Supporting structure of mold bag concrete corrugated plate

The mold bag concrete corrugated plate support structure enhances compressive strength and facilitates easy transportation and installation by using corrugated steel plates for tunnel support, overcoming the limitations of traditional building materials and shield segments.

CN119244272APending Publication Date: 2025-01-03BEIJING UNIV OF TECH +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411343214.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2025-01-03

AI Technical Summary

Technical Problem

The existing tunnel support structures face issues with poor compressive mechanical properties of traditional building materials, low strength to withstand surrounding rock deformation, and the thickness and heaviness of shield segments, which complicates transportation, maintenance, and construction.

Method used

A mold bag concrete corrugated plate support structure is introduced, utilizing corrugated steel plates for shield segments and top plates, with a protective tube assembly and top cover assembly that enables pressurized pouring and stacking, enhancing compressive strength and facilitating easy transportation and installation.

Benefits of technology

The solution improves compressive strength through pressurized pouring and simplifies transportation and installation by using corrugated plates, addressing the limitations of traditional methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119244272A_ABST
    Figure CN119244272A_ABST
Patent Text Reader

Abstract

The invention provides a mold bag concrete corrugated plate supporting structure, and relates to the field of corrugated plate supporting, the mold bag concrete corrugated plate supporting structure comprises a protection pipe assembly, the top of the protection pipe assembly is spliced with a top cover assembly, the protection pipe assembly comprises protection plates which are sequentially distributed, the protection plates are in a wave shape, and the protection plates are made of steel corrugated plates; a first mold bag is arranged on the outer side of the protection plate, extrusion blocks are arranged on the inner wall of the protection plate in an array mode, the extrusion blocks penetrate through the protection plate and extend to the inner side of the protection plate, an inner groove penetrates through the inner side of the protection plate, the protection plate is connected with the extrusion blocks in a sleeved mode through the inner groove, and first material conveying grooves are symmetrically formed in the inner wall of the protection plate. The first mold bag is matched with the second mold bag, concrete is poured into the first mold bag and the second mold bag in a pressurized pouring forming mode, exhausting, bleeding and compaction of the concrete are achieved under the action of pouring pressure, and therefore the compressive mechanical property of the concrete is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of corrugated plate support, and in particular to a mold bag concrete corrugated plate support structure. Background Art

[0002] Tunnel support structure is a vital part of tunnel engineering. Its design and construction have an important impact on the stability, safety and durability of the tunnel. The existing tunnel support structure usually adopts the method of shield segments combined with concrete tamping. When this method is used, due to the characteristics of the tamping molding process, the cubic specimens of traditional building materials concrete have poor compressive mechanical properties, and the existing shield segments have low strength to withstand surrounding rock deformation. At the same time, the existing shield segments are relatively thick and heavy, which is not convenient for transportation, maintenance and construction.

[0003] For example, the "corrugated plate tunnel initial support structure and tunnel" disclosed in the Chinese invention patent (application number: CN202010422368.2) discloses in its specification: When constructing interval tunnels in urban underground projects, in order to close the excavation surface as soon as possible and effectively reduce surface settlement, an initial support device with greater rigidity should be erected as soon as possible after soil excavation. At present, in the construction of subway interval tunnels using the mining method, the initial support method of spray anchor is adopted, that is, the spray layer, anchor rods and surrounding rock together form a ring-shaped bearing structure, which bears the pressure of the surrounding rock and forms an initial support structure. This type of initial support device is a steel grating formed by welding multiple steel bars or a steel grating structure formed by bending steel sections. In the initial support device of the prior art, each ring of the steel grating steel frame is assembled from several grating units of different shapes. Each frame of the steel grating is welded by main bars, reinforcing bars and connecting angle steels (forming end plates), and the units are connected by high-strength bolts. In actual application, the steel grating after layout will be adjusted and connected according to the pre-designed unit positions. When the grating is erected, the system anchor rods will be driven into the soil to fix the position of the grating. When the system anchor rods are not set, the steel grating can also be positioned by locking anchor rods. After the above-mentioned grating is erected, the concrete is sprayed in layers as soon as possible to form a composite force-bearing structure of the steel grating and sprayed concrete. However, the initial support device used in underground projects in the prior art, because the entire construction process of the initial lining structure of the underground project includes the transportation, installation, connection, and adjustment of the grating steel frame, as well as the two major links of concrete material preparation, air compression equipment, transportation pipelines, and spraying assembly, the installation of the existing initial support device generally requires a long construction time, and it is difficult to truly realize the "quick closure" principle of tunnel excavation support; the above-mentioned patent can prove the defects of the prior art.

[0004] Therefore, we made improvements on this and proposed a bag concrete corrugated plate support structure. Summary of the invention

[0005] The purpose of the present invention is to: for the tunnel support structure currently used, due to the characteristics of the ramming and forming process, the cubic specimens of traditional building materials concrete have poor compressive mechanical properties, and the existing shield segments have low strength to withstand deformation of surrounding rocks. At the same time, the existing shield segments are relatively thick and heavy, which is not convenient for transportation, maintenance and construction.

[0006] In order to achieve the above-mentioned purpose of the invention, the present invention provides a mold bag concrete corrugated plate supporting structure to improve the above-mentioned problems.

[0007] The specific application is as follows:

[0008] It includes a protective tube assembly, the top of which is spliced ​​with a top cover assembly, the protective tube assembly includes protective plates distributed in sequence, the protective plates are wavy, and the protective plates are made of corrugated steel plates, a first mold bag is arranged on the outer side of the protective plate, an inner wall array of the protective plate is arranged with extrusion blocks, and the extrusion blocks penetrate the protective plate and extend to the inner side thereof, an inner groove penetrates the inner side of the protective plate, the protective plate is sleeved with the extrusion block through the inner groove, and a first material transport trough is symmetrically provided on the inner wall of the protective plate.

[0009] As a preferred technical solution of the present application, the internal rectangular array of the guard plate has a connecting groove, and the connecting groove is connected to the first material transport trough, the guard plate is sleeved with the rotating shaft through the connecting groove, the outer side of the rotating shaft has a sealing ring, and the rotating shaft is squeezed and sealed with the guard plate through the sealing ring.

[0010] As a preferred technical solution of the present application, a telescopic shaft is provided at one end of the rotating shaft, the guard plate is sleeved with the telescopic shaft through the first material transport groove, a compression spring is fixedly installed at one end of the telescopic shaft away from the rotating shaft, and a ring plate is fixedly installed at the other end of the compression spring, and the ring plate is located at one end of the first material transport groove.

[0011] As a preferred technical solution of the present application, a connecting tube is provided at the other end of the rotating shaft, the guard plate is sleeved with the connecting tube through the first material transport trough, a side groove is opened on the inner side of the connecting tube, the extrusion block passes through the side groove and extends to the interior of the connecting tube, and the bottom of the extrusion block is inclined, the size of the middle part of the extrusion block is the same as the size of the side groove, and the outer side of the extrusion block has its own sealing ring.

[0012] As a preferred technical solution of the present application, a spring sheet is fixedly installed on the inner side of the connecting tube, and the spring sheet is arranged obliquely, and the spring sheet is located on one side of the side groove.

[0013] As a preferred technical solution of the present application, a clamping plate is symmetrically installed at one end of the spring sheet away from the side groove, and the clamping plate is arc-shaped, and a limiting axis is symmetrically installed on the outer side of the extrusion block, the limiting axis is located inside the connecting tube, and the limiting axis matches the clamping plate.

[0014] As a preferred technical solution of the present application, a first discharge chute is opened on the outer array of the guard plate, one end of the first discharge chute is connected to the first material transport chute, and the other end of the first discharge chute is connected to the first mold bag.

[0015] As a preferred technical solution of the present application, the top cover assembly includes a top plate arranged above the protective tube assembly, the top plate is arc-shaped, and the top plate is made of a steel corrugated pipe, and the two ends of the top plate are respectively in contact with the two groups of the protective plates.

[0016] As a preferred technical solution of the present application, a second mold bag is fixedly installed on the outer side of the top plate, a second material transport trough is symmetrically opened inside the top plate, and the second material transport trough is connected to the first material transport trough, and a second material discharge trough is symmetrically opened on the outer side of the top plate, one end of the second material discharge trough is connected to the second material transport trough, and the other end of the second material discharge trough is connected to the second mold bag.

[0017] As a preferred technical solution of the present application, a feed pipe is symmetrically installed on the inner side of the top plate, and one end of the feed pipe is connected to the second material transport trough.

[0018] Compared with the prior art, the present invention has the following beneficial effects:

[0019] In the scheme of this application:

[0020] 1. In order to solve the problem of poor compressive strength of cubic specimens of traditional building materials concrete in the prior art, the present application realizes the use of pressurized pouring molding to pour concrete into the first mold bag and the second mold bag by setting a first mold bag and a second mold bag, and realizes the exhaust, water seepage and compaction of concrete under the action of the pouring pressure, thereby greatly improving the compressive strength of concrete;

[0021] 2. In order to solve the problem that the shield segments in the prior art are relatively heavy and inconvenient to transport, maintain and construct, the present application replaces the traditional shield segments with corrugated shield segments and top plates by setting and splicing the shield segments and top plates. In addition, since the shield segments and bottom plates are made of corrugated plates and the characteristics of the corrugated plates make them easy to transport, install and maintain during use.

[0022] 3. By setting up a rotating shaft and cooperating with a guard plate connected to the rotating shaft, it is possible to rotate the rotating shaft and stack and clamp different guard plates, thereby solving the problem in the prior art that the guard plates are difficult to stack and install during transportation, which causes the guard plates to tilt easily and thus be damaged. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 A schematic diagram of the structure of the mold bag concrete corrugated plate support structure provided for this application;

[0024] Figure 2 A structural schematic diagram of the filling state of the mold bag concrete corrugated plate support structure provided in this application;

[0025] Figure 3 A schematic diagram of the structure of the stacked state of the mold bag concrete corrugated plate support structure provided in this application;

[0026] Figure 4 A schematic diagram of the structure of the protective pipe assembly of the mold bag concrete corrugated plate support structure provided for this application;

[0027] Figure 5 A structural side view of the protective pipe assembly of the mold bag concrete corrugated plate support structure provided for this application;

[0028] Figure 6 A structural side view of the protective plate of the mold bag concrete corrugated plate support structure provided for this application;

[0029] Figure 7 A structural cross-sectional view of the protective plate of the mold bag concrete corrugated plate support structure provided for this application;

[0030] Figure 8 The mold bag concrete corrugated board support structure provided for this application Figure 8 Schematic diagram of the enlarged result at A in the middle;

[0031] Fig. 9 A cross-sectional view of the connection structure of the connecting pipe of the mold bag concrete corrugated plate support structure provided in this application;

[0032] Fig.10 A schematic diagram of the connection structure of the cardboard of the mold bag concrete corrugated plate support structure provided in this application;

[0033] Fig.11 A cross-sectional view of the connection structure of the rotating shaft of the mold bag concrete corrugated plate support structure provided in this application;

[0034] Fig.12 A schematic diagram of the connection structure of the telescopic shaft of the mold bag concrete corrugated plate support structure provided in this application;

[0035] Fig.13 A schematic diagram of the structure of the top cover assembly of the mold bag concrete corrugated plate support structure provided for this application;

[0036] Fig.14 A structural cross-sectional view of the top plate of the mold bag concrete corrugated plate support structure provided in this application.

[0037] Indicated in the figure:

[0038] 1. Protective tube assembly; 101. Protective plate; 102. First mold bag; 103. First material transport trough; 104. First material discharge trough; 105. Rotating shaft; 106. Connecting groove; 107. Telescopic shaft; 108. Compression spring; 109. Ring plate; 110. Connecting tube; 111. Extrusion block; 112. Limiting shaft; 113. Side groove; 114. Shrapnel; 115. Card plate;

[0039] 2. Top cover assembly; 201. Top plate; 202. Second mold bag; 203. Feed pipe; 204. Second material transport trough; 205. Second material discharge trough. DETAILED DESCRIPTION

[0040] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0041] As described in the background technology, the tunnel support structure currently used has poor compressive mechanical properties of cubic specimens of traditional building materials concrete due to the characteristics of the ramming and molding process, and the existing shield segments have low strength to withstand deformation of surrounding rock. At the same time, the existing shield segments are relatively thick and heavy, which is not convenient for transportation, maintenance and construction.

[0042] In order to solve this technical problem, the present invention provides a corrugated plate support structure for formwork bag concrete, which is applied to corrugated plate formwork bag concrete support.

[0043] Specifically, please refer to Figure 1 - Fig.14 The mold bag concrete corrugated plate support structure specifically includes a protective pipe assembly 1, the top of the protective pipe assembly 1 is spliced ​​with a top cover assembly 2, the protective pipe assembly 1 includes sequentially distributed protective plates 101, the protective plates 101 are wavy, and the protective plates 101 are made of steel corrugated plates, a first mold bag 102 is arranged on the outer side of the protective plate 101, an inner wall array of the protective plate 101 is provided with extrusion blocks 111, and the extrusion blocks 111 penetrate the protective plate 101 and extend to the inner side thereof, an inner groove penetrates the inner side of the protective plate 101, and the protective plate 101 is sleeved with the extrusion blocks 111 through the inner groove, and a first material transport trough 103 is symmetrically opened on the inner wall of the protective plate 101.

[0044] The formwork bag concrete corrugated plate support structure provided by the present invention realizes the replacement of traditional shield segments with wavy guard plates and top plates by setting up guard plates and top plates and splicing them. In addition, since the guard plates and bottom plates are made of corrugated plates and due to the characteristics of the corrugated plates, they are easy to transport, install and maintain when in use.

[0045] In order to enable those skilled in the art to better understand the solutions of the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings.

[0046] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features and technical solutions in the embodiments may be combined with each other.

[0047] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0048] Example 1, please refer to Figure 3 , Figure 4 , Figure 5 , Figure 6 and Figure 7 A corrugated plate support structure for mold bag concrete, wherein the inner rectangular array of the guard plate 101 has a connecting groove 106, and the connecting groove 106 is connected with the first material transport trough 103, the guard plate 101 is sleeved with the rotating shaft 105 through the connecting groove 106, and the outer side of the rotating shaft 105 has a sealing ring, and the rotating shaft 105 is squeezed and sealed with the guard plate 101 through the sealing ring.

[0049] By rotating the rotating shaft 105 to rotate it to the outside of the guard plate 101, the guard plate 101 can be supported by the rotating shaft 105. By rotating the rotating shaft 105 to completely accommodate it in the connecting groove 106, the connecting groove 106 can also be sealed and connected.

[0050] Further, such as Figure 4 , Figure 5 , Figure 6 and Fig.11 As shown, the internal rectangular array of the guard plate 101 has a connecting groove 106, and the connecting groove 106 is connected to the first material transport trough 103. The guard plate 101 is connected to the rotating shaft 105 through the connecting groove 106. The outer side of the rotating shaft 105 has a sealing ring, and the rotating shaft 105 is squeezed and sealed with the guard plate 101 through the sealing ring.

[0051] By rotating the rotating shaft 105 to rotate it to the outside of the guard plate 101, the guard plate 101 can be supported by the rotating shaft 105. By rotating the rotating shaft 105 to completely accommodate it in the connecting groove 106, the connecting groove 106 can also be sealed and connected.

[0052] Further, such as Figure 7 , Figure 8 , Fig.11 and Fig.12 As shown, a telescopic shaft 107 is provided at one end of the rotating shaft 105, and the guard plate 101 is sleeved with the telescopic shaft 107 through the first material transport groove 103. A compression spring 108 is fixedly installed at one end of the telescopic shaft 107 away from the rotating shaft 105, and a ring plate 109 is fixedly installed at the other end of the compression spring 108. The ring plate 109 is located at one end of the first material transport groove 103.

[0053] When the rotating shaft 105 rotates, the compression spring 108 will be squeezed through the telescopic shaft 107, and the telescopic shaft 107 will move along the first material transport trough 103. When the rotating shaft 105 is completely retracted to the inside of the guard plate 101, the telescopic shaft 107 will penetrate the rotating shaft 105 and extend into the inside under the action of the compression spring 108, thereby connecting the first material transport trough 103 through the telescopic shaft 107.

[0054] Further, such as Figure 6 , Figure 7 , Figure 8 and Fig. 9 As shown, a connecting tube 110 is provided at the other end of the rotating shaft 105, and the guard plate 101 is sleeved with the connecting tube 110 through the first material transport trough 103. A side groove 113 is opened on the inner side of the connecting tube 110, and the extrusion block 111 passes through the side groove 113 and extends to the inside of the connecting tube 110, and the bottom of the extrusion block 111 is inclined, the size of the middle part of the extrusion block 111 is the same as the size of the side groove 113, and the outer side of the extrusion block 111 has a sealing ring.

[0055] The extrusion block 111 is clamped by the clamping assembly, thereby driving the entire guard plate 101 to move and push the extrusion block 111, so that the extrusion block 111 passes through the side groove 113 and continuously extends into the interior of the connecting tube 110 until the side wall of the extrusion block 111 is in full contact with the side groove 113, thereby sealing the side groove 113 through the sealing ring sleeved in the middle of the extrusion block 111.

[0056] Further, such as Fig.10 As shown, a spring piece 114 is fixedly mounted on the inner side of the connecting tube 110 , and the spring piece 114 is arranged obliquely. The spring piece 114 is located at one side of the side groove 113 .

[0057] Further, such as Figure 7 , Figure 8 and Fig. 9 As shown, a clamping plate 115 is symmetrically installed at one end of the spring piece 114 away from the side groove 113, and the clamping plate 115 is arc-shaped. A limiting shaft 112 is symmetrically installed on the outer side of the extrusion block 111. The limiting shaft 112 is located inside the connecting tube 110, and the limiting shaft 112 matches the clamping plate 115.

[0058] By moving the extrusion block 111, the spring sheet 114 is squeezed. The spring sheet 114 is deformed when being squeezed, and the extrusion block 111 is continuously moved. The side groove 113 can also continuously push the connecting tube 110 to move, so that the connecting tube 110 passes through one end of the rotating shaft 105 and extends to the inner side thereof. The extrusion block 111 is continuously moved until the limiting shaft 112 is engaged with the clamping plate 115, thereby fixing the extrusion block 111 and the connecting tube 110.

[0059] Further, such as Figure 3 and Figure 4 As shown, the outer array of the guard plate 101 is provided with a first discharge chute 104 , one end of the first discharge chute 104 is connected to the first material transport chute 103 , and the other end of the first discharge chute 104 is connected to the first mold bag 102 .

[0060] Example 2, please refer to Fig.13 and Fig.14 A mold bag concrete corrugated plate support structure, specifically, the top cover assembly 2 includes a top plate 201 arranged above the protective pipe assembly 1, the top plate 201 is arc-shaped, and the top plate 201 is made of steel corrugated pipe, and the two ends of the top plate 201 are respectively in contact with the two groups of protective plates 101.

[0061] Furthermore, Fig.13 and Fig.14 A second mold bag 202 is fixedly installed on the outer side of the top plate 201, a second material transport trough 204 is symmetrically opened inside the top plate 201, and the second material transport trough 204 is connected to the first material transport trough 103, and a second discharge trough 205 is symmetrically opened on the outer side of the top plate 201, one end of the second discharge trough 205 is connected to the second material transport trough 204, and the other end of the second discharge trough 205 is connected to the second mold bag 202.

[0062] Furthermore, Fig.13 and Fig.14 A feed pipe 203 is symmetrically installed on the inner side of the top plate 201 , and one end of the feed pipe 203 is connected to the second material transport trough 204 .

[0063] Concrete is poured into the second transport chute 204 under pressure through the feed pipe 203 , and the concrete is transported to the second mold bag 202 through the second discharge chute 205 .

[0064] The use process of the mold bag concrete corrugated plate support structure provided by the present invention is as follows:

[0065] When in use, since the guard plates 101 are in a stacked state, the rotating shaft 105 sleeved inside the bottom guard plate 101 is tilted and contacts the stacking surface, thereby supporting the stacked guard plates 101, and the bottom of the tilted rotating shaft 105 inside the upper guard plate 101 extends to the inside of the connecting groove 106 provided in the guard plate 101 below it, and at the same time, the rotating shaft 105 is directly engaged with the connecting groove 106, thereby achieving one-time stacking;

[0066] When in use, first take out a set of guard plates 101, and clamp the extrusion blocks 111 that penetrate the array inside the guard plates 101 through the clamping device, and place the guard plates 101 in an appropriate position. At this time, the rotating shaft 105 is still in an inclined state, but as the guard plates 101 are constantly in contact with the inner wall of the tunnel, the rotating shaft 105 is constantly squeezed during the movement, so that it is constantly reset until the first mold bag 102 outside the guard plates 101 is fully in contact with the inner wall of the tunnel and is squeezed, so that the rotating shaft 105 is squeezed by the first mold bag 102 that is squeezed and deformed, so that the rotating shaft 105 is completely retracted to the inner wall of the guard plates 101;

[0067] When the rotating shaft 105 is continuously squeezed and rotated, the telescopic shaft 107 set at one end thereof will be continuously squeezed under the action of rotation, and the telescopic shaft 107 will squeeze the compression spring 108 and move along the first material transport groove 103 until the telescopic shaft 107 is completely rotated to the guard plate 101. At this time, the central channel of the telescopic shaft 107 is connected with the first material transport groove 103. At this time, the telescopic shaft 107 rebounds and passes through one end of the rotating shaft 105 under the action of the compression spring 108, extending to the inside thereof, thereby limiting the rotating shaft 105 until the guard plate 101 is placed. At this time, the clamping device is released and the squeezing block 111 is pushed. The squeezing block 111 When moving toward the inner wall of the guard plate 101, it moves toward the inside of the connecting tube 110 through the side groove 113 at its bottom and squeezes the spring sheet 114. At this time, the squeezing block 111 squeezes the spring sheet 114 and, under the action of the reaction force, pushes the connecting tube 110 to move until the limiting shaft 112 is engaged with the clamping plate 115, thereby limiting the connecting tube 110 and the squeezing block 111. At this time, the squeezing block 111 is in full contact with the connecting tube 110 through the side groove 113, thereby sealing the connecting tube 110. At this time, the connecting tube 110 is fully moved and extends through the other end of the rotating shaft 105 to the inside thereof, thereby sealing and penetrating the rotating shaft 105.

[0068] At this time, two sets of guard plates 101 are taken out again, and the above steps are repeated to splice them at the two ends of the guard plates 101, and at the same time, the first material transport troughs 103 symmetrically opened inside the three sets of guard plates 101 are connected;

[0069] Finally, take out the top plate 201, clamp the feed pipe 203 symmetrically arranged on the inner side of the top plate 201 through the clamping device, and place it on the top of the inner side of the tunnel, so that the two sides of the top plate 201 are spliced ​​with the two groups of guard plates 101, and ensure that the first material transport trough 103 is connected to the second material transport trough 204. At this time, concrete is pressurized and poured into the interior of the second material transport trough 204 through the feed pipe 203, and concrete is pressurized and poured into the interior of the second mold bag 202 through the second discharge trough 205. At the same time, the concrete inside the second discharge trough 205 is pressurized and poured into the interior of the first mold bag 102 through the first material transport trough 103 connected to it and the first discharge trough 104 that penetrates the first material transport trough 103, until the interior of the first mold bag 102 and the second mold bag 202 as well as the first material transport trough 103 and the second material transport trough 204 are fully filled with concrete. At this point, a set of support structures is spliced.

[0070] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0071] Obviously, the embodiments described above are only some embodiments of the present invention, rather than all embodiments. The preferred embodiments of the present invention are given in the accompanying drawings, but they do not limit the patent scope of the present invention. The present invention can be implemented in many different forms. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosure of the present invention more thorough and comprehensive. Although the present invention has been described in detail with reference to the aforementioned embodiments, for those skilled in the art, it is still possible to modify the technical solutions recorded in the aforementioned specific embodiments, or to perform equivalent replacements for some of the technical features therein. Any equivalent structure made using the contents of the specification and drawings of the present invention, directly or indirectly used in other related technical fields, is also within the scope of patent protection of the present invention.

Claims

1. A corrugated plate support structure of mold bag concrete, characterized in that: The invention comprises a protective tube assembly (1), the top of which is spliced ​​with a top cover assembly (2), the protective tube assembly (1) comprising protective plates (101) distributed in sequence, the protective plates (101) being wavy and made of corrugated steel plates, a first mold bag (102) being arranged on the outer side of the protective plate (101), an array of extrusion blocks (111) being arranged on the inner wall of the protective plate (101), and a first material transport trough (103) being symmetrically opened on the inner wall of the protective plate (101).

2. A mold bag concrete corrugated plate support structure according to claim 1, characterized in that: The inner rectangular array of the guard plate (101) has a connecting groove (106), and the connecting groove (106) is connected with the first material conveying trough (103), and the guard plate (101) is sleeved with the rotating shaft (105) through the connecting groove (106).

3. A mold bag concrete corrugated plate support structure according to claim 2, characterized in that: A telescopic shaft (107) is provided at one end of the rotating shaft (105), and the guard plate (101) is sleeved with the telescopic shaft (107) through the first material transport trough (103). A compression spring (108) is fixedly installed at one end of the telescopic shaft (107) away from the rotating shaft (105), and a ring plate (109) is fixedly installed at the other end of the compression spring (108), and the ring plate (109) is located at one end of the first material transport trough (103).

4. A mold bag concrete corrugated plate support structure according to claim 3, characterized in that: A connecting tube (110) is provided at the other end of the rotating shaft (105); the guard plate (101) is sleeved with the connecting tube (110) through the first material transport trough (103); a side groove (113) is provided on the inner side of the connecting tube (110); and the extrusion block (111) penetrates the side groove (113) and extends to the interior of the connecting tube (110).

5. A mold bag concrete corrugated plate support structure according to claim 4, characterized in that: A spring sheet (114) is fixedly mounted on the inner side of the connection tube (110), and the spring sheet (114) is arranged obliquely. The spring sheet (114) is located on one side of the side groove (113).

6. A mold bag concrete corrugated plate support structure according to claim 5, characterized in that: A clamping plate (115) is symmetrically mounted on one end of the spring sheet (114) away from the side groove (113), and the clamping plate (115) is arc-shaped. A limiting axis (112) is symmetrically mounted on the outer side of the extrusion block (111).

7. A mold bag concrete corrugated plate support structure according to claim 6, characterized in that: The outer array of the guard plate (101) is provided with a first discharge chute (104), one end of the first discharge chute (104) is connected to the first material transport chute (103), and the other end of the first discharge chute (104) is connected to the first mold bag (102).

8. The corrugated board support structure of mold bag concrete according to claim 7, characterized in that: The top cover assembly (2) comprises a top plate (201) arranged above the protective tube assembly (1); the top plate (201) is arc-shaped and is made of a steel corrugated tube; two ends of the top plate (201) are respectively in contact with two groups of the protective plates (101).

9. The corrugated board support structure of mold bag concrete according to claim 8, characterized in that: A second mold bag (202) is fixedly mounted on the outer side of the top plate (201), a second material transport trough (204) is symmetrically provided inside the top plate (201), and a second material discharge trough (205) is symmetrically provided on the outer side of the top plate (201), one end of the second material discharge trough (205) is connected to the second material transport trough (204), and the other end of the second material discharge trough (205) is connected to the second mold bag (202).

10. A mold bag concrete corrugated plate support structure according to claim 9, characterized in that: A feeding pipe (203) is symmetrically mounted on the inner side of the top plate (201), and one end of the feeding pipe (203) is connected to the second material transport trough (204).