Through the movement of the sliding mounting block and the support rod, the pipeline is directly mounted above the hanger rod to avoid passing in sequence. Pass the boom.

Benefits of technology

Improve the pipeline erection efficiency, simplify the layout process, and reduce the risk of safety accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222163827U_ABST
    Figure CN222163827U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of pipeline supports and hangers, and discloses a building electromechanical pipeline support and hanger which comprises a U-shaped frame, and supporting plates are arranged at the bottoms of the two sides of the U-shaped frame. A groove is formed in the lower surface of the supporting plate, a sliding groove matched with the sliding plate is formed in the inner wall of the groove, the two sides of the sliding plate are installed in the sliding groove in a sliding mode, and the sliding plate is installed on the lower surface of the supporting plate in a sliding mode through the sliding groove. A pipeline is erected above the hanging rod through the gap between the hanging rod and the supporting rod, then the corresponding sliding plate slides towards the inner side on the lower surface of the supporting plate along the sliding groove, meanwhile, the sliding plate drives the installation block and the supporting rod to move inwards, the end of the hanging rod and the corresponding supporting rod are connected together in an inserted mode again, and the pipeline is erected. Therefore, the pipeline does not need to sequentially penetrate through the upper portion of the hanging rod, the arranged pipeline can be directly erected on the hanging rod, arrangement of the pipeline is facilitated, and the erecting efficiency of the pipeline is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipeline support and hanger brackets, in particular to a building electromechanical pipeline support and hanger bracket. Background Art

[0002] In construction projects, pipeline supports and hangers are needed. The function of pipeline supports and hangers is to fix pipelines and bear the weight of the pipelines themselves, the weight of the pipelines inside the pipelines, and the weight of insulation materials. Fixing and limiting the position of pipelines by pipeline supports and hangers is beneficial to improving the efficiency of the project, arranging pipelines reasonably, and avoiding safety accidents caused by the intricate interweaving of pipelines.

[0003] After the existing support and hanger brackets are assembled, the hangers are fixedly hung on the top of the building. When laying out the pipelines, the pipelines need to pass through the space between the hangers and the top of the building. Since the pipelines are heavy and the ends of the pipelines are connected to equipment, it is not convenient for the pipelines to pass through multiple hangers in sequence for arrangement. In order to facilitate the arrangement of the pipelines, the present application proposes a support and hanger bracket for building mechanical and electrical pipelines. Utility Model Content

[0004] The utility model aims to provide a support and hanger for mechanical and electrical pipelines of a building to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a building mechanical and electrical pipeline support and hanger, comprising a U-shaped frame, the bottoms of both sides of the U-shaped frame are provided with support plates, the lower surface of the support plate is slidably mounted with a slide plate, the slide plate is provided with a mounting block, the inner side of the mounting block is provided with a support rod, and a hanger rod is inserted between the two support rods;

[0006] The lower surface of the support plate is provided with a groove, the inner wall of the groove is provided with a slide groove matched with the slide plate, the two sides of the slide plate are slidably installed in the slide groove, and the slide plate is slidably installed on the lower surface of the support plate through the slide groove.

[0007] Wherein, a transverse plate is provided on the inner side of the U-shaped frame, and an installation cavity is formed between the transverse plate and the inner wall of the U-shaped frame.

[0008] Wherein, mounting holes penetrating the mounting cavity are evenly opened on the top of the U-shaped frame.

[0009] The axis lines of the two support rods are located on the same straight line, and a socket is formed at one end of the support rod away from the mounting block, and the end of the suspension rod is inserted into the socket.

[0010] Wherein, two support rings are provided at positions on the lower surface of the slide plate corresponding to the support rods, and the support rods penetrate the support rings.

[0011] Wherein, the axis center line of the support ring and the axis center line of the support rod are located on the same straight line.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] When it is necessary to lay a pipeline, the utility model slides one of the slide plates outward on the lower surface of the support plate along the slide groove, and at the same time drives the mounting block and the support rod to move outward, so that one end of the suspension rod is separated from the corresponding support rod, and then the pipeline is laid above the suspension rod through the gap between the suspension rod and the support rod, and then the corresponding slide plate is slid inward on the lower surface of the support plate along the slide groove, and at the same time drives the mounting block and the support rod to move inward, so that the end of the suspension rod is re-inserted with the corresponding support rod, so that the pipeline is laid on the suspension rod. In this way, there is no need to pass the pipelines through the top of the suspension rod in turn, and the laid pipelines can be directly laid on the suspension rod, which is convenient for the arrangement of the pipelines and improves the efficiency of pipeline laying. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a schematic diagram of the overall axonometric structure of the utility model;

[0015] Figure 2 This is a schematic diagram of the overall main structure of the utility model;

[0016] Figure 3 It is a schematic diagram of the explosion structure of the support plate and the slide plate of the utility model.

[0017] In the figure: 1. U-shaped frame; 2. cross plate; 3. support plate; 4. mounting block; 5. support rod; 6. suspension rod; 7. slide plate; 8. support ring; 9. groove; 10. slide groove. DETAILED DESCRIPTION

[0018] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.

[0019] See also Figure 1-3 The utility model provides a technical solution: a building mechanical and electrical pipeline support and hanger, comprising a U-shaped frame 1, support plates 3 are provided at the bottom of both sides of the U-shaped frame 1, a slide plate 7 is slidably installed on the lower surface of the support plate 3, a mounting block 4 is provided on the slide plate 7, a support rod 5 is provided on the inner side of the mounting block 4, and a hanger 6 is inserted between the two support rods 5. When assembling, the U-shaped frame 1 is first installed on the top of the interior of the building, so that the support and hanger is installed on the top of the interior of the building. Since the slide plate 7 is slidably installed on the lower surface of the support plate 3, when the position of the sliding slide plate 7 is not needed, the slide plate 7 is fixed to the lower surface of the support plate 3 by bolts, and when the position of the sliding slide plate 7 is needed, the bolts fixing the slide plate 7 are unscrewed;

[0020] The support plate 3 is provided with a groove 9, and the inner wall of the groove 9 is provided with a slide groove 10 that cooperates with the slide plate 7. The two sides of the slide plate 7 are slidably installed in the slide groove 10, and the slide plate 7 is slidably installed on the lower surface of the support plate 3 through the slide groove 10. When it is necessary to lay the pipeline, the fixing bolts on one of the slide plates 7 are unscrewed, and then the slide plate 7 is slid outward on the lower surface of the support plate 3, and the slide plate 7 drives the mounting block 4 and the support rod 5 to move outward, so that one end of the suspension rod 6 is separated from the corresponding support rod 5, and then the pipeline is laid above the suspension rod 6 through the gap between the suspension rod 6 and the support rod 5, and then the corresponding slide plate 7 is slid inwardly on the lower surface of the support plate 3 along the slide groove 10, and the slide plate 7 drives the mounting block 4 and the support rod 5 to move inward, so that the end of the suspension rod 6 is re-inserted together with the corresponding support rod 5, so that the pipeline is laid on the suspension rod 6. In this way, there is no need to pass the pipeline through the top of the suspension rod 6 in turn, and the laid pipeline can be directly laid on the suspension rod 6, which is convenient for the arrangement of the pipeline and improves the efficiency of pipeline laying.

[0021] Among them, a horizontal plate 2 is provided on the inner side of the U-shaped frame 1, and an installation cavity is formed between the horizontal plate 2 and the inner wall of the U-shaped frame 1; installation holes that penetrate the installation cavity are evenly opened on the top of the U-shaped frame 1. When the U-shaped frame 1 needs to be fixed on the top of the building, the top of the U-shaped frame 1 is fitted with the top of the building, and then the bolts are passed through the installation holes, and the bolts are screwed through the installation cavity to the top of the building, so that the U-shaped frame 1 is installed on the top of the building.

[0022] Among them, the axial center lines of the two support rods 5 are located on the same straight line, and a socket is opened at the end of the support rod 5 away from the mounting block 4. The end of the suspension rod 6 is inserted into the socket. The end of the suspension rod 6 cooperates with the socket to clamp the suspension rod 6 between the two support rods 5, so that the suspension rod 6 is assembled in the U-shaped frame 1. The assembled suspension rod 6 can play the role of laying pipelines.

[0023] Among them, two support rings 8 are provided at the position corresponding to the support rod 5 on the lower surface of the slide plate 7, and the support rod 5 passes through the support rings 8; the axis line of the support ring 8 and the axis line of the support rod 5 are located on the same straight line, and the support rod 5 is supported by the support ring 8 to prevent the support rod 5 from tilting, ensuring that the support rod 5 is in a horizontal state, so that the insertion hole at the end of the support rod 5 is aligned with the end of the suspension rod 6.

[0024] Working principle: first install the U-shaped frame 1 on the top inside the building, so as to install the support bracket on the top inside the building, then unscrew the fixing bolts on one of the slide plates 7, and then slide the slide plate 7 outward on the lower surface of the support plate 3, and at the same time, the slide plate 7 drives the mounting block 4 and the support rod 5 to move outward, so that one end of the suspension rod 6 is separated from the corresponding support rod 5, and then the pipeline is erected above the suspension rod 6 through the gap between the suspension rod 6 and the support rod 5, and then the corresponding slide plate 7 is slid inward on the lower surface of the support plate 3 along the slide groove 10, and at the same time, the slide plate 7 drives the mounting block 4 and the support rod 5 to move inward, so that the end of the suspension rod 6 is re-inserted with the corresponding support rod 5, thereby the pipeline is erected on the suspension rod 6.

[0025] Based on the embodiments of the present utility model, all other embodiments obtained by ordinary technicians in the field without making any creative work shall fall within the scope of protection of the present utility model.

Claims

1. A building mechanical and electrical pipeline support and hanger, comprising a U-shaped frame (1), characterized in that: The bottom of both sides of the U-shaped frame (1) is provided with a support plate (3), a slide plate (7) is slidably mounted on the lower surface of the support plate (3), a mounting block (4) is provided on the slide plate (7), a support rod (5) is provided on the inner side of the mounting block (4), and a suspension rod (6) is inserted between the two support rods (5); The lower surface of the support plate (3) is provided with a groove (9), the inner wall of the groove (9) is provided with a slide groove (10) that cooperates with the slide plate (7), the two sides of the slide plate (7) are slidably installed in the slide groove (10), and the slide plate (7) is slidably installed on the lower surface of the support plate (3) through the slide groove (10).

2. A building mechanical and electrical pipeline support and hanger according to claim 1, characterized in that: A transverse plate (2) is provided on the inner side of the U-shaped frame (1), and an installation cavity is formed between the transverse plate (2) and the inner wall of the U-shaped frame (1).

3. A building mechanical and electrical pipeline support and hanger according to claim 2, characterized in that: The top of the U-shaped frame (1) is evenly provided with mounting holes that penetrate the mounting cavity.

4. A building mechanical and electrical pipeline support and hanger according to claim 1, characterized in that: The axis lines of the two support rods (5) are located on the same straight line. An insertion hole is provided at one end of the support rod (5) away from the mounting block (4), and the end of the suspension rod (6) is inserted into the insertion hole.

5. A building mechanical and electrical pipeline support and hanger according to claim 1, characterized in that: Two support rings (8) are provided on the lower surface of the slide plate (7) at positions corresponding to the support rods (5), and the support rods (5) penetrate the support rings (8).

6. A building mechanical and electrical pipeline support and hanger according to claim 5, characterized in that: The axis center line of the support ring (8) and the axis center line of the support rod (5) are located on the same straight line.