Quick dismounting and transferring device for cross-line beam plate
By designing a span beam and slab rapid removal and transport device, using the combination of columns, cross beams, longitudinal beams, slide rails, sliding vehicles, lifting beams and lifting systems, the problems of traditional bridge removal methods affecting traffic, long cycles, high risks and high costs are solved, and rapid, safe and economical beam and slab removal and transport are achieved.
Patent Information
- Application Number
- CN202420496791.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-14
- Publication Date
- 2025-03-07
- Estimated Expiration
- 2034-03-14
AI Technical Summary
The traditional cross-bridge removal method has problems that affect old road traffic, long construction cycle, high operational risk and high demolition cost.
A rapid removal and transport device for span beams and slabs is designed, including columns, cross beams, longitudinal beams, slide rails, slide trucks, lifting beams and lifting systems. These components are erected into an integral frame to provide support for the lifting system and realize the rapid removal and transport of beams and slabs.
The device can quickly remove and transfer beams without affecting lower traffic, reducing the cost of removal, simplifying the operation process and improving safety.
Smart Images

Figure CN222575292U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of bridge dismantling, and particularly relates to a device for quickly dismantling and transporting a cross-line beam plate. Background Art
[0002] With the rapid development of my country's expressway construction, many previously built sections are unable to meet the current demand for greater traffic due to low design standards, oversized sections, and service periods during repairs. In order to meet the needs of economic development, the original cross-line bridges on some roads are demolished and rebuilt. There are two traditional methods for demolishing cross-line bridges. One is blasting demolition, which requires traffic to be interrupted for 36 hours, which has a great impact on the traffic on the old road. The procedures for using explosives are cumbersome, the approval cycle is long, and it is easy to damage the structure of the road below, making the operation dangerous. The other method is mechanical demolition, which requires traffic to be interrupted for 24 hours, which has a great impact on the traffic on the old road, and requires large-scale mechanical equipment for transportation, and the demolition cost is high. Utility Model Content
[0003] The purpose of the utility model is to provide a fast dismantling and transporting device for cross-line beams and slabs, so as to solve the problems in the above-mentioned background technology that when the bridge is dismantled, the traffic on the old road is affected; the blasting demolition method has a long construction period and high operation risk; and the mechanical demolition method requires the cooperation of large-scale machinery and has high demolition costs.
[0004] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0005] A device for quickly dismantling and transferring cross-line beams and slabs, comprising columns, cross beams, longitudinal beams, slide rails, a sliding trolley, a lifting beam and a lifting system; the columns are arranged on both sides of the beam slab; the cross beam is spanned directly above the beam slab and arranged at intervals, and its two ends are respectively fixedly connected to the two columns; the longitudinal beam is arranged at the top of both sides of the cross beam along the length direction of the beam slab; the slide rail is arranged on the top surface of the longitudinal beam; the sliding trolley is arranged on the slide rail and cooperates with the slide rail; the lifting beam is spanned above the beam slab, and its two ends are respectively fixedly connected to the two sliding trolleys; the lifting system is arranged on the lifting beam and connected to the beam slab.
[0006] Furthermore, the lifting system includes a lifting pulley, a lifting motor and a cable; the lifting pulley is symmetrically arranged on the lifting beam; the lifting motor is arranged on the lifting beam corresponding to the lifting pulley; one end of the cable is connected to the lifting motor, and the other end is connected to the beam plate after bypassing the lifting pulley.
[0007] Furthermore, a stabilizing block is arranged on the side of the column, and the stabilizing block abuts against the cap beam below the beam plate.
[0008] Furthermore, track limiters are provided at both ends of the slide rail.
[0009] Furthermore, the pull rope is a steel wire rope, and a rope clamp is provided at the end thereof.
[0010] Furthermore, the columns are steel pipe columns and are arranged at intervals along the length direction of the beam and slab.
[0011] Furthermore, two groups of the lifting beam and the lifting system are provided corresponding to the two ends of the beam plate.
[0012] The utility model has the following beneficial effects:
[0013] 1. The utility model provides a fast dismantling and transporting device for cross-line beams and slabs. The frame is constructed by columns, cross beams and longitudinal beams to provide support for the lifting system. After the cutting of both ends of the beams and slabs is completed, the dismantled beams and slabs are transported on the bridge through the cooperation of the lifting system and the skid trolley, which does not affect the lower traffic operation and does not require the installation of additional large-scale mechanical equipment, thereby reducing the dismantling cost.
[0014] 2. The utility model provides a device for quickly dismantling and transferring cross-line beams and slabs, in which a stabilizing block is arranged on the side of a column and abuts against the cap beam, thereby ensuring the stability of the structure during cutting operations.
[0015] 3. The utility model provides a device for quickly dismantling and transferring cross-line beams and slabs, which has a simple structure and is easy to operate. The cooperation of two sets of lifting systems can realize the stable lifting and transfer of beams and slabs. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the overall structure of the dismantling and transporting device involved in the utility model;
[0017] Figure 2 This is a schematic diagram of the transport working state of the dismantling and transporting device involved in the utility model;
[0018] Figure 3 This is a schematic diagram of the layout of the crossbeams involved in the utility model.
[0019] In the figure: 1-column, 2-stabilizing block, 3-cross beam, 4-longitudinal beam, 5-slide rail, 6-sliding car, 7-lifting beam, 8-lifting motor, 9-lifting pulley, 10-cable, 11-beam plate, 12-cap beam. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0021] like Figure 1-3 As shown, the utility model provides a cross-line beam slab rapid dismantling and transporting device, which is used for the dismantling operation of the beam slab 11. The beam slab 11 is arranged on the cap beam 12, and includes a column 1, a stabilizing block 2, a cross beam 3, a longitudinal beam 4, a slide rail 5, a sliding vehicle 6, a lifting beam 7 and a lifting system; the column 1 is arranged on both sides of the beam slab 11; the stabilizing block 2 is arranged on the side of the column 1 and abuts against the cap beam 12, and the stability of the cap beam 12 is ensured during the cutting operation of the beam slab 11; the cross beam 3 is arranged across the beam slab 11 and is arranged at intervals, and its two ends are respectively fixedly connected to the two columns 1; the longitudinal beam 4 is arranged on the cross beam 3 along the length direction of the beam slab 11 The top of both sides; the slide rail 5 is arranged on the top surface of the longitudinal beam 4; the sliding vehicle 6 is arranged on the slide rail 5 and cooperates with the slide rail 5; the lifting beam 7 is arranged across the beam plate 11 and is higher than the cross beam 3, and its two ends are respectively fixed to the two sliding vehicles 6; the lifting system is arranged on the lifting beam 7 and connected to the beam plate 11, and the lifting system includes a lifting motor 8, a lifting pulley 9 and a cable 10; the lifting pulley 9 is symmetrically arranged on the lifting beam 7; the lifting motor 8 is arranged on the lifting beam 7 corresponding to the lifting pulley 9; one end of the cable 10 is connected to the lifting motor 8, and the other end is connected to the beam plate 11 to be removed after bypassing the lifting pulley 9.
[0022] After the cutting of both ends of the beam 11 is completed, the lifting motor 8 lifts the beam 11 through the cable 10, and then starts the sliding vehicle 6 to drive the lifting beam 7 to move, and then transfers the beam 11 to the subsequent transportation tool to complete the dismantling and transportation of the beam 11.
[0023] The columns 1 are steel pipe columns and are arranged at intervals along the length direction of the beam slab 11 .
[0024] The stabilizing block 2 includes a support column and a pad. The inner end of the support column is detachably connected to the column 1. The pad is arranged at the outer end of the support column and abuts against the cap beam 12 to expand the force-bearing area and avoid structural damage.
[0025] The cross beam 3 is arranged across the beam plate 11 .
[0026] The axis of the longitudinal beam 4 intersects with the extended axis of the column 1 .
[0027] Track limiters are arranged at both ends of the slide rail 5 to limit the movement range of the slide vehicle 6 .
[0028] The skid steer 6 is electrically connected to the control system.
[0029] The lifting beam 7 and the lifting system are both provided with two groups corresponding to the two ends of the beam plate 11. The two groups of lifting systems cooperate with each other to complete the removal and transportation of the beam plate 11.
[0030] The cable 10 is a steel wire rope, and a rope clamp is arranged at the end thereof.
[0031] When the beam slab 11 is removed, the following steps are included:
[0032] Step 1: Preliminary preparation;
[0033] 1) Remove the billboards on the guardrails on both sides of beam slab 11;
[0034] 2) Remove the water pipeline on the bridge;
[0035] 3) Clear away dirt and debris from the bridge;
[0036] 4) Prepare standard power and water sources, including 380V 100kw, 63A or above power supply, a 200kW standby generator, and water source (water pressure 4-6bar, water volume 7L / min or above);
[0037] 5) Cutting equipment and staff are in place to ensure that the equipment is in good condition;
[0038] 6) Customized canvas tent: Since the wet joint concrete between the beam and slab 11 is not very dense, a small amount of cooling water will penetrate when cutting. In order to solve the impact of this problem on driving, a canvas tent is used to cover the bottom of the bridge during construction. The top is fixed on the guardrails on both sides and forms a certain slope in the direction of the side ditch, so that the cooling water can flow to the drainage ditch outside the road by itself;
[0039] Step 2: Install the column 1, the stabilizing block 2, the cross beam 3, the longitudinal beam 4, the slide rail 5, the sliding vehicle 6, the lifting beam 7, the lifting motor 8, the lifting pulley 9 and the cable 10 in sequence;
[0040] Step 3: Set up hanging points on the beam slab 11; the hanging points should be arranged at the original designed hanging point positions, and the hanging points can be in the form of wire rope bottom binding, drilling hanging holes, etc.; the hanging point drilling should be done with a reinforced concrete high-speed drilling machine; use drilling equipment to drill hanging holes and correct the wet joint positions. The hanging holes should be located about 0.8 meters away from both ends of the beam slab 11. After drilling a 12CM long and 6.3CM wide hanging hole, tie the wire rope along the hanging hole in advance to shorten the construction time;
[0041] Step 4: The beam and slab 11 all meet the requirements of vibration-free straight-line cutting. The cutting equipment only operates on the bridge deck and no debris such as gravel falls, which does not affect the passage of vehicles under the bridge. When cutting, first cut off the connection and guardrail between the middle pier cap beam 12 and the beam and slab 11 at the abutment to completely separate the two-hole bridge, and then cut along the wet joint in a straight line. The cutting depth is 73 cm (use 80 cm, 120 cm, and 160 cm blades to cut in sequence respectively). The cutting seam should be ensured to be consistent with the wet joint to ensure that the steel bars connecting the wet joint are cut off, so that the hoisting work can proceed smoothly.
[0042] Step 5: Connect the cable 10 to the beam 11; to ensure smooth lifting, lift the beams 11 in sequence and ensure that each beam 11 is not attached to each other; pass the wire rope through the lifting hole, hold the beam 11 to be lifted, and then clamp the wire rope with a rope clamp;
[0043] Step 6: Turn on the lifting motor 8 and pull the wire rope to the position where the bottom of the beam 11 is higher than the cross beam 3, and then lock the rope clamp of the cable 10 to prevent the movable beam 11 from falling off;
[0044] Step 7: Control the skid trolley 6 to move it to the non-dismantling section, then adjust the lifting motor 8 to lower the beam slab 11 into the transport mechanism, and transport the dismantled beam slab 11 out through the transport mechanism;
[0045] Step 8: Repeat steps 3 to 7 until all beams and slabs 11 are dismantled and transported.
[0046] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A fast dismantling and transporting device for cross-line beams and slabs, characterized in that: The invention comprises a column (1), a cross beam (3), a longitudinal beam (4), a slide rail (5), a sliding vehicle (6), a lifting beam (7) and a lifting system; the column (1) is arranged on both sides of the beam plate (11); the cross beam (3) is arranged across the beam plate (11) and is arranged at intervals, and its two ends are respectively fixedly connected to the two columns (1); the longitudinal beam (4) is arranged at the top of both sides of the cross beam (3) along the length direction of the beam plate (11); the slide rail (5) is arranged on the top surface of the longitudinal beam (4); the sliding vehicle (6) is arranged on the slide rail (5) and cooperates with the slide rail (5); the lifting beam (7) is arranged across the beam plate (11), and its two ends are respectively fixedly connected to the two sliding vehicles (6); the lifting system is arranged on the lifting beam (7) and connected to the beam plate (11).
2. The device for rapid removal and transportation of cross-line beam slabs according to claim 1 is characterized in that: The lifting system comprises a lifting pulley (9), a lifting motor (8) and a cable (10); the lifting pulley (9) is symmetrically arranged on the lifting beam (7); the lifting motor (8) is arranged on the lifting beam (7) corresponding to the lifting pulley (9); one end of the cable (10) is connected to the lifting motor (8), and the other end is connected to the beam plate (11) after passing around the lifting pulley (9).
3. The device for rapid removal and transportation of cross-line beam slabs according to claim 1 is characterized in that: A stabilizing block (2) is provided on the side of the column (1), and the stabilizing block (2) abuts against a cap beam (12) below the beam plate (11).
4. The device for rapid removal and transportation of cross-line beam slabs according to claim 1 is characterized in that: Track limiters are provided at both ends of the slide rail (5).
5. The device for rapid removal and transportation of cross-line beam slabs according to claim 2 is characterized in that: The pull rope (10) is a steel wire rope, and a rope clamp is provided at the end thereof.
6. The device for rapid removal and transportation of cross-line beam slabs according to claim 1 is characterized in that: The columns (1) are steel pipe columns and are arranged at intervals along the length direction of the beam plate (11).
7. The device for rapid removal and transportation of cross-line beam slabs according to claim 1 is characterized in that: The lifting beam (7) and the lifting system are both provided in two groups corresponding to the two ends of the beam plate (11).