Model calculation based continuous casting and rolling logistic control method
A technology of model calculation and control method, applied in the direction of metal rolling, metal rolling, metal rolling racks, etc., can solve the mismatch between continuous casting rhythm and continuous rolling rhythm, inconsistent logistics and information flow, and low crane operation rate and other issues to achieve the effect of reducing manual workload, speeding up capital turnover rate and increasing production capacity
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2017-10-24
Smart Images

Figure 1
Abstract
Description
technical field
[0001] The invention belongs to the technical field of continuous casting and rolling production technology, and in particular relates to a model calculation-based continuous casting and rolling logistics control method. Background technique
[0002] At present, the slab logistics management of the continuous casting and rolling method is generally completed by manually commanding the crane and manually entering and tracking. There is a situation that the logistics and information flow are inconsistent, which may easily lead to confusion in the warehouse, inaccurate location, and low crane operation rate. The phenomenon of untimely delivery, low work efficiency, inventory backlog and affecting contract execution and many other problems, the situation of loose and tight during crane operation occurs from time to time, and the rhythm of continuous casting and continuous rolling does not match, it is difficult to guarantee the plan. orderly and smooth execution....
Examples
Embodiment Construction
[0027] The continuous casting and rolling logistics control method based on model calculation in the present invention uses a computer management system to perform model calculation, the background operating system is AIX, the background program is developed by C, the database system is oracie, and the model is coded by stored procedures. Its "four streams in one" means that the logistics control process flow of four streams continuous casting into one continuous rolling production line is as follows: figure 1 shown.
[0028] 1. Plan slab warehousing appointment
[0029] After the continuous casting slab plan is issued to the secondary computer, the secondary computer makes a storage reservation according to the off-line sign of the slab in the continuous casting slab plan, and specifies the stacking position of the slab after it goes off the line.
[0030] 2. Slab pre-hanging plan
[0031] When the slab cutting starts, the secondary computer automatically corresponds to the...