Construction method for widening gas embankments using flexible permeable pipe drainage foam concrete.
Through the soft permeable pipe drainage foam concrete construction method, the settlement differences and construction efficiency problems in embankment widening are solved. The load bearing capacity and construction quality are improved through innovative connection technology of steel mesh, and the rapid and reliable embankment widening effect is achieved.
Patent Information
- Application Number
- CN202310268900.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-17
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2043-03-17
AI Technical Summary
During the embankment widening process, the existing technology is difficult to effectively solve the settlement differences between embankments and structures and the uneven settlement problems of new and old embankments, resulting in problems such as jumping, damage to structures and instability of roadbeds, and foam concrete reinforced nets The construction efficiency and quality are difficult to guarantee.
The construction method of foam concrete for drainage of soft permeable pipes includes excavation of wide embankment foundation grooves, setting up steel pipe piles, welding angle steel pillars, pouring cast-in-place concrete foundations, setting up gravel cushions and foam concrete, and pulling rings through round steel The rake-toothed steel plate is used to fix the lower and upper steel mesh, and quickly connect the bridge head plate and the abutment to improve construction speed and quality.
The load-bearing capacity of steel pipe piles, the construction speed and tensile strength of foam concrete steel mesh are improved, the rapid connection of bridge head plates and high-quality construction of pavement structures are achieved, and the overall construction efficiency and quality are improved.
Smart Images

Figure CN116240766B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a construction method for widening a natural embankment using soft permeable pipe drainage foam concrete, which is applicable to the technical field of roadbed engineering and the construction method for widening a natural embankment using soft permeable pipe drainage foam concrete. Background Art
[0002] With the rapid development of my country's economy, my country's transportation industry has developed rapidly. In order to meet the growing demand for traffic, more and more embankment widening projects are being carried out on the basis of keeping the existing roads open to traffic. The newly widened embankment has the problem of settlement difference between the embankment and the structure and uneven settlement of the new and old embankments, which can easily cause vehicle jumping, damage to the structure and instability of the roadbed. Among them, improving the construction efficiency and quality of the bridgehead slab, as well as the construction quality and efficiency of the foam concrete steel mesh are the top priorities. It is of great significance to develop an economical and safe way to widen the embankment.
[0003] In summary, for the construction of widening the temperamental embankment, it is very important to seek a new construction method for widening the temperamental embankment with fast construction speed, simple operation and high reliable construction quality. Summary of the invention
[0004] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a construction method for widening a natural gas embankment by using a soft permeable pipe to drain foam concrete.
[0005] The construction method of the soft permeable pipe drainage foam concrete widening embankment includes the following steps:
[0006] Step 1: Widen the embankment foundation trench, construct pile foundation and cast the cap;
[0007] Step 2: Drive steel pipe piles, weld angle steel pillars to the steel pipe piles, and set a cast-in-place concrete foundation on the top of the steel pipe piles; cast the angle steel pillars and the cast-in-place concrete foundation into a whole; and fix the prefabricated panels to the angle steel pillars;
[0008] Step 3: a crushed stone cushion is set on the top of the slag at the bottom of the foundation pit, and a bottom soft water-permeable pipe is arranged in the crushed stone cushion; the prefabricated panel is fixed with the angle steel pillar;
[0009] Step 4: Foam concrete pouring: pour foam concrete, connect the lower reinforcement steel mesh and the pedestal, the upper reinforcement steel mesh and the abutment; construct a transverse blind ditch, and place an upper soft permeable pipe in the transverse blind ditch;
[0010] Step 5: Prefabricated scaffolding construction: insert steel rods into the fixing rings to connect the prefabricated scaffoldings and the abutments and prefabricated scaffoldings into a whole;
[0011] Step 6: Pavement structure construction: Carry out pavement structure and guardrail construction, and backfill soil-rock mixture on the outside of the pedestal.
[0012] Preferably, in step two, firstly, steel pipe piles are driven, and after the steel pipe piles are driven, sealing steel plates are welded, and grouting ports and reserved grooves matching the angle steel pillars are arranged on the sealing steel plates. After the welding of the sealing steel plates is completed, the angle steel pillars are inserted into the reserved grooves and welded to the sealing steel plates into a whole; then grouting is carried out through the grouting ports to form a grouting body at the bottom of the steel pipe piles.
[0013] Preferably, the piers and abutments are provided with embedded steel bars, the embedded steel bars are welded and fixed with rake-tooth steel plates, and the rake-tooth steel plates are provided with rake teeth; the lower reinforcing steel mesh is welded with round steel pull rings, and the upper reinforcing steel mesh is also welded with round steel pull rings.
[0014] Preferably, in step four, after the lower reinforcing steel mesh is processed, a round steel pull ring is welded, and the round steel pull ring of the lower reinforcing steel mesh is sleeved on the rake teeth connected to the abutment; the upper reinforcing steel mesh is also welded with a round steel pull ring, and the round steel pull ring of the upper reinforcing steel mesh is sleeved on the rake teeth of the abutment.
[0015] Preferably, in step 4, the outside of the upper soft permeable pipe is backfilled with graded gravel, a permeable geotextile is set on the top of the transverse blind ditch, and an impermeable geotextile is set at the bottom of the transverse blind ditch and near the foam concrete side.
[0016] Preferably, in step five, the prefabricated scaffolding is provided with embedded steel bars, and fixed rings are welded on the embedded steel bars; construction joints are provided between the prefabricated scaffoldings, and the fixed rings between the prefabricated scaffoldings overlap with each other, and steel rods pass through the fixed rings to connect the prefabricated scaffoldings into a whole, wherein reserved holes are provided on the steel rods, and anti-slip pins are inserted through the reserved holes on the steel rods, and fillers are arranged in the construction joints; embedded steel bars are provided on the abutments, and fixed rings are welded on the embedded steel bars, and the fixed rings of the abutments and the prefabricated scaffoldings overlap with each other, and steel rods are inserted into the fixed rings to connect the abutments and the prefabricated scaffoldings into a whole, and anti-slip pins are inserted through the reserved holes on the steel rods.
[0017] Soft permeable pipe drainage foam concrete widening quality embankment, obtained by any of the above-mentioned methods.
[0018] The beneficial effects of the present invention are:
[0019] 1) The prefabricated panel of the present invention undergoes foundation reinforcement treatment, steel pipe piles are driven, and high-pressure grouting is performed to form a grouting body at the bottom of the steel pipe piles to improve their bearing capacity.
[0020] 2) The present invention has developed a technology for quickly connecting foam concrete steel mesh with abutments and piers. The lower reinforcing steel mesh and abutment, and the upper reinforcing steel mesh and abutment are all fixedly connected by the cooperation of round steel pull rings and rake-tooth steel plates; the construction speed and tensile strength are improved.
[0021] 3) The present invention proposes a rapid connection technology between a bridgehead slab and an abutment, and a rapid connection technology for a construction joint of a bridgehead slab. The prefabricated slabs and the prefabricated slabs and the abutments are fixedly connected by the cooperation of fixing rings and steel rods, thereby improving the construction efficiency and quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a longitudinal section diagram of a flexible permeable pipe drainage foam concrete widening temperament embankment;
[0023] Figure 2 It is a schematic diagram of the transverse section of the widening of the temperamental embankment by soft permeable pipe drainage foam concrete;
[0024] Figure 3 This is a schematic diagram of the top plugging of the steel pipe pile;
[0025] Figure 4 yes Figure 1 Schematic diagram of the large sample of the middle B position;
[0026] Figure 5 It is a plane diagram of the connection between the lower steel mesh and the cap;
[0027] Figure 6 This is a schematic diagram of the large sample of the rake-tooth steel plate;
[0028] Figure 7 yes Figure 1 Schematic diagram of the cross section at position C;
[0029] Figure 8 yes Figure 1 Schematic diagram of the plane detail at the center C position;
[0030] Fig. 9 yes Figure 1 Schematic diagram of the plane detail at position A in the middle;
[0031] Fig.10 It is a construction process flow chart of the present invention.
[0032] In the figure: 1-beam slab, 2-pavement structure, 3-transverse blind ditch, 4-concrete cushion, 5-prefabricated slab, 6-construction joint, 7-upper reinforced steel mesh, 8-old road foundation, 9-upper soft permeable pipe, 10-bridge abutment, 11-cap, 12-lower reinforced steel mesh, 13-soil-rock mixture, 14-pile foundation, 15-gravel cushion, 16-bottom soft permeable pipe, 17-slag, 18-foam concrete Concrete, 19-guardrail, 20-guardrail base, 21-pebble concrete hardened panel, 22-angle steel pillar, 23-prefabricated panel, 24-cast-in-place concrete foundation, 25-grouting body, 26-steel pipe pile, 27-sealing steel plate, 28-grouting port, 29-embedded steel bars, 30-rake tooth steel plate, 31-rake teeth, 32-round steel pull ring, 33-anti-slip pin, 34-steel rod, 35-fixing ring. DETAILED DESCRIPTION
[0033] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for ordinary persons in the art, without departing from the principle of the present invention, the present invention can also be modified in some ways, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
[0034] Embodiment 1
[0035] As an example, Fig.10 As shown in the figure, the construction method of widening the gas embankment with soft permeable pipe drainage foam concrete has the following main construction steps:
[0036] Step 1: Excavation of the widened embankment foundation trench: In order to improve the stability of the new widened embankment foundation trench, a high-capped roadbed is used to first fill and pre-load it, and then excavate and replace it.
[0037] Pile foundation and capping platform construction: The pile foundation 14 is constructed by rotary drilling, the capping platform 11 is cast on the upper part of the pile foundation 14, and embedded steel bars 29 are set at the connection position between the capping platform 11 and the lower reinforcing steel mesh 12.
[0038] Step 2, steel pipe pile construction: prefabricated panels 23 are used for foundation reinforcement, steel pipe piles 26 are driven, and after the steel piles are driven, the sealing steel plate 27 is welded, and a grouting port 28 and a reserved groove for the angle steel support 22 are set on the sealing steel plate 27. After the welding of the sealing steel plate 27 is completed, the angle steel support 22 is inserted into the reserved groove on the sealing steel plate 27 and welded to the sealing steel plate 27 into a whole; then high-pressure grouting is carried out through the grouting port 28 to form a grouting body 25 at the bottom of the steel pipe pile 26 to improve its bearing capacity.
[0039] Cast-in-place concrete foundation construction: a cast-in-place concrete foundation 24 is set on the upper part of the steel pipe pile 26; the angle steel support 22 and the cast-in-place concrete foundation 24 are cast into a whole; and the prefabricated panel 23 is fixedly connected to the angle steel support 22.
[0040] Step 3: Construction of bottom soft water-permeable pipes: A crushed stone cushion layer 15 is arranged on the top of the slag 17 at the bottom of the foundation trench, and bottom soft water-permeable pipes 16 are arranged at intervals in the crushed stone cushion layer 15 .
[0041] Prefabricated panel construction: The prefabricated panel 23 is processed in the factory and fixedly connected with the angle steel support 22.
[0042] Step 4, pouring of foam concrete: pour foam concrete 18 in layers in the foundation trench, and set the lower reinforcing steel mesh 12, the upper reinforcing steel mesh 7 and the same fixed connection structure as the abutment 11 and the abutment 10. The abutment 11 and the abutment 10 are both provided with embedded steel bars 29, and the lower reinforcing steel mesh 12 is taken as an example; the embedded steel bars 29 are welded and fixed to the rake-tooth steel plate 30, and the rake-tooth steel plate 30 is a steel plate with rake teeth 31 formed by cutting or welding steel plates; after the lower reinforcing steel mesh 12 is processed, a round steel pull ring 32 is welded, and the round steel pull ring 32 of the lower reinforcing steel mesh 12 is sleeved on the rake teeth 31 connected to the abutment 11, thereby improving the installation efficiency of the lower reinforcing steel mesh 12 and the tensile strength of the connection with the abutment 11; the upper reinforcing steel mesh 7 is also welded with a round steel pull ring 32, and the round steel pull ring 32 of the upper reinforcing steel mesh 7 is sleeved on the rake teeth 31 of the abutment 10.
[0043] The transverse blind ditch 3 is constructed, the upper soft permeable pipe 9 is built in the transverse blind ditch 3, the outer part of the upper soft permeable pipe 9 is backfilled with graded gravel, a permeable geotextile is set on the top of the transverse blind ditch 3, and an impermeable geotextile is set at the bottom of the transverse blind ditch 3 and near the foam concrete 18 side.
[0044] Step 5, construction of prefabricated scaffolding: the prefabricated scaffolding 5 is prefabricated in the factory, and embedded steel bars 29 are arranged on it, and fixing rings 35 are welded on the embedded steel bars; a construction joint 6 is reserved at the designed position of the prefabricated scaffolding 5, and the prefabricated scaffolding 5 is connected into a whole by a steel rod 34 passing through the fixing ring 35, wherein a reserved hole is arranged on the steel rod 34, and an anti-slip pin 33 is inserted into the reserved hole to prevent the steel rod 34 from falling off and shifting. After the prefabricated scaffolding 5 is fixed, a filler is arranged in the construction joint 6; the connection form between the abutment 10 and the prefabricated scaffolding 5 is consistent with the connection form of the prefabricated scaffolding 5 at the construction joint 6, embedded steel bars 29 are arranged on the abutment 10 and a fixing ring 35 is welded, and the steel rod 34 is inserted into the fixing ring 35 to connect the abutment 10 and the prefabricated scaffolding 5 into a whole, thereby improving the construction quality and construction efficiency of the connection between the abutment 10 and the prefabricated scaffolding 5.
[0045] Step 6: Construction of pavement structure: After the construction of the prefabricated slab 5 is completed, the pavement structure 2 and the guardrail 19 are constructed, and the soil-rock mixture 13 outside the cap 11 is backfilled.
[0046] Embodiment 2
[0047] As another example, Figures 1 to 9As shown, the soft permeable pipe drainage foam concrete widening quality embankment obtained by the method in Example 1 includes: a beam slab 1, a pavement structure 2, a transverse blind ditch 3, a concrete cushion layer 4, a prefabricated slab 5, a construction joint 6, an upper reinforced steel mesh 7, an old road foundation structure 8, an upper soft permeable pipe 9, an abutment 10, a cap 11, a lower reinforced steel mesh 12, a soil-rock mixture 13, a pile foundation 14, a crushed stone cushion layer 15, a bottom soft permeable pipe 16, slag 17, foam concrete 18, a guardrail 19, a guardrail base 20, a small stone concrete hardened panel 21, an angle steel support 22, a prefabricated Panel 23, cast-in-place concrete foundation 24, grouting body 25, steel pipe pile 26, sealing steel plate 27, grouting port 28, embedded steel bars 29, rake-tooth steel plate 30, rake teeth 31, round steel pull ring 32, anti-slip pin 33, steel rod 34, fixing ring 35; the new widened embankment adopts the technology of first filling and pre-compressing the high-cap embankment and then excavating and replacing the filling, the technology of fixing the steel mesh with reserved reinforcement on the embankment, the technology of quick fixing of prefabricated panels, the technology of integral connection between the bridgehead cladding and the foam concrete lightweight embankment, the technology of connecting the bridgehead cladding with construction joints with tie rods, and the technology of first filling and pre-compressing the high-cap embankment and then excavating and replacing the filling.
[0048] The prefabricated panel 23 is subjected to foundation reinforcement treatment, and the prefabricated panel 23 is fixedly connected to the angle steel support 22; a steel pipe pile 26 is driven into the slag 17 below the prefabricated panel 23, and a plugging steel plate 27 is welded to the steel pipe pile 26. A grouting port 28 and a reserved groove for the angle steel support 22 are arranged on the plugging steel plate 27. After the welding of the plugging steel plate 27 is completed, the angle steel support 22 is inserted into its reserved groove and welded to the plugging steel plate 27 as a whole; high-pressure grouting is performed through the grouting port 28 to form a grouting body 25 at the bottom of the steel pipe pile 26 to improve its bearing capacity; a cast-in-place concrete foundation 24 is arranged on the upper part of the steel pipe pile 26; the angle steel support 22 and the steel pipe pile 26 are welded as a whole; the angle steel support 22 and the cast-in-place concrete foundation 24 are cast as a whole.
[0049] The lower reinforcing steel mesh 12 and the abutment 11, the upper reinforcing steel mesh 7 and the abutment 10 are all fixedly connected by the cooperation of the round steel pull ring 32 and the rake-tooth steel plate 30; the prefabricated slats 5, the prefabricated slats 5 and the abutment 10 are all fixedly connected by the cooperation of the fixing ring 35 and the steel rod 34; the lower reinforcing steel mesh 12 and the upper reinforcing steel mesh 7 have the same fixed connection structure as the abutment 11 and the abutment 10, and the abutment 11 and the abutment 10 are both provided with embedded steel bars 29, and the lower reinforcing steel mesh 12 is taken as an example; the embedded steel bars 29 are welded and fixed to the rake-tooth steel plate 30, and the rake-tooth steel plate 30 is formed by cutting or welding steel plates with rake teeth 31; the round steel pull ring 32 is welded after the lower reinforcing steel mesh 12 is processed, and the round steel pull ring 32 of the lower reinforcing steel mesh 12 is sleeved on the rake teeth 31 connected to the abutment 11; the installation efficiency of the lower reinforcing steel mesh 12 and the tensile strength of the connection with the abutment 11 are improved. The upper reinforcing steel mesh 7 is also welded with a round steel pull ring 32 , and the round steel pull ring 32 of the upper reinforcing steel mesh 7 is sleeved on the rake teeth 31 of the abutment 10 .
[0050] The transverse blind ditch 3 is arranged on the side of the abutment 10 below the prefabricated slab 5, and an upper soft permeable pipe 9 is arranged in the transverse blind ditch 3; a crushed stone cushion layer 15 is arranged on the top of the slag 17, and a bottom soft permeable pipe 16 is arranged in the crushed stone cushion layer 15, and foam concrete 18 is poured above the crushed stone cushion layer 15.
[0051] The prefabricated slats 5 are prefabricated in a factory, and embedded steel bars 29 are arranged on them, and fixed rings 35 are welded on the embedded steel bars; a construction joint 6 is reserved at the designed position of the prefabricated slats 5, and the prefabricated slats 5 are connected into a whole by a steel rod 34 passing through the fixed ring 35, wherein a reserved hole is arranged on the steel rod 34, and an anti-slip pin 33 is inserted into the reserved hole to prevent the steel rod 34 from falling off and shifting. After the prefabricated slats 5 are fixed, a filler is arranged in the construction joint 6; the connection form between the abutment 10 and the prefabricated slats 5 is consistent with the connection form of the prefabricated slats 5 at the construction joint 6, embedded steel bars 29 are arranged on the abutment 10 and a fixed ring 35 is welded, and the steel rod 34 is inserted into the fixed ring 35 to connect the abutment 10 and the prefabricated slats 5 into a whole, thereby improving the construction quality and construction efficiency of the connection between the abutment 10 and the prefabricated slats 5.
Claims
1. A construction method for widening a natural embankment using soft permeable pipe drainage foam concrete, characterized in that: The following steps are involved: Step 1: widen the embankment foundation trench, construct the pile foundation (14) and cast the cap (11); Step 2: driving the steel pipe pile (26), welding the angle steel support (22) to the steel pipe pile (26), and setting a cast-in-place concrete foundation (24) on the upper part of the steel pipe pile (26); casting the angle steel support (22) and the cast-in-place concrete foundation (24) into an integral body; fixing the prefabricated panel (23) to the angle steel support (22); after the steel pipe pile (26) is driven, welding the sealing steel plate (27), and setting a grouting port (28) and a reserved groove matching the angle steel support (22) on the sealing steel plate (27); after the sealing steel plate (27) is welded, insert the angle steel support (22) into the reserved groove and weld it to the sealing steel plate (27) into an integral body; then grouting is performed through the grouting port (28) to form a grouting body (25) at the bottom of the steel pipe pile (26); Step 3: a crushed stone cushion layer (15) is provided on the top of the slag (17) at the bottom of the foundation trench, and a bottom soft water-permeable pipe (16) is arranged in the crushed stone cushion layer (15); the prefabricated panel (23) is fixed to the angle steel support (22); Step 4, pouring foam concrete: pouring foam concrete (18), connecting the lower reinforcing steel mesh (12) and the pedestal (11), the upper reinforcing steel mesh (7) and the abutment (10); constructing a transverse blind ditch (3), wherein the transverse blind ditch (3) has an upper soft permeable pipe (9) built therein; the pedestal (11) and the abutment (10) are both provided with embedded steel bars (29), the embedded steel bars (29) are welded and fixed with a rake-tooth steel plate (30), and the rake-tooth steel plate (30) is provided with rake teeth (31); the lower The reinforcing steel mesh (12) is welded with a round steel pull ring (32), and the upper reinforcing steel mesh (7) is also welded with a round steel pull ring (32); after the lower reinforcing steel mesh (12) is processed, the round steel pull ring (32) is welded, and the round steel pull ring (32) of the lower reinforcing steel mesh (12) is sleeved on the rake teeth (31) connected to the abutment (11); the upper reinforcing steel mesh (7) is also welded with a round steel pull ring (32), and the round steel pull ring (32) of the upper reinforcing steel mesh (7) is sleeved on the rake teeth (31) of the abutment (10); Step 5: Prefabricated scaffolding construction: insert the steel rod (34) into the fixing ring (35) to connect the prefabricated scaffolding (5) and the abutment (10) and the prefabricated scaffolding (5) into a whole; Step 6: Construction of pavement structure: Construction of pavement structure (2) and guardrail (19) is performed, and soil-rock mixture (13) is backfilled outside the cap (11).
2. The construction method of widening the quality embankment by using soft permeable pipe drainage foam concrete according to claim 1 is characterized in that: In step 4, the outer part of the upper soft permeable pipe (9) is backfilled with graded gravel, a permeable geotextile is set on the top of the transverse blind ditch (3), and an impermeable geotextile is set on the bottom of the transverse blind ditch (3) and on the side close to the foam concrete (18).
3. The construction method of widening the quality embankment with soft permeable pipe drainage foam concrete according to claim 1 is characterized in that: In step 5, the prefabricated slats (5) are provided with embedded steel bars (29), and the embedded steel bars (29) are welded with fixing rings (35); construction joints (6) are provided between the prefabricated slats (5), and the fixing rings (35) between the prefabricated slats (5) overlap each other, and steel rods (34) pass through the fixing rings (35) to connect the prefabricated slats (5) into a whole, wherein the steel rods (34) are provided with reserved holes, and anti-slip A movable latch (33) is provided in the construction joint (6); a filler is provided on the abutment (10); a pre-buried steel bar (29) is welded to a fixing ring (35); the fixing rings (35) of the abutment (10) and the prefabricated slab (5) overlap each other; a steel rod (34) is inserted into the fixing ring (35) to connect the abutment (10) and the prefabricated slab (5) into a whole; and an anti-slip latch (33) is inserted into the steel rod (34) through a reserved hole.
4. Soft permeable pipe drainage foam concrete widening quality embankment, characterized in that: Obtained by the method described in any one of claims 1 to 3.