Power grid project management method
A technology of engineering management and power grid, applied in the direction of data processing applications, instruments, information technology support systems, etc., can solve the problems of human and physical waste, error-prone, slow statistical data, etc., to reduce costs, avoid omissions, and fast and accurate statistical data Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0050] figure 1 A schematic flowchart of a power grid project management method provided by the first embodiment of the present invention is shown.
[0051] The method flow shown in this embodiment includes the following steps:
[0052] Step S110, acquiring the project management task, the category and level of the project management task.
[0053]In this embodiment, the project management task is obtained in response to the user's input operation, and the task category and level corresponding to the project management task are obtained according to the user's selection operation.
[0054] Wherein, according to the attributes of the project management tasks, the categories of the project management tasks can be divided into relocation projects, infrastructure projects, technical renovation projects, and the like.
[0055] According to the scale of the engineering management tasks, the grades of the engineering management tasks can be divided into first-level tasks, second-le...
Embodiment 2
[0112] image 3 A schematic flowchart of a power grid project management method provided by the second embodiment of the present invention is shown.
[0113] The method flow shown in this embodiment includes the following steps:
[0114] Step S210, acquiring the project management task, the category and level of the project management task.
[0115] In step S220, the multi-level task implementation node of the engineering management task corresponding to the category is determined according to the preset engineering management task template.
[0116] Step S230, according to the actual duration of each task implementation node of all historical projects with the same category and level as the engineering management task, a preset calculation is used to obtain a duration threshold corresponding to each task implementation node.
[0117] Step S240, determining the planned duration corresponding to the multi-level task implementation node according to the duration threshold.
...
Embodiment 3
[0134] Figure 4 A schematic structural diagram of a power grid engineering management system provided by an embodiment of the present invention is shown. The power grid engineering management system 300 corresponds to the power grid engineering management method in Embodiment 1.
[0135] The power grid project management system 300 includes: a task acquisition module 310 , a task implementation node determination module 320 , a planned construction period evaluation module 330 , an actual construction period acquisition module 340 , a storage module 350 , a reading generation module 360 and a calculation module 370 .
[0136] The task acquisition module 310 is configured to acquire the project management task, the category and level of the project management task.
[0137] The task implementation node determining module 320 is configured to determine the multi-level task implementation node of the engineering management task according to the category.
[0138] The planned d...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com