On-line pressure regulating device and on-line pressure regulating method for gas transmission pipeline
A pressure regulating device and gas pipeline technology, which is applied in the pipeline system, gas/liquid distribution and storage, mechanical equipment, etc., can solve the problem that the pressure cannot be transferred relatively smoothly, the backup system cannot be put into use in time, and there is no automatic detection and protection and other issues, to achieve the effect of reducing equipment investment and construction costs, reducing construction procedures, and facilitating operation and maintenance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] Example 1, such as figure 1 As shown, an online pressure regulating device for a gas transmission pipeline according to an embodiment of the present invention includes: an active pressure regulating branch pipeline 5-1 and a standby pressure regulating branch pipeline 6-1.
[0041] Both ends of the pressure regulating branch pipeline 5-1 are respectively connected with the first manifold 4 and the second manifold 7, and the pressure regulating branch pipeline 5-1 is sequentially connected with the first process ball valve 5-2, The first process belt actuator ball valve 5-3, the first monitoring pressure regulating valve 5-4, the first action pressure regulating valve 5-5, the first local temperature gauge 5-23, and the first pressure transmitter 5-24 , the second pressure transmitter 5-25, the third pressure transmitter 5-26, the first check valve 5-6 and the second process ball valve 5-7, the first monitoring pressure regulating valve 5-4 and the first The pressure tr...
Embodiment 2
[0052] Embodiment 2, an online pressure regulating method of an online pressure regulating device of a gas transmission pipeline, using the online pressure regulating device described in the embodiment, includes the following steps:
[0053] Step 1, natural gas is input into the first manifold 4, and enters the active pressure regulating branch pipeline 5-1 and the standby pressure regulating branch pipeline 6-1 respectively through the first process ball valve 5-2 and the seventh process ball valve 6-2 ;
[0054] Step 2, respectively set the first pressure controller 5-27, the second pressure controller 5-28, the first pressure high-high relay 5-29, the third pressure controller 6-27, the fourth pressure controller 6- 28 and the pressure setting value of the second pressure high-high relay 6-29, and ensure that the pressure setting values of the first operating pressure regulating valve 5-5 and the second operating pressure regulating valve 6-5 are different;
[0055] Step...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 