Power system modeling method and device for new energy base
By obtaining the unit parameters of the new energy base, dividing them into stations and establishing simulation models, it solves the problem that it is difficult to simultaneously study the electromagnetic transient characteristics of new energy units and stations in the existing technology, and realizes the rapid and efficient establishment of the power system model and hardware in-ring simulation capabilities.
Patent Information
- Application Number
- CN202411277342.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2024-12-03
AI Technical Summary
The existing technology is difficult to simultaneously study the electromagnetic transient characteristics of new energy units and the electromagnetic transient characteristics of new energy stations in the same simulation model, and lacks hardware in-loop simulation capabilities, so it is impossible to realize the closed loop between the controller and the simulator of new energy units. Real-time simulation.
By obtaining the parameter information of each new energy unit in the new energy base, it is divided into new energy station collection according to the type, selecting units with the same structure and parameters to establish a simulation model of the power generation unit and a collecting line equivalent model, and establishing power through the collection bus connection System model, with simulation capabilities of single unit and station.
It has achieved rapid and efficient establishment of the power system model of the new energy base, and has the ability to simulate electromagnetic transient feature and station simulation for a single unit, which reduces the use of computing resources and supports the hardware in-loop real-time simulation of the new energy unit controller.
Smart Images

Figure CN119070385A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power grids, and in particular to a method and device for modeling a power system of a new energy base. Background Art
[0002] At present, the construction of new domestic power systems is in full swing, the proportion of new energy sources is increasing, large-scale new energy bases represented by deserts and Gobi regions are accelerating development, the scale of ultra-high voltage direct current long-distance transmission continues to increase, and the appearance of the power system has undergone profound changes. As the new control object of the power system, large-scale new energy bases have changed from a few homogeneous large-capacity synchronous generators on the original power generation side to massive heterogeneous power generation systems widely distributed in hundreds of square kilometers or even thousands of square kilometers, mainly including wind turbines, photovoltaic units, SVG units, and STATOM units. The single-unit capacity of the above power generation units and reactive power compensation units is small, the number is huge, and all of them are connected to the grid by power electronic converters, which is very different from traditional synchronous generators. The above changes have put forward higher requirements for power system simulation technology, which are mainly manifested in two aspects: first, larger-scale parallel simulation computing resources are needed to complete electromagnetic transient simulation, and second, smaller simulation steps are needed to achieve accurate simulation of power electronic switching devices, so that it is possible to carry out broadband oscillation research and system stability analysis on large-scale new energy power systems.
[0003] At present, electromagnetic transient simulation of DC power transmission systems for large-scale new energy bases is mainly constrained by simulation computing power. The method generally adopted by domestic and foreign peers is the equivalent modeling of new energy stations. A large new energy station is simulated by multiplying single machines and aggregating groups of units of the same model to make hundreds or thousands of new energy generators equivalent to a single unit or several units. However, this method has the following disadvantages:
[0004] 1. Without a single unit model, it is impossible to simulate and analyze the electromagnetic transient characteristics of a single unit.
[0005] 2. The model is not universal. It is not possible to study the electromagnetic transient characteristics of a single unit as well as the electromagnetic transient characteristics of the collector and station levels of new energy units in the same simulation model.
[0006] 3. It does not have hardware-in-the-loop simulation capabilities, cannot realize closed-loop real-time simulation of new energy unit controllers and simulators, and cannot conduct simulation tests of new energy unit control programs in large power grids. Summary of the invention
[0007] Based on this, the present invention provides a power system modeling method and device for a new energy base, and establishes a standard power system model for a large-scale new energy base, so that the model has the electromagnetic transient characteristics simulation capability of a single new energy unit and the simulation capability of a new energy station.
[0008] In a first aspect, a power system modeling method for a new energy base includes:
[0009] Obtain parameter information of each new energy unit in the new energy base;
[0010] Divide into at least one new energy station set according to the type of the new energy unit;
[0011] For each set of new energy stations, if the structures and parameters of at least two new energy units connected by the collectors in the set of new energy stations are the same, a new energy unit connected by one of the collectors is selected to establish a power generation unit simulation model, and the new energy stations connected by the other collectors are used to establish equivalent models of the new energy collectors. The power generation unit simulation model and the equivalent model are connected to the first-level busbar through the collector to obtain the power system model of the new energy base.
[0012] Furthermore, the power system modeling method of the new energy base also includes:
[0013] According to the voltage parameters of the first-level collecting bus and the second-level collecting bus, in combination with the simulation model and equivalent model of the power generation unit connected to the collecting line on the first-level collecting bus, and the overhead line structure of the second-level collecting bus, a first station equivalent model is established, wherein the first station equivalent model is connected to the second-level collecting bus through the overhead line;
[0014] According to the voltage parameters of the second-level collection bus and the third collection bus, combined with the simulation model and equivalent model of the power generation unit connected to the collection line on the first-level collection bus, and the overhead line structure of the third-level collection, a second station equivalent model is established, and the second station equivalent model is connected to the third-level collection bus through the overhead line;
[0015] The first-level busbar and the second-level busbar are connected via a first transformer structure, and the second-level busbar and the third-level busbar are connected via a second transformer structure.
[0016] The first level busbar is a 35 kV busbar, the second level busbar is a 220 kV busbar, and the third level busbar is a 500 kV busbar.
[0017] The first station equivalent model is a new energy 220kV station equivalent model, and the second station equivalent model is a new energy 500kV station equivalent model.
[0018] Furthermore, the power loss of the new energy station represented by the power generation unit simulation model is:
[0019]
[0020] in, For the The line impedance value, For the The apparent power exported by each new energy unit, For the The voltage at the outlet of each new energy unit, is the grid voltage, The number of new energy units connected to the collector line.
[0021] Furthermore, the total loss of a single collector line in the power system of the new energy base is ,in is the total loss of a single collector line.
[0022] Furthermore, the power loss of the equivalent model of the new energy collector is:
[0023] ,
[0024] in, is the power loss of the equivalent model of the collector, is the line impedance after equalization, is the sum of the apparent power exported by each new energy unit, is the grid-connected point voltage vector value.
[0025] Furthermore, the capacity of the new energy generating units before and after the equalization satisfies the first constraint condition, and the expression of the first constraint condition is:
[0026] ,
[0027] in For the The capacity of the unit, is the number of units in the new energy station before the equivalent value, For the The capacity of the equivalent unit, is the number of units after equalization.
[0028] In a second aspect, the present invention further provides a power system modeling device for a new energy base, comprising:
[0029] The parameter acquisition module is used to obtain the parameter information of each new energy unit in the new energy base;
[0030] A unit classification module, used for classifying the new energy units into at least one new energy station set according to their types;
[0031] A model building module is used for each set of new energy stations. If the structures and parameters of the new energy units connected by at least two collectors in the set of new energy stations are the same, a new energy unit connected by one of the collectors is selected to establish a power generation unit simulation model, and the new energy stations connected by other collectors are used to establish equivalent models of the new energy collectors. The power generation unit simulation model and the equivalent model are connected to the first-level busbar through the collector to obtain the power system model of the new energy base.
[0032] In a third aspect, the present invention further provides a computer-readable storage medium having a computer program stored thereon, wherein the computer program, when executed by a processor, implements the steps of any one of the methods for modeling a power system of a new energy base in the first aspect.
[0033] In a fourth aspect, the present invention further provides a computer device, comprising a memory and a processor, wherein the memory stores a computer program, and when the processor executes the computer program, it executes any one of the methods for modeling a power system of a new energy base in the first aspect.
[0034] The beneficial effects of adopting the above technical solution are as follows: the present invention establishes single-machine fine simulation models and equivalent models for new energy stations with the same topological structure and the same parameters in the new energy base, so that the models connected to the same collecting bus include both new energy power generation unit models and new energy collector equivalent models, so that the simulation model has the electromagnetic transient characteristics simulation capabilities of a single unit and the new energy station simulation capabilities, and reduces the computing resources occupied by the establishment of the new energy base model, and can more quickly and efficiently establish the standard model of the power system of the energy base. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art are briefly introduced below.
[0036] Figure 1 A schematic diagram of a method for modeling a power system of a new energy base in one embodiment of the present application;
[0037] Figure 2 A schematic diagram of a standard model of a power system of a new energy base in one embodiment of the present application;
[0038] Figure 3 This is a schematic diagram of a single busbar model of a new energy base in one embodiment of the present application;
[0039] Figure 4 This is a schematic diagram of the hardware-in-the-loop real-time simulation structure of a power system standard model of a new energy base in one embodiment of the present application;
[0040] Figure 5This is a schematic diagram of a power system modeling device for a new energy base in one embodiment of the present application. DETAILED DESCRIPTION
[0041] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. In order to explain the present invention in more detail, the power system modeling method and device for the new energy base provided by the present invention are specifically described below in combination with the drawings.
[0042] Unless otherwise defined, the technical terms or scientific terms used in the disclosure of this application should be understood by people with ordinary skills in the field to which the present invention belongs. The "first", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. Similarly, similar words such as "one", "one" or "the" do not indicate a quantitative limit, but indicate that there is at least one. Similar words such as "include" or "include" mean that the elements or objects appearing in front of the word cover the elements or objects listed after the word and their equivalents, without excluding other elements or objects. Similar words such as "connect" or "connected" are not limited to physical or mechanical connections, but can include electrical connections, whether direct or indirect. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship can also change accordingly.
[0043] With the construction of the power system, the appearance of the power system has undergone profound changes. As the new control object of the power system, large-scale new energy bases have changed from a few homogeneous large-capacity synchronous generators on the original power generation side to widely distributed massive heterogeneous power generation resources, including power generation units and reactive power compensation units, where power generation units include but are not limited to wind power generators and photovoltaic generators, and reactive power compensation units include but are not limited to static VAR generators (SVG) units and static synchronous compensators (STATCOM) units. Since the above-mentioned power generation units and reactive power compensation units have small single-unit capacities but huge numbers, they are all connected to the grid by power electronic converters, which is very different from traditional synchronous generators. In the prior art, new energy stations mostly adopt the method of equivalent modeling of new energy units. The new energy units in a large new energy station are multiplied by single machines and grouped by units of the same model to make hundreds or thousands of new energy generating units equivalent to single units or units to realize power system modeling. Since the constructed model can neither reflect the electromagnetic transient characteristics of a single unit nor has universality, the electromagnetic transient characteristics of a single unit and the electromagnetic transient characteristics of the collector level of the new energy unit cannot be observed at the same time in the constructed power system model.
[0044] In this regard, the present invention provides a method for modeling the power system of a new energy base, and establishes a standard power system model for a large-scale new energy base, so that the model has both the simulation capability of the electromagnetic transient characteristics of a single new energy unit and the simulation capability of a new energy station. Figure 1 The schematic diagram of the power system modeling method of the new energy base and the attached Figure 2 The schematic diagram of the standard simulation model of the power system of the new energy base is shown, and the application of this method to terminal equipment is used as an example to illustrate.
[0045] This embodiment provides an application scenario of the method for modeling the power system of a new energy base, and the application scenario includes the terminal device provided in the embodiment, and the terminal device includes but is not limited to a smart phone and a computer device, wherein the computer device can be at least one of a desktop computer, a portable computer, a laptop computer, a mainframe computer, a platform computer, a tablet computer, a server, a cloud server, etc. It is used to operate the terminal device to obtain a power system model of a new energy base. For the specific process, please refer to the embodiment of the method for modeling the power system of a new energy base.
[0046] Step S101, obtaining parameter information of each new energy unit in the new energy base.
[0047] Among them, a new energy base refers to a large geographical area that integrates multiple new energy stations and other related equipment (such as energy storage systems, transmission lines, etc.) to form a comprehensive renewable energy system. New energy bases are generally cross-regional and achieve higher energy output and effective resource allocation through economies of scale. A new energy station is a collection of multiple new energy units, which can be a wind farm or a solar photovoltaic power station. A new energy station includes not only the power generation equipment itself, but also related substations, booster stations, control systems and other auxiliary equipment. The setting of a new energy station is to centrally manage and optimize power generation efficiency and facilitate the transmission of electricity to the power grid. The new energy unit is the most basic power generation unit in a new energy station. It can be a single wind turbine, one or more connected solar panels, or any small renewable energy power generation equipment. The new energy unit is usually the part that directly participates in power generation.
[0048] Specifically, the parameter information of each new energy unit in the new energy base includes but is not limited to (1) parameters of electrical components of the main circuit of the new energy converter, such as resistance, capacitance, inductance, power electronic switch devices, converter topology connection relationship, etc.; (2) electrical parameters of wind power energy units, such as stator parameters, rotor parameters, leakage inductance, mutual inductance, excitation inductance, etc. of wind power energy units; (3) electrical parameters of photovoltaic energy units, such as open circuit voltage, short circuit current, maximum power point voltage, maximum power point current, maximum power, filling factor, etc.; (4) electrical parameters of static VAR generator (SVG) units, such as parameters of components such as capacitance, capacitance, inductance, power electronic switch devices, etc.; (5) electrical parameters of static synchronous compensator (STATCOM) units, such as parameters of components such as capacitance, capacitance, inductance, resistance, power electronic switch devices, etc.; (6) key control parameters of converter controller; (7) parameters of power electronic component drive circuit; (8) other protection control parameters, such as overvoltage protection parameters, overcurrent protection parameters, overfrequency protection parameters, etc.
[0049] Step S102: dividing the new energy generating units into at least one new energy station set according to their types.
[0050] Specifically, considering that the wind power generator sets, photovoltaic generator sets, static VAR generator sets, and static synchronous compensator sets contained in the new energy stations have great differences in electromagnetic transient characteristics, it is not appropriate to perform merged equivalent modeling or clustering modeling. Therefore, it is necessary to divide the new energy units of the same type in the new energy base into a new energy station set according to the type of new energy unit, and different types of new energy units are classified into different new energy station sets. After division, this embodiment at least includes a wind power new energy station set, a photovoltaic new energy station set, an SVG new energy station set, and a STATCOM new energy station set.
[0051] Step S103, for each new energy station set, if the structures and parameters of the new energy units connected to at least two collectors in the new energy station set are the same, select the new energy units connected to one of the collectors to establish a power generation unit simulation model, and the new energy units connected to the other collectors to establish equivalent models of the new energy collectors. The power generation unit simulation model and the equivalent model are connected to the first-level busbar through the collector to obtain the power system model of the new energy base.
[0052] Specifically, for the same type of new energy units, the new energy station units and parameters connected by multiple collectors are further judged to see whether there are at least two new energy units connected by collectors with the same structure and parameters. When the topological structure and parameters of at least two new energy units connected by collectors are the same, a single-machine fine power generation unit simulation model can be established for one of the new energy units connected by the collectors, which can be used to study the electromagnetic transient characteristics of a single unit; and equivalent models can be established for the other new energy units connected by the collectors, which can reduce the amount of calculation in the simulation model and clearly display the electromagnetic transient characteristics of the collector level of the new energy units.
[0053] Through the above steps, the new energy units on the first-level busbar are modeled, as shown in the attached figure. Figure 3 As shown, the 35kV collection bus includes a power generation unit simulation model for fine simulation of a single new energy unit, as well as an equivalent model established using an equivalent algorithm for the new energy units connected to the collection line.
[0054] Among them, the rated capacity of each new energy unit is a, and the total system capacity is b. Two collectors are set at the 35kV collector. Each collector in the simulation station corresponds to a district. Each line adopts a sub-network parallel calculation method to improve the simulation rate. There are 5 accurate digital simulation models of new energy units in District 1, that is, N=5, and the new energy units are connected by 35kV short feeders. In addition, for District 2, which has the same topological structure and parameters as the new energy units in District 1, it also contains 5 actual new energy units, and the feeder connecting the 35kV grid connection point and the short feeder between the 5 units are equivalent to a single feeder unit. The equivalent feeder length is set to 8km, and the unit length feeder parameters are calculated to obtain an equivalent model, that is, District 2 model. District 2 is connected to the equivalent single unit model of the collector with an aggregation multiple of 5 and a capacity of 5×aMW. At this time, the total system capacity is b=5×2×a.
[0055] It should be noted that a transformer structure is also provided between the new energy power generation unit and the collection bus, and the transformer structure is generally set to a 0.8kV / 35kV box-type transformer.
[0056] Based on this, considering that the power system can be divided into the first-level busbar, the second-level busbar and the third-level busbar according to the scale of power processed, voltage level and specific location, the first-level busbar corresponds to the 35kV busbar, the second-level busbar corresponds to the 220kV busbar, and the third-level busbar corresponds to the 500kV busbar. Based on the model on the first-level busbar, the specific construction steps of the second-level busbar and the third-level busbar model are as follows:
[0057] Step S201, based on the voltage parameters of the first busbar and the second-level busbar, combined with the simulation model and equivalent model of the power generation unit connected to the collector line on the first-level busbar, and the overhead line structure of the second-level busbar, establish a first station equivalent model, and the first station equivalent model is connected to the second-level busbar through the overhead line.
[0058] Specifically, the first-level busbar is a 35kV busbar, the second-level busbar is a 220kV busbar, the first station equivalent model is a new energy 220kV station equivalent model, and the new energy station 220kV station equivalent model is connected to the 220kV busbar through overhead lines.
[0059] Step S202, based on the voltage parameters of the second-level busbar and the third busbar, combined with the simulation model and equivalent model of the power generation unit connected to the collector line on the first-level busbar, and the overhead line structure of the third-level collection, establish a second station equivalent model, and the second station equivalent model is connected to the third-level busbar through the overhead line.
[0060] Specifically, the second-level busbar is a 220kV busbar, the third-level busbar is a 500kV busbar, the second station equivalent model is a new energy 500kV station equivalent model, and the new energy station 500kV station equivalent model is connected to the 500kV busbar through overhead lines.
[0061] Step S203: the first-level busbar is connected to the second-level busbar via a first transformer structure, and the second-level busbar is connected to the third-level busbar via a second transformer structure.
[0062] Specifically, the first-level busbar and the second-level busbar are connected via a 220kV / 35kV transformer, and the second-level busbar and the third-level busbar are connected via a 500kV / 220kV transformer.
[0063] Combined with Figure 2As shown in the figure, the standard simulation model of the power system of the new energy base includes new energy power generation units, new energy collector equivalent models, new energy 220kV station equivalent models, and new energy 500kV station equivalent models. Among them, there are N new energy power generation units. According to the current general actual situation in the industry, N is generally not more than 16. This part of the model is a single-machine fine simulation model with the hardware-in-loop real-time simulation capability of the new energy unit controller. There are M new energy collector equivalent models. According to the current general actual situation in the industry, M is generally not more than 12. This part uses the equivalent algorithm to equate all new energy power generation units on a collector to a single unit model. M new energy collector equivalent models are equivalent to M new energy unit models. There are P new energy 220kV station equivalent models. According to the current general actual situation in the industry, the number of P is 2-16, that is, each 500kV station collects P 220kV new energy stations. Each 220kV new energy station is equivalent to a new energy unit model, and P 220kV stations are equivalent to P new energy unit models. There are Q new energy 500kV station equivalent models. According to the current general actual situation in the industry, the number of Q does not exceed 10. Each 500kV new energy station is equivalent to a new energy unit model, and Q 500kV stations are equivalent to Q new energy unit models.
[0064] Based on the above standard simulation model of the power system of the new energy base, the power loss of the new energy station represented by the power generation unit simulation model is:
[0065] ,
[0066] in, For the The line impedance value, For the The apparent power exported by each new energy unit, For the The voltage at the outlet of each new energy unit, is the grid voltage, The number of new energy units connected to the collector line.
[0067] Therefore, the total collector loss is .
[0068] Assuming the line impedance is equal to , is the sum of the apparent power at the export of each new energy unit, then the power loss of the above equivalent model is:
[0069] ,
[0070] in, is the grid-connected point voltage vector value.
[0071] The power loss before and after the equalization is equal, then: .
[0072] The specific expression of the equivalent impedance value of the line can be obtained as follows: .
[0073] In the above equivalent calculation, only resistance and inductance parameters are considered, that is, , and the capacitive parameters are calculated separately. Ignoring the voltage difference in the new energy station, the capacitance value after equalization is equal to the sum of the capacitance values of all lines before equalization, so the reactance relationship before and after equalization is:
[0074] ,
[0075] in is the equivalent capacitive reactance value, is the equivalent admittance value, is the admittance value of each feeder.
[0076] In addition, since the total power output of the units before the equivalence is equal to the total power output of the units after the equivalence, a single unit can be directly combined with a multiplied controllable current source to achieve multi-unit aggregation in the form of current multiplication. The new energy units before and after the equivalence meet the following conditions: ,in For the The capacity of the unit, is the number of units in the original new energy station, For the The capacity of the equivalent unit, is the equivalent number of units.
[0077] The power system modeling method based on the above-mentioned new energy base can bring the following beneficial effects:
[0078] (1) The number of simulations of new energy unit models has been greatly reduced. If the full topology modeling method of new energy units is adopted, and the equivalent modeling method of collector lines and stations is not adopted, the number of new energy units that need to be modeled for simulating a large-scale new energy base of the same scale is B=N×M×P×Q, which is about 30,000 new energy units. The current computing power of simulators at home and abroad is still unable to achieve microsecond-level electromagnetic transient precision simulation. Figure 2The standard model of the power system of the new energy base shown in the figure includes a total of A new energy units, A=N+M+P+Q, which generally does not exceed 55 new energy units, including N new energy single-machine fine simulation models, M collector station new energy equivalent models, P 220kV station new energy equivalent models and Q 500kV station new energy equivalent models. It can be seen that A is much smaller than B. It is an effective method that can complete single-machine fine simulation and realize panoramic simulation of large-scale new energy bases.
[0079] (2) As attached Figure 2 The standard model of the power system of the new energy base shown can be simulated by real-time simulation technology, such as the RTDS real-time simulator hardware platform. The platform only needs to meet the computing power of 55 new energy unit models (the current experience of domestic and foreign peers can achieve microsecond-level electromagnetic transient real-time simulation calculations for hundreds of new energy units at most), and at the same time has the controller hardware-in-the-loop real-time simulation capability of N new energy single-machine fine simulation models. The closed-loop hardware connection communication between the RTDS simulator and the controller is realized through a high-speed communication interface. The specific connection relationship is as follows: Figure 4 As shown. Among them, the RTDS real-time simulation device cluster is responsible for completing the precise digital model of a total of A new energy units, among which some or all unit models in the N new energy single-machine fine simulation models can realize real-time communication with the hardware device of the new energy unit controller through a high-speed communication interface device according to research needs, forming a closed-loop simulation structure. The remaining M, P, and Q stations with different voltage levels of collector or station models adopt the equivalent modeling method to establish a precise digital equivalent model to realize a panoramic real-time simulation platform for large-scale new energy bases.
[0080] It should be understood that although the Figure 1 The steps in the flowchart are shown in sequence as indicated by the arrows, but these steps are not necessarily executed in the order indicated by the arrows. Unless otherwise specified in this document, there is no strict order restriction for the execution of these steps, and these steps can be executed in other orders. Figure 1 At least part of the steps may include multiple sub-steps or sub-stages. These sub-steps or stages are not necessarily executed at the same time, but can be executed at different times. The execution order of these sub-steps or stages is not necessarily sequential, but can be executed in turn or alternately with other steps or at least part of the sub-steps or stages of other steps.
[0081] The above embodiments disclosed in the present invention describe in detail the power system modeling method of the new energy base. The above method disclosed in the present invention can be implemented by various forms of equipment. Therefore, the present invention also discloses a power system modeling device for the new energy base corresponding to the above method. Figure 5, specific embodiments are given below to explain in detail.
[0082] The parameter acquisition module 501 is used to obtain parameter information of each new energy unit in the new energy base;
[0083] A unit classification module 502, configured to classify the new energy units into at least one new energy station set according to their types;
[0084] The model building module 503 is used for establishing a simulation model of a power generation unit for each set of new energy stations. If at least two new energy units connected by collectors in the set of new energy stations have the same structure and parameters, one of the new energy units connected by the collectors is selected to establish an equivalent model of the new energy collectors, and the new energy stations connected by the other collectors are established. The power generation unit simulation model and the equivalent model are connected to the first-level busbar through the collectors to obtain a power system model of the new energy base.
[0085] Furthermore, the power system modeling device of the new energy base also includes the following modules:
[0086] The second busbar model establishment module 601 is used to establish a first station equivalent model according to the voltage parameters of the first-level busbar and the second-level busbar, in combination with the simulation model and equivalent model of the power generation unit connected to the collector line on the first-level busbar, and the overhead line structure of the second-level busbar, wherein the first station equivalent model is connected to the second-level busbar through the overhead line;
[0087] The third busbar model establishment module 602 is used to establish a second station equivalent model according to the voltage parameters of the second-level busbar and the third busbar, in combination with the simulation model and equivalent model of the power generation unit connected to the collector line on the first-level busbar, and the overhead line structure of the third-level busbar, wherein the second station equivalent model is connected to the third-level busbar through the overhead line;
[0088] The first-level busbar and the second-level busbar are connected via a first transformer structure, and the second-level busbar and the third-level busbar are connected via a second transformer structure.
[0089] For the power system modeling device of the new energy base, all the methods are defined above, which will not be described here. Each module in the above device can be implemented in whole or in part by software, hardware and a combination thereof. Each of the above modules can be embedded in or independent of the processor of the terminal device in the form of hardware, or can be stored in the memory of the terminal device in the form of software, so that the processor can call and execute the operations corresponding to each of the above modules.
[0090] In one embodiment, the present invention further provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the steps of the above-mentioned method for modeling the power system of the new energy base are implemented.
[0091] The computer-readable storage medium may be an electronic memory such as a flash memory, an EEPROM (electrically erasable programmable read-only memory), an EPROM (erasable programmable read-only memory), a hard disk or a ROM. Optionally, the computer-readable storage medium includes a non-transitory computer-readable storage medium. The computer-readable storage medium has a storage space for program codes for executing any method step of the above method. These program codes may be read from or written into one or more computer program products, and the program codes may be compressed in an appropriate form.
[0092] In one embodiment, the present invention provides a computer device, including a memory and a processor, wherein the memory stores a computer program, and the processor executes the above-mentioned power system modeling method of the new energy base when executing the computer program.
[0093] The computer device includes a memory, a processor and one or more computer programs, wherein the one or more computer programs can be stored in the memory and configured to be executed by one or more processors, and the one or more application programs are configured to execute the above-mentioned power system modeling method of the new energy base.
[0094] The processor may include one or more processing cores. The processor uses various interfaces and lines to connect the various parts of the entire computer device, and executes various functions of the computer device and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory, and calling data stored in the memory. Optionally, the processor can be implemented in at least one hardware form of digital signal processing (Digital Signal Processing, DSP), field programmable gate array (Field-Programmable Gate Array, FPGA), and programmable logic array (Programmable Logic Array, PLA). The processor can integrate one or more combinations of a central processing unit (Central Processing Unit, CPU), a reporting verifier (Graphics Processing Unit, GPU) for buried data, and a modem. Among them, the CPU mainly processes the operating system, user interface, and application programs; the GPU is responsible for rendering and drawing display content; and the modem is used to process wireless communications. It can be understood that the above-mentioned modem may not be integrated into the processor, but may be implemented separately through a communication chip.
[0095] The memory may include a random access memory (RAM) or a read-only memory (ROM). The memory may be used to store instructions, programs, codes, code sets or instruction sets. The memory may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for implementing at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc. The data storage area may also store data created by the terminal device during use, etc.
[0096] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A power system modeling method for a new energy base, It is characterized in that include: Obtain parameter information of each new energy unit in the new energy base; Divide into at least one new energy station set according to the type of the new energy unit; For each set of new energy stations, if the structures and parameters of at least two new energy units connected by the collectors in the set of new energy stations are the same, a new energy unit connected by one of the collectors is selected to establish a power generation unit simulation model, and the new energy stations connected by the other collectors are used to establish equivalent models of the new energy collectors. The power generation unit simulation model and the equivalent model are connected to the first-level busbar through the collector to obtain the power system model of the new energy base.
2. The power system modeling method of the new energy base according to claim 1, It is characterized in that Also includes: According to the voltage parameters of the first-level collecting bus and the second-level collecting bus, in combination with the simulation model and equivalent model of the power generation unit connected to the collecting line on the first-level collecting bus, and the overhead line structure of the second-level collecting bus, a first station equivalent model is established, wherein the first station equivalent model is connected to the second-level collecting bus through the overhead line; According to the voltage parameters of the second-level collection bus and the third collection bus, combined with the simulation model and equivalent model of the power generation unit connected to the collection line on the first-level collection bus, and the overhead line structure of the third-level collection, a second station equivalent model is established, and the second station equivalent model is connected to the third-level collection bus through the overhead line; The first-level busbar and the second-level busbar are connected via a first transformer structure, and the second-level busbar and the third-level busbar are connected via a second transformer structure.
3. The power system modeling method of the new energy base according to claim 2, It is characterized in that The first level busbar is a 35 kV busbar, the second level busbar is a 220 kV busbar, and the third level busbar is a 500 kV busbar; The first station equivalent model is a new energy 220kV station equivalent model, and the second station equivalent model is a new energy 500kV station equivalent model.
4. The power system modeling method of the new energy base according to claim 3, It is characterized in that The power loss of the new energy station represented by the power generation unit simulation model is: in, For the The line impedance value, For the The apparent power exported by each new energy unit, For the The voltage at the outlet of each new energy unit, is the grid voltage, The number of new energy units connected to the collector line.
5. The power system modeling method of the new energy base according to claim 4, It is characterized in that The total loss of a single collector line in the power system of the new energy base is ,in is the total loss of a single collector line.
6. The power system modeling method of the new energy base according to claim 5, It is characterized in that The power loss of the equivalent model of the new energy collector is: , in, is the power loss of the equivalent model of the collector, is the line impedance after equalization, is the sum of the apparent power exported by each new energy unit, is the grid-connected point voltage vector value.
7. The power system modeling method of the new energy base according to claim 6, It is characterized in that The capacity of the new energy generating units before and after the equalization satisfies the first constraint condition, and the expression of the first constraint condition is: , in For the The capacity of the unit, is the number of units in the new energy station before the equivalent value, For the The capacity of the equivalent unit, is the number of units after equalization.
8. A power system modeling device for a new energy base, It is characterized in that include: The parameter acquisition module is used to obtain the parameter information of each new energy unit in the new energy base; A unit classification module, used for classifying the new energy units into at least one new energy station set according to their types; A model building module is used for each set of new energy stations. If the structures and parameters of the new energy units connected by at least two collectors in the set of new energy stations are the same, a new energy unit connected by one of the collectors is selected to establish a power generation unit simulation model, and the new energy stations connected by other collectors are used to establish equivalent models of the new energy collectors. The power generation unit simulation model and the equivalent model are connected to the first-level busbar through the collector to obtain the power system model of the new energy base.
9. A computer-readable storage medium having a computer program stored thereon, It is characterized in that When the computer program is executed by a processor, the steps of the method for modeling a power system of a new energy base in any one of claims 1 to 7 are implemented.
10. A computer device comprising a memory and a processor, wherein the memory stores a computer program. It is characterized in that When the processor executes the computer program, it performs the power system modeling method for a new energy base according to any one of claims 1 to 7.
Citation Information
Cited By
New energy station electromagnetic transient model conversion method and related device
CN119623104A
Real-time simulation test modeling method and system for new energy station
CN119668130A
A Real-Time Simulation Test Modeling Method and System for New Energy Power Stations
CN119668130B
Full-link equivalent acceleration electromagnetic transient modeling method, system and equipment for large-scale photovoltaic station and medium
CN120781579A
Method, system, device and medium for full-link equivalent accelerated electromagnetic transient modeling of large-scale photovoltaic power station
CN120781579B