Mine karst water inrush point roadway bottom plate reinforcing device

By laying fixed plates and connectors on the bottom plate of the mine tunnel, an inclined drilling structure is formed, which solves the problem of reinforcement stability of water burst point, and effectively realizes cement mortar filling and water burst prevention, improving the safety and flexibility of the tunnel floor plate. sex.

CN119041950APending Publication Date: 2024-11-29SICHUAN HUAYINGSHAN LONGTAN COAL
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411121768.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

After reinforcement, the bottom plate of the mine karst water inrush point tunnel is prone to deformation and cracks due to the huge pressure of cement mortar and water inrush, making it difficult to effectively prevent water inrush accidents.

Method used

A plurality of fixed plates are laid along the length of the tunnel, and through the connecting parts and drilling structures, a first drilling hole and a circular through hole with an incline of 45 degrees are formed to avoid damage to the water burst point, and cement mortar is poured into the water burst to Block.

Benefits of technology

It effectively avoids early water burst at the water burst point, improves the reinforcement stability of the tunnel floor, facilitates later cement mortar filling, enhances the water burst prevention effect, and the device can be adjusted and removed as needed, improving the fault tolerance rate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041950A_ABST
    Figure CN119041950A_ABST
Patent Text Reader

Abstract

The invention relates to mine reinforcement, and provides a mine karst water inrush point roadway bottom plate reinforcing device which comprises a plurality of fixing plates laid at the bottom of a roadway in the length direction of the roadway, connecting pieces used for connecting the adjacent fixing plates, side plates arranged at the two ends of the fixing plates and first connecting holes formed in the side plates. The first drilling holes are formed in the two sides of the bottom of the roadway, the semicircular through holes are formed in the side edges of the fixing plates, and the first connecting rods are inserted into the first connecting holes and the first drilling holes at the same time; the included angle between the side plate and the bottom plate is 135 degrees, and the first drill holes are perpendicular to the plane where the side edges are located; and the through holes of the adjacent fixing plates are enclosed to form a circle. According to the mine karst water inrush point roadway bottom plate reinforcing device, a roadway bottom plate can be reinforced on the basis of the original roadway bottom plate, and cement mortar can be conveniently poured in the later period after reinforcement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of mine reinforcement, and in particular to a mine karst water burst point tunnel floor reinforcement device. Background Art

[0002] Karst water inrush points in mines refer to the phenomenon of large amounts of water suddenly gushing out from underground water that is stored and moves in karst aquifers when it is artificially exposed or affected by natural factors. This phenomenon is often accompanied by sand and mud gushing out, which endangers safety. Karst is a geological process in which water chemically dissolves soluble rocks (such as carbonate rocks, gypsum, rock salt, etc.), as well as mechanical actions such as water erosion, subsidence and collapse, as well as the general term for the phenomena caused by these actions. Karst water inrush is particularly prone to cause serious well flooding accidents.

[0003] Mine water inrush can occur in different parts of the mining shaft, such as working face water inrush and tunnel water inrush, which can be specifically divided into excavation face water inrush, mining face water inrush, roof water inrush, floor water inrush and lateral water inrush.

[0004] For water bursting from the bottom plate, most of the solutions are to drill holes in the bottom plate, and then pour a large amount of cement mortar into the holes under high pressure, and then seal the water bursting places after the cement mortar solidifies. Although the excess water will be pumped out through the holes before pouring the cement mortar, when pouring the cement mortar, the bottom plate of the mine tunnel will inevitably deform and crack due to the huge pressure of the cement mortar and the water bursting. Therefore, for potential water bursting hazards or those that have already occurred, the corresponding bottom plate needs to be reinforced on the original basis. Summary of the invention

[0005] The purpose of the present invention is to provide a tunnel floor reinforcement device for karst water bursting points in mines, which can reinforce the tunnel floor on the basis of its original foundation and facilitate the subsequent pouring of cement mortar after reinforcement.

[0006] The embodiments of the present invention are realized through the following technical scheme: the bottom plate reinforcement device of the mine karst water bursting point tunnel of the present invention comprises a plurality of fixed plates laid on the bottom of the tunnel along the length direction of the tunnel, connecting parts for connecting adjacent fixed plates, side plates arranged at both ends of the fixed plates, a first connecting hole opened on the side plates, a first drilled hole opened on both sides of the bottom of the tunnel, a semicircular through hole opened on the side of the fixed plate, and a first connecting rod inserted into the first connecting hole and the first drilled hole at the same time; the angle between the side plate and the bottom plate is 135 degrees, and the first drilled hole is perpendicular to the plane where the side is located; the through holes of adjacent fixed plates are enclosed to form a circle.

[0007] Furthermore, the connecting member includes a first connecting plate simultaneously attached to the adjacent side plates, and a second connecting hole opened on the first connecting plate; the first connecting hole corresponds to the second connecting hole one by one; the end of the first connecting rod away from the first drilled hole passes through the first connecting hole and the second connecting hole in sequence and is threadedly connected with a fastening bolt; the fastening bolt abuts against the first connecting plate.

[0008] Furthermore, the diameter of the first borehole is the same as the diameter of the first connecting hole, and the diameter of the first connecting hole is larger than the diameter of the first connecting rod; and cement mortar is poured into the first borehole.

[0009] Furthermore, the connecting member further includes a second connecting plate disposed on the upper side between adjacent fixing plates; both ends of the second connecting plate are fixedly connected to the first connecting plate, and the second connecting plate is used to cover the through hole.

[0010] Furthermore, first grooves are provided on both side edges of the fixing plate, and the second connecting plate is clamped in the first grooves.

[0011] Furthermore, the depth of the first groove is the same as the thickness of the second connecting plate.

[0012] Furthermore, a plurality of third connecting holes are opened on the fixing plate, and a plurality of second drilled holes are opened at the bottom of the tunnel; the third connecting holes correspond one-to-one to the second drilled holes; and a plurality of second connecting rods are also included, and the second connecting rods are simultaneously inserted into the third connecting holes and the second drilled holes.

[0013] Furthermore, a coaxially arranged second groove is provided on the upper side of the third connecting hole, and a limiting plate is provided on the upper end of the second connecting rod; the limiting plate is clamped in the second groove.

[0014] Furthermore, the diameter of the second borehole is equal to the diameter of the third connecting hole; the diameter of the second borehole is greater than the diameter of the second connecting rod; and cement mortar is poured into the second borehole.

[0015] The technical solution of the embodiment of the present invention has at least the following advantages and beneficial effects: the bottom plate reinforcement device for the mine karst water burst point of the present invention, when in use, first lays the fixed plate on the bottom of the tunnel, then drills the first borehole according to the position of the side plate and the first connecting hole on the side plate, inserts the first connecting rod after drilling the first borehole, fixes the side plate, and can directly fix the fixed plate through the side plate. And because the first borehole is drilled at an angle of 45 degrees, it can well avoid damage to the water burst point at the bottom of the tunnel, and can avoid water bursting in advance at the water burst point. And the through holes between adjacent fixed plates are surrounded by circular holes, so that when water burst occurs or is about to burst in the later stage, it can be directly drilled through, and cement mortar is directly poured into the borehole after drilling and solidified, so as to further prevent water burst. In addition, since the device is composed of multiple fixed plates, the length of the fixed plate can be increased or decreased as needed, and the fixed plate can be added in the later stage, or it can be continued to be used after being dismantled, so that the fault tolerance rate of the device is higher. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0017] Figure 1 A schematic diagram of the structure of a tunnel floor reinforcement device for a karst water inrush point in a mine provided by an embodiment of the present invention;

[0018] Figure 2 A schematic structural diagram of a first drilling portion provided in an embodiment of the present invention;

[0019] Figure 3 A schematic structural diagram of a second drilling portion provided by an embodiment of the present invention;

[0020] Figure 4 A schematic diagram of the structure of the fixing plate assembly provided by an embodiment of the present invention;

[0021] Figure 5 A schematic diagram of the structure of a fixed plate provided in an embodiment of the present invention when part of the fixed plate is unfolded;

[0022] Figure 6 A schematic diagram of the structure of a fixing plate portion provided by an embodiment of the present invention;

[0023] Figure 7 A schematic structural diagram of a connector portion provided in an embodiment of the present invention.

[0024] Icons: 10-alleyway, 11-first drill hole, 12-second drill hole, 21-fixed plate, 22-through hole, 23-first groove, 24-side plate, 25-first connecting hole, 26-third connecting hole, 27-second groove, 28-second connecting rod, 29-limiting plate, 31-first connecting plate, 32-second connecting plate, 33-second connecting hole, 34-first connecting rod. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0026] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0027] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0028] In the description of the present invention, it should be noted that if the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside" and the like appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship in which the product of the application is usually placed when used. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0029] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0030] Example

[0031] The following is further described in conjunction with specific embodiments. Figure 1 -Attached Figure 7 As shown, the bottom plate reinforcement device of the mine karst water inrush point tunnel 10 of this embodiment includes a plurality of fixed plates 21 laid at the bottom of the tunnel 10 along the length direction of the tunnel 10, connecting parts for connecting adjacent fixed plates 21, side plates 24 arranged at both ends of the fixed plates 21, first connecting holes 25 opened on the side plates 24, first drilled holes 11 opened on both sides of the bottom of the tunnel 10, semicircular through holes 22 opened on the sides of the fixed plates 21, and a first connecting rod 34 inserted into the first connecting hole 25 and the first drilled hole 11 at the same time; the angle between the side plate 24 and the bottom plate is 135 degrees, the first drilled hole 11 is perpendicular to the plane where the side is located; the through holes 22 of adjacent fixed plates 21 are enclosed to form a circle. Specifically, when in use, the fixing plate 21 is first laid at the bottom of the lane 10, and then the first borehole 11 is drilled according to the position of the side plate 24 and the first connecting hole 25 on the side plate 24. After the first borehole 11 is drilled, the first connecting rod 34 is inserted to fix the side plate 24, and the fixing plate 21 can be directly fixed by the side plate 24. And because the first borehole 11 is drilled at an angle of 45 degrees, it can well avoid damage to the water burst point at the bottom of the lane 10, and can avoid water bursting in advance at the water burst point. And the through holes 22 between adjacent fixing plates 21 are surrounded by circular holes, so that when water burst occurs or is about to burst in the later stage, it can be directly drilled through, and cement mortar is directly poured into the borehole after drilling and solidified, so as to further prevent water burst. In addition, since the device is composed of multiple fixing plates 21, the length of the fixing plate 21 can be increased or reduced as needed, and the fixing plate 21 can also be added in the later stage, or it can be continued to be used after being removed, so that the fault tolerance rate of the device is higher.

[0032] The connecting member in this embodiment includes a first connecting plate 31 which is simultaneously attached to the adjacent side plates 24, and a second connecting hole 33 which is opened on the first connecting plate 31; the first connecting hole 25 corresponds to the second connecting hole 33 one by one; the end of the first connecting rod 34 away from the first bore hole 11 passes through the first connecting hole 25 and the second connecting hole 33 in sequence and is threadedly connected with the fastening bolt; the fastening bolt abuts against the first connecting plate 31. The diameter of the first bore hole 11 is the same as the diameter of the first connecting hole 25, and the diameter of the first connecting hole 25 is larger than the diameter of the first connecting rod 34; cement mortar is poured into the first bore hole 11. Specifically, by using the first connecting plate 31 to press on the side plate 24, not only can the fixing plate 21 be connected and fixed by the first connecting plate 31, but also it is convenient to add a new fixing plate 21 later, and the installation and removal of the fixing plate 21 are more convenient. By increasing the diameter of the first bore hole 11 and pouring cement mortar into the first bore hole 11, not only can the first connecting rod 34 be better fixed, but also cement mortar can be poured through the first bore hole 11 when water inrush occurs (this situation only occurs when water inrush has occurred or is about to occur when the fixing plate 21 is installed).

[0033] The connecting member in this embodiment also includes a second connecting plate 32 disposed on the upper side between adjacent fixed plates 21; both ends of the second connecting plate 32 are fixedly connected to the first connecting plate 31, and the second connecting plate 32 is used to block the through hole 22. Both sides of the fixed plate 21 are provided with a first groove 23, and the second connecting plate 32 is clamped in the first groove 23. The depth of the first groove 23 is the same as the thickness of the second connecting plate 32. Specifically, the use of the second connecting plate 32 can not only better press the fixed plate 21 so that multiple fixed plates 21 are in the same horizontal plane, but also can well block the through hole 22. When it is necessary to drill a hole at the through hole 22, it is only necessary to loosen the fastening screw, then remove the first connecting plate 31 and the second connecting plate 32, and after pouring cement mortar, fix the first connecting plate 31 and the second connecting plate 32 back to their original positions.

[0034] In this embodiment, a plurality of third connection holes 26 are provided on the fixed plate 21, and a plurality of second bore holes 12 are provided at the bottom of the lane 10; the third connection holes 26 correspond to the second bore holes 12 one by one; and a plurality of second connection rods 28 are also provided, and the second connection rods 28 are inserted into the third connection holes 26 and the second bore holes 12 at the same time. A coaxially arranged second groove 27 is provided on the upper side of the third connection hole 26, and a limit plate 29 is provided on the upper end of the second connection rod 28; the limit plate 29 is clamped in the second groove 27. The diameter of the second bore hole 12 is equal to the diameter of the third connection hole 26; the diameter of the second bore hole 12 is greater than the diameter of the second connection rod 28; and cement mortar is poured into the second bore hole 12. Specifically, the functions of the second bore hole 12 are to seal the karst water burst by pouring cement mortar into the karst water burst through the second bore hole 12, and to fix the fixed plate 21 through the second connection rod 28. When dismantling, it is only necessary to remove the limit plate 29 and leave the second connecting rod 28 in place (cement mortar is poured into the second borehole 12, which is difficult to remove). The limit plate 29 can be directly cut off, or the limit plate 29 and the second connecting plate 32 can be connected by threads. It is also possible not to set the second borehole 12 at the beginning, and drill the second borehole 12 when a water inrush occurs, and then insert the second connecting rod 28 for fixing after pouring cement. In this way, there are more holes on the entire fixed plate 21 that can be drilled, which can better cope with water inrush situations in different parts.

[0035] In summary, the bottom plate reinforcement device of the mine karst water bursting point tunnel 10 of the present embodiment, when in use, first lays the fixed plate 21 at the bottom of the tunnel 10, then drills the first borehole 11 according to the position of the side plate 24 and the first connecting hole 25 on the side plate 24, inserts the first connecting rod 34 after the first borehole 11 is drilled, fixes the side plate 24, and can directly fix the fixed plate 21 through the side plate 24. And because the first borehole 11 is drilled at an angle of 45 degrees, it can well avoid damage to the water bursting point at the bottom of the tunnel 10, and can avoid water bursting in advance at the water bursting point. And the through holes 22 between adjacent fixed plates 21 are surrounded by circular holes, so that when water bursting occurs or is about to occur in the later stage, it can be directly drilled through, and cement mortar is directly poured into the borehole after drilling and solidified, so as to further prevent water bursting. In addition, since the device is composed of multiple fixing plates 21, the length of the fixing plates 21 can be increased or decreased as needed, and additional fixing plates 21 can be added at a later stage, or the device can continue to be used after being removed, which makes the device more fault-tolerant.

[0036] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A floor reinforcement device for a mine karst water inrush point tunnel (10), characterized in that: The invention comprises a plurality of fixing plates (21) laid at the bottom of the lane (10) along the length direction of the lane (10), a connecting piece for connecting adjacent fixing plates (21), side plates (24) arranged at both ends of the fixing plates (21), a first connecting hole (25) opened on the side plates (24), a first drilling hole (11) opened at both sides of the bottom of the lane (10), a semicircular through hole (22) opened on the side of the fixing plate (21), and a first connecting rod (34) inserted into both the first connecting hole (25) and the first drilling hole (11); The angle between the side plate (24) and the bottom plate is 135 degrees, the first drilled hole (11) is perpendicular to the plane where the side edge is located; and the through holes (22) of the adjacent fixing plates (21) are enclosed to form a circle.

2. The bottom plate reinforcement device for a mine karst water inrush point tunnel (10) according to claim 1 is characterized in that: The connecting member comprises a first connecting plate (31) attached to the adjacent side plate (24) at the same time, and a second connecting hole (33) opened on the first connecting plate (31); The first connecting hole (25) corresponds to the second connecting hole (33) one by one; the end of the first connecting rod (34) away from the first drilling hole (11) passes through the first connecting hole (25) and the second connecting hole (33) in sequence and is threadedly connected with a fastening bolt; the fastening bolt abuts against the first connecting plate (31).

3. The bottom plate reinforcement device for a mine karst water inrush point tunnel (10) according to claim 2 is characterized in that: The diameter of the first borehole (11) is the same as the diameter of the first connecting hole (25), and the diameter of the first connecting hole (25) is larger than the diameter of the first connecting rod (34); cement mortar is poured into the first borehole (11).

4. The bottom plate reinforcement device for a mine karst water inrush point tunnel (10) according to claim 2 is characterized in that: The connecting member further comprises a second connecting plate (32) arranged on the upper side between adjacent fixing plates (21); both ends of the second connecting plate (32) are fixedly connected to the first connecting plate (31), and the second connecting plate (32) is used to cover the through hole (22).

5. The bottom plate reinforcement device for a mine karst water inrush point tunnel (10) according to claim 4 is characterized in that: Both side edges of the fixing plate (21) are provided with first grooves (23), and the second connecting plate (32) is clamped in the first grooves (23).

6. The bottom plate reinforcement device for a mine karst water inrush point tunnel (10) according to claim 5 is characterized in that: The depth of the first groove (23) is the same as the thickness of the second connecting plate (32).

7. The bottom plate reinforcement device for a mine karst water inrush point tunnel (10) according to claim 1 is characterized in that: The fixing plate (21) is provided with a plurality of third connection holes (26), and the bottom of the tunnel (10) is provided with a plurality of second bore holes (12); the third connection holes (26) correspond one to one with the second bore holes (12); It also includes a plurality of second connecting rods (28), wherein the second connecting rods (28) are inserted into the third connecting holes (26) and the second bore holes (12) at the same time.

8. The bottom plate reinforcement device for a mine karst water inrush point tunnel (10) according to claim 7 is characterized in that: A coaxially arranged second groove (27) is provided on the upper side of the second connecting hole (33), and a limiting plate (29) is provided on the upper end of the second connecting rod (28); the limiting plate (29) is clamped in the second groove (27).

9. The bottom plate reinforcement device for a mine karst water inrush point tunnel (10) according to claim 8, characterized in that: The diameter of the second borehole (12) is equal to the diameter of the third connecting hole (26); the diameter of the second borehole (12) is greater than the diameter of the second connecting rod (28); and cement mortar is poured into the second borehole (12).