Grid-connected debugging method of power grid in digital power grid scene

A technology of digital grid and debugging method, which is applied in data processing applications, instruments, calculations, etc., and can solve problems such as wasting manpower and affecting equipment grid connection and operation

Pending Publication Date: 2021-03-05
海南电网有限责任公司
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] Through sorting out and researching the business process of grid-connected commissioning work, it is found that the current grid-connected commissioning work requires personnel on both sides of the commissioning operation to initiate by phone through the pre-agreed time and equipment measurement items of the grid-connected object. The personnel at the terminal side check the name, operation content, and status performance of each equipment item that needs to be measured one by one. The personnel at the main station side check the relevant display of the monitoring system according to the oral description of the station side personnel to judge whether the measurement target is met. Back and forth, each grid-connected commissioning work has to go through thousands to tens of thousands of point signal verifications and checks, which is extremely wasteful of manpower and affects the grid-connected operation of the equipment

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Grid-connected debugging method of power grid in digital power grid scene

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0021] In order to better understand the technical content of the present invention, specific embodiments are provided below, and the present invention is further described in conjunction with the accompanying drawings.

[0022] see figure 1 , a grid-connected debugging method in a digital grid scenario, comprising the following steps:

[0023] A grid-connected debugging method in a digital grid scenario, applied to a server, the method includes the following steps:

[0024] Step 101: The commissioning platform obtains multiple grid-connection requests, generates a grid-connection plan, and sends the grid-connection plan to a designated commissioning implementation object;

[0025] The grid connection request includes: the user fills in online and submits the grid connection application form to the commissioning platform.

[0026] At the same time, in an embodiment of the present invention, the commissioning platform has built-in grid-connected debugging items and a rule lib...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a grid-connected debugging method for a power grid in a digital power grid scene, and the method comprises the following steps that a main station transmits a plurality of pieces of request information to a debugging platform, and the debugging platform generates a grid-connected schedule based on the plurality of pieces of request information, and transmits the schedule toa station; a field station audits the grid-connected schedule, and if agreement is made, the field station carries out grid-connected debugging operation within agreed time; the station uploads process information to a debugging platform in the grid-connected debugging operation process, and the debugging platform checks the grid-connected debugging operation process according to the process information; and the debugging platform generates a debugging report according to the process information.

Description

technical field [0001] The invention relates to the technical field of grid-connected debugging, in particular to a method for grid-connected debugging of a power grid under the scene of a digital power grid. Background technique [0002] Through sorting out and researching the business process of grid-connected commissioning work, it is found that the current grid-connected commissioning work requires personnel on both sides of the commissioning operation to initiate by phone through the pre-agreed time and equipment measurement items of the grid-connected object. The personnel at the terminal side check the name, operation content, and status performance of each equipment item that needs to be measured one by one. The personnel at the main station side check the relevant display of the monitoring system according to the oral description of the station side personnel to judge whether the measurement target is met. Back and forth, each grid-connected commissioning work has t...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/10G06Q50/06
CPCG06Q10/103G06Q50/06
Inventor 董芸州何启远王诚潘德泰符方友林师王艳王新玉邢博翔
Owner 海南电网有限责任公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products