Construction method of full-section roof covering for tunnel pilot tunnel turning into main tunnel

By using folded steel cages and unfolding components to unfold the steel cages within inclined passages, the problem of difficult installation of steel cages within inclined passages is solved, effectively reducing construction time and costs.

CN115263375BActive Publication Date: 2024-11-15SHANDONG LUQIAO CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211071405.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-02
Publication Date
2024-11-15
Estimated Expiration
2042-09-02

AI Technical Summary

Technical Problem

When laying steel cages in inclined passages, it is difficult to fully prefabricate and transport the steel cages, resulting in complex construction, long construction time and high cost, as well as safety hazards.

Method used

The steel cage is folded and unfolded in an inclined channel using a unfolding assembly. Combined with airbag-assisted unfolding and locking components for fixation, the installation process of the steel cage is simplified and its dependence on space is reduced.

Benefits of technology

It greatly shortens construction time, reduces the probability of safety accidents, saves human resources and construction costs, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115263375B_ABST
    Figure CN115263375B_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of tunnel engineering construction, and specifically discloses a method for constructing a full-section roof for converting a tunnel pilot tunnel to a main tunnel, which includes S1. Construction preparation, measuring and calculating in the pilot tunnel, and then marking the corresponding position on the inner wall of the pilot tunnel; S2. Drilling and blasting, drilling the corresponding hole at the mark by a drilling trolley, then charging and connecting the holes, and detonating the explosives in the holes after the drilling trolley is withdrawn to a safe distance, and repeating this process until an oblique channel through the pilot tunnel and the main tunnel is drilled; S3. Support construction, transporting the steel cage to a designated position in the oblique channel, unfolding the steel cage through an unfolding assembly, and then installing an arc steel frame on the side of the steel cage away from the inner wall of the oblique channel, and installing an arch on the side of the steel cage close to the main tunnel, and finally spraying concrete on the steel cage; S4. Steel arch frame installation, installing the steel arch frame above the main tunnel and spraying concrete again. The present application has the effect of shortening the installation time of the steel cage in the oblique channel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of tunnel engineering construction, and in particular to a method for constructing a full-section roof covering for a tunnel pilot tunnel to a main tunnel. Background Art

[0002] The pilot tunnel includes the upper pilot tunnel, the left pilot tunnel, the parallel pilot tunnel, etc. The parallel pilot tunnel is a pilot tunnel parallel to the tunnel main tunnel, and is connected to the tunnel main tunnel through multiple oblique passages. The full section method is to excavate the tunnel section once, and then support the lining. Its advantage is that it can reduce the repeated disturbance of the surrounding rock by excavation, which is conducive to protecting the natural bearing capacity of the surrounding rock and is convenient for construction. The disadvantage is that it has strict requirements on geological conditions and requires good self-stabilization performance of the surrounding rock.

[0003] When constructing the oblique passage between the pilot tunnel and the main tunnel, the inner wall of the pilot tunnel is first excavated by a drilling trolley, and explosives are charged into the excavated hole to form an oblique passage. Then, locking anchor rods or hollow grouting anchor rods are driven into the inner wall of the oblique passage. Then, steel bars are sent into the oblique passage and a steel cage is formed by binding or welding. Concrete is sprayed on the steel cage and the inner wall of the oblique passage. Finally, an arch frame is installed above the main tunnel to cover the top and concrete is sprayed again.

[0004] With respect to the above-mentioned related technologies, the inventors believe that the following defects exist: when laying the steel cage in the oblique channel, since the diameter of the oblique channel is small, and the diameter of the steel cage is slightly different from the diameter of the oblique channel, it is difficult to completely prefabricate the steel cage outside and then transport it into the oblique channel for installation; when the steel cage is not prefabricated outside, the steel bars need to be transported to the oblique channel first and then assembled into the steel cage by workers. The operation steps are relatively complicated and time-consuming, which leads to higher construction costs and increased construction risks. Summary of the invention

[0005] In order to improve the problem of time-consuming installation of steel cages in inclined passages, the present application provides a full-section roof construction method for converting a tunnel pilot tunnel into a main tunnel.

[0006] The present application provides a method for constructing a full-section roof-covering tunnel from a pilot tunnel to a main tunnel, which adopts the following technical solutions:

[0007] A method for constructing a full-section roof for a tunnel pilot tunnel, comprising the following steps:

[0008] S1. Construction preparation: measure and calculate in the pilot tunnel, and then mark the corresponding position on the inner wall of the pilot tunnel;

[0009] S2. Drilling and blasting: Drill the corresponding holes at the marked positions with the drilling trolley, then charge the holes with explosives and detonate the explosives in the holes after the drilling trolley is withdrawn to a safe distance. Repeat this process until an oblique passage that penetrates the pilot tunnel and the main tunnel is drilled;

[0010] S3. Support construction: process the folded steel cage at the external site, and install an expansion component to control the expansion of the steel cage on the steel cage. Then, transport the steel cage to the designated position in the oblique channel, and then expand the steel cage through the expansion component. Then, install an arc steel frame on the side of the steel cage away from the oblique channel, and install an arch on the side of the steel cage close to the main tunnel. Finally, spray concrete on the steel cage.

[0011] S4. Installation of steel arch frame: install the steel arch frame above the main tunnel and spray concrete.

[0012] By adopting the above technical scheme, during the support construction, the prefabricated steel cage is first folded, and then the folded steel cage is transported to the inclined channel, the steel cage is placed at the corresponding position, and finally the folded steel cage is unfolded by the unfolding assembly, and the subsequent operation steps can be carried out. In the process of installing the steel cage, there is no need for workers to position, tie or weld the steel bars one by one, and the problem of the inconvenience of moving the prefabricated steel cage in the inclined channel caused by the small space in the inclined channel is also reduced, which greatly reduces the entire construction time, and then shortens the time when the inclined channel is not supported, that is, reduces the probability of safety accidents, and also saves human resources and shortens the construction period.

[0013] Optionally, the steel cage includes two sliding steel meshes respectively close to the inner bottom wall of the inclined channel and a plurality of folding steel meshes located between the two sliding steel meshes; the steel cage also includes a connecting component for connecting the folding steel mesh with the sliding steel mesh and two adjacent folding steel meshes, and the steel cage is also provided with a locking member for locking the steel cage.

[0014] By adopting the above technical solution, after the folded steel cage is placed at the corresponding position of the inclined channel, the steel cage is unfolded by the unfolding component, that is, the two adjacent folded steel meshes are rotated, the sliding steel mesh and the folded steel mesh are rotated through the connecting component, and then the steel cage is locked by the locking piece. The whole process is relatively simple.

[0015] Optionally, the connecting assembly includes an articulated seat and connectors hinged at both ends of the articulated seat, and the connectors are threadedly sleeved on one end of the steel bars of the sliding steel mesh close to the folded steel mesh and on both ends of the steel bars of the folded steel mesh.

[0016] By adopting the above technical scheme, when prefabricating the steel cage, threads are opened on the ends of the steel bars of the sliding steel mesh and the folding steel mesh, and then the connector is threadedly sleeved on the steel bars of the steel cage, so that the steel cage can be prefabricated in a foldable manner; when rotation occurs between the sliding steel mesh and the folding steel mesh and between two adjacent folding steel meshes, the connector rotates smoothly on the hinge seat, so that the steel cage can be folded and unfolded smoothly. At the same time, the entire connection component structure is relatively simple, reliable, and low in cost, so that the failure rate is low during actual construction.

[0017] Optionally, a plurality of channel steels are placed horizontally and perpendicular to the axis of the inner bottom wall of the inclined channel, a plurality of slide plates are integrally extended from one side of the sliding steel mesh close to the channel steel, and the slide plates are slidably arranged in the grooves of the channel steel.

[0018] By adopting the above technical solution, before the steel cage is unfolded, a channel steel is first placed under the slide plate of the steel cage. After the steel cage is placed on the channel steel, the steel cage is unfolded by the unfolding assembly. During this process, the slide plate slides relatively smoothly in the channel steel until the steel cage is fully unfolded. The sliding of the slide plate in the channel steel is smoother than the sliding of the steel cage directly on the rock and soil.

[0019] Optionally, an arc-shaped steel frame is placed in the groove at the end of the channel steel, and the arc-shaped steel frame is in contact with the inner side of the steel cage, and a plurality of groups of locking foot anchor rods are implanted in the inner wall of the oblique channel, each group of locking foot anchor rods has two locking foot anchor rods and are arranged on both sides of the arc-shaped steel frame, and a clamping rod is fixedly connected between the ends of the two locking foot anchor rods in the same group, which is against the side of the arc-shaped steel frame away from the inner wall of the oblique channel.

[0020] By adopting the above technical scheme, after the steel cage is fully unfolded, the locking foot anchor rods are implanted into the inner wall of the oblique channel, and then the arc-shaped steel frame is placed in the channel steel to make the arc-shaped steel frame fit with the steel cage, and finally the clamping rods are welded to the exposed part of the locking foot anchor rods, so that the arc-shaped steel frame is fixed by the clamping rods and the locking foot anchor rods, and the fixed arc-shaped steel plate further strengthens the fixation of the steel cage, that is, the steel cage does not need to be fixed by other anchor rods, which reduces the number of anchor rods required to be implanted and saves construction time. At the same time, the oblique channel after the concrete is sprayed is also more stable due to the support of the arc-shaped steel frame.

[0021] Optionally, clamping plates are fixedly connected to both ends of the channel of the channel steel, and the clamping plates are in contact with a side of the arc-shaped steel frame away from the steel cage, and when no arc-shaped steel frame is placed in the channel steel, the clamping plates are not connected to the channel steel.

[0022] By adopting the above technical solution, after the arc steel frame is installed, the clamping plates are fixed to the two ends of the channel steel in the groove, so that the clamping plates are pressed against the side of the arc steel frame away from the steel cage. At this time, the channel steel and the clamping plates further reinforce the arc steel frame, thereby making the arc steel frame more stably fix the steel cage.

[0023] Optionally, the unfolding assembly in S3 includes an airbag arranged on the inner side of the steel cage, a cable tie arranged on the steel bar and wrapped around the outside of the airbag, and an air pump connected to the airbag, and when the airbag is in a full state, the airbag is adapted to the arc portion of the oblique channel.

[0024] By adopting the above technical solution, before unfolding the steel cage, the airbag is first connected to the steel cage by a cable tie, and then the air pump is turned on to input air into the airbag, thereby expanding the airbag. During the expansion and stretching process, the airbag pushes the steel cage to unfold. When the steel cage is unfolded and locked, the airbag is deflated and the cable tie is removed to remove the airbag from the steel cage. During the process of unfolding the steel cage, the operation is relatively simple, and the airbag can be reused, which effectively saves resources.

[0025] Optionally, the locking member is a locking block fixedly connected between two adjacent folded steel meshes and between the folded steel mesh and the sliding steel mesh, and when the folded steel mesh and the sliding steel mesh are not fully unfolded, the locking block is not set on the steel cage.

[0026] By adopting the above technical solution, after the steel cage is unfolded, the locking blocks are placed at the hinges of the steel cage, and then the locking blocks are fixed. The operation steps are relatively simple and the structure is simple.

[0027] Optionally, a reinforcing rod is placed between the channel steels, and a fixing groove that is slidingly adapted to the reinforcing rod is opened on the side of the channel steel away from the bottom wall of the inclined channel, and the reinforcing rod is also threaded with nuts on both sides of the channel steel.

[0028] By adopting the above technical solution, after laying the channel steel, the reinforcing rod is placed on the channel steel, and then by tightening the nuts, the reinforcing rod is clamped to the channel steel through the nuts located on both sides of the channel steel, so that the reinforcing hoop and the channel steel are relatively stable to each other, thereby further enhancing the stability of the oblique channel after grouting.

[0029] In summary, the present application includes at least one of the following beneficial technical effects:

[0030] 1. The folded steel cage in the oblique channel can be unfolded by unfolding the components, and the subsequent operation steps can be carried out. In the process of installing the steel cage, there is no need for workers to locate, tie or weld steel bars one by one, and the problem of inconvenience of moving the prefabricated steel cage in the oblique channel caused by the small space in the oblique channel is also reduced, which greatly reduces the entire construction time;

[0031] 2. During the expansion of the steel cage, the slide plate slides smoothly in the channel steel until the steel cage is fully expanded. The slide plate slides more smoothly in the channel steel than the steel cage slides directly on the rock and soil;

[0032] 3. Before unfolding the steel cage, first connect the airbag to the steel cage with a cable tie, then turn on the air pump to input air into the airbag, so that the airbag expands. During the expansion and stretching process, the airbag pushes the steel cage to unfold. When the steel cage is unfolded and locked, deflate the airbag and remove the cable tie to remove the airbag from the steel cage. In the process of unfolding the steel cage, the operation is relatively simple, and the airbag can be reused, which effectively saves resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 It is a structural schematic diagram of the embodiment of the present application mainly used to display the unfolding components, steel cage, connection components and channel steel.

[0034] Figure 2 The embodiment of the present application is mainly used to show the structural schematic diagram of the steel cage, connection components, arches, channel steels and curved steel frames.

[0035] Figure 3 It is a schematic diagram of the structure of the steel cage in a folded state in an embodiment of the present application.

[0036] Figure numerals: 1. unfolding assembly; 11. airbag; 12. cable tie; 13. air pump; 2. steel cage; 21. sliding steel mesh; 211. slide plate; 22. folding steel mesh; 3. connecting assembly; 31. hinged seat; 32. connector; 4. arch; 5. locking block; 6. channel steel; 61. reinforcing rod; 62. nut; 7. arc steel frame; 71. locking foot anchor rod; 72. clamping rod; 73. clamping plate. DETAILED DESCRIPTION

[0037] The following is combined with Figure 1-3 This application is described in further detail.

[0038] The present application discloses a method for constructing a tunnel pilot tunnel into a full-section roof. Figure 1 and Figure 2 The construction method of the full-section roof of the tunnel pilot tunnel to the main tunnel includes the following steps:

[0039] S1. Construction preparation: measure and calculate in the pilot tunnel, and then mark the corresponding position on the inner wall of the pilot tunnel;

[0040] S2. Drilling and blasting: Drill the corresponding holes at the marked positions with the drilling trolley, then charge the holes with explosives and detonate the explosives in the holes after the drilling trolley is withdrawn to a safe distance. Repeat this process until an oblique passage that penetrates the pilot tunnel and the main tunnel is drilled;

[0041] S3. Support construction, processing the folded steel cage 2 at the external site, and installing the unfolding component 1 for controlling the unfolding of the steel cage 2 on the steel cage 2, then transporting the steel cage 2 to the designated position in the oblique channel, unfolding the steel cage 2 by the unfolding component 1, and then installing the arc steel frame 7 on the side of the steel cage 2 away from the inner wall of the oblique channel, and installing the arch 4 on the side of the steel cage 2 close to the main hole, and finally spraying concrete on the steel cage 2;

[0042] S4. Installation of steel arch frame: install the steel arch frame above the main tunnel and spray concrete.

[0043] The arch 4 is a steel structure arch 4, and a plurality of foot locking anchor rods 71 ​​are buried on both sides of the arch 4. The top of the arch 4 is welded to an arch frame for supporting the guide hole, and finally concrete is poured.

[0044] During the support construction, the folded steel cage 2 is transported to the inclined channel, the steel cage 2 is placed at the corresponding position, and finally the folded steel cage 2 is unfolded by the unfolding component 1, and the subsequent operation steps can be carried out. In the process of installing the steel cage 2, there is no need for workers to position, tie or weld the steel bars one by one, and the problem of the prefabricated steel cage 2 being inconvenient to move in the inclined channel due to the small space in the inclined channel is also reduced, which greatly reduces the entire construction time, and thus shortens the time when the inclined channel is not supported, that is, reduces the probability of safety accidents, and also saves human resources and shortens the construction period.

[0045] Reference Figure 1 The steel cage 2 in S3 includes two sliding steel meshes 21 respectively close to the inner bottom wall of the oblique channel and a plurality of folded steel meshes 22 located between the two sliding steel meshes 21. There can be two, three or more folded steel meshes 22, but the more folded steel meshes 22, the lower the strength. In the embodiment of the present application, there are two folded steel meshes 22; the steel cage 2 also includes a connecting component 3 for connecting the folded steel mesh 22 with the sliding steel mesh 21 and two adjacent folded steel meshes 22. The steel cage 2 is also provided with a locking member for locking the steel cage 2.

[0046] After the folded steel cage 2 is placed at the corresponding position of the oblique channel, the steel cage 2 is unfolded by the unfolding component 1, that is, the two adjacent folded steel meshes 22 are rotated through the connecting component 3, the sliding steel mesh 21 and the folded steel mesh 22 are rotated, and then the steel cage 2 is locked by the locking piece. The whole process is relatively simple.

[0047] Reference Figure 1 The connecting assembly 3 includes an articulated seat 31 and connectors 32 hinged at both ends of the articulated seat 31. The connectors 32 are threadedly sleeved on one end of the steel bars of the sliding steel mesh 21 close to the folded steel mesh 22 and on both ends of the steel bars of the folded steel mesh 22.

[0048] When prefabricating the steel cage 2, threads are opened on the steel bars of the sliding steel mesh 21 and the steel bars of the folding steel mesh 22, and then the connector 32 is threadedly sleeved on the steel bars of the steel cage 2; when rotation occurs between the sliding steel mesh 21 and the folding steel mesh 22 and between two adjacent folding steel meshes 22, the connector 32 rotates smoothly on the hinge seat 31, thereby allowing the steel cage 2 to be folded and unfolded smoothly.

[0049] Reference Figure 2 When the steel mesh is fully unfolded, the locking member is a locking block 5 welded between two adjacent folded steel meshes 22 and between the folded steel mesh 22 and the sliding steel mesh 21. In the embodiment of the present application, the locking block 5 is welded at the gap between the hinge seat 31 and the connector 32. After the steel cage 2 is unfolded, the locking block 5 is placed at each hinge of the steel cage 2, and then the locking block 5 is fixed. The operation steps are relatively simple and the structure is simple.

[0050] Reference Figure 2 and 3 A plurality of channel steels 6 are placed horizontally and perpendicular to the axis of the bottom wall of the oblique channel. A plurality of slide plates 211 are integrally extended on one side of the sliding steel mesh 21 close to the channel steel 6. The two side edges of the slide plates 211 along the length direction of the channel steel 6 are upturned, and the slide plates 211 are slidably arranged in the groove of the channel steel 6. A reinforcing rod 61 is placed between the channel steels 6. A fixing groove that is slidably matched with the reinforcing rod 61 is provided on the side of the channel steel 6 away from the bottom wall of the oblique channel. The reinforcing rod 61 can be welded and fixed to the channel steel 6, or nuts 62 can be threadedly sleeved on both sides of the reinforcing rod 61 on the channel steel 6. In the embodiment of the present application, the reinforcing rod 61 is threadedly connected to the nuts 62 on both sides of the channel steel 6.

[0051] Before the steel cage 2 is unfolded, the channel steel 6 is placed under the slide plate 211 of the steel cage 2. After the steel cage 2 is placed on the channel steel 6, the steel cage 2 is unfolded by the unfolding assembly 1. During this process, the slide plate 211 slides relatively smoothly in the channel steel 6 until the steel cage 2 is fully unfolded. The slide plate 211 slides more smoothly in the channel steel 6 than the steel cage 2 slides directly on the rock and soil. After the channel steel 6 is laid, the reinforcing rod 61 is placed on the channel steel 6, and then the reinforcing rod 61 is clamped on the channel steel 6 through the nuts 62 on both sides of the channel steel 6 by tightening the nuts 62, so that the reinforcing hoop and the channel steel 6 are relatively stable to each other, thereby further strengthening the stability of the oblique channel after grouting.

[0052] Reference Figure 2 , an arc-shaped steel frame 7 is placed in the groove at the end of the channel steel 6, and the arc-shaped steel frame 7 is fitted with the inner side of the steel cage 2, and multiple groups of locking foot anchor rods 71 ​​are implanted in the inner wall of the oblique channel, each group of locking foot anchor rods has two and are arranged on both sides of the arc-shaped steel frame 7, and a clamping rod 72 is fixed between the ends of the two locking foot anchor rods 71 ​​of the same group, which is against the side of the arc-shaped steel frame 7 away from the inner wall of the oblique channel. When the arc-shaped steel frame 7 is placed in the groove of the channel steel 6, clamping plates 73 are fixed at both ends in the groove of the channel steel 6, and the clamping plates 73 are fitted with the side of the arc-shaped steel frame 7 away from the steel cage 2.

[0053] After the steel cage 2 is fully unfolded, the locking foot anchor rod 71 is implanted into the inner wall of the oblique channel, and then the arc steel frame 7 is placed in the channel steel 6, so that the arc steel frame 7 fits the steel cage 2, and finally the clamping rod 72 is welded to the part of the locking foot anchor rod 71 exposed outside, so that the arc steel frame 7 is fixed by the clamping rod 72 and the locking foot anchor rod 71, and then the clamping plate 73 is attached to the side of the arc steel frame 7 away from the steel cage 2 and welded to the channel steel 6. The fixed arc steel plate further strengthens the fixation of the steel cage 2, that is, the steel cage 2 does not need to be fixed with other anchor rods, which reduces the number of anchor rods required to be implanted and saves construction time. At the same time, the oblique channel after the concrete is sprayed is supported by the arc steel frame 7, which also makes the oblique channel more stable.

[0054] Reference Figure 1 The deployment component 1 includes an airbag 11 placed inside the steel cage 2, a cable tie 12 arranged on the steel bar and wrapped around the outside of the airbag 11, and an air pump 13 connected to the airbag 11. When the airbag 11 is in a full state, the airbag 11 is adapted to the arc portion of the oblique channel.

[0055] Before unfolding the steel cage 2, first fix the two sliding steel meshes 21 with ropes, then turn on the air pump 13, and input air into the airbag 11 to expand the airbag 11. The airbag 11 in the process of expansion and stretching pushes the steel cage 2 to unfold. When the steel cage 2 is unfolded and locked, the airbag 11 is deflated and the cable tie 12 is removed to remove the airbag 11 from the steel cage 2. In the process of unfolding the steel cage 2, the operation is relatively simple, and the airbag 11 can also be reused, which effectively saves resources.

[0056] The implementation principle of the full-section roof construction method for the tunnel pilot tunnel conversion of the embodiment of the present application is as follows: a channel steel 6 is placed on the bottom wall of the oblique channel, and then the folded steel cage 2 is transported into the oblique channel, the steel cage 2 is placed at a corresponding position, and the slide plate 211 is located in the groove of the channel steel 6, the air pump 13 is turned on, the air bag 11 is inflated to expand the steel cage 2, and then the locking block 5 is welded to the steel cage 2 to prevent the steel cage 2 from retracting. At this time, the expansion of the steel cage 2 is completed, and the whole process effectively shortens the oblique channel. Then, the locking foot anchor rod 71 is implanted in the inner wall of the inclined channel, and then the arc steel frame 7 is placed in the channel steel 6, so that the arc steel frame 7 fits with the steel cage 2, and finally, the clamping rod 72 is welded to the part of the locking foot anchor rod 71 exposed outside, so that the arc steel frame 7 is fixed by the clamping rod 72 and the locking foot anchor rod 71, and then the clamping plate 73 is attached to the side of the arc steel frame 7 away from the steel cage 2 and welded to the channel steel 6, and finally, grouting is completed to the inner wall of the inclined channel.

[0057] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A method for constructing a full-section roof for a tunnel pilot tunnel. Features: The following steps are involved: S1. Construction preparation: measure and calculate in the pilot tunnel, and then mark the corresponding position on the inner wall of the pilot tunnel; S2. Drilling and blasting: Drill the corresponding holes at the marked positions with the drilling trolley, then charge the holes with explosives and detonate the explosives in the holes after the drilling trolley is withdrawn to a safe distance. Repeat this process until an oblique passage that penetrates the pilot tunnel and the main tunnel is drilled; S3. Support construction, processing the folded steel cage (2) at an external site, and installing an unfolding component (1) on the steel cage (2) for controlling the unfolding of the steel cage (2), then transporting the steel cage (2) to a designated position in the inclined channel, unfolding the steel cage (2) by means of the unfolding component (1), then installing an arc-shaped steel frame (7) on the side of the steel cage (2) away from the inner wall of the inclined channel, and installing an arch (4) on the side of the steel cage (2) close to the main hole, and finally spraying concrete on the steel cage (2); S4. Steel arch installation: install the steel arch above the main tunnel and spray concrete; The steel cage (2) comprises two sliding steel meshes (21) respectively close to the inner bottom wall of the oblique channel and a plurality of folded steel meshes (22) located between the two sliding steel meshes (21); The steel cage (2) further comprises a connecting assembly (3) for connecting the folded steel mesh (22) and the sliding steel mesh (21) and two adjacent folded steel meshes (22); the steel cage (2) is also provided with a locking member for locking the steel cage (2); A plurality of channel steels (6) are arranged horizontally on the inner bottom wall of the oblique channel perpendicular to the axis thereof, a plurality of slide plates (211) are integrally extended from one side of the sliding steel mesh (21) close to the channel steel (6), and the slide plates (211) are slidably arranged in the groove of the channel steel (6); An arc-shaped steel frame (7) is placed in the groove at the end of the channel steel (6), and the arc-shaped steel frame (7) is fitted with the inner side of the steel cage (2). A plurality of groups of locking foot anchor rods (71) are implanted in the inner wall of the oblique channel, each group of locking foot anchor rods (71) has two and are arranged on both sides of the arc-shaped steel frame (7), and a clamping rod (72) is fixedly connected between the ends of the two locking foot anchor rods (71) of the same group and abuts against the side of the arc-shaped steel frame (7) away from the inner wall of the oblique channel.

2. The full-section roof construction method for converting a tunnel pilot hole into a regular hole according to claim 1, Features: The connection assembly (3) comprises an articulated seat (31) and connectors (32) articulated at both ends of the articulated seat (31), and the connectors (32) are threadedly sleeved on one end of the steel bars of the sliding steel mesh (21) close to the folded steel mesh (22) and on both ends of the steel bars of the folded steel mesh (22).

3. The full-section roof construction method for converting a tunnel pilot hole into a regular hole according to claim 1, Features: Clamping plates (73) are fixedly connected to both ends of the channel steel (6), the clamping plates (73) are in contact with a side of the arc-shaped steel frame (7) away from the steel cage (2), and when the arc-shaped steel frame (7) is not placed in the channel steel (6), the clamping plates (73) are not connected to the channel steel (6).

4. The full-section roof construction method for converting a tunnel pilot hole into a regular hole according to claim 1, Features: The unfolding assembly (1) in S3 comprises an airbag (11) arranged inside the steel cage (2), a cable tie (12) arranged on the steel bar and wrapped around the outside of the airbag (11), and an air pump (13) connected to the airbag (11), and when the airbag (11) is in a full state, the airbag (11) is adapted to the arc portion of the oblique channel.

5. The full-section roof construction method for converting a tunnel pilot hole into a regular hole according to claim 1, Features: The locking member is a locking block (5) fixedly connected between two adjacent folded steel meshes (22) and between the folded steel mesh (22) and the sliding steel mesh (21); and when the folded steel mesh (22) and the sliding steel mesh (21) are not fully unfolded, the locking block (5) is not arranged on the steel cage (2).

6. The full-section roof construction method for converting a tunnel pilot hole into a regular hole according to claim 1, Features: A reinforcing rod (61) is placed between adjacent channel steels (6), and a fixing groove slidably matched with the reinforcing rod (61) is provided on a side of the channel steel (6) away from the bottom wall of the inclined channel. Nuts (62) are threadedly sleeved on both sides of the reinforcing rod (61).