Intelligent beam field production management and control system

Through modular management, the smart beam yard production management and control system solves the information barrier problem of prefabricated beam yard production management, realizes intelligent management throughout the process, improves project quality and construction efficiency, and ensures project safety.

CN119027063AInactive Publication Date: 2024-11-26JIANGSU WISTRON INTELLIGENT TRANSPORTATION TECH CO LTD

Patent Information

Application Number
CN202411479873.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-23
Publication Date
2024-11-26
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the prior art, the production management process of prefabricated beam yards lacks intelligent management throughout the process, resulting in information barriers and it is difficult to achieve the correlation between upstream and downstream production, affecting project quality, construction progress and project safety.

Method used

Design a smart beam yard production management and control system, including the beam yard basic information module, order management module, main production planning module, daily production planning module, material storage module, material procurement module, beam storage and beam search module, safety management module and transportation The supervision module realizes the rapid transmission and management of the entire process information through automatic analysis and reminders.

Benefits of technology

Improve the quality of the project, speed up the construction progress, reduce project costs, and ensure project safety. Through comprehensive monitoring and management of information flow, logistics and people flow, the chain reaction of production period, process and raw material supply is achieved, and the information is improved. Transmission efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119027063A_ABST
    Figure CN119027063A_ABST
Patent Text Reader

Abstract

The invention discloses an intelligent beam yard production management and control system which comprises a beam yard basic information module, an order management module, a main production plan module, a daily production plan module, a material storage module, a material purchase module, a beam storage and searching module, a security management module and a transportation supervision module. A pedestal site is represented in a map layout mode, technologies such as a time schedule, construction nodes and material management are adopted, rapid message transmission is achieved, and when any link of the whole process changes, whether linkage change needs to be carried out on the upper link and the lower link or not can be automatically analyzed, and relevant reminding is carried out; construction management personnel of the precast beam field can quickly know the production process of the precast beam field; meanwhile, the position information of the precast beams is tracked through radio frequency signals, and the parking and searching speed of the precast beams is increased; the method can improve the engineering quality, accelerate the construction progress, reduce the engineering cost and guarantee the engineering safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a smart beam yard production control system, which belongs to the intelligent production control technology for prefabricated beams in the road construction process. Background Art

[0002] With the continuous development of transportation construction and the rapid growth of transportation, the construction progress of domestic expressways is also accelerating. As an important part of highway bridge construction, precast beams have the advantages of short construction period, controllable quality, and economic efficiency, and are widely used in expressway projects. As an important production site and storage place for precast beams, precast beam yards play an important role in engineering; therefore, the development of construction technology and management of precast beam yards is of great significance to improving engineering quality, accelerating construction progress, reducing engineering costs, and ensuring engineering safety.

[0003] The production of precast beams is a key step: during the production process, it is necessary to strictly select raw materials according to the design requirements, design and produce molds, control the concrete mixing ratio and vibration process, and ensure that the quality and strength of the beam meet the standards; it is also necessary to consider the design and processing of the internal prestressed steel bars of the precast beam to ensure that the bearing capacity and seismic performance of the beam meet the requirements. The temporary storage of precast beams is a step that must be considered: factors such as the number of beam storage pedestals and the age of concrete limit the circulation volume and storage time of precast beams. The transportation of precast beams is also an important link: during the transportation process, it is necessary to select appropriate transportation tools and methods to ensure that the beam is not damaged during transportation. At the same time, the transportation route and traffic conditions must be considered to ensure that the beam can reach the construction site safely and quickly. The assembly and installation of precast beams also require technical support: during the on-site construction process, it is necessary to carry out assembly design and plan formulation according to the shape and size of the beam, adopt appropriate lifting and installation methods to ensure that the beam is accurately installed in place, and at the same time strictly control the connection and coordination between the beams to ensure the safety and reliability of the overall structure. At the same time, construction management personnel of prefabricated beam yards need to have professional knowledge and rich experience, establish a reasonable organizational structure and division of labor, and pay attention to production safety and quality management; only by doing a good job in each management link can the construction progress and quality be ensured to meet the expected goals.

[0004] In summary, the production management of precast beams mainly involves processes such as order management, production planning, material purchase, beam storage and search, safety management and transportation. In the existing technology, these processes are usually managed separately, and information is summarized and plans are adjusted through personnel exchanges such as meetings and interviews. This is undoubtedly not conducive to the full-process management of precast beams; breaking through the information barriers between upstream and downstream, establishing the correlation between upstream and downstream production, and realizing the full-process intelligent management of precast beam yards will further improve project quality, speed up construction progress, reduce project costs, and ensure project safety. Summary of the invention

[0005] Purpose of the invention: In order to overcome the deficiencies in the prior art, the present invention provides a smart beam yard production control system to establish full-process smart management of the precast beam yard. When any link in the whole process changes, it will automatically analyze whether the upper and lower links need to be chained and make relevant reminders, so that the construction management personnel of the precast beam yard can quickly understand the production process of the precast beam yard, improve the project quality, speed up the construction progress, reduce the project cost, and ensure the safety of the project.

[0006] Technical solution: To achieve the above purpose, the technical solution adopted by the present invention is: A smart beam yard production control system includes a beam yard basic information module, an order management module, a main production plan module, a daily production plan module, a material storage module, a material procurement module, a beam storage and search module, a sense of security management module and a transportation supervision module; the beam yard basic information module collects basic information of the beam yard and evaluates the production capacity and beam storage capacity of the beam yard. The basic information of the beam yard includes parameters such as the beam yard space size, the type and corresponding number of beam-making pedestals, concrete mixing capacity, steel bar processing capacity, number of construction personnel, inventory capacity of different production raw materials, types and corresponding numbers of beam storage pedestals, and concrete age of different precast beams. The production raw materials include low-level precast parts, concrete, steel bars and embedded parts; the order management module splits the order products into precast parts step by step according to the specification requirements and delivery deadline of the order products, and combines the production capacity of the beam yard with the production capacity of the beam yard. The main production plan module, in combination with the material consumption and the specification requirements of the prefabricated parts, further defines the earliest start time and the latest completion time of the prefabricated parts, and adjusts the time schedule; the daily production plan module divides the production process of the prefabricated parts into construction nodes, and plans the production raw material demand list for each construction node; the material storage module registers all the production raw material demand lists, and forms a production raw material procurement list in combination with the time schedule; the material procurement module purchases materials according to the production raw material procurement list; the beam storage and search module is used to establish the connection between the prefabricated beam and the beam storage pedestal position; the sense of security management module uses image recognition to monitor the beam yard for safety; the transportation supervision module is used to establish the connection between the prefabricated beam and the transfer vehicle.

[0007] Specifically, the basic information module of the beam yard includes an information collection unit, a beam yard production capacity estimation unit and a beam storage capacity estimation unit; the information collection unit is used to collect parameters including the spatial size of the beam yard, the type and corresponding quantity of beam-making pedestals, concrete mixing capacity, steel bar processing capacity, number of construction personnel, inventory capacity of different production raw materials, type and corresponding quantity of beam storage pedestals, and concrete age of different precast beams, and the production raw materials include low-grade precast parts, concrete, steel bars and embedded parts; the beam yard production capacity estimation unit selects the required type of beam-making pedestals, production raw materials and unit usage according to the type of precast beams, and estimates the maximum production capacity of precast beams of a specified type based on the allocated number of beam-making pedestals, number of construction personnel and number of production raw materials; the beam storage capacity estimation unit selects the required type of beam storage pedestals according to the type of precast beams, and estimates the maximum storage capacity of precast beams of a specified type based on the allocated number of beam storage pedestals.

[0008] Specifically, the order management module collects order products and corresponding delivery deadlines, and splits the order products into low-level prefabricated parts step by step until the lowest-level prefabricated parts. The order products are the highest-level prefabricated parts, that is, prefabricated beams; the delivery deadlines of the order products are shown on the time schedule, and the planned progress bars and actual progress bars of the prefabricated parts at each level are shown in a tree chart. The start time of the higher-level prefabricated parts is after the completion time of the lower-level prefabricated parts; the time schedule is synchronized to the main production planning module.

[0009] Specifically, the main production planning module collects basic information of prefabricated parts at all levels, including structural dimensions, production materials and unit usage, production processes and the shortest production time; adjusts the earliest start time and the latest completion time of prefabricated parts at all levels on the planned progress bar of the time schedule; and synchronizes the time schedule to the order management module and the daily production planning module.

[0010] Specifically, the daily production planning module divides the production process of prefabricated parts at each level into construction nodes, including steel bar binding nodes, formwork installation nodes, concrete pouring nodes, concrete vibration nodes, spray curing nodes, steam curing nodes, tensioning nodes and grouting nodes, and plans the production raw material demand list for each construction node; selects the beam-making pedestal or processing location, and plans the start time of each construction node according to the earliest start time and the latest completion time of the prefabricated parts at each level, and adjusts the start time and completion time of the prefabricated parts at each level on the planned progress bar of the time schedule; synchronizes the time schedule to the main production planning module, sends the production raw material demand list for each construction node to the material storage module, marks the demand time, demand type and demand quantity of the production raw materials on the production raw material demand list, and marks the beam-making pedestal ID or the processing location ID.

[0011] Specifically, the material storage module registers all production raw material demand lists, collects statistics on all production raw material demands, calculates the out-of-stock time of each type of production raw materials based on the inventory quantity, demand quantity and demand time of the production raw materials; sends the production raw material purchase list to the material procurement module based on the out-of-stock time and stocking cycle of the production raw materials, and marks the demand time, demand type and demand quantity of the production raw materials on the production raw material purchase list; sends the production raw material transfer instruction based on the production raw material demand list and updates the inventory quantity of the production raw materials after the production raw material transfer is completed.

[0012] Specifically, the material procurement module registers all production raw material procurement lists, collects statistics on all production raw material demands, and updates the inventory quantity of production raw materials after the production raw materials are put into storage.

[0013] Specifically, a radio frequency card is installed on the prefabricated beam, and a radio frequency receiver A is set on the beam storage pedestal; the beam storage and beam search module includes a layout map of the beam storage pedestals, and the beam storage pedestals are marked one by one on the layout map of the beam storage pedestals; after the prefabricated beam is completed, first find an idle beam storage pedestal on the layout map of the beam storage pedestals, then transfer the prefabricated beam to the beam storage pedestal and establish a communication connection between the radio frequency card and the radio frequency receiver A, the beam storage and beam search module receives the communication connection signal from the radio frequency receiver A, marks the beam storage pedestal as occupied on the layout map of the beam storage pedestal, and starts a timer at the same time to restrict the prefabricated beam from being transferred out before the concrete age reaches; after the prefabricated beam is transferred out of the beam storage pedestal, the communication between the radio frequency card and the radio frequency receiver A is disconnected, the beam storage and beam search module receives the communication disconnection signal from the radio frequency receiver A, marks the beam storage pedestal as idle on the layout map of the beam storage pedestal, and resets the timer at the same time.

[0014] Specifically, forward and reverse sensors and positioning sensors are set on the transfer vehicle, and a radio frequency receiver B is set at the exit of the beam yard where the operating vehicle exits; the transportation supervision module transfers the prefabricated beams to the transfer vehicle and drives it to the exit of the beam yard, and then establishes a communication connection between the radio frequency card and the radio frequency receiver B. The transportation supervision module receives the communication connection signal from the radio frequency receiver B, and simultaneously triggers the forward and reverse sensors and positioning sensors to monitor the position and operating status of the transfer vehicle, and track the transportation trajectory until it reaches the destination.

[0015] Specifically, a group of cameras are arranged in the beam yard to collect video streams from all viewing angles in the beam yard; the sense of security management module includes a video stream target capture and analysis unit, which captures and analyzes targets in the video stream: performs face recognition on human targets, and performs real-time monitoring and early warning reminders on dangerous behaviors including whether a safety helmet is worn, whether a safety rope is fastened, and whether construction equipment is used correctly; for non-human targets, real-time identification and early warning reminders are performed on dangerous sources including deep foundation pits and high slopes.

[0016] The present invention tracks the entire order cycle from the order to the delivery of the order product to the destination, and tracks the entire production cycle from the task disassembly of the order product to the delivery of the order product to the destination; and, in the beam yard, all-round monitoring is carried out to realize all-round supervision of information flow, logistics, personnel flow, etc. in the beam yard; at the same time, due to any changes in the production deadline, production process, personnel changes, production raw material supply, etc., it is possible to cause a chain reaction. Compared with the prior art that requires communication between personnel from various departments, this application adopts time schedules, construction nodes, material management and other technologies to achieve rapid transmission of messages, and directly reports in a way that has the most direct impact on relevant personnel, which can improve project quality, speed up construction progress, reduce project costs, and ensure project safety. For example, the adjustment of the production personnel's allocation may lead to changes in the completion date of the concrete mixing task, and then the production raw material purchase list and the production raw material demand list may have changes in the material preparation date, and the change in the state of the construction node will involve changes in the actual progress bar; in this way, the purchasing department, warehousing department, construction department, management department and sales department can all see the impact of their respective business tables on themselves due to the construction personnel's leave. Of course, each department usually leaves a margin when conducting deadline management, and not all changes at any node will be known to other departments. For example, although the concrete mixing task is not completed according to the requirements of this department, it may still be able to meet the requirements of the purchasing department. In this way, the impact will only be absorbed by this department and will not be passed on to other departments.

[0017] Since the installation site of the beam storage pedestal is relatively large, beam storage and beam search are relatively difficult problems to overcome in the existing technology. This case creatively uses radio frequency signals to register the placement of prefabricated beams by establishing a signal connection between the prefabricated beams and the beam storage pedestal. The radio frequency card registers the identity information of the prefabricated beams, and the radio frequency receiver also establishes a one-to-one correspondence with the installed equipment. Therefore, the connection of the radio frequency signal also confirms the relationship between the prefabricated beams and the beam storage pedestal. After finding the prefabricated beams on the layout map of the beam storage pedestal, the location of the beam storage pedestal is also found, and there is no need to check the numbers of the prefabricated beams one by one in the whole site to find the beams.

[0018] At the same time, in the design of the time schedule, considering the different needs of different departments, different expressions are adopted in the sales department, management department and production department, which are more detailed at each level and also adapt to the actual needs of the beam yard. The estimation results of the beam yard production capacity estimation unit and the beam storage capacity estimation unit can be the estimation given by the on-site personnel based on the provided parameter information and expert experience, or the calculated value given based on the workload and the working capacity of personnel and equipment. It should be noted that when performing the calculation, the limit value of the beam yard capacity is used as a constraint.

[0019] It should be noted that for the management security of the entire beam yard, it is necessary to set permissions for the system of the present invention. Since the focus of this case is not on the management of production safety and information security, no further design in terms of review and confirmation is carried out, and no detailed explanation of permission login is given. However, considering that different departments are using it, the permissions can be managed and upgraded.

[0020] Specifically, in the daily production plan module, the construction nodes are lit up to indicate whether each construction node in the production process has been completed. This marking method is to enable on-site staff to quickly understand the construction progress and have a basic understanding of the workload, so as to facilitate relevant adjustments and planning in advance.

[0021] Specifically, the material storage module counts all production raw material demands, allocates each type of production raw material according to the demand time, and allocates production raw materials to those with earlier demand time; whether each type of production raw material in the production raw material purchase list can be adequately allocated is fed back to the production raw material demand list of each construction node in the daily production plan module; in the daily production plan module, for construction nodes that have not been completed, the construction nodes where all production raw materials are fully prepared and the construction nodes where production raw materials are not fully prepared are displayed separately. This marking method is to enable on-site staff to quickly understand the construction progress and have a basic understanding of the workload, so as to facilitate relevant adjustments and planning in advance.

[0022] Specifically, the material procurement module registers all production raw material purchase lists, compiles statistics on all production raw material needs, generates steel bar processing schedules, concrete mixing schedules and material preparation schedules, and updates the inventory quantity of production raw materials after the production raw materials are put into storage. Generating steel bar processing schedules and concrete mixing schedules is generally a job within the beam yard, but for advanced prefabricated parts, they are production raw materials, so they are placed in the material procurement module. After the schedule is completed, it needs to be sent to the relevant construction department for construction; and steel bars, embedded parts and other preparation materials generally need to be purchased from outside, and are also placed in the material procurement module. After the schedule is completed, it needs to be sent to the procurement department for procurement.

[0023] Specifically, the sense of security management module also includes various special equipment monitoring units. The special equipment includes tower cranes, bridge erection machines, crawler cranes and gantries installed in the beam yard. Various sensors are installed on the special equipment, and monitoring cameras are installed for each feature equipment. The sensor detection data and monitoring camera collection information are sent to each special equipment monitoring unit. The sensors include height sensors, rotation angle sensors, wind speed and force sensors, driving speed sensors and limit sensors. In each special equipment monitoring unit, the special equipment model is loaded, and the special equipment model, basic parameters, real-time sensor detection data and monitoring camera collection information are displayed in partitions on the display screen. When there are abnormalities in the real-time sensor detection data and the monitoring camera collection information, a buzzer warning is issued.

[0024] Specifically, the basic information module of the beam yard also includes a layout map of the beam-making pedestal, on which the beam-making pedestals are marked one by one, and whether there are precast beams on the beam-making pedestals; for the precast beams on the beam-making pedestals, the completed precast beams and the unfinished precast beams are displayed separately, and the precast beams that have been reserved for the beam-making pedestals but have not yet been generated are displayed separately; a radio frequency receiver C is set on the beam-making pedestal; when the precast beam is ready to be produced on the reserved beam-making pedestal, a communication connection is first established between the radio frequency card and the radio frequency receiver C, and the beam-making search module receives the communication connection signal from the radio frequency receiver C, and marks the beam-making pedestal as occupied on the layout map of the beam-making pedestal, and marks the production progress of the precast beam according to the actual progress bar or construction node. Similar to the beam storage pedestal, the distribution area of ​​the beam-making pedestal is also large. Through the layout map of the beam-making pedestal, the position of the precast beam can be tracked, and the production process of the precast beam can also be tracked, which is convenient for updating the status of the construction node.

[0025] Specifically, it also includes a personnel management module, which includes an entry and exit personnel identity recognition unit, an on-site personnel information table, a personnel attendance unit and a personnel assessment unit; when the entry and exit personnel identity recognition unit recognizes that a person enters the beam yard, the person is registered in the on-site personnel information table; when the entry and exit personnel identity recognition unit recognizes that a person leaves the beam yard, the person is removed from the on-site personnel information table; the video stream target capture and analysis unit in the sense of security management module issues a buzzer warning if the identified human target is not in the on-site personnel information table.

[0026] Beneficial effects: The smart beam yard production control system provided by the present invention tracks the entire order cycle, from the start of the order to the end of the delivery of the order product to the destination, and tracks the entire production cycle, from the task disassembly of the order product to the delivery of the order product to the destination; and conducts all-round monitoring in the beam yard, realizing all-round supervision of information flow, logistics, personnel flow, etc. in the beam yard; at the same time, since any changes in production deadlines, production progress, personnel changes, production raw material supply, etc. may lead to chain reactions, compared with the prior art that requires communication between personnel from various departments, this application adopts time schedules, construction nodes, material management and other technologies to achieve rapid transmission of messages, and directly reports in the way that most directly affects relevant personnel, which can improve project quality, speed up construction progress, reduce project costs, and ensure project safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 A schematic diagram of a display method of a layout map of a beam-making pedestal; Figure 2 A schematic diagram of a display method of a time schedule; Figure 3 It is a schematic diagram of a display method of expressing the daily production plan by construction nodes; Figure 4 A schematic diagram of the production plan formation process; Figure 5 A schematic diagram showing a layout map of a beam pedestal. DETAILED DESCRIPTION

[0028] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.

[0029] A smart beam yard production control system includes a beam yard basic information module, an order management module, a main production plan module, a daily production plan module, a material storage module, a material procurement module, a beam storage and search module, a sense of security management module, a transportation supervision module and a personnel management module; the beam yard basic information module collects basic information of the beam yard and evaluates the production capacity and beam storage capacity of the beam yard; the order management module divides the order products into prefabricated parts step by step according to the specification requirements and delivery deadline of the order products, and preliminarily formulates a time schedule for ordering prefabricated parts in combination with the production capacity and beam storage capacity of the beam yard to form a production plan with a tree diagram structure; the main production plan module combines material usage and prefabricated parts The specification requirements further limit the earliest start time and the latest completion time of the prefabricated parts, and adjust the time schedule; the daily production plan module divides the production process of prefabricated parts into construction nodes, and plans the production raw material demand list for each construction node; the material storage module registers all production raw material demand lists, and forms a production raw material procurement list in combination with the time schedule; the material procurement module purchases materials according to the production raw material procurement list; the beam storage and search module is used to establish a connection between the prefabricated beam and the position of the beam storage pedestal; the sense of security management module uses image recognition to monitor the safety of the beam yard; the transportation supervision module is used to establish a connection between the prefabricated beam and the transfer vehicle.

[0030] This case tracks the entire order cycle from the order to the delivery of the ordered products to the destination, and tracks the entire production cycle from the task disassembly of the ordered products to the delivery of the ordered products to the destination; and conducts all-round monitoring in the beam yard, realizing all-round supervision of the information flow, logistics, and personnel flow in the beam yard. The following is a detailed description of each module.

[0031] 1. Beam yard basic information module The beam yard basic information module includes an information collection unit, a beam yard production capacity estimation unit, a beam storage capacity estimation unit and a layout map of the beam manufacturing pedestal.

[0032] The information collection unit is used to collect parameters including the space size of the beam yard, the type and corresponding number of beam pedestals, concrete mixing capacity, steel bar processing capacity, number of construction personnel, inventory capacity of different production materials, types and corresponding numbers of beam storage pedestals, and concrete age of different prefabricated beams. The production materials include low-grade prefabricated parts, concrete, steel bars and embedded parts. Generally speaking, the basic information of the beam yard will not change much after the completion of construction, and the change of personnel is also very slow; however, these basic information are very important for calculating the various production capacities of the beam yard.

[0033] The beam yard production capacity estimation unit selects the required beam-making pedestal type, production materials and unit usage according to the type of precast beam, and estimates the maximum production capacity of the specified type of precast beam based on the number of allocated beam-making pedestals, the number of construction personnel and the number of production materials. The beam yard production capacity can be estimated based on historical experience. After understanding the factors such as the equipment and personnel that can be allocated, it is basically possible to estimate the number of orders that can be undertaken. During the estimation process, the default allocation amount is the maximum limit of the beam yard; when equipment in the beam yard is occupied, it needs to be adjusted or automatically adjusted.

[0034] The beam storage capacity estimation unit selects the required beam storage pedestal type according to the type of precast beam, and estimates the maximum beam storage capacity of the specified type of precast beam based on the number of allocated beam storage pedestals. The beam storage capacity of the beam yard can be calculated based on factors such as the spatial size of the beam yard, the current number of stored beams, and the type of precast beams. During the estimation process, the default allocation amount is the maximum limit of the beam yard; when equipment in the beam yard is occupied, it needs to be adjusted or automatically adjusted.

[0035] In the prior art, the occupancy status of beam-making pedestals and beam-storage pedestals can only be known through on-site surveys or reports from production personnel, and pedestal resources can only be allocated based on experience, which makes it impossible to accurately grasp the overall pedestal information of the beam yard, and makes it difficult to plan beam-making orders and plan the storage of beams, which in turn causes difficulties in finding and locating beams in the later stage. This case designs a layout map of beam-making pedestals, marks the beam-making pedestals one by one on the layout map of the beam-making pedestals, and marks whether there are prefabricated beams on the beam-making pedestals; for the prefabricated beams on the beam-making pedestals, the completed prefabricated beams and the unfinished prefabricated beams are distinguished, and the prefabricated beams that have been reserved for the beam-making pedestals but have not yet been generated are distinguished. Excluding the beam-making pedestals occupied by these three types of prefabricated beams, the remaining are idle beam-making pedestals, which can be directly fed back to the information collection unit such as Figure 1 As shown, a layout map display method of beam-making pedestals is shown, which displays all beam-making pedestals in the area, distinguishes between precast beams that have been completed but not transferred, those in the production process, and those planned for production. Statistical data are also given. After selecting a precast beam, the basic information and production information of the precast beam can also be displayed. Production personnel can reasonably plan the use of the pedestals based on key monitoring parameters such as the current occupancy status, idle status, and release cycle of the beam-making pedestals, so as to maximize the utilization rate of the pedestals and effectively realize efficient and stable operation of the pedestal scheduling.

[0036] Before the production of precast beams, radio frequency card information is compiled for the precast beams, and the beam-making pedestal can be reserved through the radio frequency card information; a radio frequency receiver C is installed on each beam-making pedestal, and when the precast beam starts to be produced on the beam-making pedestal, a communication connection is first established between the radio frequency card and the radio frequency receiver C, and the beam-making and beam-seeking module receives the communication connection signal from the radio frequency receiver C, and marks the beam-making pedestal as occupied on the layout map of the beam-making pedestal. The occupancy information of the beam-making pedestal will be synchronized to other modules in the system to realize information sharing.

[0037] 2. Order Management Module The order management module is used to collect order products and corresponding delivery deadlines, and split the order products into low-level prefabricated parts up to the lowest-level prefabricated parts step by step. The order products are the highest-level prefabricated parts, that is, prefabricated beams; the delivery deadlines of the order products are shown on the time schedule, and the planned progress bars and actual progress bars of the prefabricated parts at each level are shown in a tree chart. The start time of the higher-level prefabricated parts is after the completion time of the lower-level prefabricated parts; the time schedule is synchronized to the main production planning module.

[0038] In the order management module, the system will automatically provide a product disassembly model according to the type of prefabricated parts, and gradually split the order products into low-level prefabricated parts until the lowest level prefabricated parts, and provide the production cycle of the prefabricated parts, so that the procurement department can have a preliminary understanding of the production cycle to properly arrange the delivery time, ensure the timeliness of continuous construction, and ensure the matching of productivity. The execution status can be obtained from the progress database in real time for analysis and adjustment of production scheduling. Figure 2 As shown, this is a display method of the time schedule, which can intuitively compare the delivery deadline, planned progress bar and actual progress bar to assist decision-making.

[0039] 3. Master Production Planning Module After the order management module has initially formulated a time schedule, it will be sent to the main production planning module. After the designers have deepened the design of the order products, they will adjust the prefabricated parts at all levels, and update the structural size information, delivery time, earliest start time, latest completion time, construction type, applicable steel bars, embedded parts, production process and planning cycle of the prefabricated parts at all levels. All prefabricated components to be produced will be reclassified according to the type, production process and completion date of the prefabricated components to be produced. After the division is completed, all kinds of prefabricated components will be produced in the same way. The prefabricated components can be arranged for production on the same mold platform, and the last date of production completion is also the same, and the steel bar processing plan, casting plan and component processing plan will be generated accordingly. After completing the design of all prefabricated parts, the designers will adjust the earliest start time and the latest completion time of the prefabricated parts at all levels on the planned progress bar of the time schedule; and synchronize the time schedule to the order management module and the daily production planning module.

[0040] 4. Daily production planning module When the master production plan module makes detailed adjustments to the time schedule, a further production plan is formed. After the plan is sent to the daily production plan module, it will be further arranged in detail through the daily production plan module; the daily production plan module divides the production process of each level of prefabricated parts into construction nodes, including steel bar binding nodes, formwork installation nodes, concrete pouring nodes, concrete vibration nodes, spray curing nodes, steam curing nodes, tensioning nodes and grouting nodes, and plans the production raw material demand list for each construction node; selects the beam pedestal or processing location, and plans the start time of each construction node according to the earliest start time and latest completion time of each level of prefabricated parts, and adjusts the start time and completion time of each level of prefabricated parts on the planned progress bar of the time schedule; synchronizes the time schedule to the master production plan module, sends the production raw material demand list of each construction node to the material storage module, marks the production raw material demand time, demand type and demand quantity on the production raw material demand list, and marks the beam pedestal ID or processing location ID. The production raw material demand list can be understood as the production raw material demand plan, which refers to the production raw material information required for the production of various prefabricated components calculated based on the steel bar processing plan, casting plan, and component processing plan.

[0041] like Figure 3 As shown, the production of each prefabricated part is divided into each construction node, and the construction nodes are lit up to indicate whether each construction node in the production process has been completed, so that the progress of the construction can be clearly seen.

[0042] 5. Material Storage Module The material storage module reflects the warehousing function. The material storage module registers all production raw material demand lists, counts all production raw material demands, and calculates the out-of-stock time of each type of production raw materials based on the inventory quantity, demand quantity and demand time of the production raw materials; sends the production raw material purchase list to the material procurement module based on the out-of-stock time and stocking cycle of the production raw materials, and marks the demand time, demand type and demand quantity of the production raw materials on the production raw material purchase list; sends the production raw material transfer instruction based on the production raw material demand list and updates the inventory quantity of the production raw materials after the production raw material transfer is completed.

[0043] The material storage module counts all the demands for production raw materials, allocates each type of production raw materials according to the demand time, and allocates the production raw materials with earlier demand time; the material storage module feeds back whether each type of production raw materials in the production raw material procurement list can be adequately allocated to the daily production planning module's production raw material demand list for each construction node; in the daily production planning module, for construction nodes that have not been completed, a distinction is made between construction nodes where all production raw materials are available and construction nodes where not all production raw materials are available; this design enables the production department to predict the subsequent production process in advance.

[0044] 6. Material Procurement Module The material procurement module registers all production raw material procurement lists, compiles statistics on all production raw material demands, generates a steel bar processing schedule, a concrete mixing schedule and a material preparation schedule, and updates the inventory quantity of production raw materials after the production raw materials are put into storage.

[0045] like Figure 4 As shown in the figure, the daily production plan, material preparation plan, concrete mixing plan and steel bar processing plan are gradually formed starting from the order product, covering the production control of the entire life cycle of prefabricated parts from the order to the completion of production; any changes in any link in the process, if they have an impact on other links, will be automatically synchronized in real time, without the need for personnel to notify each department one by one, thereby improving the efficiency of information flow.

[0046] 7. Beam storage and beam search module When beams need to be erected urgently but there are many stored beams, it is impossible to find them quickly and one can only check the sprayed beam numbers one by one on site. This case uses radio frequency card positioning to automatically submit the storage location of each prefabricated beam. Combined with the layout map of the beam storage pedestal, beam storage and search can be quickly realized.

[0047] Similar to the design of the beam-making pedestal, this case also designs a layout map for the beam storage pedestals, and marks the beam storage pedestals one by one on the layout map of the beam storage pedestals; a radio frequency receiver A is set on the beam storage pedestals, and after the precast beam is completed, first find an empty beam storage pedestal on the layout map of the beam storage pedestals, then transfer the precast beam to the beam storage pedestal and establish a communication connection between the radio frequency card and the radio frequency receiver A, the beam storage search module receives the communication connection signal from the radio frequency receiver A, marks the beam storage pedestal as occupied on the layout map of the beam storage pedestal, and starts the timer at the same time to restrict the precast beam from being transferred out before the concrete age reaches; after the precast beam is transferred out of the beam storage pedestal, the communication between the radio frequency card and the radio frequency receiver A is disconnected, the beam storage search module receives the communication disconnection signal from the radio frequency receiver A, marks the beam storage pedestal as idle on the layout map of the beam storage pedestal, and resets the timer at the same time.

[0048] like Figure 5 As shown, this is a display method of the layout map of the beam storage pedestal. The position of the RF receiver A and the beam storage pedestal are interrelated. The signal of the RF receiver A can automatically add or delete prefabricated beams in the layout map of the beam storage pedestal. After the signal is synchronized to other modules, information sharing can be realized.

[0049] 8. Transport supervision module A forward and reverse sensor and a positioning sensor are set on the transfer vehicle, and a radio frequency receiver B is set at the exit of the beam yard where the operating vehicle exits; the transportation supervision module transfers the prefabricated beam to the transfer vehicle and drives it to the exit of the beam yard, and then establishes a communication connection between the radio frequency card and the radio frequency receiver B. The transportation supervision module receives the communication connection signal from the radio frequency receiver B, and at the same time triggers the forward and reverse sensor and the positioning sensor to monitor the position and operating status of the transfer vehicle, track the transportation trajectory until it reaches the destination, and support the backtracking of component information on the beam erection site.

[0050] 9. Sense of Security Management Module The safety management in the beam yard requires the use of cameras and sensors, which are mainly divided into two parts: video analysis and equipment monitoring. A group of cameras are arranged in the beam yard to collect video streams from all angles in the beam yard. The sense of security management module includes a video stream target capture and analysis unit and various special equipment monitoring units.

[0051] The video stream target capture and analysis unit uses AI technology to capture and analyze targets in the video stream: performs face recognition on human targets, and conducts real-time monitoring and early warning of dangerous behaviors including whether a helmet is worn, whether a safety rope is tied, and whether construction equipment is used correctly; for non-human targets, real-time identification and early warning of dangerous sources including deep foundation pits and high slopes are performed; at the same time, cooperates with the smart broadcasting system for directional broadcasting and early warning. Smart broadcasting includes team education and publicity, safety education and publicity, emergency rescue support, smart voice reminders, remote calls and other functions.

[0052] In the beam yard, special equipment with high risks such as tower cranes, bridge erectors, crawler cranes and gantry cranes require special safety management. By installing the "black box" early warning monitoring system, real-time monitoring of the transportation of special equipment can be achieved, and buzzer warnings and SMS push notifications can be sent in abnormal conditions, turning silent management into "sound management". The "black box" early warning monitoring system includes various sensors (such as height sensors, rotation angle sensors, wind speed sensors, driving speed sensors and limit sensors, etc.) and monitoring cameras, and sends sensor detection data and monitoring camera collection information to each special equipment monitoring unit. In each special equipment monitoring unit, the special equipment model is loaded, and the special equipment model, basic parameters, real-time sensor detection data and monitoring camera collection information are displayed on the display screen in partitions.

[0053] 10. Personnel Management Module The personnel management module includes an entry and exit personnel identity recognition unit, an on-site personnel information table, a personnel attendance unit and a personnel assessment unit; when the entry and exit personnel identity recognition unit recognizes that a person enters the beam yard, the person is registered in the on-site personnel information table; when the entry and exit personnel identity recognition unit recognizes that a person leaves the beam yard, the person is removed from the on-site personnel information table; the video stream target capture and analysis unit in the sense of security management module issues a buzzer warning if the recognized human target is not in the on-site personnel information table.

[0054] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the above embodiments do not limit the present invention in any form, and any technical solution obtained by equivalent replacement or equivalent transformation falls within the protection scope of the present invention.

Claims

1. A smart beam yard production control system, characterized by: It includes a beam yard basic information module, an order management module, a main production plan module, a daily production plan module, a material storage module, a material procurement module, a beam storage and search module, a sense of security management module and a transportation supervision module; the beam yard basic information module collects the basic information of the beam yard and evaluates the production capacity and beam storage capacity of the beam yard. The basic information of the beam yard includes parameters such as the space size of the beam yard, the type and corresponding number of beam-making pedestals, concrete mixing capacity, steel bar processing capacity, number of construction personnel, inventory capacity of different production raw materials, types and corresponding numbers of beam storage pedestals, and concrete age of different prefabricated beams. The production raw materials include low-level prefabricated parts, concrete, steel bars and embedded parts; the order management module splits the order products into prefabricated parts step by step according to the specification requirements and delivery deadline of the order products, and preliminarily formulates a time schedule for ordering prefabricated parts in combination with the production capacity and beam storage capacity of the beam yard to form a production plan with a tree diagram structure; the main production plan module further limits the earliest start time and the latest completion time of the prefabricated parts in combination with the material consumption and the specification requirements of the prefabricated parts, and adjusts the time schedule; The daily production planning module divides the production process of prefabricated parts into construction nodes and plans the production raw material demand list for each construction node; the material storage module registers all production raw material demand lists and forms a production raw material procurement list in combination with the time schedule; the material procurement module purchases materials according to the production raw material procurement list; the beam storage and search module is used to establish a connection between the prefabricated beam and the position of the beam storage pedestal; the sense of security management module uses image recognition to monitor the safety of the beam yard; the transportation supervision module is used to establish a connection between the prefabricated beam and the transfer vehicle.

2. The intelligent beam yard production control system according to claim 1 is characterized in that: The basic information module of the beam yard includes an information collection unit, a beam yard production capacity estimation unit and a beam storage capacity estimation unit; the information collection unit is used to collect parameters including the space size of the beam yard, the type and corresponding number of beam-making pedestals, concrete mixing capacity, steel bar processing capacity, number of construction personnel, inventory capacity of different production raw materials, types and corresponding numbers of beam storage pedestals, and concrete ages of different precast beams, and the production raw materials include low-grade precast parts, concrete, steel bars and embedded parts; the beam yard production capacity estimation unit selects the required type of beam-making pedestals, production raw materials and unit usage according to the type of precast beams, and estimates the maximum production capacity of the specified type of precast beams based on the allocated number of beam-making pedestals, number of construction personnel and number of production raw materials; the beam storage capacity estimation unit selects the required type of beam storage pedestals according to the type of precast beams, and estimates the maximum beam storage capacity of the specified type of precast beams based on the allocated number of beam storage pedestals; The order management module collects order products and corresponding delivery deadlines, and splits the order products into low-level prefabricated parts until the lowest-level prefabricated parts step by step. The order products are the highest-level prefabricated parts, i.e., prefabricated beams; the delivery deadlines of the order products are shown on the time schedule, and the planned progress bars and actual progress bars of the prefabricated parts at each level are shown in a tree chart. The start time of the higher-level prefabricated parts is after the completion time of the lower-level prefabricated parts; the time schedule is synchronized to the main production planning module; The main production planning module collects basic information of prefabricated parts at all levels, including structural dimensions, production materials and unit usage, production process and shortest production time; adjusts the earliest start time and the latest completion time of prefabricated parts at all levels on the planned progress bar of the time schedule; and synchronizes the time schedule to the order management module and the daily production planning module; The daily production planning module divides the production process of prefabricated parts at all levels into construction nodes, including steel bar binding nodes, formwork installation nodes, concrete pouring nodes, concrete vibration nodes, spray curing nodes, steam curing nodes, tensioning nodes and grouting nodes, and plans the production raw material demand list for each construction node; selects the beam making pedestal or processing location, and plans the start time of each construction node according to the earliest start time and the latest completion time of the prefabricated parts at all levels, and adjusts the start time and completion time of the prefabricated parts at all levels on the planned progress bar of the time schedule; synchronizes the time schedule to the main production planning module, sends the production raw material demand list for each construction node to the material storage module, marks the production raw material demand time, demand type and demand quantity on the production raw material demand list, and marks the beam making pedestal ID or processing location ID; The material storage module registers all production material demand lists, collects statistics on all production material demands, and calculates the out-of-stock time of each type of production material based on the inventory quantity, demand quantity and demand time of the production material; sends the production material purchase list to the material procurement module based on the out-of-stock time and stocking cycle of the production material, and marks the demand time, demand type and demand quantity of the production material on the production material purchase list; sends the production material transfer instruction based on the production material demand list and updates the inventory quantity of the production material after the production material transfer is completed; The material procurement module registers all production raw material procurement lists, counts all production raw material requirements, and updates the inventory quantity of production raw materials after the production raw materials are put into storage; A radio frequency card is installed on the precast beam, and a radio frequency receiver A is set on the beam storage pedestal; the beam storage and beam search module includes a layout map of the beam storage pedestals, and the beam storage pedestals are marked one by one on the layout map of the beam storage pedestals; after the precast beam is completed, first find an idle beam storage pedestal on the layout map of the beam storage pedestals, then transfer the precast beam to the beam storage pedestal and establish a communication connection between the radio frequency card and the radio frequency receiver A, the beam storage and beam search module receives a communication connection signal from the radio frequency receiver A, marks the beam storage pedestal as occupied on the layout map of the beam storage pedestal, and starts a timer at the same time to restrict the precast beam from being transferred out before the concrete age reaches; after the precast beam is transferred out of the beam storage pedestal, the communication between the radio frequency card and the radio frequency receiver A is disconnected, the beam storage and beam search module receives a communication disconnection signal from the radio frequency receiver A, marks the beam storage pedestal as idle on the layout map of the beam storage pedestal, and resets the timer at the same time; A forward and reverse sensor and a positioning sensor are set on the transfer vehicle, and a radio frequency receiver B is set at the exit of the beam yard where the operating vehicle drives out; the transport supervision module transfers the prefabricated beam to the transfer vehicle and drives it to the exit of the beam yard, and establishes a communication connection between the radio frequency card and the radio frequency receiver B. The transport supervision module receives the communication connection signal from the radio frequency receiver B, and at the same time triggers the forward and reverse sensor and the positioning sensor to monitor the position and operating status of the transfer vehicle, and track the transport trajectory until it reaches the destination; A group of cameras are arranged in the beam yard to collect video streams from all viewing angles in the beam yard; The sense of security management module includes a video stream target capture and analysis unit, which captures and analyzes targets in the video stream: performs face recognition on human targets, and performs real-time monitoring and early warning reminders on dangerous behaviors including whether a helmet is worn, whether a safety rope is tied, and whether construction equipment is used correctly; For non-human targets, real-time identification and early warning of dangerous sources including deep foundation pits and high slopes are carried out.

3. The intelligent beam yard production control system according to claim 1 is characterized in that: In the daily production plan module, a construction node is lit up to indicate whether each construction node in the production process has been completed.

4. The intelligent beam yard production control system according to claim 3 is characterized in that: The material storage module collects statistics on all production raw material demands, allocates each type of production raw material in order of demand time, and allocates production raw materials to those with earlier demand times; it feeds back whether each type of production raw material in the production raw material procurement list can be adequately allocated to the production raw material demand list of each construction node in the daily production planning module; in the daily production planning module, for construction nodes that have not been completed, a distinction is made between construction nodes where all production raw materials are available and construction nodes where not all production raw materials are available.

5. The intelligent beam yard production control system according to claim 2 is characterized in that: The material procurement module registers all production raw material procurement lists, compiles statistics on all production raw material demands, generates a steel bar processing schedule, a concrete mixing schedule and a material preparation schedule, and updates the inventory quantity of the production raw materials after the production raw materials are put into storage.

6. The intelligent beam yard production control system according to claim 2 is characterized in that: The sense of security management module also includes various special equipment monitoring units. The special equipment includes tower cranes, bridge erection machines, crawler cranes and gantries installed in the beam yard. Various sensors are installed on the special equipment, and monitoring cameras are installed for each feature equipment. The sensor detection data and monitoring camera collection information are sent to each special equipment monitoring unit. The sensors include height sensors, rotation angle sensors, wind speed and force sensors, driving speed sensors and limit sensors. In each special equipment monitoring unit, the special equipment model is loaded, and the special equipment model, basic parameters, real-time sensor detection data and monitoring camera collection information are displayed in partitions on the display screen. When there are abnormalities in the real-time sensor detection data and monitoring camera collection information, a buzzer warning is issued.

7. The intelligent beam yard production control system according to claim 2 is characterized in that: The basic information module of the beam yard also includes a layout map of the beam-making pedestals, on which the beam-making pedestals are marked one by one, and it is marked whether there are prefabricated beams on the beam-making pedestals; for the prefabricated beams on the beam-making pedestals, completed prefabricated beams and unfinished prefabricated beams are displayed separately, and at the same time, prefabricated beams that have been reserved for the beam-making pedestals but have not yet been generated are displayed separately; a radio frequency receiver C is set on the beam-making pedestal; when the prefabricated beam is ready to be produced on the reserved beam-making pedestal, a communication connection is first established between the radio frequency card and the radio frequency receiver C, and the beam-making and beam-seeking module receives the communication connection signal from the radio frequency receiver C, and the beam-making pedestal is marked as occupied on the layout map of the beam-making pedestal, and the production progress of the prefabricated beam is marked according to the actual progress bar or construction node.

8. The intelligent beam yard production control system according to claim 2 is characterized in that: It also includes a personnel management module, which includes an entry and exit personnel identification unit, an on-site personnel information table, a personnel attendance unit, and a personnel assessment unit; when the entry and exit personnel identification unit identifies a person entering the beam yard, the person is registered in the on-site personnel information table; when the entry and exit personnel identification unit identifies a person leaving the beam yard, the person is removed from the on-site personnel information table; The video stream target capture and analysis unit in the sense of security management module issues a buzzer warning if the identified human target is not in the on-site personnel information table.

Citation Information

Patent Citations

  • BIM-based fabricated building management and control and material tracing production line construction method

    CN112731892A

  • Intelligent construction site comprehensive management platform and method thereof

    CN114399408A

  • Beam field planning design and production scheduling system

    CN115018440A

Cited By

  • Optimal configuration method and system for steel bar profile steel processing personnel

    CN119940881A