Cast-in-place concrete inspection well construction device

The cast-in-place concrete inspection well construction device composed of steel formwork solves the problems of low construction efficiency and high cost, achieves rapid construction and high-quality concrete pouring, and reduces construction costs and labor investment.

CN222295066UActive Publication Date: 2025-01-03NO 22 METALLURGICAL ROAD & BRIDGE CONSTR (HEBEI) CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420609160.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-27
Publication Date
2025-01-03
Estimated Expiration
2034-03-27

AI Technical Summary

Technical Problem

In the construction of communication cables or low-voltage cables in the ground, the construction efficiency of inspection wells in the prior art is low, the material cost is high, the quality is difficult to control, and the procurement cycle of prefabricated wells in the factory is long, which increases the construction difficulty and cost.

Method used

The cast-in-place concrete inspection well construction device consisting of steel formwork, including inner formwork and outer formwork. The inner formwork is nested inside the outer formwork, and the cast area is between the bottom plate and the side plate, equipped with pulling bolts, attachment vibrators and funnel components. , rapid pouring and dense concrete is achieved through the design of the formwork and vibrator.

Benefits of technology

The rapid construction of concrete inspection wells has been achieved, the amount of excavation of foundation pits has been reduced, the construction cost has been reduced, the construction efficiency and quality has been improved, labor investment has been simplified, and service life has been extended.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222295066U_ABST
    Figure CN222295066U_ABST
Patent Text Reader

Abstract

The utility model relates to building construction, in particular to a cast-in-place concrete inspection well construction device. Comprising a template, the template is a steel template, the template comprises an inner template and an outer template, the inner template is nested in the outer template, a bottom plate is arranged at the lower end of the inner template, pouring areas are arranged between side plates of the inner template and the outer template and between the bottom plate of the inner template and a well bottom, and a split bolt is arranged between the inner template and the outer template; an attached vibrator is arranged on a bottom plate of the inner template, and an attached vibrator is arranged on a side plate of the outer template; preformed holes are symmetrically formed in side plates on the two sides of the inner template and the outer template, hole cover dies penetrate through the preformed holes, and the hole cover dies are of hollow structures. According to the utility model, the rapid cast-in-place construction of the concrete inspection well is realized, the earth excavation volume of a foundation pit is reduced, the construction cost is saved, compared with a masonry process, the construction efficiency is improved, the labor input is reduced, the construction quality of the concrete inspection well is effectively ensured, and the service life is prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to building construction, in particular to a cast-in-place concrete inspection well construction device. Background Art

[0002] When constructing underground communication cables or low-voltage cables, inspection wells need to be set up at certain intervals in the pipelines. The conventional design and construction method is to dig grooves on site and then lay bricks or use factory prefabrication. On-site bricklaying requires manual work in the trench, which increases the size of the trench excavation and the workload. In addition, brick-laid wells have high requirements on materials and are difficult to control in quality. Factory prefabricated wells have high procurement costs and long production cycles, which are not conducive to on-site construction.

[0003] A Chinese utility model with authorization announcement number CN212405052U discloses a concrete pouring device for a municipal engineering inspection well wall panel. The utility model requires a wooden formwork cover to be set up on the formwork, which requires a large amount of construction. Utility Model Content

[0004] The utility model aims to solve the above technical problems, thereby providing a cast-in-place concrete inspection well construction device to improve construction efficiency.

[0005] The utility model solves the technical problem and adopts the following technical solution:

[0006] A cast-in-place concrete inspection well construction device includes a template, which is a steel template. The template includes an inner template and an outer template. The inner template is nested in the outer template. A bottom plate is provided at the lower end of the inner template. The inner template and the side plates of the outer template, and the bottom plate of the inner template and the bottom of the well are all casting areas. Tension bolts are provided between the inner template and the outer template; the bottom plate of the inner template is provided with an attached vibrator, and the side plates of the outer template are provided with an attached vibrator; the side plates on both sides of the inner template and the outer template are symmetrically provided with reserved holes, and a hole sleeve mold is penetrated through the reserved hole, and the hole sleeve mold is a hollow structure.

[0007] Compared with the prior art, the utility model adopting the above technical solution has the following beneficial effects:

[0008] 1. Realize the rapid construction of cast-in-place concrete inspection wells, reduce the amount of foundation pit excavation, and save construction costs;

[0009] 2. Compared with masonry technology, it improves construction efficiency and reduces labor input;

[0010] 3. Effectively ensure the construction quality of concrete inspection wells and extend their service life.

[0011] Further, the optimization scheme of the utility model is:

[0012] The inner template and the outer template are circular, square or rectangular.

[0013] A funnel assembly is provided on the top of the inner template and the outer template, and the funnel assembly includes a funnel, a feed pipe and a side guide mechanism. The upper port of the feed pipe is connected to the discharge port of the funnel, the middle and lower part of the feed pipe is placed between the inner template and the outer template, and the side guide mechanisms are symmetrically provided on both sides of the feed pipe.

[0014] The side guide mechanism includes a side guide wheel, an ear seat and a support plate. The axis of the side guide wheel is arranged vertically, the tread of the side guide wheel is rollingly matched with the side plate of the outer template or the inner template, the side guide wheel is rotatably connected to the ear plate of the ear seat through the wheel axle, an adjustment component is provided between the side end plate of the ear seat and the support plate, and the support plate is arranged horizontally and fixedly connected to the discharge pipe.

[0015] The adjustment assembly includes an adjustment plate, an adjustment screw and a fixed plate. The adjustment plate is L-shaped. The horizontal portion of the adjustment plate is fixedly connected to the upper end of the ear seat side end plate. The vertical portion of the adjustment plate passes through the adjustment hole of the support plate. The outer end of the support plate is fixedly connected to the fixed plate. An adjustment screw is provided between the fixed plate and the adjustment plate.

[0016] A supporting roller assembly is provided between the ear seat and the inner template and between the ear seat and the outer template. The supporting roller assembly includes a roller, a roller shaft and a roller support plate. The axis of the roller is arranged horizontally, the tread of the roller is rollingly connected to the top of the inner template or the outer template, the roller is rotationally connected to the roller shaft, the outer end of the roller shaft is connected to the roller support plate, and the roller support plate is connected to the ear plate of the ear seat.

[0017] The adjusting screws on both sides of the vertical part of the adjusting plate are fixedly connected with positioning rings.

[0018] The adjusting screw is screwed with a locking nut.

[0019] The upper port of the funnel is square. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 This is a schematic diagram of the overall structure of the first embodiment of the utility model;

[0021] Figure 2 for Figure 1 Side view of

[0022] Figure 3 This is a structural schematic diagram of a funnel assembly according to Embodiment 2 of the present utility model;

[0023] Figure 4 Schematic diagram of the side guide mechanism of the funnel assembly.

[0024] In the figure: outer template 1; reserved hole 1-1; inner template 2; bottom plate 2-1; tension bolt 3; hole sleeve mold 4; attached vibrator 5; conductor 6; concrete conveying trough 7; bracket 8; funnel 9; feed pipe 10; side guide wheel 11; wheel axle 11-1; ear seat 12; ear plate 12-1; side end plate 12-2; support plate 13; adjustment plate 14; adjustment screw 15; fixing plate 16; positioning ring 17; roller 18; roller shaft 19; roller support plate 20. DETAILED DESCRIPTION

[0025] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. Embodiment 1

[0026] See also Figure 1 , Figure 2 , this embodiment provides a cast-in-place concrete inspection well construction device, which is mainly composed of an outer formwork 1, an inner formwork 2, tension bolts 3 and an attached vibrator 5. The outer formwork 1 and the inner formwork 2 are both steel formworks, and the outer formwork 1 and the inner formwork 2 are rectangular, circular or square, and the present embodiment is rectangular. The outer formwork 1 and the inner formwork 2 are made according to the design size of the inspection well. The upper and lower ports of the outer formwork 1 are both open structures, which are assembled from four side panels, and the joints are welded and sealed with adhesive strips. A bottom plate 2-1 is welded to the lower end of the inner formwork 2, and the upper port of the inner formwork 2 is an open structure. The inner formwork 2 is assembled from five steel plates, and the joints are welded and sealed with adhesive strips.

[0027] The inner formwork 2 is nested in the outer formwork 1. The gaps between the side plates of the inner formwork 2 and the side plates of the outer formwork 1, and between the bottom plate 2-1 of the inner formwork 2 and the bottom of the well are all casting areas. The outer formwork 1 and the inner formwork 2 are connected by tension bolts 3. The two ends of the tension bolts 3 pass through the side plates of the outer formwork 1 and the inner formwork 2 respectively. Two tension bolts 3 are installed at the bottom and the top of the opposite sides of the outer formwork 1 and the inner formwork 2 respectively. The tension bolts 3 are composed of long screws, nuts and sleeves, with a total of eight. The tension bolts 3 are through-length structures, with four on each side of the template in the horizontal and vertical directions, which are used to fix the outer formwork 1 and the inner formwork 2 and prevent the inner formwork 2 from shifting during use. The part where the screw contacts the concrete is isolated with a plastic sleeve for easy extraction.

[0028] The side plates of the outer formwork 1 and the inner formwork 2 are symmetrically provided with reserved holes 1-1, which are consistent with the direction of the cable tube. The cable passes through here after the construction is completed. The hole sleeve 4 runs through the reserved hole 1-1. The hole sleeve 4 is a sleeve with a hollow structure, and its cross-section is rectangular or circular. The size of the hole sleeve 4 is designed according to the reserved hole 1-1 of the inspection well. When pouring concrete, it passes through the reserved hole 1-1. The hole sleeve 4 provides support and isolation for the concrete at the reserved hole 1-1 to form a closed space.

[0029] The outer side surfaces of the four side panels of the outer formwork 1 are installed with attached vibrators 5, four of which are evenly distributed on each surface and connected in series. Vibration is generated by power supply from the shipping trolley to make the internal concrete dense. The bottom plate 2-1 of the inner formwork 2 is installed with attached vibrators 5, four of which are evenly distributed and connected in series. Vibration is generated by power supply from the shipping trolley to make the internal concrete dense. The attached vibrators 5 are electrically connected to the power supply of the shipping trolley through the wire 6 to introduce current.

[0030] A concrete conveying trough 7 is arranged above the outer formwork 1 and the inner formwork 2. The concrete conveying trough 7 is in the shape of an arc-shaped long trough. It is a two-section telescopic structure and is connected and fixed to a shipping trolley (not shown in the figure) through a bracket 8. The bracket 8 connects the concrete conveying trough 7 and the shipping trolley. The bracket 8 can adjust the position and direction. The concrete transported by the tank truck can flow into the formwork quickly and accurately through the concrete conveying trough 7.

[0031] The use process of this embodiment is: excavate the inspection well foundation trench according to the size, the size is 50cm wider on each side than the designed well size, assemble the outer template 1 outside the foundation pit, put the outer template 1 into the foundation trench, then tie and arrange the steel skeleton according to the design and put it into the outer template 1, assemble the inner template 2 and nest it into the outer template 1, and insert the hole sleeve mold 4 into the reserved hole 1-1, insert the tension bolt 3 and tighten the nut. Start the shipping car, which can use new energy and be equipped with a cargo box, adjust the concrete conveying trough 7 to a suitable position, and connect the attached vibrator 5 to the power supply of the shipping car, and start feeding the concrete conveying trough 7 from the concrete tank truck, and flow into the pouring area. After the bottom plate 2-1 is full, turn on the internal attached vibrator 5, and continue to pour the side plate after vibrating and compacting. After pouring to the top, turn on the external attached vibrator 5 to vibrate and compact the side plate. After all are completed, let it stand for initial setting and then remove the template. After the template is removed, the shipping car can be stored and moved to the next construction site to repeat this process. Embodiment 2

[0032] See also Figure 3 , Figure 4 A funnel assembly is provided on the top of the outer formwork 1 and the inner formwork 2. The funnel assembly is mainly composed of a funnel 9, a feed pipe 10 and a side guide mechanism. The upper port of the funnel 9 is square, and the upper port of the feed pipe 10 is connected to the discharge port of the funnel 9. The middle and lower part of the feed pipe 10 is placed in the casting area between the inner formwork 1 and the outer formwork 2, and side guide mechanisms are symmetrically provided on both sides of the feed pipe 10.

[0033] The side guide mechanism is mainly composed of a side guide wheel 11, an ear seat 12 and a support plate 13. The axis of the side guide wheel 11 is arranged vertically, and the tread of the side guide wheel 11 is rollingly matched with the side plate of the outer template 1 or the inner template 2. The side guide wheel 11 is rotatably connected to the ear plate 12-1 of the ear seat 12 through the wheel axle 11-1. An adjustment component is provided between the side end plate 12-2 of the ear seat 12 and the support plate 13. The support plate 13 is arranged horizontally, and the inner end of the support plate 13 is welded to the discharge pipe 10.

[0034] The adjustment assembly is mainly composed of an adjustment plate 14, an adjustment screw 15 and a fixed plate 16. The adjustment plate 14 is L-shaped. The horizontal portion of the adjustment plate 14 is welded to the upper end of the outer side of the side end plate 12-2. The vertical portion of the adjustment plate 14 passes through the adjustment hole of the support plate 13. The adjustment hole is a long hole. A fixed plate 16 is welded to the upper portion of the outer end of the support plate 13. An adjustment screw 15 is installed between the fixed plate 16 and the vertical portion of the adjustment plate 14. The fixed plate 16 is provided with a threaded hole. The adjustment screw 15 is screwed with the threaded hole. A locking nut is screwed on the adjustment screw 15. The inner end of the adjustment screw 15 passes through the vertical portion of the adjustment plate 14. Positioning rings 17 are welded to the adjustment screws 15 on both sides of the vertical portion of the adjustment plate 14. The adjustment assembly is used to adjust the distance between the side guide wheel 11 and the outer template 1 or the inner template 2.

[0035] A supporting roller assembly is provided between the ear seat 12 and the outer template 1, and between the ear seat 12 and the inner template 2. The supporting roller assembly mainly consists of a roller 18, a roller shaft 19 and a roller support plate 20. The axis of the roller 18 is arranged horizontally, the tread of the roller 18 is rollingly connected to the top of the outer template 1 or the inner template 2, the roller 18 is rotatably connected to the roller shaft 19, the outer end of the roller shaft 19 passes through the roller support plate 20 and is connected to the roller support plate 20, and the lower end of the roller support plate 20 is welded to the ear plate 12-1 of the ear seat 12. The supporting roller assembly reduces the resistance of the funnel assembly moving on the template.

[0036] When pouring concrete, the funnel assembly moves on the outer formwork 1 and the inner formwork 2 with the pouring position, and the concrete in the concrete conveying trough 7 enters the funnel 9, and then enters the pouring area through the discharge pipe 10, ensuring that all the concrete enters the pouring area to prevent the concrete from leaking out.

[0037] The utility model can also be used in the construction of hand holes and small manhole inspection wells for underground communication cables or low-voltage cable pipelines, realizing assembly of prefabricated formwork, rapid concrete molding, electric vibration, and convenient disassembly.

[0038] The above description is only a preferred feasible embodiment of the present utility model, and does not limit the scope of rights of the present utility model. All equivalent structural changes made using the contents of the specification and drawings of the present utility model are included in the scope of rights of the present utility model.

Claims

1. A cast-in-place concrete inspection well construction device, comprising a template, the template is a steel template, and is characterized in that: The template comprises an inner template and an outer template, wherein the inner template is nested in the outer template, a bottom plate is provided at the lower end of the inner template, and casting areas are provided between the inner template and the side plates of the outer template, and between the bottom plate of the inner template and the bottom of the well, and tension bolts are provided between the inner template and the outer template; The bottom plate of the inner template is provided with an attached vibrator, and the side plate of the outer template is provided with an attached vibrator; the side plates on both sides of the inner template and the outer template are symmetrically provided with reserved holes, and a hole sleeve mold penetrates through the reserved holes, and the hole sleeve mold is a hollow structure.

2. The cast-in-place concrete inspection well construction device according to claim 1 is characterized in that: The inner template and the outer template are circular, square or rectangular.

3. The cast-in-place concrete inspection well construction device according to claim 1 is characterized in that: A funnel assembly is provided on the top of the inner template and the outer template, and the funnel assembly includes a funnel, a feed pipe and a side guide mechanism. The upper port of the feed pipe is connected to the discharge port of the funnel, the middle and lower part of the feed pipe is placed between the inner template and the outer template, and the side guide mechanisms are symmetrically provided on both sides of the feed pipe.

4. The cast-in-place concrete inspection well construction device according to claim 3 is characterized in that: The side guide mechanism includes a side guide wheel, an ear seat and a support plate. The axis of the side guide wheel is arranged vertically, the tread of the side guide wheel is rollingly matched with the side plate of the inner template or the outer template, the side guide wheel is rotatably connected to the ear plate of the ear seat through the wheel axle, an adjustment component is provided between the bottom plate of the ear seat and the support plate, and the support plate is arranged horizontally and fixedly connected to the discharge pipe.

5. The cast-in-place concrete inspection well construction device according to claim 4 is characterized in that: The adjustment assembly includes an adjustment plate, an adjustment screw and a fixed plate. The adjustment plate is L-shaped. The horizontal portion of the adjustment plate is fixedly connected to the upper end of the ear seat side end plate. The vertical portion of the adjustment plate passes through the adjustment hole of the support plate. The outer end of the support plate is fixedly connected to the fixed plate. An adjustment screw is provided between the fixed plate and the adjustment plate.

6. The cast-in-place concrete inspection well construction device according to claim 4 is characterized in that: A supporting roller assembly is provided between the ear seat and the inner template and between the ear seat and the outer template. The supporting roller assembly includes a roller, a roller shaft and a roller support plate. The axis of the roller is arranged horizontally, the tread of the roller is rollingly connected to the top of the inner template or the outer template, the roller is rotationally connected to the roller shaft, the outer end of the roller shaft is connected to the roller support plate, and the roller support plate is connected to the ear plate of the ear seat.

7. The cast-in-place concrete inspection well construction device according to claim 5 is characterized in that: The adjusting screws on both sides of the vertical part of the adjusting plate are fixedly connected with positioning rings.

8. The cast-in-place concrete inspection well construction device according to claim 5 is characterized in that: The adjusting screw is screwed with a locking nut.

9. The cast-in-place concrete inspection well construction device according to claim 3 is characterized in that: The upper port of the funnel is square.